SlideShare une entreprise Scribd logo
1  sur  18
Télécharger pour lire hors ligne
1
NIGERIAN ELECTRICTY REGULATORY COMMISSION
DRAFT FEED-IN TARIFF REGULATIONSFORRENEWABLE ENERGY SOURCED ELECTRICITY IN
NIGERIA
2
REGULATIONS NO: NERC – XXXX
NIGERIAN ELECTRICITY REGULATORY COMMISSION
DRAFT FEED-IN TARIFF REGULATIONS FOR RENEWABLE ENERGY SOURCED ELECTRICITY IN
NIGERIA
In exercise of the powers conferred under Sections 32 (1)(b),(d) & (f), 32 (2)(a) & (g), of the
Electric Power Sector Reform Act, 2005 (Act no. 6 of 2005), and all other powers enabling it on
this behalf, the Nigerian Electricity Regulatory Commission (NERC) hereby makes the following
Regulationsfor procurement and pricing for renewable energy sourced electricity.
ARRANGEMENT OF CLAUSES
CHAPTER I
GENERAL
1. Definitions and Interpretation:
(a) In these REGULATIONS, unless the context otherwise requires:
“Act” means the Electric Power Sector Reform Act, 2005.
“Applicant” means a person who has applied to the Commission for licence under
these REGULATIONS.
“Agreement" or "PPA": power purchase agreement means the agreement
between the Investor and the Off-taker together with any related agreement;
“Buyer”: Off-taker or purchaser of electrical energy from Feed-in-Tariff power
plant.
“Commission” means the Nigerian Electricity Regulatory Commission
3
“Commissioning”: the conduct of tests necessary to put a Unit or the Plant (as
the case may be) into operation and supply to the grid;
“Commissioning Date”: the date on which the developed power plant commences the
operation of supplying electricity to the grid;
“Connection Point”: the point of common coupling at which the energy sent out(Net
Electrical Output) from the Seller’s Plant is delivered into Buyer’s system;
“Grid” as defined in the Grid code.
“kW”: abbreviation for kilowatt;
“kWh”: abbreviation for kilowatt hour being three million six hundred thousand
(3,600,000) Joules as defined in ISO 1000.1992(E);
“’Licensee’’ means any person who holds a licence issued under Part IV of the Act.
“Month” means a calendar month.
MW”: abbreviation for megawatt being one thousand (1,000) kW;
“Off-Taker”: the Buyer of electrical energy for the purpose of selling the electricity to
customers connected to the national grid or off-grid (mini-grid) systems.
“Plant”: Seller’s electrical energy generating power plant ;
“Seller”: Investor/Developer of Feed-in-Tariff power plant
“Year” means a period of twelve (12) months.
(b) Any term that is defined in the Act, and Rules and Codes of the Commission and used,
but not defined in these regulations has the same meaning.
4
CHAPTER II
Feed-in Tariffs (FIT) is a regulatory mechanism for accelerating investment in renewable
energy sources electricity using long-term contracts and pricing based on the levelised cost of
production. By offering long-term contracts and guaranteed pricing, producers are protected
from some of the inherent risks in renewable energy production, thus allowing for more
diversity in energy technologies. Focused on new renewable energy power projects, FIT
contains an obligation to connect as well as obligation to purchase by the distribution
companies thus giving assured long term revenue flow for investors and a reduced financial
risk.The basic economic principle underpinning the FITs is the establishment of a tariff (price)
that covers the cost of generation plus a "reasonable profit" to incentivise developers to
invest.
To stimulate investment, the price for the electricity produced should be high enough to bring
reasonable return on investment for a specific technology and should be certain and for a
term long enough to allow for project financing to be raised by the project.
Renewable Energy FIT guarantees a purchase price over a fixed duration for different priority
technologies, ensuring appropriate return on investment for developers butlimiting producer
surplus (that could impact negatively on electricity prices) via a gradual annual tariff reduction
(known as tariff degression) for new projects as a result of learning effects and cost
reductions. The extra unit energy cost arising from the inclusion of renewable energy is met
through a marginal increase in consumer tariff (burden sharing by all consumers).
Maximum annual capacity limits is established for specified technologies to avoid excessive
increases on consumer electricity prices and to limit impacts of intermittent and non-firm
power on gridstability and power quality.The qualifying renewable energy generators will
accept a Standardised Power Purchase Agreement thus reducing administrative costs.
The feed in tariff covering solar,wind, small hydro and biomass sources, published in 2010 by
the Commission as part of the MYTO 2,elicited very high investment interest in solar energy
resource. Although, the tariffs have not resulted in the signing of any PPA, the feedback from
the PPA negotiation process has necessitated a review of some of the assumptions and
clauses in the extant FIT for clarity and easy interpretation of the regulation.
5
To reduce the transactions costs associated with negotiating and signing a PPA for a small
renewable generator, thefeed in tariff is accompanied bystandardised PPA for projects of up
to 30 MW, connected at distribution voltages as embedded, non-despatchable generators.For
larger projects, competitive tendering procurement process will be conducted following
resource assessments and generation adequacy studies to identify the supply gaps and
suitable interconnection nodes.In line with the extant bulk electricity procurement regulation,
non-solicited renewable projects larger than 30 MW may also be accepted but they have to
pass load flow and system stability tests. While the tariffs offered are technology-specific, the
Standardised PPA is technology-neutral with only a limited number of negotiable clauses and
penalties for non-delivery on agreed commercial operation date (COD).
With the aim of supporting the wider green electricity market and ensuring flexibility in the
market, renewable energy IPPs are permitted to sell power direct to buyers wishing to
purchase renewable energy outside of the REFIT mechanism, subject to fulfilment of
necessary licence conditions.
The establishment of the Renewable Energy Feed-In Tariff (REFIT) will provide an excellent
opportunity to increase the deployment of renewable energy in the country and contribute
towards thesustained growth of the sector in the country, the region and internationally.
6
OBJECTIVE AND SCOPE
The overall aim of the REFIT regulation is to boost power supply in the country,enhance
attainment of the national targets on renewable energy sourced electricity and encourage as
well as support greater private sector participation in power generation from renewable
energy technologies, byproviding investment security and market stability for investors in
electricity generation from renewable energy sources.This is in line with the vision of the
National Energy Policy which include among others: “To develop, promote and harness the
Renewable Energy (RE) resources of the country and incorporate all viable ones into the
national energy mix”. It is also intended to encourage private investors to operate their
power plants prudently and efficiently so as to maximize returns.
Objective of the REFIT
 establish a guaranteed price for electricity generated from renewables for a fixed
period of time that provides a stable income stream and an adequate return on
investment;
 provide access to the grid and an obligation to purchase power generated;
 establish a level playing field for renewable and conventional electricity generation;
 attract private sector investment to support the establishment of a self-sustaining
renewable market.
The initial phase of the REFIT is aimed at kick starting and stimulating the renewable energy
sector and has therefore been designed to be simple and streamlined. Future phases may add
more technologies, bands within technologies, and incentives for projects in different
geographical areas.
2. Scope
The programme cap for the REFIT program is 2000MW. The capacity caps for each renewable
energy technology is as contained in table 1.
The provisions of these Regulations shall apply to
7
a) All qualifying renewable energy sourced electricity of capacity above 1MW and smaller
than 30MW at a site that is connected to the transmission grid or the distribution
networks
b) The renewable component of a hybrid installation where such component meets the
requisite size conditions as stated in (a) above.
Minimum and Maximum Project Size
.
8
CHAPTER III
3. Purchase Obligation
Subject to the costs being met by the developer, the Off-taker shall connect to plants
generating electricity from eligible renewable energy sources. The Off-taker shall guarantee
priority purchase and distribution of all electricity supplied by such renewable energy projects
(capacity up to 30 MW) as defined in this regulation.
The Feed-in-Tariffs values set in this regulation include a standardised allowance for
interconnection costs. The costs of connection, including the costs of construction,
upgrading of transmission/distribution lines, substations, and associated equipment are
therefore to be borne by the developer.
Pursuant to this regulation the Bulk Trader shall be obliged to, as a matter of priority,
purchase 50% of the renewable energy electricity capacity limit established by this regulation
leaving the remaining 50% for the Distribution licensees. Distribution Licensees shall be
obliged to provide access and connect licensed embedded renewable energy electricity
generation plants to the distribution network in their areas of operation.
The Renewable Energy Power Generators shall be responsible for all costs for shallow
connection to the grid. Thus, the Renewable Energy Power Generators shall pay for the costs
