SlideShare une entreprise Scribd logo
1  sur  8
Télécharger pour lire hors ligne
Information and knowledge management                                                          www.iiste.org
ISSN 2224-5758 (Paper) ISSN 2224-896X (Online)
Vol.1, No.4, 2011




   Review of Kanban planning and execution in the context of
                    Lean manufacturing
                                    Prakash Divakaran (Corresponding Author)
                 Polyrub Extrusions (India) Pvt.Ltd, Pune, India, E- mail – Prakashtek@gmail.com


                                                Dr.C.T.Sunil Kumar
                                       Food Corporation of India, Trivandrum
                                    Kerala, India,E-mail – hamsingh@ymail.com




Abstract
In this paper the various principles of Kanban planning and execution is illustrated with respect to cellular
manufacturing, total quality management, total preventive maintenance and Engineering change
management concepts as applied to Lean Manufacturing. A detailed investigation of Kaizen costing and
cost analysis is also presented in this paper

1.Kanban Planning and Execution
1.1 Introduction
Kanban is a method for maintaining an orderly flow of material. Kanban cards are used to indicate points at
which material should be ordered, how much material is needed, from where the material should be ordered,
and to where it should be delivered. With IFS’ Kanban solution, you can perform an advanced Kanban
calculation using an actual demand profile to determine whether an inventory stock out is likely to occur
with the current system settings. The system can calculate Kanban quantity or the number of Kanbans
based on past usage of parts. You can recalculate and redeploy your Kanban circuits within a day when
demand shifts IFS’ Kanban solution lets you perform stock out simulations by retrieving demand from a
variety of sources and for different time spans to determine whether you Kanban quantities are balanced
You can use either visual or electronic signals for replenishment. Kanban replenishment can be from
supplier, a sister plant, an inventory location, a location group or a production line. Options for demand
type, Kanban formula, safety factor, signal type, and replenishment type let you adjust the use of Kanbans
to best match your environment.
IFS’ Kanban solution helps you maintain your Kanban cards. You can easily keep track of the number of cards
used in the system, add or subtract cards during seasonal changes in demand, or print or replace cards



1.2. Vendor-Managed Inventory
Instead of sending Kanban signals to your suppliers, you can give them responsibility for and authorization
to replenish goods. IFS’ vendor-managed inventory capabilities and web-based portal technology make it is
easier to collaborate with your suppliers. Instead of sending information back and forth, customers and
suppliers can access inventory balances and future demands through a convenient portal, and the supplier
can replenish stocks as required. The supplier can also use the portal to enter or search for information and
update documents. The supplier becomes another application user, but with limited access.


                                                     11
Information and knowledge management                                                         www.iiste.org
ISSN 2224-5758 (Paper) ISSN 2224-896X (Online)
Vol.1, No.4, 2011




1.3 Repetitive Production
With IFS’ production scheduling functionality, you can perform order less, rate-based production. This
reduces the number of report points, and simplifies and automates the production process. Final reporting
of finished items is the only production reporting required, and all components are automatically issued
(back flushed). You get reduced transactions throughout the flow, short cycle times, and less work-in
process inventory. As a result, you can focus on ensuring enough material.



2.Cellular Manufacturing
Arranging operations and/or people in a U-shaped production line allows for better utilization of people and
improves communication. Product flows smoothly from one operation to the next rather than running in a
batch and then sitting in a queue at the next work center waiting for that operation to begin. IFS
Applications™ lets you define an unlimited number of production lines, each with its own dedicated
inventory storage area. Incoming materials are routed directly to the production line at which they will be
consumed. Finished goods completed at the production line can be stored there until being shipped to the
customer.



3.Waste Reduction

Waste is commonly defined as non-value-added activity. Lean practitioners identify seven types of waste:


    • Excess (or early) production—producing more than the customer demands, or producing it earlier than
    the customer needs it. This ties up valuable labor and material resources that might otherwise be used to
    respond to customer demand.

    • Delays—waiting for materials, tools, information, equipment, etc. This may be a result of poor planning,
    late supplier deliveries, lack of communication, overbooking of equipment, or erratic demand.

    • Transportation (to/from processes)—Moving material more often than necessary. Material should be
    delivered and stored at its point of use. Why receivematerial at a receiving dock, move it to an inventory
    location, and then move it to the production floor when it can be delivered and stored where it is used?

    • Inventory—storing more material than is needed. This wastes valuable space and cash. By reducing
    inventory, plans for warehouse expansion can usually be postponed or canceled.

    • Processing—Doing more work on a part than is necessary, including inspection and reworking. This
    wastes time and money. Quality must be built into the manufacturing process so that parts are produced
    correctly the first time.

    • Defects—Defective parts. Defects consume considerable resources. In addition to the original materials
    and labor used to manufacture the part, extra labor and machine time are required to fix the defective part.
    If the defective part is sold to a customer, not only will unnecessary shipping costs be lost, but more
    resources will be consumed to resolve the eventual complaints.



                                                    12
Information and knowledge management                                                           www.iiste.org
ISSN 2224-5758 (Paper) ISSN 2224-896X (Online)
Vol.1, No.4, 2011


   • Movement—Excess motion of employees in getting tools, picking parts, or moving from one point to
   another. This is usually the result of poorly planned work layout and workflow. A variety of techniques are
   available for reducing or eliminating waste. These techniques include value stream analysis, total quality
   management, total productive maintenance, Kaizen costing and cost analysis, engineering and change
   management, and document management.

   4. Total Quality Management


   Total quality management (TQM) is a management system used to continuously improve all areas of a
   company's operation. Quality functionality is integrated throughout IFS Applications. Failure modes and
   effects analysis (FMEA) is a systematic technique for managing risk in a manufacturing process. It involves
   recording and analyzing actual and potential problems with a product design or process, along with related
   solutions. This information allows you to improve accountability, avoid repeated mistakes, and improve the
   quality of the end product. Control plans can be defined to detail the measurements and tests performed at
   any operation of a shop order, production schedule, or purchase receipt. This helps to identify defects
   before any further value is added to them. Statistical process control (SPC) is a philosophy that emphasizes
   the use of statistical techniques, such as control charts, in all areas of a company to make continuous
   improvements in quality and productivity by reducing variation in processes. With IFS Quality
   Management™, you can create, view, and analyze X bar and R, X-bar and S, X and MR, np, p, c, and u
   control charts. IFS Applications also includes material review board (MRB) functionality for handling the
   disposition of defective material.



