Managing Claims Under FIDIC
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Adrias Tan
MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Senior Legal Counsel, Hyundai Engineering & Construction Co Ltd
Fellow, Chartered Institute of Arbitrators
Fellow, Singapore Institute of Arbitrators
Fellow, Singapore Institute of Builders
Member, Society of Construction Law, UK
Member, Society of Construction Law, Singapore
Associate Member, Singapore Academy of Law
Associate Lecturer, Royal Melbourne Institute of Technology (SIM Singapore)
Panel of Arbitrators, SIArb
• Claim and Procurement
• After Contract Award: How to minimise Claims and, if the
Claims are disagreed, how to avoid contested Claims from
becoming disputes?
• Pursuing Claims (if you haven’t managed to avoid them!)
• Civil v Common Law comparison: different approaches to
Claim Quantification
• The Requirements for Notices of Claim
• Can the Conditions Precedent for notices always be enforced?
• What constitutes detailed particulars of a Claim?
• The Engineer’s Obligations
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
ADRIAS TAN
Managing Claims Under FIDIC
Claim and Procurement
• Claims Differentiated from Variations
• Contractual Provisions on Variations
– Alterations and Modifications to Original Scope and
Extent of Permanent Works
• Contractual Provisions on Claims
– Compensation not anticipated in Original Contract
• Cost Implications from Variations
– Evaluation and Remeasurement
• Cost and Time Implications from Claims
– Express contractual provisions entitling submission of
claims
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Claim and Procurement
• Contractual Basis for Variations
– Changes in quantities of any item of work included in the
Contract
– Changes to quality and other characteristics of any item of
work
– Changes to levels, positions and/or dimensions of any part of
work
– Omission of any work unless it is to be carried out by others
– Any additional work, Plant, Materials or services necessary for
Permanent Works, including any associated Tests on
Completion, boreholes and other testing and exploratory work
– Changes to sequence or timing of execution of works
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Claim and Procurement
• Contractual Basis for Claims
– Delayed drawings or instructions
– Right of access
– Setting out
– Unforeseen physical conditions
– Fossils
– Testing
– Extension of Time for Completion
– Loss and Expense due to
Variations
– Delay caused by Authorities
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
– Suspension of works
– Evaluation and
Measurement
– Omissions
– Value Engineering
– Interference with
tests on completion
– Changes in legislation
– Employer’s Risks
Managing Claims Under FIDIC
Minimising and Avoiding Claims
• Commercial Risks and Monetising Profits
• Complexity of Claims
– Changes in Design Intent and Employer’s Requirements
– Ambiguities in Contract Documents
• Contracting Strategies
– Lump Sum EPC
– Reimbursable
– Mixed or Hybrid Design/Bid/Build Procurement, etc
• Dispute Adjudication Board
– Resolving disputes at early stages
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Pursuing Claims
• Administration and Management of Contract
– Familiarity with Contract Documents, Forms of Contract
– Familiarity with Contractual procedures and protocol
• Claims Management
– Notices and Timelines
– Substantiation of Information
• Notices and Correspondence
– Timeline Condition Precedent
– Notices for Actual and Potential Delay
• Contemporary Records
– AG Falkland Islands v Gordon Forbes Construction
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Different Approaches to Claim
• Common Law Approach
– Timescales: Directory or Mandatory Requirements
– Bremer Handelgesellschaft v Vanden Avenne Izegem
• Notice precedent held binding if precise time is stipulated
• Express language used on forfeiture of rights due to non
compliance with condition precedent
– Multiplex Construction v Honeywell Control Systems
• Condition precedent allows Employer opportunity to
withdraw instructions with time implications
– Heilbut, Symons v Buckleton
• misstatement of facts, negligent misrepresentation,
fraudulent misinterpretation of contract terms
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Different Approaches to Claim
• Civil Law Approach
– More Lenient – Non compliance with time bar not fatal
– UAE Civil Code Article 243(2)
• “With regard to the rights (obligations) arising out of the
contract, each of the contracting parties must perform that
which the contract obliges him to do”
– UAE Civil Code Article 265(1)
• “If the wording of a contract is clear, it may not be
departed from by way of interpretation to ascertain the
intention of the parties”
– UAE Civil Code Article 246(1)
• “The contract must be performed in ... good faith”
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Different Approaches to Claim
• Civil Law Approach
– UAE Civil Code Article 318
• “No person may take the property of another without
lawful cause, and if he takes it he must return it”
– Doctrine of Unjust Enrichment
• The Employer precluded from relying on a time bar
provision to avoid payment to the Contractor for works
performed and for works from which the Employer has