of connecting their plant physically to the nearest point of the electricity distribution network
(at the appropriate voltage level).
With prior arrangements, the Off-taker may construct or upgrade its grid at a reasonable
economic expense to facilitate interconnection and meet all technical requirements and
recover the associated costs from the Seller through the Feed-in-Tariff. Any costs for
reinforcements of the network (deep connection cost) shall be borne by either the System
Operator or the Licensed Distributors, whichever is applicable
The purchase and transmission and distribution of electricity supplied by large renewable
energy projects (capacity exceeds 30 MW) shall be subject to the terms of the negotiated PPA.
The Standardised PPA template is to be used as basis for negotiations by the two sides.
9
Qualifying Renewable Energy Generators
For the purpose of this regulation the eligible Renewable Energy Power sources shall be
defined as a new electricity generating project using the following technologies and of a
capacity equal or greater than the stated minimum for that technology as in table 2:
• Wind (on - shore)
• Small hydro (less than 30 MW)
• Biomass (including municipal solid waste)
• Solar Photovoltaic
Qualification of other renewable energy technologies will be considered for inclusion in later
time. REFIT only includes power generation from generators connected to the Transmission
System and Distribution System and excludes off-grid power generation
REFIT is limited to projects between 1 MW and 30 MW installed capacity. Renewable energy
projects above the Maximum Installed Project Capacity can be developed through the existing
power procurement guidelines/regulation and negotiation of with either the Bulk Trader,
Distribution licensees or individual buyers. NERC has already developed a model PPA for such
bilateral transaction. Off-grid projects are not included in the REFIT arrangement. NERC shall
work in close consultation and collaboration with the Rural Electrification Agency to develop
the technical and operational modalities for off-grid projects
Applications to qualify as an RE Generator shall be made to the Commission in conjunction
with the application for a licence to generate electricity. Applicants are required to state the
specific REFIT technology and tariff category. Approval of qualification for the REFIT shall be
defined in the Generation Licence. This will specify the technology, the tariff approved,
duration of the REFIT and other specific licensing conditions.
Application forms for a Generation Licence are provided on www.nercng.org. Details on the
application process are provided in the relevant Sections of the Electricity Power Sector
Regulation Act 2005.
Tariffs
The tariff schedule for the period starting from 2015based on long range marginal cost is set
out in Appendix 1.
10
Licensees awarded these tariffs will have them adjusted for inflation using the Consumer Price
Index (CPI) or another suitable inflation index semi-annually (November and May).The
Commission will monitor uptake, taking into account the impacts of each REFIT in an annual
tariff review. This will take place as part of the annual monitoring and review.
A full tariff review will take place every year for the first five year period of implementation
and every three years thereafter. The resulting tariffs will only be applicable to new projects.
Following the completion and end of the duration of the contracted REFIT tariff, the Generator
shall be required to negotiate tariffs under market conditions applicable at the time.
Project Capacity Cap
The maximum total installed renewable energy project capacity is based on the draft National
Energy Master Plan which envisaged that by the end of the decade, 10% of the national
energy supply shall be from renewable.
It is recognized that certain renewable technologies are more expensive than the others, the
country must encourage the inclusion of every viable renewable resource in the energy mix
for the purpose of energy security and regional spread. The additional power generation costs
resulting from the REFIT may be covered through the following sources:
• Burden sharing by electricity consumers
• Power Consumer assistance Fund (PCAF)
• Rural Electrification Fund
• Donor support
• Carbon finance.
However since all the last four are either not in place yet, this value not predictable or are not
under the control of the Commission, burden sharing is the only financing mechanism
considered.
The Commission is fully aware of the need to avoid high increases in electricity prices which
could have negative socio-economic impacts on the country’s poor and on industry; hence,
capacity limits are applied to all REFIT technologies, specifically limiting the uptake of certain
high-cost technologies. The limits have been carefully determine based on the least cost
optimization model.
11
A total of 2000MW of RE power is envisaged to be admissible into the grid (1000 MW by the
end of 2018 and 2000 MW by the end of 2020) while the total grid capacity is anticipated to
be within10000 MW to 20000MW by 2020. Based on a total cost optimization study the
following technology limits have been established. The NBET should procure 50% of the
requirement and Disco to procure 50%. The following will be guidelines for NBET and Discos in
respect of technologies
Table 1: Target Grid-Connected Renewable Generation Capacity by the year 2020
Technology Capacity Limit (MW)
Solar 387
Wind 412
SHP 675
Biomass 526
To prevent over subscription of REFIT, and minimize the resulting increase tariff, the
Commission shall limits specific technologies for each DisCo (see table 2) in line with the
potential of the renewable energy resources in its jurisdiction. A capacity cap for any resource
may be exceeded if the additional capacity is at the price of next cheaper technology.
Table 2: Allocation of Renewable Energy Capacity (MW) by Buyers up to 2018
Biomass Solar small Hydro Wind Total
Abuja 8.6 17.3 17.3 14.4 57.5
Benin 15.8 9.0 13.5 6.8 45
Enugu 15.8 9.0 13.5 6.8 45
Ibadan 22.8 13.0 19.5 9.8 65
Jos 4.1 8.3 8.3 6.9 27.5
Kaduna 6.0 12.0 12.0 10.0 40
Kano 6.0 12.0 12.0 10.0 40
Eko 19.3 11.0 16.5 8.3 55
Ikeja 26.3 15.0 22. 11.3 75
Port Harcourt 11.4 6.5 9.8 4.9 32.5
Yola 2.6 5.3 5.3 4.4 17.5
Total(Disco) 138.5 118.3 150.0 93.3 500.0
NBET 125 75 187.5 112.5 500.0
System Total 263.5 193.3 337.5 205.8 1000.0
12
Tariff Methodology
The Long Run Marginal Cost (LRMC) and Levelised Cost of Energy (LCOE) is adopted as the
methodology used to set the Feed-In Tariffs (REFITs) for the qualifying REFIT technologies. This
methodology allows the cost of capital and the operating cost of the project to be recovered
over the term of the Power Purchase Agreement (PPA) based on reasonable level of
output/capacity;
Feed-in tariff Assumptions
REFIT assumptions and values for small renewable projects (1-30MW) are provided in the
schedule 1 to this regulation.
The following policy assumptions underlie the calculation of these REFIT values:
i. REFIT values are calculated on a technology-specific basis using the principle of LRMC
which incorporate a reasonable investor return;
ii. REFIT values shall not exceed the Long Run Marginal Costs (LRMC)of generation
iii. the REFIT is denominated in US dollars or the equivalent for other currencies converted
at the naira Exchange Rate on the Effective Date of the Power Purchase Agreement
published by Central Bank of Nigeria;
iv. the REFIT applicable at the time a PPA is signed is the fixed value which will apply over
the 20 year life of the PPA, except for the O&M component (the Indexed Component)
of the REFIT will be subject to semi annual indexation using the Nigerian Consumer
Price Index, using the base index prevailing at the time of signing the PPA.
v. The REFIT will continue to be adjusted in relation to US$ to naira exchange rate on a
semi-annual basis.
The escalable portion of the tariff for each respective technology is provided in schedule
13
Table 3: Assumptions for Renewable energy feed in Tariff Computation
Renewable
Energy
Capital
Cost
US$/kW
Fixed
Cost
US$/kW
Capacity
Utilisation
Factor
Auxiliary
Power
Requirement
Useful
Life(years)
Wind 1165 1823 32% 1% 20
Small
Hydro
1560 5064 45% 1% 20
Solar PV 2025 2228 19% 1% 20
Biomass 901 4861 60% 10% 20
TERM OF TARIFF
The term of the REFIT Power Purchase Agreement will be twenty (20) years
The REFIT will be reviewed every year for the first five-year period of implementation and
every three years thereafter and the resulting tariffs will apply only to new projects. The
annual review will allow appropriate adjustment for new entrant in view of the falling price of
RE technologies. It will also prevent capacity hoarding since the contract becomes effective
only at the time of feeding power into the grid.
Due to the lack of local real-time project data, a reduction rate will currently not be applicable
to REFIT. Tariff adjustments providing a tariff line-of-sight will be taken into account in
subsequent reviews when the local market becomes established;
REFIT Governance Structure
In accordance with its mandate under the section of Electricity Power Sector Reform Act of
2005, NERC shall be fully responsible for the regulation of the feed-in tariffs. Such
responsibilities include review of the tariff structure for priority renewable energy
technologies; Development and review of the REFIT guidelines; monitoring licensed renewable
energy generators and verifying electricity production; Establishing and reviewing technology
specific capacity limits to prevent oversubscription of the REFIT; Reviewing and updating the
REFIT tariff model in line with the monitoring exercise. A standard technology-specific PPA will