   5.Total Productive Maintenance

   Total productive maintenance capitalizes on proactive and progressive maintenance methodologies and
   calls on the knowledge and cooperation of operators, equipment vendors, engineering, and support
   personnel to optimize machine performance. IFS Maintenance™ is a world-class maintenance package that
   is completely integrated with IFS’ supply chain management solution. Both maintenance and production
   workers have complete visibility into maintenance and production information and schedules. Operators
   can regularly perform preventive maintenance on equipment and tools, with maintenance personnel
   handling more detailed overhauls and repairs. The result is optimal equipment performance, including the
   elimination of breakdowns, a reduction in unscheduled and scheduled downtime, improved utilization,
   higher throughput, and better product quality. Bottom-line results include lower operating costs, longer
   equipment life, and lower overall maintenance costs.

   6. Kaizen Costing and Cost Analysis


   Unlike standard costing systems, a Kaizen costing system focuses on continuous cost reduction rather than
   simply meeting the standard and avoiding unfavorable variances. As part of the Kaizen process, you verify
   that the costing target has been reached and then continuously review existing production conditions to
   further reduce costs. In IFS Applications, you can set a cost target, calculate cost gaps, and plan activities to
   reduce costs. Major cost reductions can be broken into smaller reductions for which separate activities can
   be created that are easier to handle. Each activity is possible to evaluate from a cost reduction potential and
   from an investment need.

   IFS Applications also allows you to perform commonality analyses. If an item is used in multiple places,
   commonality analysis helps you see which components are common for different structures and whether

                                                     13
Information and knowledge management                                                        www.iiste.org
ISSN 2224-5758 (Paper) ISSN 2224-896X (Online)
Vol.1, No.4, 2011


   they can be used for other parts to save money. Cost/value analysis helps you analyze the costs of a
   component or product in relation to customer value.

   7. Engineering and Change Management


   IFS Applications manages the changes a design goes through during its lifetime in two stages: During the
   Engineering Change Requests stage, all change proposals from the organization are registered. These
   change proposals might include fault reports from the service department, the design departments own
   improvements, or a recommendation from the purchasing department to change supplier material.

   The proposals are analyzed and formally approved. Then, in the Engineering Change Order stage, the
   design change is planned and implemented. The product structure helps to define items and minimize the
   work involved in making modifications. When the work is finished, a new part revision is created.



   8. Document Management


   For most businesses, managing documentation is not an end in itself. It’s an essential part of day-to-day
   operations—a way of ensuring that the right people get the right information at the right time.
   Mismanaging the flow of information can result in confusion, unnecessary delays, and costly errors. With
   IFS Document Management™, you get full control over your company's documentation so you can focus
   on the things that really matter: selling your products and services, keeping your plant and equipment in top
   shape, and meeting or exceeding your business goals.

   A framework was created to analyze manufacturing systems and assess the impact of various practices on
   system performance. A literature review of Lean Manufacturing resulted in the discovery of significant
   gaps in two areas: (1) modeling the effects of implementing Lean Manufacturing using control theory
   principles, and (2) a design framework for building Cellular Manufacturing Systems and making the
   transition from traditional manufacturing to Lean Manufacturing. Work in these areas led to the conclusion
   that reducing the Order Lead Time until it is less than Tall, the allowable customer lead time for
   post-payment production, would yield tremendous benefits both for individual factories as well as for entire
   Linear Distribution Systems. To fill these gaps, a model was created which analyzed the dynamics of
   Linear Distribution Systems, and showed how Lean Manufacturing represents an opportunity to sidestep
   many previously insurmountable difficulties that arise as a result of producing to fill inventory levels. The
   methods for implementation of Lean Principles were explored, from prerequisites for Cellular
   Manufacturing Systems, to design and optimization of Cells, through exploration of the improvements in
   quality that are possible in Cellular Manufacturing Systems. A thorough a dissemination of the various
   contributions to Order Lead Time showed that changeover reduction, information flow, zero defects and
   cellular manufacturing are all indispensable in achieving the goal of OLT < Tall. Finally, conclusions were
   presented which show that achieving this reduction allows for production under an entirely new philosophy
   that completely eliminates capital investment in inventory.

   The difficulties that companies face in today’s marketplace are fierce: shifting customer demand, increasing
   variation in products and demands for perfect quality. Meeting these demands while dealing with complex
   distribution systems and multi-tiered chains of suppliers is better understood in light of system dynamics
   (Forrester [1969]) and finding ways to minimize their cyclical nature. The way to escape the pitfalls faced
   by aerospace companies today requires a redefinition of inventory and a new production philosophy which
   eliminates the need to produce based on forecasts, or to fill stock levels, and to eliminate rework and

                                                   14
Information and knowledge management                                                           www.iiste.org
ISSN 2224-5758 (Paper) ISSN 2224-896X (Online)
Vol.1, No.4, 2011


   acceptance of non-conformances Lean Manufacturing is a term popularized by Womack, Jones and Roos
   [1991] to describe a method for production based on the Toyota Production System (TPS) (Shingo 1989,
   Ohno 1988). There is a tremendous body of literature available on the details of the TPS. The purpose of
   this thesis is to take the principles enumerated in the literature one step further and show how lean
   manufacturing can address the difficulties of aircraft manufacturing as a linear distribution system (LDS).


   9.Cellular Manufacturing (CM)- Processing of parts or part families in a single cell, with no backtracking.
   Each part follows a predetermined part path, and is said to be trackable. Individual cells may be built
   around Group Technology formed part families or based on a single product line (which facilitates ABC
   methods). In CM the operators move independently of the part processing time. A cell processes a subset of
   the total operations in the production system. Cells process parts sequentially through a series of machines
   or manual stations, whereas a job shop processes parts in parallel processing through duplicated machines.
   A cellular manufacturing production system is network of logically linked cells (Cochran [1994]). Hence
   throughput of cells can be dependent on (a) a single machine’s cycle time (the bottleneck), or (b) the speed
   of the material handler or operator.


   •   Changeover Time- The length of time a machine or processing area is down (not producing parts) in
       order to change over from one part type to another. It begins when the machine finishes producing the
       last part of type A and ends at the beginning of the production of the first good unit of type B.


