SlideShare une entreprise Scribd logo
1  sur  26
 Presented by : Aazam Nirban
 Civil Engineering Department
 T. Y. Civil
 3105
Presentation on
BURJ KHALIFA
 The Burj Khalifa is the ever built tallest
man made structure.
 This tower rises in the sky to 828m
carrying 162 floors.
 The Burj khalifa took 6years for its
construction
and was completed in the year 2010.
 For erecting this city in the sky several
new technologies had to be used.
INTRODUCTION
 The soil stratum of Dubai is very week
so they had to excavate up to 50m
deep to get a hard rock structure
 But the rock that they found was
fragile and saturated with ground
water
 So that any hole made
will be cured immediately
EXCAVATION
 The engineers filled this with a viscous polymer
slurry
 This pushes the rock and the ground water to the
edges of the boreholes to keep it open
 This slurry is denser than water and liter than
concrete, so that when concrete is pumped the
concrete displaces the fluid and forms the
foundation.
 194 piles were constructed
for avoiding the sinking of
this structure.
EXCAVATION Cont.
 The casting of the whole structure is mainly done by two
materials
1. Concrete
2. Steel
 Over 30,000 tons of steel were used
 About 250,000 m2 concrete was also used
 The reinforced concrete acts as the backbone of the whole
structure
CASTING OF THE STRUCTURE
 The Burj can accommodate about 35,000 people
at a time
 Consist of 57 elevators and 8 escalators
 The biggest elevator carries about 46 people at
a time
 These elevators travel at a speed of 35km/hr
 The Burj has a service/firemans elevator which
have a capacity to hold about 5,500kg
 And this is the worlds tallest service elevator.
ELEVATORS AND ESCALATORS
 The Burj is cladded with high-tech glass which
forms as a curtain wall
 If the whole cladding has to be done with high-
tech glass which will cost about 100 million
dollars
CLADDING OF THE TOWER
 The cladding should withstand the heavy sand
storms that with in include water and dust
 Prototypes were selected and with the help of
propellers artificially created storm was
allowed to hit the glass panels at a greater
speed
 The glass panels withstands the storm up to
75km/hr
TEST FOR THE CLADDING AGAINST
STORM
 As the building has to be built more than half a
km, it had to challenge many factors that
haven't faced by any other building
 Has to be completed with in the short period
limit
 So the time was money
 For erecting such a structure in the sky steel
and glass panels have to be raised
 This was done by cranes
SPEED OF CONSTRUCTION
 The cranes consist of two plates on the two
sides
 It could jump from one floor to the another
 So that they were called the kangaroo cranes
 So as to speed up the construction the RCC
walls was done in a simple and clever
engineering way.
Cranes
 For simplicity and speed the engineers made no. of steel cages
 These cages were inserted to the formworks that can be moved easily
 After installation of cages concrete was filled in these formworks
 Only took 12hrs for the setting of concrete
 After setting the concrete the formworks would move to the next
level with in 2hrs
CASTING OF RCC WALLS
 High performance concrete(HPC)
 Low permeability
 High durability
 C80-C60 cube strength concrete was used
 It includes fly ash, Portland cement
 Two largest concrete pumping machines in the world were used for
this purpose
 For reducing cracks due to high temperature concreting was done only
at night
 So that air is cooler and humidity is higher with ice added to the mix
CONCRETE USED
 The pump needs 630HP to pump about 25000 tons of concrete
 It had took about 14 mints for reaching the concrete to the 150th
floor
 They completed every new floor in 3 day
CONCRETE USED Cont.
 Every year the storm attacks Dubai
 As the building grows much higher to the sky the top will be badly
affected by the wind
 This causes a sway at the top floors of the building
 So that they studied many other skyscrapers
 The buildings must be in a definite shape
WIND
 They made a study on the Sears tower at
Chicago
 The Sears tower had a layer of steel, and
an another layer of steel which forms an
exoskeleton to the building
 9 such blocks were used in this Sears
tower in definite shape
 So that the building was made rock solid
SHAPE
 Giving the Burj a exoskeleton was not a easy
task
 So they designed the Burj in a triangular shape
 So that this was suitable to deflect the wind to
different ways
SHAPE Cont.
 The three wings allow for greater building
height by buttressing one another by a central
core hence it is called buttressed core structural
system
 This buttressed core is a six sided central piece
 So that it is called a Hexagonal Hub
BUTTRESSED CORE
 This hub is surrounded by the three wings
 These three wings afford the torsional
resistance and the twisting of the tower
 This hub encloses the elevators
BUTTRESSED CORE Cont.
 The earthquake was one of the most important factor that had to be
challenged by the Burj Khalifa
 Any unknown concept would collapse the whole structure
 They took the Taipie101 tower for their study
EARTHQUAKE
 A year twice China is affected with earthquakes
 The Taipei 101 was raised up with 36 steel tubes
 They were filled with concrete for their rigidity
TAIPEI 101
 These columns were holding together
with outrigger trusses
 So that these elastic bands would
recover the whole movement occurred
to the building
TAIPEI 101 Cont.
 Providing such bands was not so practical for Burj
 According to Uniform Building Code(UBC) ,Dubai was classified
under a zone 2a
 Moderate seismic activity
 The Burj would resist up to 6 in the Richter scale
 Because of the massive reinforced concrete skeleton
EARTHQUAKE Cont.
 The attack against the world trade centre at sept2001 shows the
importance of evacuation in skyscrapers
 How tall the skyscrapers grow makes the evacuation much harder
 The Burj is different and have a perfect evacuation system
EVACUATION
 The Burj is naturally fire resistant as the concrete backbone is already
fire resistant
 More than that the Burj consist of refuge rooms
 These refuge rooms are made of RCC and fire proof sheets that resist
the heat up to 2hrs
 These refuge rooms has a special supply of air which pumps through
fire resistant pipes
 There are 9 refuge rooms, one in every 30 floors
EVACUATION Cont.
 The Burj Khalifa is one of the unique tallest building that was built by
man
 For rising such a city in the sky several new techniques have been
used
 The buttressed core structural system has made a great change in the
structural system of skyscrapers
 A strong buttressed core will initiate the height of the skyscrapers
 The construction of the Burj Khalifa proves that height doesn't matter
any civil engineering construction.
CONCLUSION
THANK YOU

