DEPARTMENT OF ELECTRICAL ENGINEERING
KIPM-COLLEGE OF ENGINEERING AND TECHNOLOGY, GIDA,GKP
INDUSTRIAL SUMMER TRAINING 220/132 KV SUBSTATION
BARAHUWA
ASHUTOSH SRIVASTAVA
(1375120016)
B.TECH (IV YEAR)
(EE)
TABLE OF CONTENT
 Introduction
 Single Line Diagram
 220 KV Sub-Station
 Panel Section
 Yard Section
 Battery Room
 Components of Substation
 Conclusion
 References
INTRODUCTION
Uttar Pradesh Power Corporation Limited
(UPPCL) is the company responsible for electricity
transmission and distribution within the Indian state of
Uttar Pradesh .Its chairman is Mr. Sanjay Agarwal.
UPPCL Barahuwa 220 KV substation was
established in 1979.
UPPCL Barahuwa substation is basically
contains two substation one of 220/132 KV & other
one of 132/33 KV.
Single line diagram
There are three sections of substation:
• One incoming section of 220 KV
• Two outgoing sections of 132 & 33 KV
• 220 KV INCOMMING SECTION:
There are four incoming lines of 220 KV-
* GKP CKT-1(MOTIRAM ADDA)
* GKP CKT-2(MOTIRAM ADDA)
* PGCIL SAHJANWA(INDIAN GOV.)
* NTPC TANDA(INDIAN GOV.)
• 132 KV OUTGOING SECTION:
There are seven outgoing lines of 132 KV-
*MOHADDIPUR
*MAU-1
*MAU-2(KAUDI RAM)
*FCI-1
*FCI-2
*ANAND NAGAR
*GIDA
• 33 KV OUTGOING SECTION:
There are ten outgoing lines of 33 KV-
*RUSTAMPUR
*PGCIL SAHJANWA
*LAL-DIGGI
*NAUSAD
*HARPUR GANGTAHI
*STATION TRANSFORMER-1
*STATION TRANSFORMER-2(COLONY)
*SAHJANWA
*GIDA
*SPARE
220 KV SUB-STATION:
IT IS DEVIDED INTO THREE PARTS:
TWO MAIN PART IS-
1.PANEL SECTION
-CONTROL PANEL
-RELAYAND PROTECTION PANEL
2. YARD SECTION
-220 KV SECTION
-132 KV SECTION
-33 KV SECTION
ONE OTHER PART IS-
1.BATTERY ROOM
PANEL SECTION
 it is a room which contains all type of panels.
 it has two sections:
 Control Panel Section:
It contain panels related to controlling of
instruments. E.g. feeder panel, X-mer
panel, etc.
 Relay and Protection Panel Section:
It contains panel related to relay system and
protection systems. E.g. relay panel, line
protection panel, etc.
YARD SECTION
220 KV SECTION…
• IT WORKS ON 220 KV.
• THERE ARE THREE BUS BARS IN WHICH TWO
IS MAIN BUS AND OTHER ONE IS TRANFER
BUS.
• IT HAS FOUR INCOMMING FEEDERS I.E.
FROM PGCIL SAHJANWA, NTPC TANDA,GKP
CKT-1 & GKP CKT-2.
132 KV…
• IT WORKS ON 132 KV.
•THERE ARE THREE BUS BARS IN WHICH TWO
IS MAIN BUS AND OTHER ONE IS TRANFER
BUS.
•220 KV VOLTAGE IS CONVERTED TO 132 KV
VOLTAGE USING FOUR TRANSFORMERS IN
WHICH ONE OF 160 MVA & OTHER THREE ARE
100 MVA.
• IN OTHER WORDS IT IS 220 KV/132KV
SUBSTATION.
•THIS LINE IS DIRECTLY FEDED TO MANY
OTHER SUBSTATIONS LIKE
MOHADDIPUR,GIDA ETC.
33 KV SECTION…
• THIS SECTION WORKS ON 33 KV.
• IT HAS TWO FEEDERS OF 33 KV.
• ONE FROM 63 MVA TRANSFORMER & ONE
FROM 40 MVA TRANSFORMER.
• THESE TWO TRANSFORMERS CONVERTS
132 KV/33 KV.
• IN OTHER WORDS IT IS 132 KV/33 KV
SUSTATION.
• THIS LINE IS DIRECTLY FEDED TO MANY
INDUSTRIES AND DISTRIBUTORS LIKE
GIDA,PGCIL ETC.
BATTERY ROOM
110 DC SUPPLY REQUIRED FOR OPERATION
OF CIRCUIT BREAKERS-
•55 BATTERIES OF 2V , 300AH (TAURUS-HBL
POWER SYSTEM LTD.){FOR REGULER USE}
•55 BATTERIES OF 2V , 300AH(HBL POWER
SYSTEM LTD.){FOR BACKUP}
DC SUPPLY REQUIRED FOR OPERATION IN
CONTROL ROOM-
•BATTERIES OF 2V , 500 AH (EXIDE
INDUSTRIAL)
COMPONENTS OF SUB-STATION –
•RELAY
•CIRCUIT BREAKER
•ISOLATOR
•TRANSFORMER
•CURRENT TRANSFORMER (CT)
•POTENTIAL TRANFORMER (PT)
•CAPACITOR VOLTAGE TRANSFORMER (CVT)
•LIGHTENING ARRESTER( LA )
•FEEDER
•BUS-BAR
•INSULATOR
•CAPACITOR BANK
•WAVE TRAP
RELAY
