Presentation On
STUDENT INDUSTRIAL WORK EXPERIENCE
SCHEME (SIWES)
Held at
KOPEK CONSTRUCTION LTD.(IBADAN, OYO STATE)
By
MUTIU AGUNBIADE
11/67CE/006
KWARA STATE UNIVERSITY
4/14/2015 1
SIWES
KOPEK Construction Ltd.
Various unit
Asphalt cement
Production
Pavement
Compaction
Conclusion
Reference
24/14/2015
SIWES
The Students Industrial Work Experience Scheme (SIWES) is a
skills development programme initiated by the Industrial Training
Fund (ITF), in 1973 to bridge the gap between theory and practice
among students of engineering and technology. It provides for on-
the-job practical experience for students as they are exposed to
work methods and techniques in handling equipment and
machinery that may not be available in their Institutions.
•provide students the opportunity to test their interest in a
particular career before permanent commitments are made.
•students will develop skills in the application of theory to
practical work situations.
•will increase a student's sense of responsibility.
•To prepare students for the work situation they are likely to
meet after graduation
4/14/2015 3
Kopek Construction Limited is a part of The ZARD group of
companies based in Ibadan, Oyo State of Nigeria. The group has
strong roots in different business areas like, Manufacturing,
Distribution, Construction, Packaging, Farming, Live stock,
Furniture, Education etc.,
Kopek Construction Limited was established in 1987, specialized in
roads and bridges construction and has about 40 professional and
2,500 non-professional staff.
Engaged in Road construction for the Government, World Bank
and other international organizations.
Presently they are working on :
Rehabilitation of 67km Ilesha to Akure road using Geotextile.
Construction of 6 km road in Ado- ekiti
Construction of ife, State of Osun.
4/14/2015 4
VARIOUS DEPARTMENT IN THE COMPANY
Accounting unit
Quantity Surveying unit
Surveying unit
Earthmoving Section
Laboratory Section
Engineering Section
Asphalt section.
4/14/2015 5
VARIOUS DEPARTMENT IN THE COMPANY
Accounting unit
Quantity Surveying unit
Surveying unit
Earthmoving Section
Laboratory Section
Engineering Section
Asphalt section.
4/14/2015 6
ASPHALT SECTION
This section deals with the production of Asphalt overlay and
laying of Asphalt cement.
Production of Asphalt concrete:
Material used: different sizes of aggregates, stone dust, filler and bitumen as the binder
Process Description:
First, aggregates travels through the cold feed bins,
where initial proportioning of the aggregates takes
place, The aggregate is then sent to a drier, where the
moisture is removed and is heated in the pug mill. It
continues to the hot elevator by screens to the hot
bins. The screens provide the final separation of the
aggregate. The aggregate is dropped into the pug mill
for mixing with the bitumen. The mixture is then
dropped into a waiting truck or moved to a storage
silo.
Fig. 1 Batching Plant
4/14/2015 7
4/14/2015 58
PROCESS DESCRIPTION
Fig. 2 Feed Bins Fig. 3 Pug mill
Fig. 4 Pug mill
Fig. 5 Fuel Cylinder
PROCESS DESCRIPTION CONT’D
Fig. 6
Hot Elevator
Fig. 8
Arial over view of Asphalt plant
Fig. 7 Screens 4/14/2015 9
4/14/2015 10
LAYING OF ASPHALT OVERLAY USING REINFORCEMENT.
First in the laying of the Asphalt, after the sub base has
been compacted, primed with bitumen emulsion, and
blinded. It will be opened to traffic for at least 24 hours
after which asphalt concrete can be placed on it. The
first step that was taken in laying of asphalt is to use a
sweeper, to sweep away all the blinding and dirt’s on
the surface we want to place the asphalt and then the
bitumen tanker spray bitumen emulsion at a spray rate
of 0.9 sq/m which the spraying will be monitored by
the laboratory technician, the bitumen will be allowed
to dry for some minutes then the binder asphalt
(asphalt with larger aggregates) will be placed on it at
a temperature ranging from 120°C to 140°C then it
will be compacted at a temperature of about 90°C, then
it will be open to traffic for about 24 hours before
laying the final layer wearing course.(Engr. Agboola
Stephen )
Fig. 9 Road Profile
4/14/2015 11
Bitumen is the first applied layer used to protect and stabilize the surface of the
base. We make use of Bitumen Emulsion .
The maximum amount to be applied between 0.9 and 2.3 l/m2
 The temperature of the asphalt concrete leaving the plant should not be less
than 135°C nor more than 163°C
Fig.10 4/14/2015 12
1. Adequate compaction of asphalt is essential to ensure the mix
design performance expected service life and required density is
achieved.
2. The main factors influencing the successful compaction of asphalt
are:
4/14/2015 13
 Rolling procedures and techniques.
 Temperature of the mix.
 Mix properties.
 Soundness and stiffness of the
underlying base.
 Type and numbers of rollers or other
compaction equipment
Fig.11
PROCESS DESCRIPTION
Binder Course
Fig. 13 Primed Surface
Fig. 14 Paver
Fig. 12 Sweeper
Fig. 15 Roller4/14/2015
14
PROCESS DESCRIPTION CONT’D
Wearing Course
Fig. 16 Bitumen primed Surface
Fig. 17 Backhoe use in laying of Geotextile
Fig. 18 Geotextile Surface Fig. 19 Asphalt Blinded Geotextile Surface4/14/2015 15
PROCESS DESCRIPTION CONT’D
Fig. 23 Pneumatic tired roller
Fig. 20 Laying of Wearing Course Fig. 21 Laying of Wearing Course
Fig. 22 Vibratory Steel Drum compactor
4/14/2015 16
The industrial training has helped me with the basic practical and
theoretical knowledge that I may not have gotten from the lecture
room. It also gave me the opportunity to have a feel of what it would be
like after graduation when I start working.
After my internship with Kopek Construction Company:
• I can effectively carry out a borrow pit test on any site to determine
the suitability of the soil.
• I can effectively assist in laying of Asphalt concrete with the use of
Geo-synthetics.
• I can easily identify different types of heavy duty machines used in
construction.
4/14/2015 17
4/14/2015 18
REFERENCE
Engr. Agboola Stephen (Site Supervisor Kopek Construction Limited)
Engr. Afolabi Wahab (Site Engineer Kopek Construction Limited)
Mr Thomas Oyegoke (Senior Laboratory Technician Kopek Construction Limited)
4/14/2015 19
4/14/2015
20

