5. SMO BLOCK B1
Land Clearing and Soil Removal
Sept Oct Nov
(Ha) (Ha) (Ha)
Blok B1
-Pit C2 - - -
-IPD C - - -
-OPD B14 - - -
Total land clearing area - - -
* boundary clearing 20 meter dari boundary desain
Land Clearing
2015
Sept Oct Nov
BCM BCM BCM
Pit C2 Volume 20,692 1,859 70
Lokasi Penimbunan
OPD B14 & OPD
B3
OPD B14 & OPD
B4
OPD B14 & OPD
B5
20,692 1,859 70Total volume soil removal
Soil Removal
Blok B1
2015
6. SMO BLOCK B1
Material Balance
Code Data Field Name Sep Oct Nov 2015 *
Sambarata Dump Report
B1 Sambarata B1
OPD_14 OPD14 - Out Pit Dump
Wst Total Insitu Waste 483,905 496,713 465,701 1,446,319
totptd Total Distance (Pit to Dump) During Schedule 2,525 2,714 2,704 2,648
IPD_C IPDC- In Pit Dump
Wst Total Insitu Waste 2,005,487 2,051,743 1,907,775 5,965,005
totptd Total Distance (Pit to Dump) During Schedule 2,637 2,791 2,845 2,756
Tot Total Dumping - Sambarata B1
WstD Total Insitu Waste Dumped on Dumps 2,489,392 2,548,456 2,373,476 7,411,324
IWstOF Insitu Dump Shortage(Overflow)
WstOF Dump Shortage(Overflow)
totptd Total Distance (Pit to Dump) During Schedule 2,615 2,776 2,817 2,735
VB Volume Balance 0 0 0 0
11. SMO BLOCK B1
General Issue :
• Proses land compensation untuk area radius blasting di Enau harus sudah selesai pada awal tahun 2015 untuk menghindari
terjadinya issue masalah blasting dan menghindari turunnya productivity unit karena ketidaktersediaan material blasting.
(aktual blasting maks 50 hole)
• Rekomendasi IPD C 2015 masih menunggu kajian dan release GnH.
• Lokasi dumping material rawa/lunak diarea sump C.
• Pemotongan Mineout atau floor seam H 1 meter sesuai rekomendasi GnH.
• Performa slurry pump tidak maksimal pada pit G1 sehingga mengharuskan adanya manual handling, impactnya ada
kenaikan SR karena perhitungan material blending 1:1.5
• Start Pumping di Sed Pond WMP 29 ( Slurry pump ) dan kontinyu pembentukan WMP 33