   •   Cost of Order Preparation- The costs incurred by a factory in the process of receiving an order,
       releasing it to the floor and closing the order upon receipt by the customer.



   •   Customer Lead Time- The length of time beginning when a customer places an order and ending
       when the customer receives goods to fill that order. It encompasses the Production Lead Time plus the
       time required to transmit the order to the factory and the time to ship the product to the customer.

   •   Defects vs. Errors- a defect is a product or service’s non-fulfillment of an intended requirement or
       reasonable expectation for use. An error is the result of improper processing of the part, which leads to
       a defect only when the part is inspected and fails. Thus, errors can be fixed before they become defects.



   •   External Setup Operations- Operations in changeover from one part type to the next which are done
       while the machine is still producing parts.
   •   Final vs. Absolute Defect Rate- the final defect rate reflects only the number of parts that fail the final
       inspection. However, the absolute defect rate is a measure of the number of defects for the entire
       process from start to finish (see Shingo [1986])


   10. Flexible Manufacturing System (FMS)- A group of numerically controlled machine tools
   interconnected by a central control system. The various machining cells are interconnected via loading and
   unloading stations by an automated transport system. Parts are generally processed in parallel rather than
   serially as in a Cellular Manufacturing System. Operational flexibility is enhanced by the ability to execute
   all manufacturing tasks on numerous product designs in small quantities. However, there are often
   limitations in flexibility due to the hard tooling that is required for material transport and fixturing in each
   machining cell. Capital investment is very high as compared to a manned cell.

                                                    15
Information and knowledge management                                                          www.iiste.org
ISSN 2224-5758 (Paper) ISSN 2224-896X (Online)
Vol.1, No.4, 2011



   11. Group Technology (GT)- A part classification technique used to categorize parts according to one of
   two possible similarities: (1) part geometry, or (2) processing similarities. GT is generally used to create
   part families which can then be processed in single cell.

   12. Informative vs. Subjective Inspections- An informative inspection yields information about a part,
   such as a dimensional characteristic. As a subjective inspection is a pass-failure inspection, the inspector
   must make a subjective judgment about the quality of a part.

   13. Internal Setup Operations- Operations in changeover from one part type to the next which are done
   when the machine is stopped (is not producing parts).

   14.     Job- Work order;   an order from a customer which comprises a fixed number of parts of a specified

   type.

   15. Lot Delay- In batch production, the time spent while the part is waiting for other parts in the batch to be
   processed.

   16. Lot (or Batch) Production- Producing parts in lots or batches which are greater than one part.


   17. Machine Utilization- The ratio of time during which the machine is operating to the total time
   available. The operating time should only include time in which product is being produced (setup time is
   excluded).

   18. Machine Cycle Time- The length of time required for a machine to process one part, not including
   loading and unloading time. It can be measured as the length of time beginning when the start button is
   pressed and ending when the part can be removed.

   19. Manufacturing Lead Time- The length of time from the first operation for a given order until the
   entire order has been transported to the shipping area.

   20. Order (or Production) Lead Time- The length of time beginning with receipt of an order from a
   customer and ending when product for that order has been manufactured and transported to the shipping
   area. It includes the Manufacturing Lead Time plus the time required to process the order and begin
   production.

   21Process vs. Operation- The distinction between a process and an operation is not one of time scale; the
   two have different subjects of study. A process is a flow of product from raw materials to finished parts.
   Operations are the actions of man, or machine, and what they do to the product.

   22. Process Mapping- A systematic analysis of a production system using Time Division Analysis to
   determine which operations are integral to a process, and which must be eliminated.

   32. Processing Delay- The time spent while a part is in storage, either in queue behind other batches of
   parts, or waiting due to machine downtime.

   33. Production Balancing- Efforts to make the processing time for a given part at each station in a process
   equal. In a perfectly balanced process, no stations will be idle when producing parts using single piece flow.


                                                    16
Information and knowledge management                                                         www.iiste.org
ISSN 2224-5758 (Paper) ISSN 2224-896X (Online)
Vol.1, No.4, 2011




   34. Production Leveling- Efforts to increase the product mix and decrease the batch size in a
   manufacturing system. In Level Production, assuming there is no variation in processing, at least one unit
   of each part type is produced each day.

   35. Production Synchronization- Efforts to synchronize the start, stop and transport of product at each
   machine, station and process. In Synchronous Production, the upstream process produces goods at the same
   rate (or Takt time) as the downstream process.

   36. Self (or Source) Inspection- Inspection carried out by the person (or factory) which produced the

   product.


   37. Single Piece Flow- A term describing the processing of parts in a batch size of one. The only
   processing lot size in which the lot delay is reduced to zero.

   38. Statistical Quality Control (SQC)- The application of statistical techniques to control quality.
   Generally refers to monitoring or inspecting some percentage (less than 100%) and inferring the quality of
   the rest of the parts from a sample. SQC is subject to and  errors.

   39. Successive (or Post-receipt )Inspection- Inspection by a person or factory of goods that were
   produced at an upstream station or plant. Traditionally thought to be more objective than self inspections,
   since there is no incentive to pass defective parts through the inspection. However, this inspection method
   can only discover defects after they have been made (see defects vs. errors).

   40.System- A regularly interacting or interdependent group of items forming a unified whole toward the
   achievement of a goal.

   41.Takt Time- A production rate determined by customer orders (or sales) which specifies the interval of
   time between production of successive parts. Is determined from the following equation: total time
   available for production per shift (in sec) Takt Time = required number of parts per shift

   42.Time Division Analysis- A technique similar to process mapping where a process is analyzed by
   tracking a part as it flows from raw materials to the finish crib and constantly specifying whether a part is
   being processed, transported, stored or inspected. Storage is further broken down into Lot delay,
   Transportation delay, and Processing delay.

   43. Transportation Delay- The time spent waiting for the means of transportation (i.e. waiting for a

   forklift)

   .
   44. Value Added vs. Non Value Added Processing- Value added processing refers to processing steps that
   will add value to a part, viewed from the eyes of the customer. Non value added processing includes all
   processing that does not add value. Thus a cutting operation on a machine is value added processing only if
   it creates a feature in the part that is of value to the customer.