benefitted particularly if the only reason for withholding
payment is the lateness of the Contractor’s claim
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Requirements for Notices of Claim
• Notice in Writing
– Notice served under Clause 20.1
– Within 28 days after he “became aware, or should have
become aware, of the event or circumstance”
• When should the Contractor be aware: Imputed Knowledge
or Objective standard
• Question: who is the arbiter of when the Contractor should
have become aware, the Engineer or Contractor?
– Event or Circumstance Giving Rise to Claim
• Fully detailed claim, monthly updated particulars,
extension of time required and/or additional payment
• Keeping of contemporary records
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Enforcing Condition Precedent
• Doctrine of Consensus ad Idem
– “If the Contractor fails to give notice of a claim within
such period of 28 days, the Time for Completion shall not
be extended, the Contractor shall not be entitled to
additional payment, and the Employer shall be
discharged from all liability in connection with the claim”
• Rationale
– Contractor notifies Employer, to enable Employer to avert
unintended consequences
– potential disputes resolved early
– Failure to comply with timescale – party loses right of
claim
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Enforcing Condition Precedent
• Multiplex Constr v Honeywell Control Systems
– “Contractual terms requiring a contractor to give prompt
notice of delay serve a valuable purpose; such notice
enables matters to be investigated while they are still
current. Furthermore, such notice sometimes gives the
employer the opportunity to withdraw instructions when
the financial consequences become apparent” per Justice
Jackson
– Notice triggered not only upon Contractor becoming
aware of relevant event or circumstance, but also when
Contractor should have become aware of it
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Enforcing Condition Precedent
• Non Compliance Not Fatal
– “If the Contractor fails to comply with this or another
Sub-Clause in relation to any claim, any extension of time
and/or additional payment shall take account of the
extent (if any) to which the failure has prevented or
prejudiced proper investigation of the claim …”
– Whether enforcing time bar amounts to a penalty in the
face of an Employer’s Valid Delay Factor or a Valid
Variation
– Onus of proof that the time bar should be imposed
generally lies with the Employer
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Enforcing Condition Precedent
• Obrascon Huarte Lain SA v HM’s AG for Gibraltar
– Technology and Construction Court (TCC) in London
adopted a relaxed interpretation of this requirement,
ruled that the 28-day period for notifying a claim for EOT
only begins following the onset of actual delay flowing
from the event or circumstance which caused it
– Judge Akenhead J remarked that he could see no reason
why Clause 20.1 should be construed strictly against
Contractor:
"can see reason why it should be construed reasonably
broadly, given its serious effect on what could otherwise
be good claims for instance of Employer’s breach "
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Enforcing Condition Precedent
• Obrascon Huarte Lain SA v HM’s AG for Gibraltar
– notice of a claim for EOT does not have to be given
pursuant to Clause 20.1 until there actually is delay,
although Contractor can give notice when it reasonably
believes that it will be delayed
– Clause 8.4: entitlement to extension arises if and to the
extent that the completion “is or will be delayed by”
various listed events, such as variations or
“unforeseeable” conditions
– Extension of time can be claimed either when it is clear
that there will be delay (prospective delay) or when delay
has at least started to be incurred (retrospective delay)
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Enforcing Condition Precedent
• Obrascon Huarte Lain SA v HM’s AG for Gibraltar
– Clause 20.1: “event or circumstance” described in can
mean either the incident (variation, exceptional weather
or one of the other specified grounds for extension), or
the delay which results or will inevitably result from the
incident in question
– Clause 8.4: Wording is “is or will be delayed by”, and not:
“is or will be delayed whichever is the earliest”
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Enforcing Condition Precedent
• Chiemauer Membran-und Zeltbau GmbH v New
Millennium Experience
– English Court of Appeal held that such condition
precedent is not enforceable
– Depending on commercial sense and intentions of
contracting parties, and even for some condition
precedent clauses, a court or arbitral tribunal may refuse
to interpret it literally
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Detailed Particulars of a Claim
• Chiemauer Membran-und Zeltbau GmbH v New
Millennium Experience
– Contractor to submit Fully Detailed Claim within 42 days
of “event or circumstance”
– Contractor can propose for the Engineer’s approval an
extended time period to submit a detailed claim
– Cause and effect of Delay, Culpable and Concurrent
Delay, reasonable measures taken to mitigate delay