be used for REFIT projects and the Commission will approve the PPA.
14
As the regulator, NERC approves the design of the REFIT program; develops eligibility
guidelines and screening criteria to determine whether applications received from RE
developers qualify for the program; builds and maintains the REFIT website (or retains a third
party vendor to do it); evaluates applications submitted by project developers; and manages
the project queue.
The REFIT program administrator invites applications from RE developers, which are
submitted through the website, and evaluates the applications for compliance with pre-
established eligibility criteria. Applicants are placed into a two-tier queue: the active queue
for projects that are determined to be eligible for the REFIT program and that within the
quantity cap; and the reserve queue for qualifying projects that are eligible to advance into
the active queue if space opens up. The REFIT regulator establishes the queue by evaluating
applications on a first come, first served basis. As applications are submitted, they are time
stamped and reviewed in that order
Eligible projects that apply for the REFIT after the active queue has filled up are placed in the
reserve queue. The REFIT program administrator actively monitors the projects in the active
queue for compliance with development milestones in the PPA. Applicants not meeting the
set milestone are moved to the reserve queue to make space for others. This is to prevent
capacity hoarding whereby capacity targets are reserved for non-performing licensees.
The Buyer (NBET or DisCos)– Serves as the counterparty for PPAs with RE project developers;
provides interconnection services, including design studies, cost estimates and construction of
required facilities; responsible for payment and settlement of seller’s invoices; submits
invoices to the Market Operator to pass through the cost of renewable energy to consumer
tariffs.
Standard Form RE PPA
The PPA is a must-take contract. All energy supplied by the RE developer to the buyer will be
purchased by the buyer subject only to such necessary directions and protocols as may be
issued by the buyer (or the System Operator) for the protection of its electric system. The
pricing in the PPA is based on the REFIT tariff which is calculated to cover the technology-
specific cost of renewable energy. From time-to-time, the tariff levels may change due to
15
review by NERC or annual tariff degression; however, the prevailing tariff at the time a PPA is
signed is fixed for the term of that agreement. The PPA has a term of 20 years, starting from
commencement of the Commercial Operation Date.
The PPA shows the duties and obligations that bind both the buyer and the seller, including:
(a) term of the agreement;
(b) pricing;
(c) responsibilities for grid interconnection;
(d) metering;
(e) billing and payment;
(f) coordinated operations;
(g) construction milestones;
(h) other standard contract clauses (insurance, force majeure, limitation of liability, dispute
resolution etc).
No capacity payment required and no capacity testing; contract is essentially for non-firm
energy
Application and Project Selection Process
Renewable energy generators feeding into the grid will require a PPA. The project
developerfor such renewable generation projects must be an entity legally registered in
Nigeria, such as a private or public company, a limited liability partnership, an NGO, a trust, a
public agency or government authority.
The procedures for applying for and implementing the Refit shall follow the Application and
Implementation Guidelines, as published by the NERC, the first step being submission of an
Expression of Interest (EOI).
Licensing conditions, procedures and evaluation criteria for license applications
All applicants for generation license under the REFIT shall be obliged to fulfil all the
requirements and obligations for licensing sentout by NERC pursuant to the EPSRA 2005. The
application must include:
 The type of licence required;
16
 Generation and sale of electricity under the REFIT as one of the options for type
of license required;
 Contribution of the project to grid stabilization and reduction in network losses;
 Acceptance of the standardized Power Purchase Agreement;
 To state expected socio economic impacts such as economic development and
employment creation.The cumulative capacity contribution by REFIT projects of
up to 30 MW shall not exceed 10% of system-wide generation capacity.. As
the system-wide installed generation capacity improves a comprehensive
impact study will be carried out to determine whether a higher level of
embedded capacity can be accommodated.
For large renewable projects above 30MW, integrated resource planing will be carried out
beforeNERC will initiate a competitive bidding process. In this approach, the buyers will solicit
bids, short list them on the basis of qualifications and competencies, and at the full proposal
stage, have the short listed candidates compete for the lowest levelised price in line with
existing power procurement regulation issued by the Commission.
The basis for the PPA in the case of the larger renewable generators is the Standardised
Power Purchase Agreement template with only a limited number of negotiableclauses.
DESIGN OF FEED-in-TARIFFS
Electricity generation costs vary according to the Renewable Energy Sourced Electricity
technology used. Therefore, the REFIT levels are technology specific and depend on:
i. The investment costs for the plant (including the costs of feasibility studies, site survey
etc
ii. development, construction costs, and the costs of connecting to the transmission
iii. system including transmission lines, substations and associated equipment;
iv. The Operations and Maintenance (O&M) Costs;
v. Fuel costs where applicable;
vi. Financing costs and a fair return on theinvested capital;
vii. Estimated lifetime of the power plant;
17
viii. Amount of electricity to be generated.
REFITS are also based on the best estimates of different load factors of energy availability.
The following are the assumed benchmark cost and technical parameter for each of the
identified technologies:
COMPLIANCE WITH TECHNICAL, LEGAL AND REGULATORY REQUIREMENTS
All projects implemented under the Feed-in-Tariff system shall comply with all relevant
technical, legal and regulatory requirements of Nigeria. In particular, projects will abide by the
provision of the Connection Guidelines for Small-Scale Renewable Generation Plant as well as
the relevant codes pursuant to the EPSRA 2005(Grid Code, transmission codes, health and
Safety regulation).
REVIEW OF FEED-IN-TARIFFS
This Feed-in-Tariffs policy shall be subject to review every three years due to changes in
technology from the date of publication. However, a policy review may be undertaken earlier
than three years in exceptional cases. Any changes made during such reviews shall only apply
to Renewable energy sourced electricity power plants that shall be developed after the
revised guidelines are published. For the avoidance of doubt, REFIT values applicable to an
executed PPA contracts will remain unchanged.
Rights and Obligations of Qualified Renewable Energy Power Generators
For RE Generators connecting to a Distribution System (i.e. “Embedded Generators”) the
provisions of the Distribution Code shall apply. For RE Generators connecting to the
Transmission system the Grid Code applies. The connection can be to either Transmission or
Distribution voltage networks, as appropriate. The cost of connecting to the grid at the
appropriate voltage level, ie the shallow connection, shall be borne by the RE Generator in
accordance with the Distribution/Transmission Tariff Code.
All RE Generators have the responsibility to ensure power production is from credible
renewable energy sources. Failure to provide credible evidence on renewable energy power
generation or evidence to prove that power was not produced from non-renewable sources
could lead to the termination of the Generation Licence.
18
The Buyer shall be obliged to enter into a PPA with RE Generators and make payment for
renewable energy generated and supplied to the Distribution System and Transmission
System under the REFIT. Any wheeling charges incurred in purchasing power under the REFIT
shall be at the cost of Buyer.
The Buyer shall be obliged to record the total annual cost of power purchased under REFIT
including Wheeling Charges.
The Buyer has the right and the obligation to inspect RE Generators to verify production of
renewable energy. For RE Generators with an installed capacity greater than 30MW, the
capacity verification shall be carried out annually by Buyer.
Monitoring, Reporting and Review
The Commission shall act as the overall authority for verification of the electricity production
from renewable energy sources. Also, the Commission shall maintain a database of qualifying
renewable energy producers.
The Commission shall be responsible for overall monitoring and review of the REFIT
programme. Data on the energy purchased under REFIT per technology band and the total
cost of the REFIT shall be gathered and maintained by the NERC through the Buyer.
The Commission shall liaise with Buyer and the System Operator to monitor dispatch issues
arising from the connection and generation of power under REFIT. Annually the Commission
shall publish a report on the progress achieved. This report shall include the following:
Progress on RE, Changes or additions in qualifying technologies, cost of development resulting
from the market expansion of the technologies.
THE COMMON SEAL OF
NIGERIAN ELECTRICITY REGULATORY COMMISSION
Was affixed pursuant to the ORDER OF THE COMMISSION
On this ……............................ day of…….........................................…………………. 2015.
Dr. Sam Amadi
Chairman/CEO