   45. Volume vs. Part Types Flexibility- Volume flexibility refers to the ability of a manufacturing system to
   produce parts at different rates. Part type flexibility refers to the ability to produce a number of different

                                                    17
Information and knowledge management                                                www.iiste.org
ISSN 2224-5758 (Paper) ISSN 2224-896X (Online)
Vol.1, No.4, 2011


    part types in a given period of time.
.


References


1. Cell, Charles; VE, Lean, and Six Sigma – Opportunities Leverage, 2004 SAVE International
Conference Proceedings, Canada (2004)
2. Cook, Dr. Michael; An Untapped Market – Energizing VM Usage via the Six Sigma Methodology,
2000 SAVE International Conference Proceedings, USA (2000).
3. Dean, Edwin B.; Value Engineering from the Perspective of Competitive Advantage, USA (2000).
4. Downer, John G.; From Product to Project – Forming Value into a New Shape, 2005 SAVE
International Conference Proceedings, USA (2005).
5. Fong, Patrick Sik-Wah; Charting the Future Directions of Value Engineering, 1999 SAVE
International Conference Proceedings, USA (1999).
6. George, Michael; Lean Six Sigma : Combining Six Sigma Quality with Lean Speed; McGraw Hill;
USA (2002)
7. Hino, Satoshi; Inside the Mind of Toyota : Management Principles for Enduring Growth (English
Translation); Productivity Press, Inc., USA (2006).
8. Johnson, Gordon; Conflicting or Complementing ? A Comprehensive Comparison of Six Sigma and
Value Methodology, 2003 SAVE International Conference Proceedings, USA (2003)
9. Kirk, Bozdogan; A Comparative Review of Lean Thinking, Six Sigma and Related Enterprise
Change Models, Massachusetts Institute of Technology, Lean Aerospace Institute, USA (2003).
10. Lehman, Theresa &Reiser, Paul; Maximizing Value & Minimizing Waste – Value Engineering &
Lean Construction, 2004 SAVE International Conference Proceedings, USA (2004)
11. Liker, Dr. Jeffrey; The Toyota Way, 14 Management Principles from the World’s Greatest
Manufacturer; McGraw Hill, USA (2004)
12. Maurer, John H.; What is Value Analysis / Value Engineering (VA/VE) ? , USA (1999).




                                               18

Contenu connexe

Tendances

Increase CAT Spare Parts Inventory turn (ITR) V2.0
Increase CAT Spare Parts Inventory turn (ITR) V2.0Increase CAT Spare Parts Inventory turn (ITR) V2.0
Increase CAT Spare Parts Inventory turn (ITR) V2.0
Krishnendu Chakraborty
 
Systems development project riordan manufacturing final draft
Systems development project riordan manufacturing final draftSystems development project riordan manufacturing final draft
Systems development project riordan manufacturing final draft
Valora Hawkins
 
Riordan Manufacturing
Riordan ManufacturingRiordan Manufacturing
Riordan Manufacturing
May Avery
 

Tendances (20)

Production Management
Production ManagementProduction Management
Production Management
 
A Review on Implementation of Lean Manufacturing Techniques in Manufacturing ...
A Review on Implementation of Lean Manufacturing Techniques in Manufacturing ...A Review on Implementation of Lean Manufacturing Techniques in Manufacturing ...
A Review on Implementation of Lean Manufacturing Techniques in Manufacturing ...
 
LEAN_WAREHOUSE_Eng
LEAN_WAREHOUSE_EngLEAN_WAREHOUSE_Eng
LEAN_WAREHOUSE_Eng
 
Jit & Lean Operations
Jit & Lean OperationsJit & Lean Operations
Jit & Lean Operations
 
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraIntroduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
 
Iterature Review Cellular Manufacturing And Group Technology
Iterature Review Cellular Manufacturing And Group TechnologyIterature Review Cellular Manufacturing And Group Technology
Iterature Review Cellular Manufacturing And Group Technology
 
Manufacturing Design Change
Manufacturing Design ChangeManufacturing Design Change
Manufacturing Design Change
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
Increase CAT Spare Parts Inventory turn (ITR) V2.0
Increase CAT Spare Parts Inventory turn (ITR) V2.0Increase CAT Spare Parts Inventory turn (ITR) V2.0
Increase CAT Spare Parts Inventory turn (ITR) V2.0
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
 
Chap006
Chap006Chap006
Chap006
 
Systems development project riordan manufacturing final draft
Systems development project riordan manufacturing final draftSystems development project riordan manufacturing final draft
Systems development project riordan manufacturing final draft
 
Nota rojak 2
Nota rojak 2Nota rojak 2
Nota rojak 2
 
LINE CALL REDUCTION USING PROCESS IMPROVEMENT IN AN AUTOMOBILE COMPANY: A SIM...
LINE CALL REDUCTION USING PROCESS IMPROVEMENT IN AN AUTOMOBILE COMPANY: A SIM...LINE CALL REDUCTION USING PROCESS IMPROVEMENT IN AN AUTOMOBILE COMPANY: A SIM...
LINE CALL REDUCTION USING PROCESS IMPROVEMENT IN AN AUTOMOBILE COMPANY: A SIM...
 
A Quick Guide to Production Planning Function
A Quick Guide to Production Planning FunctionA Quick Guide to Production Planning Function
A Quick Guide to Production Planning Function
 
Investigation on Cycle Time Reduction in Production and Implementation of an ...
Investigation on Cycle Time Reduction in Production and Implementation of an ...Investigation on Cycle Time Reduction in Production and Implementation of an ...
Investigation on Cycle Time Reduction in Production and Implementation of an ...
 
Riordan Manufacturing
Riordan ManufacturingRiordan Manufacturing
Riordan Manufacturing
 
Process selection
Process selectionProcess selection
Process selection
 
How to achieve traceability in manufacturing?
How to achieve traceability in manufacturing?How to achieve traceability in manufacturing?
How to achieve traceability in manufacturing?
 