Contenu connexe

Tendances

BITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADBITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADkumawat123
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNeha Vivek
 
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION Ved Jangid
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentationPawan Kumar
 
Dense Bituminous Macadam Road
Dense Bituminous Macadam RoadDense Bituminous Macadam Road
Dense Bituminous Macadam RoadSaratMishra4
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignUmer Farooq
 
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONROHITASH ROJ
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsNatarajaSaiCharan1
 
BITUMINOUS PAVING MIXES PPT
BITUMINOUS PAVING MIXES PPTBITUMINOUS PAVING MIXES PPT
BITUMINOUS PAVING MIXES PPTNischay N Gowda
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training pptSumit Singh
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road constructionAnitha Jacob
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavementRandhir Kumar
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)y Sahaja
 
GEOSYNTHETIC TESTING TECHNIQUES
GEOSYNTHETIC TESTING TECHNIQUESGEOSYNTHETIC TESTING TECHNIQUES
GEOSYNTHETIC TESTING TECHNIQUESCBRI-CSIR
 

Tendances (20)

BITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADBITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROAD
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
 
Flexible pavement presentation
Flexible pavement presentationFlexible pavement presentation
Flexible pavement presentation
 
Soil nailing
Soil nailing Soil nailing
Soil nailing
 
Dense Bituminous Macadam Road
Dense Bituminous Macadam RoadDense Bituminous Macadam Road
Dense Bituminous Macadam Road
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and Design
 
Shotcrete technology
Shotcrete technologyShotcrete technology
Shotcrete technology
 
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical Drains
 
PQC concrete road
PQC concrete roadPQC concrete road
PQC concrete road
 
BITUMINOUS PAVING MIXES PPT
BITUMINOUS PAVING MIXES PPTBITUMINOUS PAVING MIXES PPT
BITUMINOUS PAVING MIXES PPT
 
Unit 5
Unit 5Unit 5
Unit 5
 
Pumped Concrete
Pumped Concrete Pumped Concrete
Pumped Concrete
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavement
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
GEOSYNTHETIC TESTING TECHNIQUES
GEOSYNTHETIC TESTING TECHNIQUESGEOSYNTHETIC TESTING TECHNIQUES
GEOSYNTHETIC TESTING TECHNIQUES
 