Contenu connexe

Tendances

Can Balkan authorities afford to subsidise renewable energy?
Can Balkan authorities afford to subsidise renewable energy?Can Balkan authorities afford to subsidise renewable energy?
Can Balkan authorities afford to subsidise renewable energy?Atanas Georgiev
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderGensol Engineering Limited
 
New Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyNew Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyTNenergy
 
Wind Force Newsletter Feb, Edition, 2012
Wind Force Newsletter   Feb, Edition, 2012Wind Force Newsletter   Feb, Edition, 2012
Wind Force Newsletter Feb, Edition, 2012rupeshsingh_1
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Gensol Engineering Limited
 
Group captive mechanism
Group captive mechanismGroup captive mechanism
Group captive mechanismSusDevIndia
 
Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Gensol Engineering Limited
 
PG&E Demand Response Programs
PG&E Demand Response ProgramsPG&E Demand Response Programs
PG&E Demand Response Programsmichaeljmack
 
Solar net metering policy
Solar net metering policySolar net metering policy
Solar net metering policyJay Ranvir
 
Wind Force Newsletter July, Edition, 2012
Wind Force Newsletter   July, Edition, 2012Wind Force Newsletter   July, Edition, 2012
Wind Force Newsletter July, Edition, 2012rupeshsingh_1
 
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Gensol Engineering Limited
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Gensol Engineering Limited
 
Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Spark Network
 

Tendances (20)

Can Balkan authorities afford to subsidise renewable energy?
Can Balkan authorities afford to subsidise renewable energy?Can Balkan authorities afford to subsidise renewable energy?
Can Balkan authorities afford to subsidise renewable energy?
 
Power sector in nigeria
Power sector in nigeriaPower sector in nigeria
Power sector in nigeria
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
 
New Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyNew Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee Valley
 
Wind Force Newsletter Feb, Edition, 2012
Wind Force Newsletter   Feb, Edition, 2012Wind Force Newsletter   Feb, Edition, 2012
Wind Force Newsletter Feb, Edition, 2012
 
Captive gen
Captive genCaptive gen
Captive gen
 
Abt meter
Abt meterAbt meter
Abt meter
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
 
Group captive mechanism
Group captive mechanismGroup captive mechanism
Group captive mechanism
 
Report on Power failure: Ten (10) Years of EPIRA jun 2011
Report on Power failure: Ten (10) Years of EPIRA jun 2011Report on Power failure: Ten (10) Years of EPIRA jun 2011
Report on Power failure: Ten (10) Years of EPIRA jun 2011
 
Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India) Fact Sheet - Solar Net Metering Regulations (India)
Fact Sheet - Solar Net Metering Regulations (India)
 
PG&E Demand Response Programs
PG&E Demand Response ProgramsPG&E Demand Response Programs
PG&E Demand Response Programs
 
Egeruoh chigoziri
Egeruoh chigoziriEgeruoh chigoziri
Egeruoh chigoziri
 
Solar net metering policy
Solar net metering policySolar net metering policy
Solar net metering policy
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
 
Wind Force Newsletter July, Edition, 2012
Wind Force Newsletter   July, Edition, 2012Wind Force Newsletter   July, Edition, 2012
Wind Force Newsletter July, Edition, 2012
 
Bhiwandi electricity distribution
Bhiwandi electricity distributionBhiwandi electricity distribution
Bhiwandi electricity distribution
 
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019
 
Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013
 

En vedette

The efficiency of feed-in tariffs in Germany and Spain
The efficiency of feed-in tariffs in Germany and SpainThe efficiency of feed-in tariffs in Germany and Spain
The efficiency of feed-in tariffs in Germany and SpainInsulin Angel
 
Renewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationRenewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationJerry Sakala
 
Commercial Solar Feed In Tariff Explained
Commercial Solar Feed In Tariff ExplainedCommercial Solar Feed In Tariff Explained
Commercial Solar Feed In Tariff Explainedecopower
 
Energy Prices Explained: What are Feed-in Tariffs and the Renewables Obligation?
Energy Prices Explained: What are Feed-in Tariffs and the Renewables Obligation?Energy Prices Explained: What are Feed-in Tariffs and the Renewables Obligation?
Energy Prices Explained: What are Feed-in Tariffs and the Renewables Obligation?ENERGplc
 
Renewable Energy Policy: What comes after Feed-in Tariffs?
Renewable Energy Policy: What comes after Feed-in Tariffs?Renewable Energy Policy: What comes after Feed-in Tariffs?
Renewable Energy Policy: What comes after Feed-in Tariffs?Florence Shool of Regulation
 
музей письменників сумщини
музей письменників сумщинимузей письменників сумщини
музей письменників сумщини050282
 
Broucher,Fashion Designing
Broucher,Fashion DesigningBroucher,Fashion Designing
Broucher,Fashion DesigningR.K Tanwar
 
8. vanitia 113 127 (v2)
8. vanitia 113 127 (v2)8. vanitia 113 127 (v2)
8. vanitia 113 127 (v2)mogerz18
 
Brochure Guía de Finanzas 2017
Brochure Guía de Finanzas 2017Brochure Guía de Finanzas 2017
Brochure Guía de Finanzas 2017MD Group
 

En vedette (20)

The efficiency of feed-in tariffs in Germany and Spain
The efficiency of feed-in tariffs in Germany and SpainThe efficiency of feed-in tariffs in Germany and Spain
The efficiency of feed-in tariffs in Germany and Spain
 
Feed in tariff khadijah 22012014
Feed in tariff khadijah  22012014Feed in tariff khadijah  22012014
Feed in tariff khadijah 22012014
 
Renewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentationRenewable Energy Feed-in Tarriff presentation
Renewable Energy Feed-in Tarriff presentation
 
Commercial Solar Feed In Tariff Explained
Commercial Solar Feed In Tariff ExplainedCommercial Solar Feed In Tariff Explained
Commercial Solar Feed In Tariff Explained
 
Energy Prices Explained: What are Feed-in Tariffs and the Renewables Obligation?
Energy Prices Explained: What are Feed-in Tariffs and the Renewables Obligation?Energy Prices Explained: What are Feed-in Tariffs and the Renewables Obligation?
Energy Prices Explained: What are Feed-in Tariffs and the Renewables Obligation?
 
