SlideShare une entreprise Scribd logo
1  sur  38
Construction
of
500 mw boiler

by
Vaibhav G. Paydelwar
( Project Engineer)
Sunil Hi-Tech Engineers
Limited
WHAT DO YOU MEAN BY BOILER
?
 Boiler means any closed vessel exceeding 22.75 Ltr. in capacity used
for steam generation under pressure. The first boiler was developed in
1725 and its working pressure was 10 kg/ cm2.
 Boiler can be regarded as a number of interconnected heat
exchangers arranged in such manner that heat available by burning of
fuel is transferred to convert water into steam in most efficient manner.
FUNCTION OF BOILER
 To produce the steam at the desired rate at
desired pressure and temperature with use of
resources such as oil, coal & water for generating
the power.
Types of Boilers
Natural circulation Boiler :Drum to down comer - to main ring header – to ww tubes
and back -to drum. Due to difference in density of water and steam this
types of circulation takes place.

 Forced circulation (Assisted circulation) Boiler :As per operating pressure of the boiler approaches to
the critical pressure, additional pumps are required to install in down
comers, because at this pressure there is no appreciable density
difference between water and steam to have natural circulation of
water.
NEED FOR ASSISTED
CIRCULATION
0.7

Density of Water

0.6
0.5
0.4

Critical
Point

0.3
0.2
0.1

Density of Steam

0
80

100

120

140

160

180

Pressure (Kg/cm2)

200

220

240
According to working pressure

Sub critical pressure boiler : when working
pressure of boiler is between 130 to 180 kg/ cm2
critical boiler : when working pressure of boiler
is 225.56 kg/ cm2

Super critical boiler : when working pressure of
boiler is 240.10 kg/ cm2
Why to go for higher capacity ?
1’-2’ = Work done in turbine
from P1 – P2
2’-3 = Heat Rejection in
condenser
3-4 = Water pumped to boiler
4-1 = Heat addition in eco and
boiler.
SPECIAL FEATURES OF 500MW BOILER
Controlled circulation of feed water in water walls with the
help of 3 Nos. of boiler circulating water pumps installed on
down comers. Rifled bore water wall tubes as against smooth
bore tubes in 210 MW boiler.
 Provision of Orifices for equal distribution of water in water
wall tubes from bottom ring header.
 All down comers are connected to front header of the
bottom ring header.

DESIGN FACTOR
For the construction of boiler parts subjected to
pressure and their integral attachment, the designer
takes into account several factors
 Relative Cost
 Mechanical Properties
 Manufacturing Method
 Scaling Resistance
 Maintenance
Various parts of Boiler
BOILER IS DIVIDED INTO TWO PASS: FIRST PASS
 SECOND PASS
First pass of the boiler consists of:-

 Furnace water wall.
 Divisional super heater pendent assembly.
 Final Super heater pendent assembly.

 Reheater front pendent assembly. (CRH)
 Reheater rear pendent assembly. (HRH)
 Rear Arch Panel.

 Water Wall screen tubes.
Second pass of the boiler consists of: Steam cooled wall.

 Economizer lower bank coils.


Economizer middle bank coils.



Economizer upper bank coils.



LTSH lower bank coils



LTSH upper bank coils



Eco. Hanger tubes.



LTSH terminal tubes.
ECONOMISER
 Requirement why ?
 Advantages
•
•

As the economiser recover the heat in the flue gas that leaves the boiler
and transfer to working fluid there will be saving in fuel consumption.
As the feed water is preheated in the economiser and enter the boiler
tube at an elevated temperature( near to saturation temp.) the heat
transfer area required for the evaporation surface required will be
reduce considerably. As the size of boiler also will be reduced.