En vedette

Civil engineering material bitumen
Civil engineering material bitumenCivil engineering material bitumen
Civil engineering material bitumenSukhdarshan Singh
 
Asphalt presentation-by-diar ismail
Asphalt presentation-by-diar ismailAsphalt presentation-by-diar ismail
Asphalt presentation-by-diar ismaildiarfirstdiarfirst
 
Asphalt testing range
Asphalt testing rangeAsphalt testing range
Asphalt testing rangeMonu Prashar
 
Asphalt Repair & Maintenance: Do It Yourself vs Hiring A Contractor
Asphalt Repair & Maintenance: Do It Yourself vs Hiring A Contractor Asphalt Repair & Maintenance: Do It Yourself vs Hiring A Contractor
Asphalt Repair & Maintenance: Do It Yourself vs Hiring A Contractor GP Roadway Solutions
 
Asphalt & carpet specifications
Asphalt & carpet specificationsAsphalt & carpet specifications
Asphalt & carpet specificationsmaskmk
 
Pavement Surfacing Materials
Pavement Surfacing MaterialsPavement Surfacing Materials
Pavement Surfacing MaterialsAdesh V Jain
 
Porous asphalt pavement
Porous asphalt pavementPorous asphalt pavement
Porous asphalt pavementAshif AR
 
Chapter3 road pavement
Chapter3 road pavementChapter3 road pavement
Chapter3 road pavementpokjak80
 
Polymers and polymer composites
Polymers and polymer compositesPolymers and polymer composites
Polymers and polymer compositesRichard M Pradeep
 
production tests aging of bitumen and modified Bitumen
production tests aging of bitumen and modified Bitumen production tests aging of bitumen and modified Bitumen
production tests aging of bitumen and modified Bitumen Abhijeet Bhosale
 
Pavement Materials Bitumen
Pavement Materials  BitumenPavement Materials  Bitumen
Pavement Materials Bitumensrinivas2036
 

En vedette (20)

Asphalt
AsphaltAsphalt
Asphalt
 
Bituminous pavement
Bituminous pavementBituminous pavement
Bituminous pavement
 
Civil engineering material bitumen
Civil engineering material bitumenCivil engineering material bitumen
Civil engineering material bitumen
 
Asphalt english
Asphalt  englishAsphalt  english
Asphalt english
 
Asphalt presentation-by-diar ismail
Asphalt presentation-by-diar ismailAsphalt presentation-by-diar ismail
Asphalt presentation-by-diar ismail
 
Asphalt testing range
Asphalt testing rangeAsphalt testing range
Asphalt testing range
 
Erik Updyke & Imelda Diaz: Bonded Wearing Course
Erik Updyke & Imelda Diaz: Bonded Wearing CourseErik Updyke & Imelda Diaz: Bonded Wearing Course
Erik Updyke & Imelda Diaz: Bonded Wearing Course
 
Asphalt Repair & Maintenance: Do It Yourself vs Hiring A Contractor
Asphalt Repair & Maintenance: Do It Yourself vs Hiring A Contractor Asphalt Repair & Maintenance: Do It Yourself vs Hiring A Contractor
Asphalt Repair & Maintenance: Do It Yourself vs Hiring A Contractor
 
Asphalt
AsphaltAsphalt
Asphalt
 
Composites
CompositesComposites
Composites
 
Bitumin and asphalt
Bitumin and asphaltBitumin and asphalt
Bitumin and asphalt
 
Asphalt & carpet specifications
Asphalt & carpet specificationsAsphalt & carpet specifications
Asphalt & carpet specifications
 
Bituminous Road
 Bituminous Road Bituminous Road
Bituminous Road
 
Pavement Surfacing Materials
Pavement Surfacing MaterialsPavement Surfacing Materials
Pavement Surfacing Materials
 
Porous asphalt pavement
Porous asphalt pavementPorous asphalt pavement
Porous asphalt pavement
 
Chapter3 road pavement
Chapter3 road pavementChapter3 road pavement
Chapter3 road pavement
 
Polymers and polymer composites
Polymers and polymer compositesPolymers and polymer composites
Polymers and polymer composites
 
production tests aging of bitumen and modified Bitumen
production tests aging of bitumen and modified Bitumen production tests aging of bitumen and modified Bitumen
production tests aging of bitumen and modified Bitumen
 