– Particulars include correspondence, meeting minutes,
site records, photographs, narratives, schedules, etc
– Updated construction program showing planned,
impacted and actual schedule
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Engineer’s Obligations
• Engineer has 42 days to Approve or Disapprove with
Detailed Comments
– Engineer can propose for the Contractor’s approval an
extended time period to respond
– Request “any necessary further particulars”
– Engineer unreasonably delaying a response to a Claim or
requesting unnecessary further particulars
– Clause 3.5: consulting with Contractor, try to reach an
agreement. If not possible to reach agreement, make a
fair determination
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Engineer’s Obligations
• Engineer Failure to Respond within 42 days
– No express sanctions for the Engineer’s failure to provide
a timely response
– Effect is Contractor unduly relieved of his contractual
obligations; Contractor not kept aware of his contractual
rights and entitlements arising from such valid claims and
notifications
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Engineer’s Obligations
• Prevention Principle
– Where Engineer fails to provide a timely response or fails
or refuses to grant an extension of time inspite of the
Valid Delay Factor
– Employer precluded from holding Contractor to
completion date, due to Employer or his authorised
Representative’s act or omission preventing Contractor
from completing by that date
– Completion time becomes at large; obligation to
complete by specified date replaced by implied obligation
to complete within a reasonable time
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Engineer’s Obligations
• Roberts v Bury Improvement Commissioners
– well established principle at common law that:
“... no person can take advantage of the non-fulfilment of
a condition the performance of which has been hindered
by himself ...” per Blackburn and Mellor JJ
– Reason for that rule is that otherwise a most
unreasonable burden would be imposed upon the
Contractor
– Employer’s right to impose liquidated damages for delay
replaced by unliquidated damages, based on new
‘reasonable time’ completion date
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Engineer’s Obligations
• Shawton Engineering Ltd v DGP International Ltd
– Court of Appeal held that what is a reasonable time has
to be judged as at the time when the question arose, in
the light of all the relevant circumstances:
“There were variations, but no contractual mechanisms
for extending time on account of the variations (or the
mechanisms have failed). The effect in law of the
variations was that the Contractor became obligated to
complete their work within a reasonable time”
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
Engineer’s Obligations
• Shawton Engineering Ltd v DGP International Ltd
– The judge rejected that a reasonable time should be
ascertained by reference to the Original Contract Periods
as extended only by the agreed periods for variations
– “The question of what is a reasonable time within which
to complete particular work is an objective question and
is not dependent upon the actual time which a person
may have agreed to carry out the work. Parties may have
over or under estimated what time the work would
actually require. The time which has to be ascertained is
the time it would reasonably take to complete the whole
of the works”
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
FLOW CHART – Clause 20.1 Claims
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Managing Claims Under FIDIC
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
 Interactive Voting System – Multiple Choice Questions
 The Engineer is empowered under the
prevailing express conditions to
require that the Contractor submits
claims for evaluation of Variations
pursuant to Clause 20.1 and subject to
the timeline condition precedent before
he is entitled to compensation for the
additional work instructed?
1) AGREE
2) DISAGREE
Managing Claims Under FIDIC
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
 Interactive Voting System – Multiple Choice Questions
 If the Engineer delays, refuses or fails
to respond to the Contractor’s Claims
pursuant to Clause 20.1, the
Contractor’s rights may be prejudiced
as a result. The FIDIC Forms should
address this lacuna.
1) AGREE
2) DISAGREE
MSc | BSc(Hons) | LLB(Hons) | FCIArb | FSIArb
Adrias has more than two decades of practical working experience
in the construction industry, working currently as in-house legal
counsel for an MNC Company. Adrias is professionally trained in
litigation, arbitration, adjudication, mediation and dispute
resolution, and is an accredited arbitrator. He has handled several
institutional and ad-hoc arbitral proceedings, as well as having
tutored in SIArb, and conducted numerous workshops and
seminars on diverse construction, contractual and legal issues
including various Standard Forms of Contracts. He also lectures at
the Royal Melbourne Institute of Technology, at the Singapore
Institute of Management Campus teaching law subjects.
email: adriastan@yahoo.com
sg.linkedin.com/in/adrias-tan-5ab34035
Managing Claims Under FIDIC
© 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
Adrias Tan