Renewable Energy Policy: What comes after Feed-in Tariffs?
Renewable Energy Policy: What comes after Feed-in Tariffs?Renewable Energy Policy: What comes after Feed-in Tariffs?
Renewable Energy Policy: What comes after Feed-in Tariffs?
 
музей письменників сумщини
музей письменників сумщинимузей письменників сумщини
музей письменників сумщини
 
Broucher,Fashion Designing
Broucher,Fashion DesigningBroucher,Fashion Designing
Broucher,Fashion Designing
 
Asd
AsdAsd
Asd
 
Micro mid theory of production
Micro mid theory of productionMicro mid theory of production
Micro mid theory of production
 
Django
DjangoDjango
Django
 
Usa 80's
Usa 80'sUsa 80's
Usa 80's
 
Power sys tppyttyhgvcx
Power sys tppyttyhgvcxPower sys tppyttyhgvcx
Power sys tppyttyhgvcx
 
Tarea 4
Tarea 4Tarea 4
Tarea 4
 
8. vanitia 113 127 (v2)
8. vanitia 113 127 (v2)8. vanitia 113 127 (v2)
8. vanitia 113 127 (v2)
 
Bilisim_etigi
Bilisim_etigiBilisim_etigi
Bilisim_etigi
 
Abergeldie Marine
Abergeldie MarineAbergeldie Marine
Abergeldie Marine
 
Rama
RamaRama
Rama
 
Brochure Guía de Finanzas 2017
Brochure Guía de Finanzas 2017Brochure Guía de Finanzas 2017
Brochure Guía de Finanzas 2017
 
Kpi accounts payable
Kpi accounts payableKpi accounts payable
Kpi accounts payable
 

Similaire à Draft Feed-In Tariffs

Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Headway Solar
 
VIETNAM – DIRECT POWER PURCHASE AGREEMENT MECHANISM IS UNDERWAY
VIETNAM – DIRECT POWER PURCHASE AGREEMENT MECHANISM IS UNDERWAYVIETNAM – DIRECT POWER PURCHASE AGREEMENT MECHANISM IS UNDERWAY
VIETNAM – DIRECT POWER PURCHASE AGREEMENT MECHANISM IS UNDERWAYDr. Oliver Massmann
 
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...electricitygovernance
 
Power procurement through TBCB for Bundle Generation
Power procurement through TBCB for Bundle GenerationPower procurement through TBCB for Bundle Generation
Power procurement through TBCB for Bundle GenerationAmitava Nag
 
The Grüner Strom Label Criteria List 2015
The Grüner Strom Label Criteria List 2015The Grüner Strom Label Criteria List 2015
The Grüner Strom Label Criteria List 2015Grüner Strom Label e.V.
 
roof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptxroof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptxsonu1811
 
Towards a whole sale electricity market in India
Towards a whole sale electricity market in IndiaTowards a whole sale electricity market in India
Towards a whole sale electricity market in IndiaAmitava Nag
 
Tim Stone. 28th January
Tim Stone. 28th JanuaryTim Stone. 28th January
Tim Stone. 28th JanuaryUKTI2014
 
VIETNAM TO IMPLEMENT DIRECT POWER PURCHASE MECHANISM AFTER 2021
VIETNAM TO IMPLEMENT DIRECT POWER PURCHASE MECHANISM AFTER 2021VIETNAM TO IMPLEMENT DIRECT POWER PURCHASE MECHANISM AFTER 2021
VIETNAM TO IMPLEMENT DIRECT POWER PURCHASE MECHANISM AFTER 2021Dr. Oliver Massmann
 
Micro Generation And Selling Your Power
Micro Generation And Selling Your PowerMicro Generation And Selling Your Power
Micro Generation And Selling Your PowerStephen Rowley
 
Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...
Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...
Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...Emmanuel Aondowase Anchaver
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemesPrivate Consultants
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 

Similaire à Draft Feed-In Tariffs (20)

CAPSTONE FINAL VERSION
CAPSTONE FINAL VERSIONCAPSTONE FINAL VERSION
CAPSTONE FINAL VERSION
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
 
VIETNAM – DIRECT POWER PURCHASE AGREEMENT MECHANISM IS UNDERWAY
VIETNAM – DIRECT POWER PURCHASE AGREEMENT MECHANISM IS UNDERWAYVIETNAM – DIRECT POWER PURCHASE AGREEMENT MECHANISM IS UNDERWAY
VIETNAM – DIRECT POWER PURCHASE AGREEMENT MECHANISM IS UNDERWAY
 
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
 
Tariff policy
Tariff policyTariff policy
Tariff policy
 
power systems.pdf
power systems.pdfpower systems.pdf
power systems.pdf
 
Power procurement through TBCB for Bundle Generation
Power procurement through TBCB for Bundle GenerationPower procurement through TBCB for Bundle Generation
Power procurement through TBCB for Bundle Generation
 
The Grüner Strom Label Criteria List 2015
The Grüner Strom Label Criteria List 2015The Grüner Strom Label Criteria List 2015
The Grüner Strom Label Criteria List 2015
 
roof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptxroof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptx
 
Towards a whole sale electricity market in India
Towards a whole sale electricity market in IndiaTowards a whole sale electricity market in India
Towards a whole sale electricity market in India
 
Tim Stone. 28th January
Tim Stone. 28th JanuaryTim Stone. 28th January
Tim Stone. 28th January
 
VIETNAM TO IMPLEMENT DIRECT POWER PURCHASE MECHANISM AFTER 2021
VIETNAM TO IMPLEMENT DIRECT POWER PURCHASE MECHANISM AFTER 2021VIETNAM TO IMPLEMENT DIRECT POWER PURCHASE MECHANISM AFTER 2021
VIETNAM TO IMPLEMENT DIRECT POWER PURCHASE MECHANISM AFTER 2021
 
Micro Generation And Selling Your Power
Micro Generation And Selling Your PowerMicro Generation And Selling Your Power
Micro Generation And Selling Your Power
 
Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...
Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...
Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...
 
RENEWABLE POLICY
RENEWABLE POLICYRENEWABLE POLICY
RENEWABLE POLICY
 
Net energy metering manual for three schemes
Net energy metering manual for three schemesNet energy metering manual for three schemes
Net energy metering manual for three schemes
 
EMconcept.pptx
EMconcept.pptxEMconcept.pptx
EMconcept.pptx
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
A1070108
A1070108A1070108
A1070108
 
Pcci energy committe twg on power
Pcci energy committe   twg on powerPcci energy committe   twg on power
Pcci energy committe twg on power
 