Pavement Materials Bitumen
Pavement Materials  BitumenPavement Materials  Bitumen
Pavement Materials Bitumen
 
Polymer composites
Polymer compositesPolymer composites
Polymer composites
 

Similaire à Presentation on Asphalt Concrete

Developers Transflex Installation
Developers Transflex InstallationDevelopers Transflex Installation
Developers Transflex Installationguest470ea8
 
Bharat saini ( report)
Bharat saini ( report)Bharat saini ( report)
Bharat saini ( report)bharatsaini23
 
IRJET- Systematic Prevention and Repair of Potholes in Flexible Pavement
IRJET- Systematic Prevention and Repair of Potholes in Flexible PavementIRJET- Systematic Prevention and Repair of Potholes in Flexible Pavement
IRJET- Systematic Prevention and Repair of Potholes in Flexible PavementIRJET Journal
 
Concrete Mix Design Report
Concrete Mix Design ReportConcrete Mix Design Report
Concrete Mix Design ReportZakaria Yahya
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion jointakash yadav
 
Curing of concrete Amit payal
Curing of concrete  Amit payalCuring of concrete  Amit payal
Curing of concrete Amit payalAMIT PAYAL
 
IRJET- Experimental Investigation of Fly Ash based Geopolymer Concrete
IRJET- Experimental Investigation of Fly Ash based Geopolymer ConcreteIRJET- Experimental Investigation of Fly Ash based Geopolymer Concrete
IRJET- Experimental Investigation of Fly Ash based Geopolymer ConcreteIRJET Journal
 
IRJET- Systematic Prevention and Repair of Potholes in Flexible Pavement
IRJET- Systematic Prevention and Repair of Potholes in Flexible PavementIRJET- Systematic Prevention and Repair of Potholes in Flexible Pavement
IRJET- Systematic Prevention and Repair of Potholes in Flexible PavementIRJET Journal
 
Report on Cement manufacturing process
Report on Cement manufacturing process Report on Cement manufacturing process
Report on Cement manufacturing process Rohan Sharma
 
TRAINING REPORT ON CASTING
TRAINING REPORT ON CASTINGTRAINING REPORT ON CASTING
TRAINING REPORT ON CASTINGPawan Kumar
 
om industrial training report.pptx
om industrial training report.pptxom industrial training report.pptx
om industrial training report.pptxRohitYadav530108
 
Sand making machine is the necessary equipment to run a sand making plant
Sand making machine is the necessary equipment to run a sand making plantSand making machine is the necessary equipment to run a sand making plant
Sand making machine is the necessary equipment to run a sand making plantlinxiaomo
 
jyoti cnc training report
jyoti cnc training reportjyoti cnc training report
jyoti cnc training reportvikas thakkar
 
Curriculum vitae 1
Curriculum vitae 1Curriculum vitae 1
Curriculum vitae 1Mahmoud Ali
 
DELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECTDELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECTGLA University
 
processes : from raw bauxite to refractory alumina bricks
processes : from raw bauxite to refractory alumina bricksprocesses : from raw bauxite to refractory alumina bricks
processes : from raw bauxite to refractory alumina bricksParth Vaishnav
 
AAC Block Plant Consultant
AAC Block Plant ConsultantAAC Block Plant Consultant
AAC Block Plant Consultantgubbiseo
 

Similaire à Presentation on Asphalt Concrete (20)

Developers Transflex Installation
Developers Transflex InstallationDevelopers Transflex Installation
Developers Transflex Installation
 
Bharat saini ( report)
Bharat saini ( report)Bharat saini ( report)
Bharat saini ( report)
 
IRJET- Systematic Prevention and Repair of Potholes in Flexible Pavement
IRJET- Systematic Prevention and Repair of Potholes in Flexible PavementIRJET- Systematic Prevention and Repair of Potholes in Flexible Pavement
IRJET- Systematic Prevention and Repair of Potholes in Flexible Pavement
 
BBM PPT By Hchakravarti
BBM PPT By HchakravartiBBM PPT By Hchakravarti
BBM PPT By Hchakravarti
 
Concrete Mix Design Report
Concrete Mix Design ReportConcrete Mix Design Report
Concrete Mix Design Report
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion joint
 
