Project Scheduling
CPM/PERT
2
 Network techniques
 Developed in 1950’s
 CPM by DuPont for chemical plants (1957)
 PERT by Booz, Allen & Hamilton with the U.S.
Navy, for Polaris missile (1958)
 Consider precedence relationships and
interdependencies
 Each uses a different estimate of activity times
PERT and CPM
why networks/CPM/PERT?
 Gantt charts don’t explicitly show
task relationships
 don’t show impact of delays or
shifting resources well
 network models clearly show
interdependencies
4
Is the project on schedule, ahead of schedule,
or behind schedule?
Is the project over or under cost budget?
Are there enough resources available to finish
the project on time?
If the project must be finished in less than the
scheduled amount of time, what is the way to
accomplish this at least cost?
Questions Which May Be
Addressed by PERT & CPM
5
The Six Steps Common to PERT & CPM
 Define the project and prepare the work breakdown
structure,
 Develop relationships among the activities. (Decide
which activities must precede and which must follow
others.)
 Draw the network connecting all of the activities
 Assign time and/or cost estimates to each activity
 Compute the longest time path through the network.
This is called the critical path
 Use the network to help plan, schedule, monitor, and
control the project
6
Terminology
 Activity: A specific or set of tasks required by
the project
 Event: Outcome of one or more activities
 Network: Combination of all activities and
events
 Path: Series of connected activities or
between any two events
 Critical path: Longest - Any delay would delay
the project
 Slack/float: Allowable slippage for a path
7
Activity Relationships
Predecessor – an activity that is required to
start or finish before the next activity(s) can
proceed
Successor – an activity that must start or
finish after the previous activity can finish
Types of relationships are defined from the
predecessor to the successor
8
1
A
B
A & B can occur
concurrently
2
3
Activity Relationships
9
1 4
2
3
A
B
C
A must be done
before C & D can
begin
D
Activity Relationships
10
1 4
2
3
A
B E
C
B & C must be done
before E can begin
D
Activity Relationships
AOA Project Network for
a House
3
2 0
1
3
1 1
1
1 2 4 6 7
3
5
Lay
foundation
Design
house and
obtain
financing
Order and
receive
materials
Dummy
Finish
work
Select
carpet
Select
paint
Build
house
12
 Activities are defined often by beginning &
ending events
 Every activity must have unique pair of
beginning & ending events
 Otherwise, computer programs get confused
 Dummy activities maintain precedence
 Consume no time or resources
Dummy Activities
13
Job on Arc Network
 Not allowed: no two
jobs can have the
same starting and
ending node!
 Need to introduce a
dummy job.
A
B
D
C
A
B
D
C
14
1 4
3
1-2
2-3
Incorrect
1 4
2
3
5
2
2-3
3-4
1-2
2-3
2-4 4-5
3-4: Dummy
activity
Correct
Dummy Activity Example
15
Critical Path
The longest continuous path of activities
through a project, which determines the
project end date
16
A General Hospital’s Activities and
Predecessors
Activity Description Immediate
Predecessors
A -
B -
C A
D A, B
E C
F C
G D, E
H F, G
17
AON Network for General Hospital
Start
A
B
C
D
F
F
G
H
Program Evaluation and
Review Technique (PERT)
PERT is based on the assumption that an
activity’s duration follows a probability
distribution instead of being a single value.
The probabilistic information about the
activities is translated into probabilistic
information about the project.
PERT
 reflects PROBABILISTIC nature of durations
 assumes BETA distribution
 same as CPM except THREE duration
estimates
optimistic
most likely
pessimistic
PERT Calculation
a = optimistic duration estimate
m = most likely duration estimate
b = pessimistic duration estimate
expected duration:
variance:
Te
a + 4m + b
6
V =
b - a
6