Draft Feed-In Tariffs

  • 1. 1 NIGERIAN ELECTRICTY REGULATORY COMMISSION DRAFT FEED-IN TARIFF REGULATIONSFORRENEWABLE ENERGY SOURCED ELECTRICITY IN NIGERIA
  • 2. 2 REGULATIONS NO: NERC – XXXX NIGERIAN ELECTRICITY REGULATORY COMMISSION DRAFT FEED-IN TARIFF REGULATIONS FOR RENEWABLE ENERGY SOURCED ELECTRICITY IN NIGERIA In exercise of the powers conferred under Sections 32 (1)(b),(d) & (f), 32 (2)(a) & (g), of the Electric Power Sector Reform Act, 2005 (Act no. 6 of 2005), and all other powers enabling it on this behalf, the Nigerian Electricity Regulatory Commission (NERC) hereby makes the following Regulationsfor procurement and pricing for renewable energy sourced electricity. ARRANGEMENT OF CLAUSES CHAPTER I GENERAL 1. Definitions and Interpretation: (a) In these REGULATIONS, unless the context otherwise requires: “Act” means the Electric Power Sector Reform Act, 2005. “Applicant” means a person who has applied to the Commission for licence under these REGULATIONS. “Agreement" or "PPA": power purchase agreement means the agreement between the Investor and the Off-taker together with any related agreement; “Buyer”: Off-taker or purchaser of electrical energy from Feed-in-Tariff power plant. “Commission” means the Nigerian Electricity Regulatory Commission
  • 3. 3 “Commissioning”: the conduct of tests necessary to put a Unit or the Plant (as the case may be) into operation and supply to the grid; “Commissioning Date”: the date on which the developed power plant commences the operation of supplying electricity to the grid; “Connection Point”: the point of common coupling at which the energy sent out(Net Electrical Output) from the Seller’s Plant is delivered into Buyer’s system; “Grid” as defined in the Grid code. “kW”: abbreviation for kilowatt; “kWh”: abbreviation for kilowatt hour being three million six hundred thousand (3,600,000) Joules as defined in ISO 1000.1992(E); “’Licensee’’ means any person who holds a licence issued under Part IV of the Act. “Month” means a calendar month. MW”: abbreviation for megawatt being one thousand (1,000) kW; “Off-Taker”: the Buyer of electrical energy for the purpose of selling the electricity to customers connected to the national grid or off-grid (mini-grid) systems. “Plant”: Seller’s electrical energy generating power plant ; “Seller”: Investor/Developer of Feed-in-Tariff power plant “Year” means a period of twelve (12) months. (b) Any term that is defined in the Act, and Rules and Codes of the Commission and used, but not defined in these regulations has the same meaning.
  • 4. 4 CHAPTER II Feed-in Tariffs (FIT) is a regulatory mechanism for accelerating investment in renewable energy sources electricity using long-term contracts and pricing based on the levelised cost of production. By offering long-term contracts and guaranteed pricing, producers are protected from some of the inherent risks in renewable energy production, thus allowing for more diversity in energy technologies. Focused on new renewable energy power projects, FIT contains an obligation to connect as well as obligation to purchase by the distribution companies thus giving assured long term revenue flow for investors and a reduced financial risk.The basic economic principle underpinning the FITs is the establishment of a tariff (price) that covers the cost of generation plus a "reasonable profit" to incentivise developers to invest. To stimulate investment, the price for the electricity produced should be high enough to bring reasonable return on investment for a specific technology and should be certain and for a term long enough to allow for project financing to be raised by the project. Renewable Energy FIT guarantees a purchase price over a fixed duration for different priority technologies, ensuring appropriate return on investment for developers butlimiting producer surplus (that could impact negatively on electricity prices) via a gradual annual tariff reduction (known as tariff degression) for new projects as a result of learning effects and cost reductions. The extra unit energy cost arising from the inclusion of renewable energy is met through a marginal increase in consumer tariff (burden sharing by all consumers). Maximum annual capacity limits is established for specified technologies to avoid excessive increases on consumer electricity prices and to limit impacts of intermittent and non-firm power on gridstability and power quality.The qualifying renewable energy generators will accept a Standardised Power Purchase Agreement thus reducing administrative costs. The feed in tariff covering solar,wind, small hydro and biomass sources, published in 2010 by the Commission as part of the MYTO 2,elicited very high investment interest in solar energy resource. Although, the tariffs have not resulted in the signing of any PPA, the feedback from the PPA negotiation process has necessitated a review of some of the assumptions and clauses in the extant FIT for clarity and easy interpretation of the regulation.
  • 5. 5 To reduce the transactions costs associated with negotiating and signing a PPA for a small renewable generator, thefeed in tariff is accompanied bystandardised PPA for projects of up to 30 MW, connected at distribution voltages as embedded, non-despatchable generators.For larger projects, competitive tendering procurement process will be conducted following resource assessments and generation adequacy studies to identify the supply gaps and suitable interconnection nodes.In line with the extant bulk electricity procurement regulation, non-solicited renewable projects larger than 30 MW may also be accepted but they have to pass load flow and system stability tests. While the tariffs offered are technology-specific, the Standardised PPA is technology-neutral with only a limited number of negotiable clauses and penalties for non-delivery on agreed commercial operation date (COD). With the aim of supporting the wider green electricity market and ensuring flexibility in the market, renewable energy IPPs are permitted to sell power direct to buyers wishing to purchase renewable energy outside of the REFIT mechanism, subject to fulfilment of necessary licence conditions. The establishment of the Renewable Energy Feed-In Tariff (REFIT) will provide an excellent opportunity to increase the deployment of renewable energy in the country and contribute towards thesustained growth of the sector in the country, the region and internationally.
  • 6. 6 OBJECTIVE AND SCOPE The overall aim of the REFIT regulation is to boost power supply in the country,enhance attainment of the national targets on renewable energy sourced electricity and encourage as well as support greater private sector participation in power generation from renewable energy technologies, byproviding investment security and market stability for investors in electricity generation from renewable energy sources.This is in line with the vision of the National Energy Policy which include among others: “To develop, promote and harness the Renewable Energy (RE) resources of the country and incorporate all viable ones into the national energy mix”. It is also intended to encourage private investors to operate their power plants prudently and efficiently so as to maximize returns. Objective of the REFIT  establish a guaranteed price for electricity generated from renewables for a fixed period of time that provides a stable income stream and an adequate return on investment;  provide access to the grid and an obligation to purchase power generated;  establish a level playing field for renewable and conventional electricity generation;  attract private sector investment to support the establishment of a self-sustaining renewable market. The initial phase of the REFIT is aimed at kick starting and stimulating the renewable energy sector and has therefore been designed to be simple and streamlined. Future phases may add more technologies, bands within technologies, and incentives for projects in different geographical areas. 2. Scope The programme cap for the REFIT program is 2000MW. The capacity caps for each renewable energy technology is as contained in table 1. The provisions of these Regulations shall apply to
  • 7. 7 a) All qualifying renewable energy sourced electricity of capacity above 1MW and smaller than 30MW at a site that is connected to the transmission grid or the distribution networks b) The renewable component of a hybrid installation where such component meets the requisite size conditions as stated in (a) above. Minimum and Maximum Project Size .
  • 8. 8 CHAPTER III 3. Purchase Obligation Subject to the costs being met by the developer, the Off-taker shall connect to plants generating electricity from eligible renewable energy sources. The Off-taker shall guarantee priority purchase and distribution of all electricity supplied by such renewable energy projects (capacity up to 30 MW) as defined in this regulation. The Feed-in-Tariffs values set in this regulation include a standardised allowance for interconnection costs. The costs of connection, including the costs of construction, upgrading of transmission/distribution lines, substations, and associated equipment are therefore to be borne by the developer. Pursuant to this regulation the Bulk Trader shall be obliged to, as a matter of priority, purchase 50% of the renewable energy electricity capacity limit established by this regulation leaving the remaining 50% for the Distribution licensees. Distribution Licensees shall be obliged to provide access and connect licensed embedded renewable energy electricity generation plants to the distribution network in their areas of operation. The Renewable Energy Power Generators shall be responsible for all costs for shallow connection to the grid. Thus, the Renewable Energy Power Generators shall pay for the costs of connecting their plant physically to the nearest point of the electricity distribution network (at the appropriate voltage level). With prior arrangements, the Off-taker may construct or upgrade its grid at a reasonable economic expense to facilitate interconnection and meet all technical requirements and recover the associated costs from the Seller through the Feed-in-Tariff. Any costs for reinforcements of the network (deep connection cost) shall be borne by either the System Operator or the Licensed Distributors, whichever is applicable The purchase and transmission and distribution of electricity supplied by large renewable energy projects (capacity exceeds 30 MW) shall be subject to the terms of the negotiated PPA. The Standardised PPA template is to be used as basis for negotiations by the two sides.