Curing of concrete Amit payal
Curing of concrete  Amit payalCuring of concrete  Amit payal
Curing of concrete Amit payal
 
SIWES Report
SIWES ReportSIWES Report
SIWES Report
 
IRJET- Experimental Investigation of Fly Ash based Geopolymer Concrete
IRJET- Experimental Investigation of Fly Ash based Geopolymer ConcreteIRJET- Experimental Investigation of Fly Ash based Geopolymer Concrete
IRJET- Experimental Investigation of Fly Ash based Geopolymer Concrete
 
induarial trainin report
induarial trainin reportinduarial trainin report
induarial trainin report
 
IRJET- Systematic Prevention and Repair of Potholes in Flexible Pavement
IRJET- Systematic Prevention and Repair of Potholes in Flexible PavementIRJET- Systematic Prevention and Repair of Potholes in Flexible Pavement
IRJET- Systematic Prevention and Repair of Potholes in Flexible Pavement
 
Report on Cement manufacturing process
Report on Cement manufacturing process Report on Cement manufacturing process
Report on Cement manufacturing process
 
TRAINING REPORT ON CASTING
TRAINING REPORT ON CASTINGTRAINING REPORT ON CASTING
TRAINING REPORT ON CASTING
 
om industrial training report.pptx
om industrial training report.pptxom industrial training report.pptx
om industrial training report.pptx
 
Sand making machine is the necessary equipment to run a sand making plant
Sand making machine is the necessary equipment to run a sand making plantSand making machine is the necessary equipment to run a sand making plant
Sand making machine is the necessary equipment to run a sand making plant
 
jyoti cnc training report
jyoti cnc training reportjyoti cnc training report
jyoti cnc training report
 
Curriculum vitae 1
Curriculum vitae 1Curriculum vitae 1
Curriculum vitae 1
 
DELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECTDELHI-AGRA ROAD PROJECT
DELHI-AGRA ROAD PROJECT
 
processes : from raw bauxite to refractory alumina bricks
processes : from raw bauxite to refractory alumina bricksprocesses : from raw bauxite to refractory alumina bricks
processes : from raw bauxite to refractory alumina bricks
 
AAC Block Plant Consultant
AAC Block Plant ConsultantAAC Block Plant Consultant
AAC Block Plant Consultant
 

Dernier

A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEselvakumar948
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilVinayVitekari
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 

Dernier (20)