 Types of Economiser

Steaming
 Non steaming
• Plain tube economiser
• Fin-tube economiser

Plain tubes
Direction of Gas Flow
Direction of Gas Flow

Inline Arrangement
Staggered

Arrangement
Fin-tube Eonomiser
Tube size and spacing




The tubes can be made any length and diameter with 38mm to 52mm
OD. The side spacing and back spacing can be arranged for good
cleaning, absorption of heat and less draught loss. Spacing about 90mm
to 140mm.
It is composed of three banks of 130 parallel tube elements arranged in
horizontal rows in such a manner that each row is in line with the row
above and below.
Drum & Drum Internals
 Requirement
Separation of saturated steam from the steam-water mixture produced by
the evaporating tubes
 Mixing feed water from economiser and water separated from steam – water
mixture, and re-circulate through the evaporating tubes.
 Carrying out blow down for reduction of boiler water salt concentration.
 Treatment of Boiler water by chemicals


construction of drum

1

11

111
BOILER DRUM:
Construction: Fusion welded
Material specification: SA299
Design pressure: 204.9 kg/cm2
Maximum operating press: 193 kg/cm2
Thickness for straight portion: 195/165 mm
Overall length of drum : 22070 mm
Outside dia. Of Drum : 2138 mm
Internal dia. Of Drum :1778 mm
Elevation of drum centre above ground level: 71.583 meter
No. of distribution headers : 6
No. of cyclonic separator :92
No. of secondary dryers : 92
No. of final dryers : 124
Maximum permissible DT between any two parts of Drum : 50 0C
Connection to Boiler Drum

•
•
•

•


•
•

•
•
•
•
•

Main connection
Feed lines
Down comers
Up risers
Super heater supply tubes
Auxiliary connection
Blow down line
Chemical dosing line
Instrumentation tapping
Air vents
Safety valves
Nitrogen filling line
High and low level trips
Drum Internals
Feed

header
Anti vortex spider
Steam separator
Steam dryers or scrubbers
C.B.D. line
 E.B.D. line
 chemical dosing line
Water Walled Furnace
Requirement
 Advantages










In furnace not only combustion but also heat transfer is taking place
simultaneously.
The maintenance work involved in repairing the firebricks (which is
otherwise necessary) is completely eliminated.
Due to heat transfer in the furnace, temperature of the flue gas leaving
the furnace is reduced to the acceptable level of the superheating
surfaces.
Higher heat loading in the furnace is possible, as heat is being
simultaneously removed by heat transfer, and hence economy in
surfacing.
Providing a Gas tight seal to the combustion chamber to prevent air
infiltration.
Water Wall Furnace Constuction
Expansion and Sealing
53mm
29mm

58mm
174mm
36mm
330 mm
Buckstay and Furnace Guides
Superheaters
 Requirement?

By increasing the temperature of the steam, the useful energy that can be
recovered economically increases thus the efficiency of the cycle also as can
be seen in Fig.3.40.
 Superheating of steam eliminates the condensation of steam during
transporting of steam in pipelines and inside the early stages of turbines
which is harmful to the turbine blades and pipe lines.
 Limits the work done by turbine stages to avoid excessive erosion of blades

Types of superheater



radiant superheater
convective superheater
Relationship in SH Design







The steam temperature desired
The super heater surface area required
The rate of steam flow through the tubes (mass flow)
The material best suited for the super heater tubes
The gas temperature zones where the surfaces are to
be located
The arrangement of surfaces to meet the characteristics
of the fuel to be used with specific reference to the
spacing of tubes
Material for SH
ASME CODE

NOMINAL

TEMP.LIMIT 0C

COMPOSITION
SA 213

CARBON STEEL

450

SA 213 T1

C-1/2 Mo.

470

SA 213 T11

11/4 Cr. –1/2 Mo.

550

SA 213 T22

21/4 Cr.-1 Mo.

580

SA 213 T9

9 Cr.-1 Mo.

635

SA 213 TP 304 H

18 Cr.-8 Ni.

705

SA 213 TP 347 H

18 Cr.-10 Ni.

705

SA 213 TP 316 H

16 Cr.-12 Ni.-2 Mo.

705

Description

Tube Size

Material

Radiant Roof Tubes

i.
ii.

Ø 63.5 X 6.3
Ø 57 X 5.6

SA 213, T11
SA 213, T11

wall

i.
ii.
iii.

Ø 63.5 X 6.3
Ø 51 X 5
Ø 76.1 X 10

SA 210, Gr C
SA 210, Gr C
SA 210, Gr C

Steam Cooled front wall
tubes

i.
ii.
iii.

Ø 51 X 5
Ø 63.5 X 6.3
Ø 44.5 X 7.1

SA 210, Gr C
SA 210, Gr C
SA 210, Gr C

Front Wall Hanger Tubes

Ø 51 X 5.0

SA 210, Gr C

Rear Roof Tubes

i.
ii.