2
21
 3 time estimates
 Optimistic times (a)
 Most-likely time (m)
 Pessimistic time (b)
 Follow beta distribution
 Expected time: t = (a + 4m + b)/6
 Variance of times: v = (b - a)2/6
PERT Activity Times
22
Variability of Completion Time for
Noncritical Paths
Variability of times for activities on non-critical
paths must be considered when finding the
probability of finishing in a specified time.
Variation in non-critical activity may cause
change in critical path.
23
Advantages of PERT/CPM
 Especially useful when scheduling and controlling
large projects.
 Straightforward concept and not mathematically
complex.
 Graphical networks aid perception of relationships
among project activities.
 Critical path & slack time analyses help pinpoint
activities that need to be closely watched.
 Project documentation and graphics point out who is
responsible for various activities.
 Applicable to a wide variety of projects.
 Useful in monitoring schedules and costs.
24
Questions Answered by CPM & PERT
Completion date?
On Schedule?
Within Budget?
Critical Activities?
How can the project be finished early at the
least cost?
25
 Assumes clearly defined, independent, &
stable activities
 Specified precedence relationships
 Activity times (PERT) follow beta distribution
 Subjective time estimates
 Over-emphasis on critical path
Limitations of PERT/CPM
Example 2. CPM with Three Activity Time
Estimates
Ta s k
Im m e d ia t e
P re d e c e s o rs O p t im is t ic M o s t L ik e ly P e s s im is t ic
A N o n e 3 6 1 5
B N o n e 2 4 1 4
C A 6 1 2 3 0
D A 2 5 8
E C 5 1 1 1 7
F D 3 6 1 5
G B 3 9 2 7
H E , F 1 4 7
I G , H 4 1 9 2 8
Example 2. Expected Time
Calculations
T a s k
Im m e d i a t e
P re d e c e s o rs
E x p e c t e d
T i m e
A N o n e 7
B N o n e 5 . 3 3 3
C A 1 4
D A 5
E C 1 1
F D 7
G B 1 1
H E , F 4
I G , H 1 8
Example 2. Probability Exercise
What is the probability of finishing this project in
less than 53 days?
p(t < D)
TE = 54
Z =
D - TE
cp
2


t
D=53
Activity variance, = (
Pessim. - Optim.
6
)
2 2

Ta s k O p tim is tic M o s t L ik e ly P e s s im is tic V a ria n c e
A 3 6 1 5 4
B 2 4 1 4
C 6 1 2 3 0 1 6
D 2 5 8
E 5 1 1 1 7 4
F 3 6 1 5
G 3 9 2 7
H 1 4 7 1
I 4 1 9 2 8 1 6
(Sum the variance along the critical path.) 2
 = 41
p(Z < -0.156) = 0.5 - 0.0636 = 0.436, or 43.6 %
Z =
D - T
=
53- 54
41
= -.156
E
cp
2


TE = 54
p(t < D)
t
D=53
32
A Comparison of AON and AOA
Network Conventions

Contenu connexe

Similaire à CPM-PERT.ppt

Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Chandra Shekar Immani
 
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docxYagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docxjeffevans62972
 
Basics CPM&PERT.ppt
Basics CPM&PERT.pptBasics CPM&PERT.ppt
Basics CPM&PERT.pptssuserad50d3
 
C10 project management
C10 project managementC10 project management
C10 project managementhakimizaki
 
C10 project management
C10 project managementC10 project management
C10 project managementhakimizaki
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management Joshua Miranda
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPHOEBEANNEARTECHE1
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.pptDejeneDay
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Overview1) Overview – The continued discussion of project implem.docx
Overview1) Overview – The continued discussion of project implem.docxOverview1) Overview – The continued discussion of project implem.docx
Overview1) Overview – The continued discussion of project implem.docxalfred4lewis58146
 
Project management
Project managementProject management
Project managementShankaran Rd
 
Overview1) Overview – The continued discussion of .docx
Overview1)             Overview – The continued discussion of .docxOverview1)             Overview – The continued discussion of .docx
Overview1) Overview – The continued discussion of .docxalfred4lewis58146
 
PERT-CPM.pdf
PERT-CPM.pdfPERT-CPM.pdf
PERT-CPM.pdflimchoy
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering EconomicsDeepak Paithankar
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path methodPrathima Girish
 

Similaire à CPM-PERT.ppt (20)

Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...Quantitative analysis for business decision- Program Evaluation and Review Te...
Quantitative analysis for business decision- Program Evaluation and Review Te...
 