Contenu connexe

Tendances

Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contractsKheng Hoe Advocates
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFrancis Ho
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1Moustafa Ismail Abu Dief
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractProject Controls Expo
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN PanigrahiSN Panigrahi, PMP
 

Tendances (20)

FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Fidic
FidicFidic
Fidic
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi# FIDIC Payment Flow Charts # By SN Panigrahi
# FIDIC Payment Flow Charts # By SN Panigrahi
 

Similaire à FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan

FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanFIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanAdrias TAN
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsEversheds Sutherland
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidicAhmetArslan47
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes managementMohammed Tanbouz
 
How To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsHow To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsPalecek & Palecek, PLLC
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
Global Offshore Wind Trends-Implications and Challenges for Taiwan
Global Offshore Wind Trends-Implications and Challenges for TaiwanGlobal Offshore Wind Trends-Implications and Challenges for Taiwan
Global Offshore Wind Trends-Implications and Challenges for TaiwanEiger
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsRobert MacDonald
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Pierrette Khoury BComm/B Laws, GDLP
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Breyer Group PLC and Others 2015
Breyer Group PLC and Others 2015Breyer Group PLC and Others 2015
Breyer Group PLC and Others 2015Matheson Law Firm
 
Chapter 26: Holders in Due Course and Defense
Chapter 26: Holders in Due Course and Defense Chapter 26: Holders in Due Course and Defense
Chapter 26: Holders in Due Course and Defense Tara Kissel, M.Ed
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsFrancis Ho
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 

Similaire à FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan (20)

FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanFIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
How To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsHow To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal Interests
 
UK Adjudicators August 2020 newsletter
UK Adjudicators August 2020 newsletterUK Adjudicators August 2020 newsletter
UK Adjudicators August 2020 newsletter
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
Global Offshore Wind Trends-Implications and Challenges for Taiwan
Global Offshore Wind Trends-Implications and Challenges for TaiwanGlobal Offshore Wind Trends-Implications and Challenges for Taiwan
Global Offshore Wind Trends-Implications and Challenges for Taiwan
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claims
 
Colin Harris and Mark Kenney
Colin Harris and Mark KenneyColin Harris and Mark Kenney
Colin Harris and Mark Kenney
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Breyer Group PLC and Others 2015
Breyer Group PLC and Others 2015Breyer Group PLC and Others 2015
Breyer Group PLC and Others 2015
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Chapter 26: Holders in Due Course and Defense
Chapter 26: Holders in Due Course and Defense Chapter 26: Holders in Due Course and Defense
Chapter 26: Holders in Due Course and Defense
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 

FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan

  • 1. Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb Senior Legal Counsel, Hyundai Engg & Construction Co Ltd
  • 2. Managing Claims Under FIDIC © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb Senior Legal Counsel, Hyundai Engineering & Construction Co Ltd Fellow, Chartered Institute of Arbitrators Fellow, Singapore Institute of Arbitrators Fellow, Singapore Institute of Builders Member, Society of Construction Law, UK Member, Society of Construction Law, Singapore Associate Member, Singapore Academy of Law Associate Lecturer, Royal Melbourne Institute of Technology (SIM Singapore) Panel of Arbitrators, SIArb
  • 3. • Claim and Procurement • After Contract Award: How to minimise Claims and, if the Claims are disagreed, how to avoid contested Claims from becoming disputes? • Pursuing Claims (if you haven’t managed to avoid them!) • Civil v Common Law comparison: different approaches to Claim Quantification • The Requirements for Notices of Claim • Can the Conditions Precedent for notices always be enforced? • What constitutes detailed particulars of a Claim? • The Engineer’s Obligations © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb Managing Claims Under FIDIC ADRIAS TAN
  • 4. Managing Claims Under FIDIC Claim and Procurement • Claims Differentiated from Variations • Contractual Provisions on Variations – Alterations and Modifications to Original Scope and Extent of Permanent Works • Contractual Provisions on Claims – Compensation not anticipated in Original Contract • Cost Implications from Variations – Evaluation and Remeasurement • Cost and Time Implications from Claims – Express contractual provisions entitling submission of claims © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 5. Managing Claims Under FIDIC Claim and Procurement • Contractual Basis for Variations – Changes in quantities of any item of work included in the Contract – Changes to quality and other characteristics of any item of work – Changes to levels, positions and/or dimensions of any part of work – Omission of any work unless it is to be carried out by others – Any additional work, Plant, Materials or services necessary for Permanent Works, including any associated Tests on Completion, boreholes and other testing and exploratory work – Changes to sequence or timing of execution of works © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 6. Managing Claims Under FIDIC Claim and Procurement • Contractual Basis for Claims – Delayed drawings or instructions – Right of access – Setting out – Unforeseen physical conditions – Fossils – Testing – Extension of Time for Completion – Loss and Expense due to Variations – Delay caused by Authorities © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb – Suspension of works – Evaluation and Measurement – Omissions – Value Engineering – Interference with tests on completion – Changes in legislation – Employer’s Risks
  • 7. Managing Claims Under FIDIC Minimising and Avoiding Claims • Commercial Risks and Monetising Profits • Complexity of Claims – Changes in Design Intent and Employer’s Requirements – Ambiguities in Contract Documents • Contracting Strategies – Lump Sum EPC – Reimbursable – Mixed or Hybrid Design/Bid/Build Procurement, etc • Dispute Adjudication Board – Resolving disputes at early stages © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 8. Managing Claims Under FIDIC Pursuing Claims • Administration and Management of Contract – Familiarity with Contract Documents, Forms of Contract – Familiarity with Contractual procedures and protocol • Claims Management – Notices and Timelines – Substantiation of Information • Notices and Correspondence – Timeline Condition Precedent – Notices for Actual and Potential Delay • Contemporary Records – AG Falkland Islands v Gordon Forbes Construction © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 9. Managing Claims Under FIDIC Different Approaches to Claim • Common Law Approach – Timescales: Directory or Mandatory Requirements – Bremer Handelgesellschaft v Vanden Avenne Izegem • Notice precedent held binding if precise time is stipulated • Express language used on forfeiture of rights due to non compliance with condition precedent – Multiplex Construction v Honeywell Control Systems • Condition precedent allows Employer opportunity to withdraw instructions with time implications – Heilbut, Symons v Buckleton • misstatement of facts, negligent misrepresentation, fraudulent misinterpretation of contract terms © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 10. Managing Claims Under FIDIC Different Approaches to Claim • Civil Law Approach – More Lenient – Non compliance with time bar not fatal – UAE Civil Code Article 243(2) • “With regard to the rights (obligations) arising out of the contract, each of the contracting parties must perform that which the contract obliges him to do” – UAE Civil Code Article 265(1) • “If the wording of a contract is clear, it may not be departed from by way of interpretation to ascertain the intention of the parties” – UAE Civil Code Article 246(1) • “The contract must be performed in ... good faith” © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 11. Managing Claims Under FIDIC Different Approaches to Claim • Civil Law Approach – UAE Civil Code Article 318 • “No person may take the property of another without lawful cause, and if he takes it he must return it” – Doctrine of Unjust Enrichment • The Employer precluded