A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 

Presentation on Asphalt Concrete

  • 1. Presentation On STUDENT INDUSTRIAL WORK EXPERIENCE SCHEME (SIWES) Held at KOPEK CONSTRUCTION LTD.(IBADAN, OYO STATE) By MUTIU AGUNBIADE 11/67CE/006 KWARA STATE UNIVERSITY 4/14/2015 1
  • 2. SIWES KOPEK Construction Ltd. Various unit Asphalt cement Production Pavement Compaction Conclusion Reference 24/14/2015
  • 3. SIWES The Students Industrial Work Experience Scheme (SIWES) is a skills development programme initiated by the Industrial Training Fund (ITF), in 1973 to bridge the gap between theory and practice among students of engineering and technology. It provides for on- the-job practical experience for students as they are exposed to work methods and techniques in handling equipment and machinery that may not be available in their Institutions. •provide students the opportunity to test their interest in a particular career before permanent commitments are made. •students will develop skills in the application of theory to practical work situations. •will increase a student's sense of responsibility. •To prepare students for the work situation they are likely to meet after graduation 4/14/2015 3
  • 4. Kopek Construction Limited is a part of The ZARD group of companies based in Ibadan, Oyo State of Nigeria. The group has strong roots in different business areas like, Manufacturing, Distribution, Construction, Packaging, Farming, Live stock, Furniture, Education etc., Kopek Construction Limited was established in 1987, specialized in roads and bridges construction and has about 40 professional and 2,500 non-professional staff. Engaged in Road construction for the Government, World Bank and other international organizations. Presently they are working on : Rehabilitation of 67km Ilesha to Akure road using Geotextile. Construction of 6 km road in Ado- ekiti Construction of ife, State of Osun. 4/14/2015 4
  • 5. VARIOUS DEPARTMENT IN THE COMPANY Accounting unit Quantity Surveying unit Surveying unit Earthmoving Section Laboratory Section Engineering Section Asphalt section. 4/14/2015 5
  • 6. VARIOUS DEPARTMENT IN THE COMPANY Accounting unit Quantity Surveying unit Surveying unit Earthmoving Section Laboratory Section Engineering Section Asphalt section. 4/14/2015 6
  • 7. ASPHALT SECTION This section deals with the production of Asphalt overlay and laying of Asphalt cement. Production of Asphalt concrete: Material used: different sizes of aggregates, stone dust, filler and bitumen as the binder Process Description: First, aggregates travels through the cold feed bins, where initial proportioning of the aggregates takes place, The aggregate is then sent to a drier, where the moisture is removed and is heated in the pug mill. It continues to the hot elevator by screens to the hot bins. The screens provide the final separation of the aggregate. The aggregate is dropped into the pug mill for mixing with the bitumen. The mixture is then dropped into a waiting truck or moved to a storage silo. Fig. 1 Batching Plant 4/14/2015 7
  • 8. 4/14/2015 58 PROCESS DESCRIPTION Fig. 2 Feed Bins Fig. 3 Pug mill Fig. 4 Pug mill Fig. 5 Fuel Cylinder
  • 9. PROCESS DESCRIPTION CONT’D Fig. 6 Hot Elevator Fig. 8 Arial over view of Asphalt plant Fig. 7 Screens 4/14/2015 9
  • 11. LAYING OF ASPHALT OVERLAY USING REINFORCEMENT. First in the laying of the Asphalt, after the sub base has been compacted, primed with bitumen emulsion, and blinded. It will be opened to traffic for at least 24 hours after which asphalt concrete can be placed on it. The first step that was taken in laying of asphalt is to use a sweeper, to sweep away all the blinding and dirt’s on the surface we want to place the asphalt and then the bitumen tanker spray bitumen emulsion at a spray rate of 0.9 sq/m which the spraying will be monitored by the laboratory technician, the bitumen will be allowed to dry for some minutes then the binder asphalt (asphalt with larger aggregates) will be placed on it at a temperature ranging from 120°C to 140°C then it will be compacted at a temperature of about 90°C, then it will be open to traffic for about 24 hours before laying the final layer wearing course.(Engr. Agboola Stephen ) Fig. 9 Road Profile 4/14/2015 11
  • 12. Bitumen is the first applied layer used to protect and stabilize the surface of the base. We make use of Bitumen Emulsion . The maximum amount to be applied between 0.9 and 2.3 l/m2  The temperature of the asphalt concrete leaving the plant should not be less than 135°C nor more than 163°C Fig.10 4/14/2015 12
  • 13. 1. Adequate compaction of asphalt is essential to ensure the mix design performance expected service life and required density is achieved. 2. The main factors influencing the successful compaction of asphalt are: 4/14/2015 13  Rolling procedures and techniques.  Temperature of the mix.  Mix properties.  Soundness and stiffness of the underlying base.  Type and numbers of rollers or other compaction equipment Fig.11
  • 14. PROCESS DESCRIPTION Binder Course Fig. 13 Primed Surface Fig. 14 Paver Fig. 12 Sweeper Fig. 15 Roller4/14/2015 14
  • 15. PROCESS DESCRIPTION CONT’D Wearing Course Fig. 16 Bitumen primed Surface Fig. 17 Backhoe use in laying of Geotextile Fig. 18 Geotextile Surface Fig. 19 Asphalt Blinded Geotextile Surface4/14/2015 15
  • 16. PROCESS DESCRIPTION CONT’D Fig. 23 Pneumatic tired roller Fig. 20 Laying of Wearing Course Fig. 21 Laying of Wearing Course Fig. 22 Vibratory Steel Drum compactor 4/14/2015 16
  • 17. The industrial training has helped me with the basic practical and theoretical knowledge that I may not have gotten from the lecture room. It also gave me the opportunity to have a feel of what it would be like after graduation when I start working. After my internship with Kopek Construction Company: • I can effectively carry out a borrow pit test on any site to determine the suitability of the soil. • I can effectively assist in laying of Asphalt concrete with the use of Geo-synthetics. • I can easily identify different types of heavy duty machines used in construction. 4/14/2015 17
  • 18. 4/14/2015 18 REFERENCE Engr. Agboola Stephen (Site Supervisor Kopek Construction Limited) Engr. Afolabi Wahab (Site Engineer Kopek Construction Limited) Mr Thomas Oyegoke (Senior Laboratory Technician Kopek Construction Limited)