  • 9. 9 Qualifying Renewable Energy Generators For the purpose of this regulation the eligible Renewable Energy Power sources shall be defined as a new electricity generating project using the following technologies and of a capacity equal or greater than the stated minimum for that technology as in table 2: • Wind (on - shore) • Small hydro (less than 30 MW) • Biomass (including municipal solid waste) • Solar Photovoltaic Qualification of other renewable energy technologies will be considered for inclusion in later time. REFIT only includes power generation from generators connected to the Transmission System and Distribution System and excludes off-grid power generation REFIT is limited to projects between 1 MW and 30 MW installed capacity. Renewable energy projects above the Maximum Installed Project Capacity can be developed through the existing power procurement guidelines/regulation and negotiation of with either the Bulk Trader, Distribution licensees or individual buyers. NERC has already developed a model PPA for such bilateral transaction. Off-grid projects are not included in the REFIT arrangement. NERC shall work in close consultation and collaboration with the Rural Electrification Agency to develop the technical and operational modalities for off-grid projects Applications to qualify as an RE Generator shall be made to the Commission in conjunction with the application for a licence to generate electricity. Applicants are required to state the specific REFIT technology and tariff category. Approval of qualification for the REFIT shall be defined in the Generation Licence. This will specify the technology, the tariff approved, duration of the REFIT and other specific licensing conditions. Application forms for a Generation Licence are provided on www.nercng.org. Details on the application process are provided in the relevant Sections of the Electricity Power Sector Regulation Act 2005. Tariffs The tariff schedule for the period starting from 2015based on long range marginal cost is set out in Appendix 1.
  • 10. 10 Licensees awarded these tariffs will have them adjusted for inflation using the Consumer Price Index (CPI) or another suitable inflation index semi-annually (November and May).The Commission will monitor uptake, taking into account the impacts of each REFIT in an annual tariff review. This will take place as part of the annual monitoring and review. A full tariff review will take place every year for the first five year period of implementation and every three years thereafter. The resulting tariffs will only be applicable to new projects. Following the completion and end of the duration of the contracted REFIT tariff, the Generator shall be required to negotiate tariffs under market conditions applicable at the time. Project Capacity Cap The maximum total installed renewable energy project capacity is based on the draft National Energy Master Plan which envisaged that by the end of the decade, 10% of the national energy supply shall be from renewable. It is recognized that certain renewable technologies are more expensive than the others, the country must encourage the inclusion of every viable renewable resource in the energy mix for the purpose of energy security and regional spread. The additional power generation costs resulting from the REFIT may be covered through the following sources: • Burden sharing by electricity consumers • Power Consumer assistance Fund (PCAF) • Rural Electrification Fund • Donor support • Carbon finance. However since all the last four are either not in place yet, this value not predictable or are not under the control of the Commission, burden sharing is the only financing mechanism considered. The Commission is fully aware of the need to avoid high increases in electricity prices which could have negative socio-economic impacts on the country’s poor and on industry; hence, capacity limits are applied to all REFIT technologies, specifically limiting the uptake of certain high-cost technologies. The limits have been carefully determine based on the least cost optimization model.
  • 11. 11 A total of 2000MW of RE power is envisaged to be admissible into the grid (1000 MW by the end of 2018 and 2000 MW by the end of 2020) while the total grid capacity is anticipated to be within10000 MW to 20000MW by 2020. Based on a total cost optimization study the following technology limits have been established. The NBET should procure 50% of the requirement and Disco to procure 50%. The following will be guidelines for NBET and Discos in respect of technologies Table 1: Target Grid-Connected Renewable Generation Capacity by the year 2020 Technology Capacity Limit (MW) Solar 387 Wind 412 SHP 675 Biomass 526 To prevent over subscription of REFIT, and minimize the resulting increase tariff, the Commission shall limits specific technologies for each DisCo (see table 2) in line with the potential of the renewable energy resources in its jurisdiction. A capacity cap for any resource may be exceeded if the additional capacity is at the price of next cheaper technology. Table 2: Allocation of Renewable Energy Capacity (MW) by Buyers up to 2018 Biomass Solar small Hydro Wind Total Abuja 8.6 17.3 17.3 14.4 57.5 Benin 15.8 9.0 13.5 6.8 45 Enugu 15.8 9.0 13.5 6.8 45 Ibadan 22.8 13.0 19.5 9.8 65 Jos 4.1 8.3 8.3 6.9 27.5 Kaduna 6.0 12.0 12.0 10.0 40 Kano 6.0 12.0 12.0 10.0 40 Eko 19.3 11.0 16.5 8.3 55 Ikeja 26.3 15.0 22. 11.3 75 Port Harcourt 11.4 6.5 9.8 4.9 32.5 Yola 2.6 5.3 5.3 4.4 17.5 Total(Disco) 138.5 118.3 150.0 93.3 500.0 NBET 125 75 187.5 112.5 500.0 System Total 263.5 193.3 337.5 205.8 1000.0
  • 12. 12 Tariff Methodology The Long Run Marginal Cost (LRMC) and Levelised Cost of Energy (LCOE) is adopted as the methodology used to set the Feed-In Tariffs (REFITs) for the qualifying REFIT technologies. This methodology allows the cost of capital and the operating cost of the project to be recovered over the term of the Power Purchase Agreement (PPA) based on reasonable level of output/capacity; Feed-in tariff Assumptions REFIT assumptions and values for small renewable projects (1-30MW) are provided in the schedule 1 to this regulation. The following policy assumptions underlie the calculation of these REFIT values: i. REFIT values are calculated on a technology-specific basis using the principle of LRMC which incorporate a reasonable investor return; ii. REFIT values shall not exceed the Long Run Marginal Costs (LRMC)of generation iii. the REFIT is denominated in US dollars or the equivalent for other currencies converted at the naira Exchange Rate on the Effective Date of the Power Purchase Agreement published by Central Bank of Nigeria; iv. the REFIT applicable at the time a PPA is signed is the fixed value which will apply over the 20 year life of the PPA, except for the O&M component (the Indexed Component) of the REFIT will be subject to semi annual indexation using the Nigerian Consumer Price Index, using the base index prevailing at the time of signing the PPA. v. The REFIT will continue to be adjusted in relation to US$ to naira exchange rate on a semi-annual basis. The escalable portion of the tariff for each respective technology is provided in schedule
  • 13. 13 Table 3: Assumptions for Renewable energy feed in Tariff Computation Renewable Energy Capital Cost US$/kW Fixed Cost US$/kW Capacity Utilisation Factor Auxiliary Power Requirement Useful Life(years) Wind 1165 1823 32% 1% 20 Small Hydro 1560 5064 45% 1% 20 Solar PV 2025 2228 19% 1% 20 Biomass 901 4861 60% 10% 20 TERM OF TARIFF The term of the REFIT Power Purchase Agreement will be twenty (20) years The REFIT will be reviewed every year for the first five-year period of implementation and every three years thereafter and the resulting tariffs will apply only to new projects. The annual review will allow appropriate adjustment for new entrant in view of the falling price of RE technologies. It will also prevent capacity hoarding since the contract becomes effective only at the time of feeding power into the grid. Due to the lack of local real-time project data, a reduction rate will currently not be applicable to REFIT. Tariff adjustments providing a tariff line-of-sight will be taken into account in subsequent reviews when the local market becomes established; REFIT Governance Structure In accordance with its mandate under the section of Electricity Power Sector Reform Act of 2005, NERC shall be fully responsible for the regulation of the feed-in tariffs. Such responsibilities include review of the tariff structure for priority renewable energy technologies; Development and review of the REFIT guidelines; monitoring licensed renewable energy generators and verifying electricity production; Establishing and reviewing technology specific capacity limits to prevent oversubscription of the REFIT; Reviewing and updating the REFIT tariff model in line with the monitoring exercise. A standard technology-specific PPA will be used for REFIT projects and the Commission will approve the PPA.