from relying on a time bar provision to avoid payment to the Contractor for works performed and for works from which the Employer has benefitted particularly if the only reason for withholding payment is the lateness of the Contractor’s claim © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 12. Managing Claims Under FIDIC Requirements for Notices of Claim • Notice in Writing – Notice served under Clause 20.1 – Within 28 days after he “became aware, or should have become aware, of the event or circumstance” • When should the Contractor be aware: Imputed Knowledge or Objective standard • Question: who is the arbiter of when the Contractor should have become aware, the Engineer or Contractor? – Event or Circumstance Giving Rise to Claim • Fully detailed claim, monthly updated particulars, extension of time required and/or additional payment • Keeping of contemporary records © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 13. Managing Claims Under FIDIC Enforcing Condition Precedent • Doctrine of Consensus ad Idem – “If the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim” • Rationale – Contractor notifies Employer, to enable Employer to avert unintended consequences – potential disputes resolved early – Failure to comply with timescale – party loses right of claim © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 14. Managing Claims Under FIDIC Enforcing Condition Precedent • Multiplex Constr v Honeywell Control Systems – “Contractual terms requiring a contractor to give prompt notice of delay serve a valuable purpose; such notice enables matters to be investigated while they are still current. Furthermore, such notice sometimes gives the employer the opportunity to withdraw instructions when the financial consequences become apparent” per Justice Jackson – Notice triggered not only upon Contractor becoming aware of relevant event or circumstance, but also when Contractor should have become aware of it © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 15. Managing Claims Under FIDIC Enforcing Condition Precedent • Non Compliance Not Fatal – “If the Contractor fails to comply with this or another Sub-Clause in relation to any claim, any extension of time and/or additional payment shall take account of the extent (if any) to which the failure has prevented or prejudiced proper investigation of the claim …” – Whether enforcing time bar amounts to a penalty in the face of an Employer’s Valid Delay Factor or a Valid Variation – Onus of proof that the time bar should be imposed generally lies with the Employer © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 16. Managing Claims Under FIDIC Enforcing Condition Precedent • Obrascon Huarte Lain SA v HM’s AG for Gibraltar – Technology and Construction Court (TCC) in London adopted a relaxed interpretation of this requirement, ruled that the 28-day period for notifying a claim for EOT only begins following the onset of actual delay flowing from the event or circumstance which caused it – Judge Akenhead J remarked that he could see no reason why Clause 20.1 should be construed strictly against Contractor: "can see reason why it should be construed reasonably broadly, given its serious effect on what could otherwise be good claims for instance of Employer’s breach " © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 17. Managing Claims Under FIDIC Enforcing Condition Precedent • Obrascon Huarte Lain SA v HM’s AG for Gibraltar – notice of a claim for EOT does not have to be given pursuant to Clause 20.1 until there actually is delay, although Contractor can give notice when it reasonably believes that it will be delayed – Clause 8.4: entitlement to extension arises if and to the extent that the completion “is or will be delayed by” various listed events, such as variations or “unforeseeable” conditions – Extension of time can be claimed either when it is clear that there will be delay (prospective delay) or when delay has at least started to be incurred (retrospective delay) © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 18. Managing Claims Under FIDIC Enforcing Condition Precedent • Obrascon Huarte Lain SA v HM’s AG for Gibraltar – Clause 20.1: “event or circumstance” described in can mean either the incident (variation, exceptional weather or one of the other specified grounds for extension), or the delay which results or will inevitably result from the incident in question – Clause 8.4: Wording is “is or will be delayed by”, and not: “is or will be delayed whichever is the earliest” © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 19. Managing Claims Under FIDIC Enforcing Condition Precedent • Chiemauer Membran-und Zeltbau GmbH v New Millennium Experience – English Court of Appeal held that such condition precedent is not enforceable – Depending on commercial sense and intentions of contracting parties, and even for some condition precedent clauses, a court or arbitral tribunal may refuse to interpret it literally © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 20. Managing Claims Under FIDIC Detailed Particulars of a Claim • Chiemauer Membran-und Zeltbau GmbH v New Millennium Experience – Contractor to submit Fully Detailed Claim within 42 days of “event or circumstance” – Contractor can propose for the Engineer’s approval an extended time period to submit a detailed claim – Cause and effect of Delay, Culpable and Concurrent Delay, reasonable measures taken to mitigate delay – Particulars include correspondence, meeting