SA 210, Gr C
SA 210, Gr C

Steam
tubes

Cooled

Eco and
tubes

Side

LTSH

Support

Ø 51 X 5
Ø 44.5 X 7.1

Ø 47.63 X 8.6

SA 210, Gr C
Description

Tube Size

Material

Steam Cooled Side Wall tubes

Ø 51 X 5

SA 210, Gr C

Bifurcate Tubes (Bottom Header)

Ø 51 X 5

SA 210, Gr C

LTSH Horizontal Tubes

i.
ii.

Ø 51 X 5
Ø 51 X 5.6

SA 210, Gr C
SA 210, Gr C

Pendent Coil Tubes

i.
ii.

Ø 51 X 5
Ø 51 X 5.6

SA 213, T11
SA 213, T11

Divisional Panel inlet loose tubes

i.
ii.

Ø 51 X 6
Ø 44.5 X 4.5

SA 210, Gr C
SA 210, Gr C

Divisional Panel Outlet loose tubes

i.

Ø 51 X 6

SA 213, T11

Steam Cooled Spacer

i.
ii.
iii.
iv.
v.
vi.
vii.

Ø 63.5 X 8
Ø 51 X 5.6
Ø 63.5 X 6.5
Ø63.5 X 7.1
Ø 63.5 X 7.1
Ø 51 X 5.0
Ø 51 X 5.0

SA
SA
SA
SA
SA
SA
SA

213,
213,
213,
213,
210,
213,
210,

T11
TP347H
TP347H
T11
Gr C
T11
Gr C
Reheater
 Requirement?

Description

Tube Size

Material

Reheater Wall tubes

Ø 60.3 X 4

SA 313, T11

Cross over tubes

Ø 54 X 3.6

SA 213, T11
Sr
.

Heating Surface
Type

Area in m2

N
o.
1

Radiant roof, steam cooled wall LTSH

9620

Horizontal and pendent.
2

Super Heater Divisional Panel

1361

3

Final Super heater Platen

1458

4

Reheater radiant wall front and side,

5075

front platen, rear platen.
Total Heating Surface

17514 M2
Sr.

Parameters

Rating

No.
1

Super heater system flow

1681 TPH

2

Reheater System Flow

1430.64 TPH

3

Pressure at super heater outlet

179 Kg/cm2

4

Temperature at super heater outlet

540 oC

5

Pressure at reheater inlet

44.88 Kg/cm2 (g)

6

Temperature at reheater inlet

342.7 oC

7

Pressure at reheater outlet

42.68 Kg/cm2 (g)

8

Temperature of reheater outlet

540 oC

9

Feed Water temperature

255 oC

10

Ambient air temperature

28 oC

11

Combustion air temperature secondary

335 oC

12

Fuel Quantity

330 TPH

13

Air Quantity (Total Combustion air)

2030 TPH

14

Temperature of Gas at boiler exit

142 oC

15

Total Heat output of the system

1076 Kcal/Hr
BOILER AIR & FLUE GAS TEMPERATURES

PLSH

RH

MAX-134 ºC

FSH

DRUM
758-726 ºC

720 ºC

1020-793 ºC
1135-1020 ºC

LTSH
461 ºC

ECO
11001250

355 ºC
SA-318 ºC

APH
A
B

147 ºC

PA-313 ºC

143 ºC

137 ºC

ESP
BOILER WATER & STEAM TEMPERATURE

PLSH

RH

DRUM

FSH

286-349 ºC
520-540 ºC
344-540
426-520 ºC

1300-1400

349-426 ºC

LTSH

243-286 ºC ECO

APH
A
B

ESP
M.S

H.
R.
H

C.R.H

500MW BOILER

BCW
Pump
FROM F.R.S
BOTTOM RNG HDR

WW PANELS & 1ST PASS
W.W.

1ST PASS W.W O/L HDRS

ROOF I/L HEADER

2ND

2nd PASS LOWER C-HDRS

PASS UPPER C-HDR

LTSH I/L HEADER

LTSH & O/L HEADER

D.P.I/L HEADER

D.P.O/L HEADER

FINAL S.H.