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docxYagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
 
Basics CPM&PERT.ppt
Basics CPM&PERT.pptBasics CPM&PERT.ppt
Basics CPM&PERT.ppt
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
 
C10 project management
C10 project managementC10 project management
C10 project management
 
C10 project management
C10 project managementC10 project management
C10 project management
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptx
 
chapter 6.ppt
chapter 6.pptchapter 6.ppt
chapter 6.ppt
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Project management
Project managementProject management
Project management
 
Overview1) Overview – The continued discussion of project implem.docx
Overview1) Overview – The continued discussion of project implem.docxOverview1) Overview – The continued discussion of project implem.docx
Overview1) Overview – The continued discussion of project implem.docx
 
Project management
Project managementProject management
Project management
 
Overview1) Overview – The continued discussion of .docx
Overview1)             Overview – The continued discussion of .docxOverview1)             Overview – The continued discussion of .docx
Overview1) Overview – The continued discussion of .docx
 
PERT-CPM.pdf
PERT-CPM.pdfPERT-CPM.pdf
PERT-CPM.pdf
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path method
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 

Dernier

How to structure your pitch - B4i template
How to structure your pitch - B4i templateHow to structure your pitch - B4i template
How to structure your pitch - B4i templateFerruccio Martinelli
 
Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...
Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...
Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...ZurliaSoop
 
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893Health
 
How Multicultural Toys Helps in Child Development.pptx
How Multicultural Toys Helps in Child Development.pptxHow Multicultural Toys Helps in Child Development.pptx
How Multicultural Toys Helps in Child Development.pptxDiversity In Toys
 
NEON LIGHT CITY pitch deck for the new PC game
NEON LIGHT CITY pitch deck for the new PC gameNEON LIGHT CITY pitch deck for the new PC game
NEON LIGHT CITY pitch deck for the new PC gametess51
 
JAIPUR CALL GIRLS SERVICE REAL HOT SEXY 👯 CALL GIRLS IN JAIPUR BOOK YOUR DREA...
JAIPUR CALL GIRLS SERVICE REAL HOT SEXY 👯 CALL GIRLS IN JAIPUR BOOK YOUR DREA...JAIPUR CALL GIRLS SERVICE REAL HOT SEXY 👯 CALL GIRLS IN JAIPUR BOOK YOUR DREA...
JAIPUR CALL GIRLS SERVICE REAL HOT SEXY 👯 CALL GIRLS IN JAIPUR BOOK YOUR DREA...Escorts service
 
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...StartupSprouts.in
 
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.inEV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.inStartupSprouts.in
 
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdfEnabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdfSmartinfologiks
 
Dàni Velvet Personal Brand Exploration (1).pptx
Dàni Velvet Personal Brand Exploration (1).pptxDàni Velvet Personal Brand Exploration (1).pptx
Dàni Velvet Personal Brand Exploration (1).pptxdmtillman
 
Indian Call girl in Dubai 0508644382 Dubai Call girls
Indian Call girl in Dubai 0508644382 Dubai Call girlsIndian Call girl in Dubai 0508644382 Dubai Call girls
Indian Call girl in Dubai 0508644382 Dubai Call girlsMonica Sydney
 
Famedesired Project portfolio1 . Fullsail
Famedesired Project portfolio1 . FullsailFamedesired Project portfolio1 . Fullsail
Famedesired Project portfolio1 . Fullsailfergusonamani
 

Dernier (12)

How to structure your pitch - B4i template
How to structure your pitch - B4i templateHow to structure your pitch - B4i template
How to structure your pitch - B4i template
 
Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...
Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...
Jual Obat Aborsi Bojonegoro ( Asli No.1 ) 085657271886 Obat Penggugur Kandung...
 