Contenu connexe

Tendances (20)

Burj khalifa
Burj khalifa Burj khalifa
Burj khalifa
 
Presentation on burj khalifa
Presentation on burj khalifaPresentation on burj khalifa
Presentation on burj khalifa
 
Bhurj khalifa _Net Case Study
Bhurj khalifa _Net Case StudyBhurj khalifa _Net Case Study
Bhurj khalifa _Net Case Study
 
Burj kalifa
Burj kalifaBurj kalifa
Burj kalifa
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Empire state building
Empire state buildingEmpire state building
Empire state building
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildings
 
High rise buildings
High rise buildingsHigh rise buildings
High rise buildings
 
Pm burj case
Pm burj casePm burj case
Pm burj case
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
TALL BUILDINGS
TALL BUILDINGSTALL BUILDINGS
TALL BUILDINGS
 
high rise building construction
high rise building constructionhigh rise building construction
high rise building construction
 
Skyscraper
SkyscraperSkyscraper
Skyscraper
 
Burje-khalifa
Burje-khalifaBurje-khalifa
Burje-khalifa
 
Earthquake resistance in buildings
Earthquake resistance in buildingsEarthquake resistance in buildings
Earthquake resistance in buildings
 
Burj khalifa, Dubai.
Burj khalifa, Dubai.Burj khalifa, Dubai.
Burj khalifa, Dubai.
 