R.H.HEADER

2ND

ECONOMISER

PASS ROOF O/L HDR(REAR
Construction of 500 MW Steam Boiler

Contenu connexe

Tendances

Tendances (20)

Steam generator part 2
Steam generator part 2Steam generator part 2
Steam generator part 2
 
Presentation on CFBC Boilers
Presentation on CFBC BoilersPresentation on CFBC Boilers
Presentation on CFBC Boilers
 
Materials used in boiler & furnace
Materials used in boiler & furnaceMaterials used in boiler & furnace
Materials used in boiler & furnace
 
Boiler light up & loading
Boiler light up & loadingBoiler light up & loading
Boiler light up & loading
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
Air heater
Air heaterAir heater
Air heater
 
coal pulveriser
coal pulveriser coal pulveriser
coal pulveriser
 
500 mw utility boiler ppt
500 mw utility boiler ppt500 mw utility boiler ppt
500 mw utility boiler ppt
 
Training material for air preheater
Training material for air preheaterTraining material for air preheater
Training material for air preheater
 
Evaluation of a Boiler performance
Evaluation of a Boiler performanceEvaluation of a Boiler performance
Evaluation of a Boiler performance
 
High pressure boiler
High pressure boilerHigh pressure boiler
High pressure boiler
 
Steam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsSteam Boilers OR Steam Generators
Steam Boilers OR Steam Generators
 
Air Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance IndicesAir Heater and PF Boiler Performance Indices
Air Heater and PF Boiler Performance Indices
 
Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculation
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbines
 
Heat rate of coal fired power plant
Heat rate of coal fired power plantHeat rate of coal fired power plant
Heat rate of coal fired power plant
 
Boiler Water Circulation Pumps
Boiler Water Circulation PumpsBoiler Water Circulation Pumps
Boiler Water Circulation Pumps
 
performance analysis of steam boiler
performance analysis of steam boilerperformance analysis of steam boiler
performance analysis of steam boiler
 
Study and Analysis of Tube Failure in Water Tube boiler
Study and Analysis of Tube Failure in Water Tube boilerStudy and Analysis of Tube Failure in Water Tube boiler
Study and Analysis of Tube Failure in Water Tube boiler
 
Performance calculation for feed water heater
Performance calculation  for feed water heaterPerformance calculation  for feed water heater
Performance calculation for feed water heater
 

En vedette

Relief and safety valves for thermal power plants
Relief and safety valves for thermal power plantsRelief and safety valves for thermal power plants
Relief and safety valves for thermal power plants
SHIVAJI CHOUDHURY
 
Yokogawa Presantesation(1)
Yokogawa Presantesation(1)Yokogawa Presantesation(1)
Yokogawa Presantesation(1)
Maulik kunjadiya
 
Preparación física eapecífica para voleibolistas
Preparación física eapecífica para voleibolistasPreparación física eapecífica para voleibolistas
Preparación física eapecífica para voleibolistas
Fito Gómez
 
Preparación Física - Curso Entrenador Nivel I Voleibol
Preparación Física - Curso Entrenador Nivel I VoleibolPreparación Física - Curso Entrenador Nivel I Voleibol
Preparación Física - Curso Entrenador Nivel I Voleibol
Rafa Luque
 

En vedette (20)

Improving steam boiler operating efficiency
Improving steam boiler operating efficiencyImproving steam boiler operating efficiency
Improving steam boiler operating efficiency
 
Steam boiler
Steam boilerSteam boiler
Steam boiler
 
Classification of boilers and working of cochran boiler
Classification of boilers and working of cochran boilerClassification of boilers and working of cochran boiler
Classification of boilers and working of cochran boiler
 
Metal Construction & Boiler Making Projects - DEGIMA Engineering civil&naval ...
Metal Construction & Boiler Making Projects - DEGIMA Engineering civil&naval ...Metal Construction & Boiler Making Projects - DEGIMA Engineering civil&naval ...
Metal Construction & Boiler Making Projects - DEGIMA Engineering civil&naval ...
 