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
 

Similaire à Review of kanban planning and execution in the context of lean manufacturing

Holistic quality management
Holistic quality managementHolistic quality management
Holistic quality management
selinasimpson321
 
Facility Capacity Planning & its Measurement[1].pptx
Facility Capacity Planning & its Measurement[1].pptxFacility Capacity Planning & its Measurement[1].pptx
Facility Capacity Planning & its Measurement[1].pptx
MeetLalcheta
 
Facility Capacity Planning & its Measurement[1] - Copy.pptx
Facility Capacity Planning & its Measurement[1] - Copy.pptxFacility Capacity Planning & its Measurement[1] - Copy.pptx
Facility Capacity Planning & its Measurement[1] - Copy.pptx
MeetLalcheta
 
Paper id 24201491
Paper id 24201491Paper id 24201491
Paper id 24201491
IJRAT
 
Synopsis on inventory_management_system
Synopsis on inventory_management_systemSynopsis on inventory_management_system
Synopsis on inventory_management_system
Divya Baghel
 

Similaire à Review of kanban planning and execution in the context of lean manufacturing (20)

Bill Generator and Inventory Maintenance
Bill Generator and Inventory MaintenanceBill Generator and Inventory Maintenance
Bill Generator and Inventory Maintenance
 
05 lean manufacturing and the jit philosophy
05 lean manufacturing and the jit philosophy05 lean manufacturing and the jit philosophy
05 lean manufacturing and the jit philosophy
 
10 Critical Steps Small and Medium Manufacturers should undertake Today
10 Critical Steps Small and Medium Manufacturers should undertake Today10 Critical Steps Small and Medium Manufacturers should undertake Today
10 Critical Steps Small and Medium Manufacturers should undertake Today
 
Holistic quality management
Holistic quality managementHolistic quality management
Holistic quality management
 
IRJET- Research Paper on Inventory Management System
IRJET-  	  Research Paper on Inventory Management SystemIRJET-  	  Research Paper on Inventory Management System
IRJET- Research Paper on Inventory Management System
 
Facility Capacity Planning & its Measurement[1].pptx
Facility Capacity Planning & its Measurement[1].pptxFacility Capacity Planning & its Measurement[1].pptx
Facility Capacity Planning & its Measurement[1].pptx
 
Facility Capacity Planning & its Measurement[1] - Copy.pptx
Facility Capacity Planning & its Measurement[1] - Copy.pptxFacility Capacity Planning & its Measurement[1] - Copy.pptx
Facility Capacity Planning & its Measurement[1] - Copy.pptx
 
Lean System
Lean SystemLean System
Lean System
 
Optimize your inventory. Guide for Factory Managers.
Optimize your inventory. Guide for Factory Managers.Optimize your inventory. Guide for Factory Managers.
Optimize your inventory. Guide for Factory Managers.
 
Production System optimization: Case Study of a Local Textile Company
Production System optimization: Case Study of a Local Textile CompanyProduction System optimization: Case Study of a Local Textile Company
Production System optimization: Case Study of a Local Textile Company
 
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case StudyProductivity Improvement by Optimum Utilization of Plant Layout: A Case Study
Productivity Improvement by Optimum Utilization of Plant Layout: A Case Study
 
ERP implementation at steel mill
ERP implementation at steel millERP implementation at steel mill
ERP implementation at steel mill
 
Management Presentation on Managing Operations.
Management Presentation on Managing Operations.Management Presentation on Managing Operations.
Management Presentation on Managing Operations.
 
Paper id 24201491
Paper id 24201491Paper id 24201491
Paper id 24201491
 
Prodt& Opt Mgmt Ppt
Prodt& Opt Mgmt PptProdt& Opt Mgmt Ppt
Prodt& Opt Mgmt Ppt
 
Kingsleys Power Point Presentation on Operations Management.pptx
Kingsleys Power Point Presentation on Operations Management.pptxKingsleys Power Point Presentation on Operations Management.pptx
Kingsleys Power Point Presentation on Operations Management.pptx
 
Synopsis on inventory_management_system
Synopsis on inventory_management_systemSynopsis on inventory_management_system
Synopsis on inventory_management_system
 
Production and operation management ppt @ bec doms bagalkot
Production and operation management ppt @ bec doms bagalkot Production and operation management ppt @ bec doms bagalkot
Production and operation management ppt @ bec doms bagalkot
 
Material Management
Material ManagementMaterial Management
Material Management
 
Inventory & Inventory Management ( By BU AIS 2nd Batch)
Inventory & Inventory Management ( By BU AIS 2nd Batch)Inventory & Inventory Management ( By BU AIS 2nd Batch)
Inventory & Inventory Management ( By BU AIS 2nd Batch)
 

Plus de Alexander Decker

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...
Alexander Decker
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websites
Alexander Decker
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banks
Alexander Decker
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized d
Alexander Decker
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistance
Alexander Decker
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifham
Alexander Decker
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibia
Alexander Decker
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school children
Alexander Decker
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banks
Alexander Decker
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget for
Alexander Decker
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjab
Alexander Decker
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...
Alexander Decker
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incremental
Alexander Decker
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniques
Alexander Decker
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo db
Alexander Decker
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloud
Alexander Decker
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveraged
Alexander Decker
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenya
Alexander Decker
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health of
Alexander Decker
 

Plus de Alexander Decker (20)

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale in
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websites
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banks
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized d
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistance
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifham
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibia
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school children
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banks
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget for
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjab
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incremental
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniques
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo db
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloud
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveraged
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenya
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health of
 

Dernier

IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
Enterprise Knowledge
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
vu2urc
 

Dernier (20)

Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Slack Application Development 101 Slides
Slack Application Development 101 SlidesSlack Application Development 101 Slides
Slack Application Development 101 Slides
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 