  • 14. 14 As the regulator, NERC approves the design of the REFIT program; develops eligibility guidelines and screening criteria to determine whether applications received from RE developers qualify for the program; builds and maintains the REFIT website (or retains a third party vendor to do it); evaluates applications submitted by project developers; and manages the project queue. The REFIT program administrator invites applications from RE developers, which are submitted through the website, and evaluates the applications for compliance with pre- established eligibility criteria. Applicants are placed into a two-tier queue: the active queue for projects that are determined to be eligible for the REFIT program and that within the quantity cap; and the reserve queue for qualifying projects that are eligible to advance into the active queue if space opens up. The REFIT regulator establishes the queue by evaluating applications on a first come, first served basis. As applications are submitted, they are time stamped and reviewed in that order Eligible projects that apply for the REFIT after the active queue has filled up are placed in the reserve queue. The REFIT program administrator actively monitors the projects in the active queue for compliance with development milestones in the PPA. Applicants not meeting the set milestone are moved to the reserve queue to make space for others. This is to prevent capacity hoarding whereby capacity targets are reserved for non-performing licensees. The Buyer (NBET or DisCos)– Serves as the counterparty for PPAs with RE project developers; provides interconnection services, including design studies, cost estimates and construction of required facilities; responsible for payment and settlement of seller’s invoices; submits invoices to the Market Operator to pass through the cost of renewable energy to consumer tariffs. Standard Form RE PPA The PPA is a must-take contract. All energy supplied by the RE developer to the buyer will be purchased by the buyer subject only to such necessary directions and protocols as may be issued by the buyer (or the System Operator) for the protection of its electric system. The pricing in the PPA is based on the REFIT tariff which is calculated to cover the technology- specific cost of renewable energy. From time-to-time, the tariff levels may change due to
  • 15. 15 review by NERC or annual tariff degression; however, the prevailing tariff at the time a PPA is signed is fixed for the term of that agreement. The PPA has a term of 20 years, starting from commencement of the Commercial Operation Date. The PPA shows the duties and obligations that bind both the buyer and the seller, including: (a) term of the agreement; (b) pricing; (c) responsibilities for grid interconnection; (d) metering; (e) billing and payment; (f) coordinated operations; (g) construction milestones; (h) other standard contract clauses (insurance, force majeure, limitation of liability, dispute resolution etc). No capacity payment required and no capacity testing; contract is essentially for non-firm energy Application and Project Selection Process Renewable energy generators feeding into the grid will require a PPA. The project developerfor such renewable generation projects must be an entity legally registered in Nigeria, such as a private or public company, a limited liability partnership, an NGO, a trust, a public agency or government authority. The procedures for applying for and implementing the Refit shall follow the Application and Implementation Guidelines, as published by the NERC, the first step being submission of an Expression of Interest (EOI). Licensing conditions, procedures and evaluation criteria for license applications All applicants for generation license under the REFIT shall be obliged to fulfil all the requirements and obligations for licensing sentout by NERC pursuant to the EPSRA 2005. The application must include:  The type of licence required;
  • 16. 16  Generation and sale of electricity under the REFIT as one of the options for type of license required;  Contribution of the project to grid stabilization and reduction in network losses;  Acceptance of the standardized Power Purchase Agreement;  To state expected socio economic impacts such as economic development and employment creation.The cumulative capacity contribution by REFIT projects of up to 30 MW shall not exceed 10% of system-wide generation capacity.. As the system-wide installed generation capacity improves a comprehensive impact study will be carried out to determine whether a higher level of embedded capacity can be accommodated. For large renewable projects above 30MW, integrated resource planing will be carried out beforeNERC will initiate a competitive bidding process. In this approach, the buyers will solicit bids, short list them on the basis of qualifications and competencies, and at the full proposal stage, have the short listed candidates compete for the lowest levelised price in line with existing power procurement regulation issued by the Commission. The basis for the PPA in the case of the larger renewable generators is the Standardised Power Purchase Agreement template with only a limited number of negotiableclauses. DESIGN OF FEED-in-TARIFFS Electricity generation costs vary according to the Renewable Energy Sourced Electricity technology used. Therefore, the REFIT levels are technology specific and depend on: i. The investment costs for the plant (including the costs of feasibility studies, site survey etc ii. development, construction costs, and the costs of connecting to the transmission iii. system including transmission lines, substations and associated equipment; iv. The Operations and Maintenance (O&M) Costs; v. Fuel costs where applicable; vi. Financing costs and a fair return on theinvested capital; vii. Estimated lifetime of the power plant;
  • 17. 17 viii. Amount of electricity to be generated. REFITS are also based on the best estimates of different load factors of energy availability. The following are the assumed benchmark cost and technical parameter for each of the identified technologies: COMPLIANCE WITH TECHNICAL, LEGAL AND REGULATORY REQUIREMENTS All projects implemented under the Feed-in-Tariff system shall comply with all relevant technical, legal and regulatory requirements of Nigeria. In particular, projects will abide by the provision of the Connection Guidelines for Small-Scale Renewable Generation Plant as well as the relevant codes pursuant to the EPSRA 2005(Grid Code, transmission codes, health and Safety regulation). REVIEW OF FEED-IN-TARIFFS This Feed-in-Tariffs policy shall be subject to review every three years due to changes in technology from the date of publication. However, a policy review may be undertaken earlier than three years in exceptional cases. Any changes made during such reviews shall only apply to Renewable energy sourced electricity power plants that shall be developed after the revised guidelines are published. For the avoidance of doubt, REFIT values applicable to an executed PPA contracts will remain unchanged. Rights and Obligations of Qualified Renewable Energy Power Generators For RE Generators connecting to a Distribution System (i.e. “Embedded Generators”) the provisions of the Distribution Code shall apply. For RE Generators connecting to the Transmission system the Grid Code applies. The connection can be to either Transmission or Distribution voltage networks, as appropriate. The cost of connecting to the grid at the appropriate voltage level, ie the shallow connection, shall be borne by the RE Generator in accordance with the Distribution/Transmission Tariff Code. All RE Generators have the responsibility to ensure power production is from credible renewable energy sources. Failure to provide credible evidence on renewable energy power generation or evidence to prove that power was not produced from non-renewable sources could lead to the termination of the Generation Licence.
  • 18. 18 The Buyer shall be obliged to enter into a PPA with RE Generators and make payment for renewable energy generated and supplied to the Distribution System and Transmission System under the REFIT. Any wheeling charges incurred in purchasing power under the REFIT shall be at the cost of Buyer. The Buyer shall be obliged to record the total annual cost of power purchased under REFIT including Wheeling Charges. The Buyer has the right and the obligation to inspect RE Generators to verify production of renewable energy. For RE Generators with an installed capacity greater than 30MW, the capacity verification shall be carried out annually by Buyer. Monitoring, Reporting and Review The Commission shall act as the overall authority for verification of the electricity production from renewable energy sources. Also, the Commission shall maintain a database of qualifying renewable energy producers. The Commission shall be responsible for overall monitoring and review of the REFIT programme. Data on the energy purchased under REFIT per technology band and the total cost of the REFIT shall be gathered and maintained by the NERC through the Buyer. The Commission shall liaise with Buyer and the System Operator to monitor dispatch issues arising from the connection and generation of power under REFIT. Annually the Commission shall publish a report on the progress achieved. This report shall include the following: Progress on RE, Changes or additions in qualifying technologies, cost of development resulting from the market expansion of the technologies. THE COMMON SEAL OF NIGERIAN ELECTRICITY REGULATORY COMMISSION Was affixed pursuant to the ORDER OF THE COMMISSION On this ……............................ day of…….........................................…………………. 2015. Dr. Sam Amadi Chairman/CEO