Boiler Mountings
Boiler MountingsBoiler Mountings
Boiler Mountings
 
Gas power plant
Gas power plantGas power plant
Gas power plant
 
High Pressure Boilers
High Pressure BoilersHigh Pressure Boilers
High Pressure Boilers
 
Boiler Operation
Boiler OperationBoiler Operation
Boiler Operation
 
Boiler final
Boiler finalBoiler final
Boiler final
 
Steam generator part 3
Steam generator part 3Steam generator part 3
Steam generator part 3
 
High pressure boilers (1)
High pressure boilers (1)High pressure boilers (1)
High pressure boilers (1)
 
Relief and safety valves for thermal power plants
Relief and safety valves for thermal power plantsRelief and safety valves for thermal power plants
Relief and safety valves for thermal power plants
 
Yokogawa Presantesation(1)
Yokogawa Presantesation(1)Yokogawa Presantesation(1)
Yokogawa Presantesation(1)
 
Water and fire tube boilers
Water and fire tube boilersWater and fire tube boilers
Water and fire tube boilers
 
FIVB MANUAL DEL ENTRENADOR DE VOLEIBOL _2
FIVB MANUAL DEL ENTRENADOR DE VOLEIBOL _2FIVB MANUAL DEL ENTRENADOR DE VOLEIBOL _2
FIVB MANUAL DEL ENTRENADOR DE VOLEIBOL _2
 
Preparación física eapecífica para voleibolistas
Preparación física eapecífica para voleibolistasPreparación física eapecífica para voleibolistas
Preparación física eapecífica para voleibolistas
 
Industrial boilers Easy Explained A to Z with Design & Analysis
Industrial boilers Easy Explained A to Z with Design & AnalysisIndustrial boilers Easy Explained A to Z with Design & Analysis
Industrial boilers Easy Explained A to Z with Design & Analysis
 
Libro manual voleibol I y II, teorico 1 SICCED
Libro manual voleibol I y II, teorico 1 SICCEDLibro manual voleibol I y II, teorico 1 SICCED
Libro manual voleibol I y II, teorico 1 SICCED
 
Boiler mountings & accessories
Boiler mountings & accessoriesBoiler mountings & accessories
Boiler mountings & accessories
 
Preparación Física - Curso Entrenador Nivel I Voleibol
Preparación Física - Curso Entrenador Nivel I VoleibolPreparación Física - Curso Entrenador Nivel I Voleibol
Preparación Física - Curso Entrenador Nivel I Voleibol
 

Similaire à Construction of 500 MW Steam Boiler

Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)
IJERD Editor
 
MET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generatorsMET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generators
Ibrahim AboKhalil
 
Steam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdfSteam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdf
GaluhAjeng26
 
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
Radha Krishna Sahoo
 

Similaire à Construction of 500 MW Steam Boiler (20)

A Brief Introduction to Boilers
A Brief Introduction to BoilersA Brief Introduction to Boilers
A Brief Introduction to Boilers
 
STEAM GENERATORS.pptx
STEAM GENERATORS.pptxSTEAM GENERATORS.pptx
STEAM GENERATORS.pptx
 
HEATING AND VENTILATION
HEATING AND VENTILATIONHEATING AND VENTILATION
HEATING AND VENTILATION
 
BOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfBOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdf
 
Study of Boilers for Mechanical Engineering
Study of Boilers for Mechanical EngineeringStudy of Boilers for Mechanical Engineering
Study of Boilers for Mechanical Engineering
 
Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)
 
MET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generatorsMET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generators
 
Steam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdfSteam_Boiler_Basics_tim_powell_hughes.pdf
Steam_Boiler_Basics_tim_powell_hughes.pdf
 
All about boilers: Complete Basics, Classification of boilers,types
All about boilers: Complete Basics, Classification of boilers,typesAll about boilers: Complete Basics, Classification of boilers,types
All about boilers: Complete Basics, Classification of boilers,types
 
Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC Ramagunadam
 
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...Husk based power plant 6 t 32 kg fbc with single stage turbine   for finance,...
Husk based power plant 6 t 32 kg fbc with single stage turbine for finance,...
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
Unit II boiloers and its mountings
Unit II boiloers and its mountingsUnit II boiloers and its mountings
Unit II boiloers and its mountings
 
Boiler md. shahidul ilsam
Boiler md. shahidul ilsamBoiler md. shahidul ilsam
Boiler md. shahidul ilsam
 
Boiler
BoilerBoiler
Boiler
 
waste heat bolier
waste heat bolierwaste heat bolier
waste heat bolier
 
ppt of EME
ppt of EMEppt of EME
ppt of EME
 
Boilers ppt (energy conversion)
Boilers ppt (energy conversion)Boilers ppt (energy conversion)
Boilers ppt (energy conversion)
 
steam boilers.pptx
steam boilers.pptxsteam boilers.pptx
steam boilers.pptx
 
Steam generators
Steam generatorsSteam generators
Steam generators
 

Dernier

Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 

Dernier (20)

Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Manulife - Insurer Innovation Award 2024
Manulife - Insurer Innovation Award 2024Manulife - Insurer Innovation Award 2024
Manulife - Insurer Innovation Award 2024
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
HTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation StrategiesHTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation Strategies
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 

Construction of 500 MW Steam Boiler

  • 1. Construction of 500 mw boiler by Vaibhav G. Paydelwar ( Project Engineer) Sunil Hi-Tech Engineers Limited
  • 2. WHAT DO YOU MEAN BY BOILER ?  Boiler means any closed vessel exceeding 22.75 Ltr. in capacity used for steam generation under pressure. The first boiler was developed in 1725 and its working pressure was 10 kg/ cm2.  Boiler can be regarded as a number of interconnected heat exchangers arranged in such manner that heat available by burning of fuel is transferred to convert water into steam in most efficient manner.
  • 3. FUNCTION OF BOILER  To produce the steam at the desired rate at desired pressure and temperature with use of resources such as oil, coal & water for generating the power.
  • 4. Types of Boilers Natural circulation Boiler :Drum to down comer - to main ring header – to ww tubes and back -to drum. Due to difference in density of water and steam this types of circulation takes place.  Forced circulation (Assisted circulation) Boiler :As per operating pressure of the boiler approaches to the critical pressure, additional pumps are required to install in down comers, because at this pressure there is no appreciable density difference between water and steam to have natural circulation of water.
  • 5. NEED FOR ASSISTED CIRCULATION 0.7 Density of Water 0.6 0.5 0.4 Critical Point 0.3 0.2 0.1 Density of Steam 0 80 100 120 140 160 180 Pressure (Kg/cm2) 200 220 240
  • 6. According to working pressure Sub critical pressure boiler : when working pressure of boiler is between 130 to 180 kg/ cm2 critical boiler : when working pressure of boiler is 225.56 kg/ cm2 Super critical boiler : when working pressure of boiler is 240.10 kg/ cm2
  • 7. Why to go for higher capacity ? 1’-2’ = Work done in turbine from P1 – P2 2’-3 = Heat Rejection in condenser 3-4 = Water pumped to boiler 4-1 = Heat addition in eco and boiler.
  • 8. SPECIAL FEATURES OF 500MW BOILER Controlled circulation of feed water in water walls with the help of 3 Nos. of boiler circulating water pumps installed on down comers. Rifled bore water wall tubes as against smooth bore tubes in 210 MW boiler.  Provision of Orifices for equal distribution of water in water wall tubes from bottom ring header.  All down comers are connected to front header of the bottom ring header. 
  • 9. DESIGN FACTOR For the construction of boiler parts subjected to pressure and their integral attachment, the designer takes into account several factors  Relative Cost  Mechanical Properties  Manufacturing Method  Scaling Resistance  Maintenance
  • 10. Various parts of Boiler BOILER IS DIVIDED INTO TWO PASS: FIRST PASS  SECOND PASS First pass of the boiler consists of:-  Furnace water wall.  Divisional super heater pendent assembly.  Final Super heater pendent assembly.  Reheater front pendent assembly. (CRH)  Reheater rear pendent assembly. (HRH)  Rear Arch Panel.  Water Wall screen tubes.
  • 11. Second pass of the boiler consists of: Steam cooled wall.  Economizer lower bank coils.  Economizer middle bank coils.  Economizer upper bank coils.  LTSH lower bank coils  LTSH upper bank coils  Eco. Hanger tubes.  LTSH terminal tubes.
