7. 132kV 5 Pole structure
replacement with
132kV monopoles
The existing pole structures were damaged
by woodpeckers and deteriorated over years.
The challenge was to replace the structures
with steel mono poles with the minimum
outage time. The line could only be switched
off over weekends which was a huge
challenge for this project.
The picture is before construction began
during the surveying stage to compile a
report on the condition of the structures.
8. 132kV 5 Pole structure
replacement with
132kV monopoles.
The new 132kV strain mono
pole in place.