Skyscrapers
SkyscrapersSkyscrapers
Skyscrapers
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Bruj khalifa
Bruj khalifaBruj khalifa
Bruj khalifa
 
CONSTRUCTION OF DOMES
CONSTRUCTION OF DOMESCONSTRUCTION OF DOMES
CONSTRUCTION OF DOMES
 

En vedette

Art and stuff
Art and stuffArt and stuff
Art and stufftrevor106
 
Jinmao tower (11) siti yaumilia salsa
Jinmao tower (11) siti yaumilia salsaJinmao tower (11) siti yaumilia salsa
Jinmao tower (11) siti yaumilia salsasalsa moyara
 
The Basics of Chi
The Basics of ChiThe Basics of Chi
The Basics of Chijusten2ecnu
 
Shanghai World Financial Center
Shanghai World Financial CenterShanghai World Financial Center
Shanghai World Financial CenterDeb Bee
 
Shanghai office tower (salsa)
Shanghai office tower (salsa)Shanghai office tower (salsa)
Shanghai office tower (salsa)salsa moyara
 

En vedette (7)

Art and stuff
Art and stuffArt and stuff
Art and stuff
 
Burj Khalifa Dubai
Burj Khalifa DubaiBurj Khalifa Dubai
Burj Khalifa Dubai
 
Jinmao tower (11) siti yaumilia salsa
Jinmao tower (11) siti yaumilia salsaJinmao tower (11) siti yaumilia salsa
Jinmao tower (11) siti yaumilia salsa
 
The Basics of Chi
The Basics of ChiThe Basics of Chi
The Basics of Chi
 
Shanghai World Financial Center
Shanghai World Financial CenterShanghai World Financial Center
Shanghai World Financial Center
 
Shanghai office tower (salsa)
Shanghai office tower (salsa)Shanghai office tower (salsa)
Shanghai office tower (salsa)
 
Sears tower
Sears towerSears tower
Sears tower
 

Similaire à Seminar presentation Burj Khalifa

Aadil final presentation
Aadil final presentationAadil final presentation
Aadil final presentationAmir Amdani
 
Skyscrapers ppt
Skyscrapers pptSkyscrapers ppt
Skyscrapers pptSAI KIRAN
 
ANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptxANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptxAnshuBarmase
 
BURJ AL ARAB Presentation on Structural System
BURJ AL ARAB Presentation on Structural SystemBURJ AL ARAB Presentation on Structural System
BURJ AL ARAB Presentation on Structural SystemABDURRAB ANSARI
 
Structure
StructureStructure
Structuresnarse
 
Birth of skyscrapers
Birth of skyscrapersBirth of skyscrapers
Birth of skyscrapersAbhiniti Garg
 
The petronas twin towers
The petronas twin towersThe petronas twin towers
The petronas twin towersaman shukla
 
Construction of Burj Al Arab, Dubai
Construction of Burj Al Arab, DubaiConstruction of Burj Al Arab, Dubai
Construction of Burj Al Arab, DubaiAr. Md Shahroz Alam
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written ReportYap Xin
 
PPT by Team Kasim burj khalifa.pptx by m
PPT by Team Kasim burj khalifa.pptx by mPPT by Team Kasim burj khalifa.pptx by m
PPT by Team Kasim burj khalifa.pptx by mcivilstudio2208
 

Similaire à Seminar presentation Burj Khalifa (20)

burjjjj new
burjjjj newburjjjj new
burjjjj new
 
burj khalifa
burj khalifaburj khalifa
burj khalifa
 
Skyscrapers
SkyscrapersSkyscrapers
Skyscrapers
 
Aadil final presentation
Aadil final presentationAadil final presentation
Aadil final presentation
 
Skyscrapers ppt
Skyscrapers pptSkyscrapers ppt
Skyscrapers ppt
 
ANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptxANSHU PPT NARDEY SIR.pptx
ANSHU PPT NARDEY SIR.pptx
 
KINGDOM TOWER JEDDAH TOWER
KINGDOM TOWER JEDDAH TOWERKINGDOM TOWER JEDDAH TOWER
KINGDOM TOWER JEDDAH TOWER
 
Making of burj khalifa
Making of burj khalifaMaking of burj khalifa
Making of burj khalifa
 