  • 12. ECONOMISER  Requirement why ?  Advantages • • As the economiser recover the heat in the flue gas that leaves the boiler and transfer to working fluid there will be saving in fuel consumption. As the feed water is preheated in the economiser and enter the boiler tube at an elevated temperature( near to saturation temp.) the heat transfer area required for the evaporation surface required will be reduce considerably. As the size of boiler also will be reduced.  Types of Economiser Steaming  Non steaming • Plain tube economiser • Fin-tube economiser 
  • 13. Plain tubes Direction of Gas Flow Direction of Gas Flow Inline Arrangement Staggered Arrangement
  • 15. Tube size and spacing   The tubes can be made any length and diameter with 38mm to 52mm OD. The side spacing and back spacing can be arranged for good cleaning, absorption of heat and less draught loss. Spacing about 90mm to 140mm. It is composed of three banks of 130 parallel tube elements arranged in horizontal rows in such a manner that each row is in line with the row above and below.
  • 16. Drum & Drum Internals  Requirement Separation of saturated steam from the steam-water mixture produced by the evaporating tubes  Mixing feed water from economiser and water separated from steam – water mixture, and re-circulate through the evaporating tubes.  Carrying out blow down for reduction of boiler water salt concentration.  Treatment of Boiler water by chemicals  construction of drum 1 11 111
  • 17. BOILER DRUM: Construction: Fusion welded Material specification: SA299 Design pressure: 204.9 kg/cm2 Maximum operating press: 193 kg/cm2 Thickness for straight portion: 195/165 mm Overall length of drum : 22070 mm Outside dia. Of Drum : 2138 mm Internal dia. Of Drum :1778 mm Elevation of drum centre above ground level: 71.583 meter No. of distribution headers : 6 No. of cyclonic separator :92 No. of secondary dryers : 92 No. of final dryers : 124 Maximum permissible DT between any two parts of Drum : 50 0C
  • 18. Connection to Boiler Drum  • • • •  • • • • • • • Main connection Feed lines Down comers Up risers Super heater supply tubes Auxiliary connection Blow down line Chemical dosing line Instrumentation tapping Air vents Safety valves Nitrogen filling line High and low level trips
  • 19.
  • 20. Drum Internals Feed header Anti vortex spider Steam separator Steam dryers or scrubbers C.B.D. line  E.B.D. line  chemical dosing line
  • 21.
  • 22. Water Walled Furnace Requirement  Advantages       In furnace not only combustion but also heat transfer is taking place simultaneously. The maintenance work involved in repairing the firebricks (which is otherwise necessary) is completely eliminated. Due to heat transfer in the furnace, temperature of the flue gas leaving the furnace is reduced to the acceptable level of the superheating surfaces. Higher heat loading in the furnace is possible, as heat is being simultaneously removed by heat transfer, and hence economy in surfacing. Providing a Gas tight seal to the combustion chamber to prevent air infiltration.
  • 23. Water Wall Furnace Constuction
  • 24.
  • 27. Superheaters  Requirement? By increasing the temperature of the steam, the useful energy that can be recovered economically increases thus the efficiency of the cycle also as can be seen in Fig.3.40.  Superheating of steam eliminates the condensation of steam during transporting of steam in pipelines and inside the early stages of turbines which is harmful to the turbine blades and pipe lines.  Limits the work done by turbine stages to avoid excessive erosion of blades 
  • 28. Types of superheater   radiant superheater convective superheater