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
+971565801893>>Safe and original mtp kit for sale in Dubai>>+971565801893
 
How Multicultural Toys Helps in Child Development.pptx
How Multicultural Toys Helps in Child Development.pptxHow Multicultural Toys Helps in Child Development.pptx
How Multicultural Toys Helps in Child Development.pptx
 
NEON LIGHT CITY pitch deck for the new PC game
NEON LIGHT CITY pitch deck for the new PC gameNEON LIGHT CITY pitch deck for the new PC game
NEON LIGHT CITY pitch deck for the new PC game
 
JAIPUR CALL GIRLS SERVICE REAL HOT SEXY 👯 CALL GIRLS IN JAIPUR BOOK YOUR DREA...
JAIPUR CALL GIRLS SERVICE REAL HOT SEXY 👯 CALL GIRLS IN JAIPUR BOOK YOUR DREA...JAIPUR CALL GIRLS SERVICE REAL HOT SEXY 👯 CALL GIRLS IN JAIPUR BOOK YOUR DREA...
JAIPUR CALL GIRLS SERVICE REAL HOT SEXY 👯 CALL GIRLS IN JAIPUR BOOK YOUR DREA...
 
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
Shareholders Agreement Template for Compulsorily Convertible Debt Funding- St...
 
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.inEV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
EV Electric Vehicle Startup Pitch Deck- StartupSprouts.in
 
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdfEnabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
Enabling Business Users to Interpret Data Through Self-Service Analytics (2).pdf
 
Dàni Velvet Personal Brand Exploration (1).pptx
Dàni Velvet Personal Brand Exploration (1).pptxDàni Velvet Personal Brand Exploration (1).pptx
Dàni Velvet Personal Brand Exploration (1).pptx
 
Indian Call girl in Dubai 0508644382 Dubai Call girls
Indian Call girl in Dubai 0508644382 Dubai Call girlsIndian Call girl in Dubai 0508644382 Dubai Call girls
Indian Call girl in Dubai 0508644382 Dubai Call girls
 
Famedesired Project portfolio1 . Fullsail
Famedesired Project portfolio1 . FullsailFamedesired Project portfolio1 . Fullsail
Famedesired Project portfolio1 . Fullsail
 