Burj Al Arab
Burj Al ArabBurj Al Arab
Burj Al Arab
 
BURJ AL ARAB Presentation on Structural System
BURJ AL ARAB Presentation on Structural SystemBURJ AL ARAB Presentation on Structural System
BURJ AL ARAB Presentation on Structural System
 
Structure
StructureStructure
Structure
 
Burj al arab
Burj al arabBurj al arab
Burj al arab
 
Birth of skyscrapers
Birth of skyscrapersBirth of skyscrapers
Birth of skyscrapers
 
The petronas twin towers
The petronas twin towersThe petronas twin towers
The petronas twin towers
 
Construction of Burj Al Arab, Dubai
Construction of Burj Al Arab, DubaiConstruction of Burj Al Arab, Dubai
Construction of Burj Al Arab, Dubai
 
CT Assignment Written Report
CT Assignment Written ReportCT Assignment Written Report
CT Assignment Written Report
 
PPT by Team Kasim burj khalifa.pptx by m
PPT by Team Kasim burj khalifa.pptx by mPPT by Team Kasim burj khalifa.pptx by m
PPT by Team Kasim burj khalifa.pptx by m
 
burjkhalifa-160318164437.pdf
burjkhalifa-160318164437.pdfburjkhalifa-160318164437.pdf
burjkhalifa-160318164437.pdf
 
Al dar hq
Al dar hqAl dar hq
Al dar hq
 
TOWER BUILDINGS
TOWER BUILDINGSTOWER BUILDINGS
TOWER BUILDINGS
 

Dernier

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 

Dernier (20)