  • 29. Relationship in SH Design       The steam temperature desired The super heater surface area required The rate of steam flow through the tubes (mass flow) The material best suited for the super heater tubes The gas temperature zones where the surfaces are to be located The arrangement of surfaces to meet the characteristics of the fuel to be used with specific reference to the spacing of tubes
  • 30. Material for SH ASME CODE NOMINAL TEMP.LIMIT 0C COMPOSITION SA 213 CARBON STEEL 450 SA 213 T1 C-1/2 Mo. 470 SA 213 T11 11/4 Cr. –1/2 Mo. 550 SA 213 T22 21/4 Cr.-1 Mo. 580 SA 213 T9 9 Cr.-1 Mo. 635 SA 213 TP 304 H 18 Cr.-8 Ni. 705 SA 213 TP 347 H 18 Cr.-10 Ni. 705 SA 213 TP 316 H 16 Cr.-12 Ni.-2 Mo. 705 Description Tube Size Material Radiant Roof Tubes i. ii. Ø 63.5 X 6.3 Ø 57 X 5.6 SA 213, T11 SA 213, T11 wall i. ii. iii. Ø 63.5 X 6.3 Ø 51 X 5 Ø 76.1 X 10 SA 210, Gr C SA 210, Gr C SA 210, Gr C Steam Cooled front wall tubes i. ii. iii. Ø 51 X 5 Ø 63.5 X 6.3 Ø 44.5 X 7.1 SA 210, Gr C SA 210, Gr C SA 210, Gr C Front Wall Hanger Tubes Ø 51 X 5.0 SA 210, Gr C Rear Roof Tubes i. ii. SA 210, Gr C SA 210, Gr C Steam tubes Cooled Eco and tubes Side LTSH Support Ø 51 X 5 Ø 44.5 X 7.1 Ø 47.63 X 8.6 SA 210, Gr C
  • 31. Description Tube Size Material Steam Cooled Side Wall tubes Ø 51 X 5 SA 210, Gr C Bifurcate Tubes (Bottom Header) Ø 51 X 5 SA 210, Gr C LTSH Horizontal Tubes i. ii. Ø 51 X 5 Ø 51 X 5.6 SA 210, Gr C SA 210, Gr C Pendent Coil Tubes i. ii. Ø 51 X 5 Ø 51 X 5.6 SA 213, T11 SA 213, T11 Divisional Panel inlet loose tubes i. ii. Ø 51 X 6 Ø 44.5 X 4.5 SA 210, Gr C SA 210, Gr C Divisional Panel Outlet loose tubes i. Ø 51 X 6 SA 213, T11 Steam Cooled Spacer i. ii. iii. iv. v. vi. vii. Ø 63.5 X 8 Ø 51 X 5.6 Ø 63.5 X 6.5 Ø63.5 X 7.1 Ø 63.5 X 7.1 Ø 51 X 5.0 Ø 51 X 5.0 SA SA SA SA SA SA SA 213, 213, 213, 213, 210, 213, 210, T11 TP347H TP347H T11 Gr C T11 Gr C
  • 32. Reheater  Requirement? Description Tube Size Material Reheater Wall tubes Ø 60.3 X 4 SA 313, T11 Cross over tubes Ø 54 X 3.6 SA 213, T11
  • 33. Sr . Heating Surface Type Area in m2 N o. 1 Radiant roof, steam cooled wall LTSH 9620 Horizontal and pendent. 2 Super Heater Divisional Panel 1361 3 Final Super heater Platen 1458 4 Reheater radiant wall front and side, 5075 front platen, rear platen. Total Heating Surface 17514 M2
  • 34. Sr. Parameters Rating No. 1 Super heater system flow 1681 TPH 2 Reheater System Flow 1430.64 TPH 3 Pressure at super heater outlet 179 Kg/cm2 4 Temperature at super heater outlet 540 oC 5 Pressure at reheater inlet 44.88 Kg/cm2 (g) 6 Temperature at reheater inlet 342.7 oC 7 Pressure at reheater outlet 42.68 Kg/cm2 (g) 8 Temperature of reheater outlet 540 oC 9 Feed Water temperature 255 oC 10 Ambient air temperature 28 oC 11 Combustion air temperature secondary 335 oC 12 Fuel Quantity 330 TPH 13 Air Quantity (Total Combustion air) 2030 TPH 14 Temperature of Gas at boiler exit 142 oC 15 Total Heat output of the system 1076 Kcal/Hr
  • 35. BOILER AIR & FLUE GAS TEMPERATURES PLSH RH MAX-134 ºC FSH DRUM 758-726 ºC 720 ºC 1020-793 ºC 1135-1020 ºC LTSH 461 ºC ECO 11001250 355 ºC SA-318 ºC APH A B 147 ºC PA-313 ºC 143 ºC 137 ºC ESP
  • 36. BOILER WATER & STEAM TEMPERATURE PLSH RH DRUM FSH 286-349 ºC 520-540 ºC 344-540 426-520 ºC 1300-1400 349-426 ºC LTSH 243-286 ºC ECO APH A B ESP
  • 37. M.S H. R. H C.R.H 500MW BOILER BCW Pump FROM F.R.S BOTTOM RNG HDR WW PANELS & 1ST PASS W.W. 1ST PASS W.W O/L HDRS ROOF I/L HEADER 2ND 2nd PASS LOWER C-HDRS PASS UPPER C-HDR LTSH I/L HEADER LTSH & O/L HEADER D.P.I/L HEADER D.P.O/L HEADER FINAL S.H. R.H.HEADER 2ND ECONOMISER PASS ROOF O/L HDR(REAR