minutes, site records, photographs, narratives, schedules, etc – Updated construction program showing planned, impacted and actual schedule © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 21. Managing Claims Under FIDIC Engineer’s Obligations • Engineer has 42 days to Approve or Disapprove with Detailed Comments – Engineer can propose for the Contractor’s approval an extended time period to respond – Request “any necessary further particulars” – Engineer unreasonably delaying a response to a Claim or requesting unnecessary further particulars – Clause 3.5: consulting with Contractor, try to reach an agreement. If not possible to reach agreement, make a fair determination © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 22. Managing Claims Under FIDIC Engineer’s Obligations • Engineer Failure to Respond within 42 days – No express sanctions for the Engineer’s failure to provide a timely response – Effect is Contractor unduly relieved of his contractual obligations; Contractor not kept aware of his contractual rights and entitlements arising from such valid claims and notifications © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 23. Managing Claims Under FIDIC Engineer’s Obligations • Prevention Principle – Where Engineer fails to provide a timely response or fails or refuses to grant an extension of time inspite of the Valid Delay Factor – Employer precluded from holding Contractor to completion date, due to Employer or his authorised Representative’s act or omission preventing Contractor from completing by that date – Completion time becomes at large; obligation to complete by specified date replaced by implied obligation to complete within a reasonable time © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 24. Managing Claims Under FIDIC Engineer’s Obligations • Roberts v Bury Improvement Commissioners – well established principle at common law that: “... no person can take advantage of the non-fulfilment of a condition the performance of which has been hindered by himself ...” per Blackburn and Mellor JJ – Reason for that rule is that otherwise a most unreasonable burden would be imposed upon the Contractor – Employer’s right to impose liquidated damages for delay replaced by unliquidated damages, based on new ‘reasonable time’ completion date © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 25. Managing Claims Under FIDIC Engineer’s Obligations • Shawton Engineering Ltd v DGP International Ltd – Court of Appeal held that what is a reasonable time has to be judged as at the time when the question arose, in the light of all the relevant circumstances: “There were variations, but no contractual mechanisms for extending time on account of the variations (or the mechanisms have failed). The effect in law of the variations was that the Contractor became obligated to complete their work within a reasonable time” © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 26. Managing Claims Under FIDIC Engineer’s Obligations • Shawton Engineering Ltd v DGP International Ltd – The judge rejected that a reasonable time should be ascertained by reference to the Original Contract Periods as extended only by the agreed periods for variations – “The question of what is a reasonable time within which to complete particular work is an objective question and is not dependent upon the actual time which a person may have agreed to carry out the work. Parties may have over or under estimated what time the work would actually require. The time which has to be ascertained is the time it would reasonably take to complete the whole of the works” © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 27. Managing Claims Under FIDIC FLOW CHART – Clause 20.1 Claims © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb
  • 28. Managing Claims Under FIDIC © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb  Interactive Voting System – Multiple Choice Questions  The Engineer is empowered under the prevailing express conditions to require that the Contractor submits claims for evaluation of Variations pursuant to Clause 20.1 and subject to the timeline condition precedent before he is entitled to compensation for the additional work instructed? 1) AGREE 2) DISAGREE
  • 29. Managing Claims Under FIDIC © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb  Interactive Voting System – Multiple Choice Questions  If the Engineer delays, refuses or fails to respond to the Contractor’s Claims pursuant to Clause 20.1, the Contractor’s rights may be prejudiced as a result. The FIDIC Forms should address this lacuna. 1) AGREE 2) DISAGREE
  • 30. MSc | BSc(Hons) | LLB(Hons) | FCIArb | FSIArb Adrias has more than two decades of practical working experience in the construction industry, working currently as in-house legal counsel for an MNC Company. Adrias is professionally trained in litigation, arbitration, adjudication, mediation and dispute resolution, and is an accredited arbitrator. He has handled several institutional and ad-hoc arbitral proceedings, as well as having tutored in SIArb, and conducted numerous workshops and seminars on diverse construction, contractual and legal issues including various Standard Forms of Contracts. He also lectures at the Royal Melbourne Institute of Technology, at the Singapore Institute of Management Campus teaching law subjects. email: adriastan@yahoo.com sg.linkedin.com/in/adrias-tan-5ab34035 Managing Claims Under FIDIC © 2016 Adrias Tan MSc BSc(Hons) LLB(Hons) FCIArb FSIArb Adrias Tan