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 

Seminar presentation Burj Khalifa

  • 1.  Presented by : Aazam Nirban  Civil Engineering Department  T. Y. Civil  3105 Presentation on BURJ KHALIFA
  • 2.  The Burj Khalifa is the ever built tallest man made structure.  This tower rises in the sky to 828m carrying 162 floors.  The Burj khalifa took 6years for its construction and was completed in the year 2010.  For erecting this city in the sky several new technologies had to be used. INTRODUCTION
  • 3.  The soil stratum of Dubai is very week so they had to excavate up to 50m deep to get a hard rock structure  But the rock that they found was fragile and saturated with ground water  So that any hole made will be cured immediately EXCAVATION
  • 4.  The engineers filled this with a viscous polymer slurry  This pushes the rock and the ground water to the edges of the boreholes to keep it open  This slurry is denser than water and liter than concrete, so that when concrete is pumped the concrete displaces the fluid and forms the foundation.  194 piles were constructed for avoiding the sinking of this structure. EXCAVATION Cont.
  • 5.  The casting of the whole structure is mainly done by two materials 1. Concrete 2. Steel  Over 30,000 tons of steel were used  About 250,000 m2 concrete was also used  The reinforced concrete acts as the backbone of the whole structure CASTING OF THE STRUCTURE
  • 6.  The Burj can accommodate about 35,000 people at a time  Consist of 57 elevators and 8 escalators  The biggest elevator carries about 46 people at a time  These elevators travel at a speed of 35km/hr  The Burj has a service/firemans elevator which have a capacity to hold about 5,500kg  And this is the worlds tallest service elevator. ELEVATORS AND ESCALATORS
  • 7.  The Burj is cladded with high-tech glass which forms as a curtain wall  If the whole cladding has to be done with high- tech glass which will cost about 100 million dollars CLADDING OF THE TOWER
  • 8.  The cladding should withstand the heavy sand storms that with in include water and dust  Prototypes were selected and with the help of propellers artificially created storm was allowed to hit the glass panels at a greater speed  The glass panels withstands the storm up to 75km/hr TEST FOR THE CLADDING AGAINST STORM
  • 9.  As the building has to be built more than half a km, it had to challenge many factors that haven't faced by any other building  Has to be completed with in the short period limit  So the time was money  For erecting such a structure in the sky steel and glass panels have to be raised  This was done by cranes SPEED OF CONSTRUCTION
  • 10.  The cranes consist of two plates on the two sides  It could jump from one floor to the another  So that they were called the kangaroo cranes  So as to speed up the construction the RCC walls was done in a simple and clever engineering way. Cranes
  • 11.  For simplicity and speed the engineers made no. of steel cages  These cages were inserted to the formworks that can be moved easily  After installation of cages concrete was filled in these formworks  Only took 12hrs for the setting of concrete  After setting the concrete the formworks would move to the next level with in 2hrs CASTING OF RCC WALLS
  • 12.  High performance concrete(HPC)  Low permeability  High durability  C80-C60 cube strength concrete was used  It includes fly ash, Portland cement  Two largest concrete pumping machines in the world were used for this purpose  For reducing cracks due to high temperature concreting was done only at night  So that air is cooler and humidity is higher with ice added to the mix CONCRETE USED
  • 13.  The pump needs 630HP to pump about 25000 tons of concrete  It had took about 14 mints for reaching the concrete to the 150th floor  They completed every new floor in 3 day CONCRETE USED Cont.
  • 14.  Every year the storm attacks Dubai  As the building grows much higher to the sky the top will be badly affected by the wind  This causes a sway at the top floors of the building  So that they studied many other skyscrapers  The buildings must be in a definite shape WIND
  • 15.  They made a study on the Sears tower at Chicago  The Sears tower had a layer of steel, and an another layer of steel which forms an exoskeleton to the building  9 such blocks were used in this Sears tower in definite shape  So that the building was made rock solid SHAPE
  • 16.  Giving the Burj a exoskeleton was not a easy task  So they designed the Burj in a triangular shape  So that this was suitable to deflect the wind to different ways SHAPE Cont.
  • 17.  The three wings allow for greater building height by buttressing one another by a central core hence it is called buttressed core structural system  This buttressed core is a six sided central piece  So that it is called a Hexagonal Hub BUTTRESSED CORE
  • 18.  This hub is surrounded by the three wings  These three wings afford the torsional resistance and the twisting of the tower  This hub encloses the elevators BUTTRESSED CORE Cont.
  • 19.  The earthquake was one of the most important factor that had to be challenged by the Burj Khalifa  Any unknown concept would collapse the whole structure  They took the Taipie101 tower for their study EARTHQUAKE
  • 20.  A year twice China is affected with earthquakes  The Taipei 101 was raised up with 36 steel tubes  They were filled with concrete for their rigidity TAIPEI 101
  • 21.  These columns were holding together with outrigger trusses  So that these elastic bands would recover the whole movement occurred to the building TAIPEI 101 Cont.
  • 22.  Providing such bands was not so practical for Burj  According to Uniform Building Code(UBC) ,Dubai was classified under a zone 2a  Moderate seismic activity  The Burj would resist up to 6 in the Richter scale  Because of the massive reinforced concrete skeleton EARTHQUAKE Cont.
  • 23.  The attack against the world trade centre at sept2001 shows the importance of evacuation in skyscrapers  How tall the skyscrapers grow makes the evacuation much harder  The Burj is different and have a perfect evacuation system EVACUATION
  • 24.  The Burj is naturally fire resistant as the concrete backbone is already fire resistant  More than that the Burj consist of refuge rooms  These refuge rooms are made of RCC and fire proof sheets that resist the heat up to 2hrs  These refuge rooms has a special supply of air which pumps through fire resistant pipes  There are 9 refuge rooms, one in every 30 floors EVACUATION Cont.
  • 25.  The Burj Khalifa is one of the unique tallest building that was built by man  For rising such a city in the sky several new techniques have been used  The buttressed core structural system has made a great change in the structural system of skyscrapers  A strong buttressed core will initiate the height of the skyscrapers  The construction of the Burj Khalifa proves that height doesn't matter any civil engineering construction. CONCLUSION