CPM-PERT.ppt

  • 2. 2  Network techniques  Developed in 1950’s  CPM by DuPont for chemical plants (1957)  PERT by Booz, Allen & Hamilton with the U.S. Navy, for Polaris missile (1958)  Consider precedence relationships and interdependencies  Each uses a different estimate of activity times PERT and CPM
  • 3. why networks/CPM/PERT?  Gantt charts don’t explicitly show task relationships  don’t show impact of delays or shifting resources well  network models clearly show interdependencies
  • 4. 4 Is the project on schedule, ahead of schedule, or behind schedule? Is the project over or under cost budget? Are there enough resources available to finish the project on time? If the project must be finished in less than the scheduled amount of time, what is the way to accomplish this at least cost? Questions Which May Be Addressed by PERT & CPM
  • 5. 5 The Six Steps Common to PERT & CPM  Define the project and prepare the work breakdown structure,  Develop relationships among the activities. (Decide which activities must precede and which must follow others.)  Draw the network connecting all of the activities  Assign time and/or cost estimates to each activity  Compute the longest time path through the network. This is called the critical path  Use the network to help plan, schedule, monitor, and control the project
  • 6. 6 Terminology  Activity: A specific or set of tasks required by the project  Event: Outcome of one or more activities  Network: Combination of all activities and events  Path: Series of connected activities or between any two events  Critical path: Longest - Any delay would delay the project  Slack/float: Allowable slippage for a path
  • 7. 7 Activity Relationships Predecessor – an activity that is required to start or finish before the next activity(s) can proceed Successor – an activity that must start or finish after the previous activity can finish Types of relationships are defined from the predecessor to the successor
  • 8. 8 1 A B A & B can occur concurrently 2 3 Activity Relationships
  • 9. 9 1 4 2 3 A B C A must be done before C & D can begin D Activity Relationships
  • 10. 10 1 4 2 3 A B E C B & C must be done before E can begin D Activity Relationships
  • 11. AOA Project Network for a House 3 2 0 1 3 1 1 1 1 2 4 6 7 3 5 Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house
  • 12. 12  Activities are defined often by beginning & ending events  Every activity must have unique pair of beginning & ending events  Otherwise, computer programs get confused  Dummy activities maintain precedence  Consume no time or resources Dummy Activities
  • 13. 13 Job on Arc Network  Not allowed: no two jobs can have the same starting and ending node!  Need to introduce a dummy job. A B D C A B D C
  • 14. 14 1 4 3 1-2 2-3 Incorrect 1 4 2 3 5 2 2-3 3-4 1-2 2-3 2-4 4-5 3-4: Dummy activity Correct Dummy Activity Example
  • 15. 15 Critical Path The longest continuous path of activities through a project, which determines the project end date
  • 16. 16 A General Hospital’s Activities and Predecessors Activity Description Immediate Predecessors A - B - C A D A, B E C F C G D, E H F, G
  • 17. 17 AON Network for General Hospital Start A B C D F F G H
  • 18. Program Evaluation and Review Technique (PERT) PERT is based on the assumption that an activity’s duration follows a probability distribution instead of being a single value. The probabilistic information about the activities is translated into probabilistic information about the project.
  • 19. PERT  reflects PROBABILISTIC nature of durations  assumes BETA distribution  same as CPM except THREE duration estimates optimistic most likely pessimistic
  • 20. PERT Calculation a = optimistic duration estimate m = most likely duration estimate b = pessimistic duration estimate expected duration: variance: Te a + 4m + b 6 V = b - a 6        2
  • 21. 21  3 time estimates  Optimistic times (a)  Most-likely time (m)  Pessimistic time (b)  Follow beta distribution  Expected time: t = (a + 4m + b)/6  Variance of times: v = (b - a)2/6 PERT Activity Times
  • 22. 22 Variability of Completion Time for Noncritical Paths Variability of times for activities on non-critical paths must be considered when finding the probability of finishing in a specified time. Variation in non-critical activity may cause change in critical path.
  • 23. 23 Advantages of PERT/CPM  Especially useful when scheduling and controlling large projects.  Straightforward concept and not mathematically complex.  Graphical networks aid perception of relationships among project activities.  Critical path & slack time analyses help pinpoint activities that need to be closely watched.  Project documentation and graphics point out who is responsible for various activities.  Applicable to a wide variety of projects.  Useful in monitoring schedules and costs.
  • 24. 24 Questions Answered by CPM & PERT Completion date? On Schedule? Within Budget? Critical Activities? How can the project be finished early at the least cost?
  • 25. 25  Assumes clearly defined, independent, & stable activities  Specified precedence relationships  Activity times (PERT) follow beta distribution  Subjective time estimates  Over-emphasis on critical path Limitations of PERT/CPM
  • 26. Example 2. CPM with Three Activity Time Estimates Ta s k Im m e d ia t e P re d e c e s o rs O p t im is t ic M o s t L ik e ly P e s s im is t ic A N o n e 3 6 1 5 B N o n e 2 4 1 4 C A 6 1 2 3 0 D A 2 5 8 E C 5 1 1 1 7 F D 3 6 1 5 G B 3 9 2 7 H E , F 1 4 7 I G , H 4 1 9 2 8
  • 27. Example 2. Expected Time Calculations T a s k Im m e d i a t e P re d e c e s o rs E x p e c t e d T i m e A N o n e 7 B N o n e 5 . 3 3 3 C A 1 4 D A 5 E C 1 1 F D 7 G B 1 1 H E , F 4 I G , H 1 8
  • 28. Example 2. Probability Exercise What is the probability of finishing this project in less than 53 days? p(t < D) TE = 54 Z = D - TE cp 2   t D=53
  • 29. Activity variance, = ( Pessim. - Optim. 6 ) 2 2  Ta s k O p tim is tic M o s t L ik e ly P e s s im is tic V a ria n c e A 3 6 1 5 4 B 2 4 1 4 C 6 1 2 3 0 1 6 D 2 5 8 E 5 1 1 1 7 4 F 3 6 1 5 G 3 9 2 7 H 1 4 7 1 I 4 1 9 2 8 1 6 (Sum the variance along the critical path.) 2  = 41
  • 30. p(Z < -0.156) = 0.5 - 0.0636 = 0.436, or 43.6 % Z = D - T = 53- 54 41 = -.156 E cp 2   TE = 54 p(t < D) t D=53
  • 31. 32 A Comparison of AON and AOA Network Conventions