Review of kanban planning and execution in the context of lean manufacturing

  • 1. Information and knowledge management www.iiste.org ISSN 2224-5758 (Paper) ISSN 2224-896X (Online) Vol.1, No.4, 2011 Review of Kanban planning and execution in the context of Lean manufacturing Prakash Divakaran (Corresponding Author) Polyrub Extrusions (India) Pvt.Ltd, Pune, India, E- mail – Prakashtek@gmail.com Dr.C.T.Sunil Kumar Food Corporation of India, Trivandrum Kerala, India,E-mail – hamsingh@ymail.com Abstract In this paper the various principles of Kanban planning and execution is illustrated with respect to cellular manufacturing, total quality management, total preventive maintenance and Engineering change management concepts as applied to Lean Manufacturing. A detailed investigation of Kaizen costing and cost analysis is also presented in this paper 1.Kanban Planning and Execution 1.1 Introduction Kanban is a method for maintaining an orderly flow of material. Kanban cards are used to indicate points at which material should be ordered, how much material is needed, from where the material should be ordered, and to where it should be delivered. With IFS’ Kanban solution, you can perform an advanced Kanban calculation using an actual demand profile to determine whether an inventory stock out is likely to occur with the current system settings. The system can calculate Kanban quantity or the number of Kanbans based on past usage of parts. You can recalculate and redeploy your Kanban circuits within a day when demand shifts IFS’ Kanban solution lets you perform stock out simulations by retrieving demand from a variety of sources and for different time spans to determine whether you Kanban quantities are balanced You can use either visual or electronic signals for replenishment. Kanban replenishment can be from supplier, a sister plant, an inventory location, a location group or a production line. Options for demand type, Kanban formula, safety factor, signal type, and replenishment type let you adjust the use of Kanbans to best match your environment. IFS’ Kanban solution helps you maintain your Kanban cards. You can easily keep track of the number of cards used in the system, add or subtract cards during seasonal changes in demand, or print or replace cards 1.2. Vendor-Managed Inventory Instead of sending Kanban signals to your suppliers, you can give them responsibility for and authorization to replenish goods. IFS’ vendor-managed inventory capabilities and web-based portal technology make it is easier to collaborate with your suppliers. Instead of sending information back and forth, customers and suppliers can access inventory balances and future demands through a convenient portal, and the supplier can replenish stocks as required. The supplier can also use the portal to enter or search for information and update documents. The supplier becomes another application user, but with limited access. 11
  • 2. Information and knowledge management www.iiste.org ISSN 2224-5758 (Paper) ISSN 2224-896X (Online) Vol.1, No.4, 2011 1.3 Repetitive Production With IFS’ production scheduling functionality, you can perform order less, rate-based production. This reduces the number of report points, and simplifies and automates the production process. Final reporting of finished items is the only production reporting required, and all components are automatically issued (back flushed). You get reduced transactions throughout the flow, short cycle times, and less work-in process inventory. As a result, you can focus on ensuring enough material. 2.Cellular Manufacturing Arranging operations and/or people in a U-shaped production line allows for better utilization of people and improves communication. Product flows smoothly from one operation to the next rather than running in a batch and then sitting in a queue at the next work center waiting for that operation to begin. IFS Applications™ lets you define an unlimited number of production lines, each with its own dedicated inventory storage area. Incoming materials are routed directly to the production line at which they will be consumed. Finished goods completed at the production line can be stored there until being shipped to the customer. 3.Waste Reduction Waste is commonly defined as non-value-added activity. Lean practitioners identify seven types of waste: • Excess (or early) production—producing more than the customer demands, or producing it earlier than the customer needs it. This ties up valuable labor and material resources that might otherwise be used to respond to customer demand. • Delays—waiting for materials, tools, information, equipment, etc. This may be a result of poor planning, late supplier deliveries, lack of communication, overbooking of equipment, or erratic demand. • Transportation (to/from processes)—Moving material more often than necessary. Material should be delivered and stored at its point of use. Why receivematerial at a receiving dock, move it to an inventory location, and then move it to the production floor when it can be delivered and stored where it is used? • Inventory—storing more material than is needed. This wastes valuable space and cash. By reducing inventory, plans for warehouse expansion can usually be postponed or canceled. • Processing—Doing more work on a part than is necessary, including inspection and reworking. This wastes time and money. Quality must be built into the manufacturing process so that parts are produced correctly the first time. • Defects—Defective parts. Defects consume considerable resources. In addition to the original materials and labor used to manufacture the part, extra labor and machine time are required to fix the defective part. If the defective part is sold to a customer, not only will unnecessary shipping costs be lost, but more resources will be consumed to resolve the eventual complaints. 12
  • 3. Information and knowledge management www.iiste.org ISSN 2224-5758 (Paper) ISSN 2224-896X (Online) Vol.1, No.4, 2011 • Movement—Excess motion of employees in getting tools, picking parts, or moving from one point to another. This is usually the result of poorly planned work layout and workflow. A variety of techniques are available for reducing or eliminating waste. These techniques include value stream analysis, total quality management, total productive maintenance, Kaizen costing and cost analysis, engineering and change management, and document management. 4. Total Quality Management Total quality management (TQM) is a management system used to continuously improve all areas of a company's operation. Quality functionality is integrated throughout IFS Applications. Failure modes and effects analysis (FMEA) is a systematic technique for managing risk in a manufacturing process. It involves recording and analyzing actual and potential problems with a product design or process, along with related solutions. This information allows you to improve accountability, avoid repeated mistakes, and improve the quality of the end product. Control plans can be defined to detail the measurements and tests performed at any operation of a shop order, production schedule, or purchase receipt. This helps to identify defects before any further value is added to them. Statistical process control (SPC) is a philosophy that emphasizes the use of statistical techniques, such as control charts, in all areas of a company to make continuous improvements in quality and productivity by reducing variation in processes. With IFS Quality Management™, you can create, view, and analyze X bar and R, X-bar and S, X and MR, np, p, c, and u control charts. IFS Applications also includes material review board (MRB) functionality for handling the disposition of defective material. 5.Total Productive Maintenance Total productive maintenance capitalizes on proactive and progressive maintenance methodologies and calls on the knowledge and cooperation of operators, equipment vendors, engineering, and support personnel to optimize machine performance. IFS Maintenance™ is a world-class maintenance package that is completely integrated with IFS’ supply chain management solution. Both maintenance and production workers have complete visibility into maintenance and production information and schedules. Operators can regularly perform preventive maintenance on equipment and tools, with maintenance personnel handling more detailed overhauls and repairs. The result is optimal equipment performance, including the elimination of breakdowns, a reduction in unscheduled and scheduled downtime, improved utilization, higher throughput, and better product quality. Bottom-line results include lower operating costs, longer equipment life, and lower overall maintenance costs. 