SlideShare une entreprise Scribd logo
1  sur  13
PERT & CPM
SHASHWATVISHWAKARMA
1304
Introduction
■ Project management can be understood as a systematic way of planning, scheduling,
executing, monitoring, controlling the different aspects of the project, so as to attain the
goal made at the time of project formulation.
■ PERT and CPM are the two network based project management techniques, which
exhibit the flow and sequence of the activities and events.
■ Program (Project) Management and ReviewTechnique (PERT) is appropriate for the
projects where time needed to complete different activities are not known.
■ Critical Path Method or CPM, is apt for the projects which are recurring in nature.
PERT
■ PERT is an acronym for Program (Project) Evaluation and ReviewTechnique, in which planning,
scheduling, organising, coordinating and controlling of uncertain activities take place.
■ The technique studies and represents the tasks undertaken to complete a project, to identify
the least time for completing a task and the minimum time required to complete the whole
project.
■ It is aimed to reduce the time and cost of the project.
■ PERT uses time as a variable which represents the planned resource application along
with performance specification.
■ In this technique, first of all, the project is divided into activities and events. After that
proper sequence is ascertained, and a network is constructed.
■ After that time needed in each activity is calculated and the critical path (longest path
connecting all the events) is determined.
CPM
■ Developed in the late 1950’s,Critical Path Method or CPM is an algorithm used for
planning, scheduling, coordination and control of activities in a project.
■ Here, it is assumed that the activity duration are fixed and certain. CPM is used to
compute the earliest and latest possible start time for each activity.
■ The process differentiates the critical and non-critical activities to reduce the time and
avoid the queue generation in the process.The reason behind the identification of
critical activities is that, if any activity is delayed, it will cause the whole process to
suffer.That is why it is named as Critical Path Method.
CPM
■ In this method, first of all, a list is prepared consisting of all the activities needed to
complete a project, followed by the computation of time required to complete each
activity.
■ After that, the dependency between the activities is determined. Here, ‘path’ is
defined as a sequence of activities in a network.
■ The critical path is the path with the highest length.
TECHNICALTERMS USED IN C.P.M
[CRITICAL PATH METHOD]
ACTIVITY
An activity is a part of the project denoted by an arrow on the network.
The tail of the arrow indicates the start of the activity whereas the head indicates the end
of the activity.
One and only one arrow is used to represent one activity of given duration.The arrows of
the activities are not drawn to scale.
The durations of the activities are written along their arrows.
(2) DUMMYACTIVITY
The activity which neither uses any resources nor any time for its completion is called
dummy activity. It is represented by a dotted arrow or a solid arrow with zero time
duration.
(3) EVENT
Event is the stage or point where all previous jobs merging in it are completed and the
jobs bursting out are still to be completed.
See the figure shown below-
■ Event 1 is the starting point of the project.
■ Event 6 is the point where activities B(3), F(3), H(2) and K(5) merge and activity L(4)
bursts.
■ Events are generally represented by circles or nodes at the junctions of arrows. Events
are serially numbered in their sequential order.
(4) NETWORK
The diagrammatic representation of the activities of the entire project is called network of
flow diagram. On this diagram various jobs of the project are shown in the order in which
these are required to be performed.
(5) EARLY STARTTIME (E.S.T.)
The earliest possible time at which an activity may start, is called early start time.
(6) EARLY FINISHTIME (E.F.T.)
The sum of the earliest start time of an activity and the time required for its completion is
called early finish time.
(7) LATE STARTTIME (L.S.T.)
The latest possible time at which an activity may start without delaying the date of the
project, is called late start time.
(8) LATE FINISHTIME (L.F.T.)
The sum of the late start time of an activity and the time required for its completion is
called late finish time.
(9)TOTAL FLOAT
The difference between the maximum time allowed for an activity and its estimated
duration is called total float. It is the duration of time by which the activity can be started
late, without disturbing the project schedule. It is generally denoted by S.
(10) FREE FLOAT
The duration of time by which the completion time of an activity can be delayed without
affecting the start of succeeding activities is called free float. It is generally denoted
by S.F.
(11) CRITICALACTIVITIES
The event which has no float, are called critical activities.The critical events are required
to be completed on schedule.
(12) CRITICAL PATH
The path in the network joining the critical events is called the critical path of the work.
Comparison between PERT and CPM
PERT CPM
PERT is a project management technique, used
to manage uncertain activities of a project.
CPM is a statistical technique of project
management that manages well defined
activities of a project.
A technique of planning and control of time. A method to control cost and time.
Event-oriented Activity-oriented
Evolved as Research & Development project Evolved as Construction project
Probabilistic Model Deterministic Model
Time Time-cost trade-off
Three time estimates One time estimate