6. Kaizen Costing and Cost Analysis Unlike standard costing systems, a Kaizen costing system focuses on continuous cost reduction rather than simply meeting the standard and avoiding unfavorable variances. As part of the Kaizen process, you verify that the costing target has been reached and then continuously review existing production conditions to further reduce costs. In IFS Applications, you can set a cost target, calculate cost gaps, and plan activities to reduce costs. Major cost reductions can be broken into smaller reductions for which separate activities can be created that are easier to handle. Each activity is possible to evaluate from a cost reduction potential and from an investment need. IFS Applications also allows you to perform commonality analyses. If an item is used in multiple places, commonality analysis helps you see which components are common for different structures and whether 13
  • 4. Information and knowledge management www.iiste.org ISSN 2224-5758 (Paper) ISSN 2224-896X (Online) Vol.1, No.4, 2011 they can be used for other parts to save money. Cost/value analysis helps you analyze the costs of a component or product in relation to customer value. 7. Engineering and Change Management IFS Applications manages the changes a design goes through during its lifetime in two stages: During the Engineering Change Requests stage, all change proposals from the organization are registered. These change proposals might include fault reports from the service department, the design departments own improvements, or a recommendation from the purchasing department to change supplier material. The proposals are analyzed and formally approved. Then, in the Engineering Change Order stage, the design change is planned and implemented. The product structure helps to define items and minimize the work involved in making modifications. When the work is finished, a new part revision is created. 8. Document Management For most businesses, managing documentation is not an end in itself. It’s an essential part of day-to-day operations—a way of ensuring that the right people get the right information at the right time. Mismanaging the flow of information can result in confusion, unnecessary delays, and costly errors. With IFS Document Management™, you get full control over your company's documentation so you can focus on the things that really matter: selling your products and services, keeping your plant and equipment in top shape, and meeting or exceeding your business goals. A framework was created to analyze manufacturing systems and assess the impact of various practices on system performance. A literature review of Lean Manufacturing resulted in the discovery of significant gaps in two areas: (1) modeling the effects of implementing Lean Manufacturing using control theory principles, and (2) a design framework for building Cellular Manufacturing Systems and making the transition from traditional manufacturing to Lean Manufacturing. Work in these areas led to the conclusion that reducing the Order Lead Time until it is less than Tall, the allowable customer lead time for post-payment production, would yield tremendous benefits both for individual factories as well as for entire Linear Distribution Systems. To fill these gaps, a model was created which analyzed the dynamics of Linear Distribution Systems, and showed how Lean Manufacturing represents an opportunity to sidestep many previously insurmountable difficulties that arise as a result of producing to fill inventory levels. The methods for implementation of Lean Principles were explored, from prerequisites for Cellular Manufacturing Systems, to design and optimization of Cells, through exploration of the improvements in quality that are possible in Cellular Manufacturing Systems. A thorough a dissemination of the various contributions to Order Lead Time showed that changeover reduction, information flow, zero defects and cellular manufacturing are all indispensable in achieving the goal of OLT < Tall. Finally, conclusions were presented which show that achieving this reduction allows for production under an entirely new philosophy that completely eliminates capital investment in inventory. The difficulties that companies face in today’s marketplace are fierce: shifting customer demand, increasing variation in products and demands for perfect quality. Meeting these demands while dealing with complex distribution systems and multi-tiered chains of suppliers is better understood in light of system dynamics (Forrester [1969]) and finding ways to minimize their cyclical nature. The way to escape the pitfalls faced by aerospace companies today requires a redefinition of inventory and a new production philosophy which eliminates the need to produce based on forecasts, or to fill stock levels, and to eliminate rework and 14
  • 5. Information and knowledge management www.iiste.org ISSN 2224-5758 (Paper) ISSN 2224-896X (Online) Vol.1, No.4, 2011 acceptance of non-conformances Lean Manufacturing is a term popularized by Womack, Jones and Roos [1991] to describe a method for production based on the Toyota Production System (TPS) (Shingo 1989, Ohno 1988). There is a tremendous body of literature available on the details of the TPS. The purpose of this thesis is to take the principles enumerated in the literature one step further and show how lean manufacturing can address the difficulties of aircraft manufacturing as a linear distribution system (LDS). 9.Cellular Manufacturing (CM)- Processing of parts or part families in a single cell, with no backtracking. Each part follows a predetermined part path, and is said to be trackable. Individual cells may be built around Group Technology formed part families or based on a single product line (which facilitates ABC methods). In CM the operators move independently of the part processing time. A cell processes a subset of the total operations in the production system. Cells process parts sequentially through a series of machines or manual stations, whereas a job shop processes parts in parallel processing through duplicated machines. A cellular manufacturing production system is network of logically linked cells (Cochran [1994]). Hence throughput of cells can be dependent on (a) a single machine’s cycle time (the bottleneck), or (b) the speed of the material handler or operator. • Changeover Time- The length of time a machine or processing area is down (not producing parts) in order to change over from one part type to another. It begins when the machine finishes producing the last part of type A and ends at the beginning of the production of the first good unit of type B. • Cost of Order Preparation- The costs incurred by a factory in the process of receiving an order, releasing it to the floor and closing the order upon receipt by the customer. • Customer Lead Time- The length of time beginning when a customer places an order and ending when the customer receives goods to fill that order. It encompasses the Production Lead Time plus the time required to transmit the order to the factory and the time to ship the product to the customer. • Defects vs. Errors- a defect is a product or service’s non-fulfillment of an intended requirement or reasonable expectation for use. An error is the result of improper processing of the part, which leads to a defect only when the part is inspected and fails. Thus, errors can be fixed before they become defects. • External Setup Operations- Operations in changeover from one part type to the next which are done while the machine is still producing parts. • Final vs. Absolute Defect Rate- the final defect rate reflects only the number of parts that fail the final inspection. However, the absolute defect rate is a measure of the number of defects for the entire process from start to finish (see Shingo [1986]) 10. Flexible Manufacturing System (FMS)- A group of numerically controlled machine tools interconnected by a central control system. The various machining cells are interconnected via loading and unloading stations by an automated transport system. Parts are generally processed in parallel rather than serially as in a Cellular Manufacturing System. Operational flexibility is enhanced by the ability to execute all manufacturing tasks on numerous product designs in small quantities. However, there are often limitations in flexibility due to the hard tooling that is required for material transport and fixturing in each machining cell. Capital investment is very high as compared to a manned cell. 15
  • 6. Information and knowledge management www.iiste.org ISSN 2224-5758 (Paper) ISSN 2224-896X (Online) Vol.1, No.4, 2011 11. Group Technology (GT)- A part classification technique used to categorize parts according to one of two possible similarities: (1) part geometry, or (2) processing similarities. GT is generally used to create part families which can then be processed in single cell. 12. Informative vs. Subjective Inspections- An informative inspection yields information about a part, such as a dimensional characteristic. As a subjective inspection is a pass-failure inspection, the inspector must make a subjective judgment about the quality of a part. 13. Internal Setup Operations- Operations in changeover from one part type to the next which are done when the machine is stopped (is not producing parts). 14. Job- Work order; an order from a customer which comprises a fixed number of parts of a specified type. 15. Lot Delay- In batch production, the time spent while the part is waiting for other parts in the batch to be processed. 16. Lot (or Batch) Production- Producing parts in lots or batches which are greater than one part. 17. Machine Utilization- The ratio of time during which the machine is operating to the total time available. The operating time should only include time in which product is being produced (setup time is excluded). 18. Machine Cycle Time- The length of time required for a machine to process one part, not including loading and unloading time. It can be measured as the length of time beginning when the start button is pressed and ending when the part can be removed. 19. Manufacturing Lead Time- The length of time from the first operation for a given order until the entire order has been transported to the shipping area. 20. Order (or Production) Lead Time- The length of time beginning with receipt of an order from a customer and ending when product for that order has been manufactured and transported to the shipping area. It includes the Manufacturing Lead Time plus the time required to process the order and begin production. 21Process vs. Operation- The distinction between a process and an operation is not one of time scale; the two have different subjects of study. A process is a flow of product from raw materials to finished parts. Operations are the actions of man, or machine, and what they do to the product. 22. Process Mapping- A systematic analysis of a production system using Time Division Analysis to determine which operations are integral to a process, and which must be eliminated. 32. Processing Delay- The time spent while a part is in storage, either in queue behind other batches of parts, or waiting due to machine downtime. 33. Production Balancing- Efforts to make the processing time for a given part at each station in a process equal. In a perfectly balanced process, no stations will be idle when producing parts using single piece flow. 16
  • 7. Information and knowledge management www.iiste.org ISSN 2224-5758 (Paper) ISSN 2224-896X (Online) Vol.1, No.4, 2011 34. Production Leveling- Efforts to increase the product mix and decrease the batch size in a manufacturing system. In Level Production, assuming there is no variation in processing, at least one unit of each part type is produced each day. 35. Production Synchronization- Efforts to synchronize the start, stop and transport of product at each machine, station and process. In Synchronous Production, the upstream process produces goods at the same rate (or Takt time) as the downstream process. 36. Self (or Source) Inspection- Inspection carried out by the person (or factory) which produced the product. 37. Single Piece Flow- A term describing the processing of parts in a batch size of one. The only processing lot size in which the lot delay is reduced to zero. 38. Statistical Quality Control (SQC)- The application of statistical techniques to control quality. Generally refers to monitoring or inspecting some percentage (less than 100%) and inferring the quality of the rest of the parts from a sample. SQC is subject to and  errors. 39. Successive (or Post-receipt )Inspection- Inspection by a person or factory of goods that were produced at an upstream station or plant. Traditionally thought to be more objective than self inspections, since there is no incentive to pass defective parts through the inspection. However, this inspection method can only discover defects after they have been made (see defects vs. errors). 40.System- A regularly interacting or interdependent group of items forming a unified whole toward the achievement of a goal. 41.Takt Time- A production rate determined by customer orders (or sales) which specifies the interval of time between production of successive parts. Is determined from the following equation: total time available for production per shift (in sec) Takt Time = required number of parts per shift 42.Time Division Analysis- A technique similar to process mapping where a process is analyzed by tracking a part as it flows from raw materials to the finish crib and constantly specifying whether a part is being processed, transported, stored or inspected. Storage is further broken down into Lot delay, Transportation delay, and Processing delay. 43. Transportation Delay- The time spent waiting for the means of transportation (i.e. waiting for a forklift) . 44. Value Added vs. Non Value Added Processing- Value added processing refers to processing steps that will add value to a part, viewed from the eyes of the customer. Non value added processing includes all processing that does not add value. Thus a cutting operation on a machine is value added processing only if it creates a feature in the part that is of value to the customer. 45. Volume vs. Part Types Flexibility- Volume flexibility refers to the ability of a manufacturing system to produce parts at different rates. Part type flexibility refers to the ability to produce a number of different 17
  • 8. Information and knowledge management www.iiste.org ISSN 2224-5758 (Paper) ISSN 2224-896X (Online) Vol.1, No.4, 2011 part types in a given period of time. . References 1. Cell, Charles; VE, Lean, and Six Sigma – Opportunities Leverage, 2004 SAVE International Conference Proceedings, Canada (2004) 2. Cook, Dr. Michael; An Untapped Market – Energizing VM Usage via the Six Sigma Methodology, 2000 SAVE International Conference Proceedings, USA (2000). 3. Dean, Edwin B.; Value Engineering from the Perspective of Competitive Advantage, USA (2000). 4. Downer, John G.; From Product to Project – Forming Value into a New Shape, 2005 SAVE International Conference Proceedings, USA (2005). 5. Fong, Patrick Sik-Wah; Charting the Future Directions of Value Engineering, 1999 SAVE International Conference Proceedings, USA (1999). 6. George, Michael; Lean Six Sigma : Combining Six Sigma Quality with Lean Speed; McGraw Hill; USA (2002) 7. Hino, Satoshi; Inside the Mind of Toyota : Management Principles for Enduring Growth (English Translation); Productivity Press, Inc., USA (2006). 8. Johnson, Gordon; Conflicting or Complementing ? A Comprehensive Comparison of Six Sigma and Value Methodology, 2003 SAVE International Conference Proceedings, USA (2003) 9. Kirk, Bozdogan; A Comparative Review of Lean Thinking, Six Sigma and Related Enterprise Change Models, Massachusetts Institute of Technology, Lean Aerospace Institute, USA (2003). 10. Lehman, Theresa &Reiser, Paul; Maximizing Value & Minimizing Waste – Value Engineering & Lean Construction, 2004 SAVE International Conference Proceedings, USA (2004) 11. Liker, Dr. Jeffrey; The Toyota Way, 14 Management Principles from the World’s Greatest Manufacturer; McGraw Hill, USA (2004) 12. Maurer, John H.; What is Value Analysis / Value Engineering (VA/VE) ? , USA (1999). 18