Contenu connexe

Tendances (20)

crashing of project
crashing of project crashing of project
crashing of project
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPM
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Pert
PertPert
Pert
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
Float in Projects
Float in ProjectsFloat in Projects
Float in Projects
 

Similaire à PERT and CPM

Similaire à PERT and CPM (20)

Nce603 mod unit2
Nce603 mod unit2Nce603 mod unit2
Nce603 mod unit2
 
Project managemen PERT VS CPM
Project managemen  PERT VS CPMProject managemen  PERT VS CPM
Project managemen PERT VS CPM
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
A760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.pptA760535773_16727_28_2018_u6.ppt
A760535773_16727_28_2018_u6.ppt
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
06 pert cpm (1)
06 pert cpm (1)06 pert cpm (1)
06 pert cpm (1)
 
PERT/CPM
PERT/CPMPERT/CPM
PERT/CPM
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
porject management
porject managementporject management
porject management
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
S pert cpm
S pert cpmS pert cpm
S pert cpm
 

Plus de student

E-Rickshaw market in India
E-Rickshaw market in India E-Rickshaw market in India
E-Rickshaw market in India student
 
Business canvassing
Business canvassingBusiness canvassing
Business canvassingstudent
 
Presentation corporate
Presentation corporatePresentation corporate
Presentation corporatestudent
 
Presentation (1)
Presentation (1)Presentation (1)
Presentation (1)student
 
Capstone presentation
Capstone presentationCapstone presentation
Capstone presentationstudent
 
Valuation of bond and shares
Valuation of bond and sharesValuation of bond and shares
Valuation of bond and sharesstudent
 
Decline in market share of Bajaj 2 wheeler in India
Decline in market share of Bajaj  2 wheeler in IndiaDecline in market share of Bajaj  2 wheeler in India
Decline in market share of Bajaj 2 wheeler in Indiastudent
 
E-waste as construction materials
E-waste as construction materialsE-waste as construction materials
E-waste as construction materialsstudent
 
Eureka forbes presentation
Eureka forbes presentationEureka forbes presentation
Eureka forbes presentationstudent
 

Plus de student (9)

E-Rickshaw market in India
E-Rickshaw market in India E-Rickshaw market in India
E-Rickshaw market in India
 
Business canvassing
Business canvassingBusiness canvassing
Business canvassing
 
Presentation corporate
Presentation corporatePresentation corporate
Presentation corporate
 
Presentation (1)
Presentation (1)Presentation (1)
Presentation (1)
 
Capstone presentation
Capstone presentationCapstone presentation
Capstone presentation
 
Valuation of bond and shares
Valuation of bond and sharesValuation of bond and shares
Valuation of bond and shares
 
Decline in market share of Bajaj 2 wheeler in India
Decline in market share of Bajaj  2 wheeler in IndiaDecline in market share of Bajaj  2 wheeler in India
Decline in market share of Bajaj 2 wheeler in India
 
E-waste as construction materials
E-waste as construction materialsE-waste as construction materials
E-waste as construction materials
 
Eureka forbes presentation
Eureka forbes presentationEureka forbes presentation
Eureka forbes presentation
 

Dernier

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 

Dernier (20)

Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 

PERT and CPM

  • 2. Introduction ■ Project management can be understood as a systematic way of planning, scheduling, executing, monitoring, controlling the different aspects of the project, so as to attain the goal made at the time of project formulation. ■ PERT and CPM are the two network based project management techniques, which exhibit the flow and sequence of the activities and events. ■ Program (Project) Management and ReviewTechnique (PERT) is appropriate for the projects where time needed to complete different activities are not known. ■ Critical Path Method or CPM, is apt for the projects which are recurring in nature.
  • 3. PERT ■ PERT is an acronym for Program (Project) Evaluation and ReviewTechnique, in which planning, scheduling, organising, coordinating and controlling of uncertain activities take place. ■ The technique studies and represents the tasks undertaken to complete a project, to identify the least time for completing a task and the minimum time required to complete the whole project. ■ It is aimed to reduce the time and cost of the project.
  • 4. ■ PERT uses time as a variable which represents the planned resource application along with performance specification. ■ In this technique, first of all, the project is divided into activities and events. After that proper sequence is ascertained, and a network is constructed. ■ After that time needed in each activity is calculated and the critical path (longest path connecting all the events) is determined.
  • 5. CPM ■ Developed in the late 1950’s,Critical Path Method or CPM is an algorithm used for planning, scheduling, coordination and control of activities in a project. ■ Here, it is assumed that the activity duration are fixed and certain. CPM is used to compute the earliest and latest possible start time for each activity. ■ The process differentiates the critical and non-critical activities to reduce the time and avoid the queue generation in the process.The reason behind the identification of critical activities is that, if any activity is delayed, it will cause the whole process to suffer.That is why it is named as Critical Path Method.
  • 6. CPM ■ In this method, first of all, a list is prepared consisting of all the activities needed to complete a project, followed by the computation of time required to complete each activity. ■ After that, the dependency between the activities is determined. Here, ‘path’ is defined as a sequence of activities in a network. ■ The critical path is the path with the highest length.
  • 7. TECHNICALTERMS USED IN C.P.M [CRITICAL PATH METHOD] ACTIVITY An activity is a part of the project denoted by an arrow on the network. The tail of the arrow indicates the start of the activity whereas the head indicates the end of the activity. One and only one arrow is used to represent one activity of given duration.The arrows of the activities are not drawn to scale. The durations of the activities are written along their arrows.
  • 8. (2) DUMMYACTIVITY The activity which neither uses any resources nor any time for its completion is called dummy activity. It is represented by a dotted arrow or a solid arrow with zero time duration. (3) EVENT Event is the stage or point where all previous jobs merging in it are completed and the jobs bursting out are still to be completed.
  • 9. See the figure shown below- ■ Event 1 is the starting point of the project. ■ Event 6 is the point where activities B(3), F(3), H(2) and K(5) merge and activity L(4) bursts. ■ Events are generally represented by circles or nodes at the junctions of arrows. Events are serially numbered in their sequential order.
  • 10. (4) NETWORK The diagrammatic representation of the activities of the entire project is called network of flow diagram. On this diagram various jobs of the project are shown in the order in which these are required to be performed. (5) EARLY STARTTIME (E.S.T.) The earliest possible time at which an activity may start, is called early start time. (6) EARLY FINISHTIME (E.F.T.) The sum of the earliest start time of an activity and the time required for its completion is called early finish time.
  • 11. (7) LATE STARTTIME (L.S.T.) The latest possible time at which an activity may start without delaying the date of the project, is called late start time. (8) LATE FINISHTIME (L.F.T.) The sum of the late start time of an activity and the time required for its completion is called late finish time. (9)TOTAL FLOAT The difference between the maximum time allowed for an activity and its estimated duration is called total float. It is the duration of time by which the activity can be started late, without disturbing the project schedule. It is generally denoted by S.
  • 12. (10) FREE FLOAT The duration of time by which the completion time of an activity can be delayed without affecting the start of succeeding activities is called free float. It is generally denoted by S.F. (11) CRITICALACTIVITIES The event which has no float, are called critical activities.The critical events are required to be completed on schedule. (12) CRITICAL PATH The path in the network joining the critical events is called the critical path of the work.
  • 13. Comparison between PERT and CPM PERT CPM PERT is a project management technique, used to manage uncertain activities of a project. CPM is a statistical technique of project management that manages well defined activities of a project. A technique of planning and control of time. A method to control cost and time. Event-oriented Activity-oriented Evolved as Research & Development project Evolved as Construction project Probabilistic Model Deterministic Model Time Time-cost trade-off Three time estimates One time estimate