A relay is an electrically operated switch.
A relay is a sensing device which sense the abnormal
condition and then produce an alarm or open the
breaker contact.
CIRCUIT BREAKER
A circuit breaker is an automatically operated
electrical switch designed to protect an electrical
circuit from damage caused by over-current or
overload or short circuit.
ISOLATOR
Isolator is used to ensure that an electrical circuit is
completely de-energized for service or maintenance.
TRANSFORMER
A transformer is an electrical device that transfers
electrical energy between two or more circuits through
electromagnetic induction.
There are eight step down transformer at substation:
220/132 KV TRANSFORMER-
1. 160 MVA(AREVA)
2. 100 MVA(MISTIBUSHI)
3. 100 MVA(MISTIBUSHI)
4. 100 MVA(TELK-TRANFORMERS & ELECTRICLS LIMITED KERALA) (NOT
INSTALLED BUT UNDER PROCESS)
132/33 KV TRANSFORMER-
1. 63 MVA(ADITYA VIDYUT APPLIANCES LTD.)
2. 40 MVA(AREVA)
33000/400 VOLT TRANSFORMER-
1. 250 KVA(FOR SUB-STATION)(SWASTIK COPPER JAIPUR)
2. 250 KVA(FOR COLONY)(NGEF)
CURRENT TRANSFORMER
It is a step up transformer which is used to measure the
current, by stepping up the voltage level.
POTENTIAL TRANSFORMER
It is a step down transformer which is used to measure
the voltage, by stepping up the voltage level.
CAPACITOR VOLTAGE TRANSFORMER
A capacitor voltage transformer (CVT) is a
transformer used to step down extra high voltage
signals and provide a low voltage signal for voltage
measurement & It also forms a carrier communication
network through the transmission network.
LIGHTENING ARRESTER
It provides low impedance path for high frequency and
high current supply.
FEEDER
A set of conductors that originate at a primary
distribution centre and supply power to one or more
secondary distribution centre.
BUS-BAR
An assembly of conductors for collecting electric
currents and distributing them to outgoing feeders.
INSULATOR
A material of such low conductivity that the flow of
current through it is negligible.
CAPACITOR BANK
It is used to componsate the power factor from lagging
to leading nature.
WAVETRAP
Tripping the high frequency communication signal
sent on the line from the remote substation and
diverting them to the telecom panel in the substation
control room.
CONCLUSION
An engineer needs to have not just theoretical
but practical as well as and so every student is
supposed to undergo practical training session
after 3rd year where I have imbibed the
knowledge about transmission, distribution and
maintenance with economical issues related to
it.
At last I would like to say that practical training
taken at 220 KV substation barahuwa has
broadened my knowledge and widened my
thinking as a professional.
REFERENCES
 www.slideshare.net
 www.seminarprojects.org
 www.scribd.com
 www.projectsreport.org
 www.fullreports.net
At last i would say……
SAVE ENERGY,SAVE FUTURE
THANK YOU..

Contenu connexe

Tendances

Tendances (20)

Substations
SubstationsSubstations
Substations
 
substation internship report
substation internship report substation internship report
substation internship report
 
Shashikdoc
ShashikdocShashikdoc
Shashikdoc
 
33kv substation
33kv substation33kv substation
33kv substation
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
 
132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
 
Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
PPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppclPPT on 33/11 sub-station uppcl
PPT on 33/11 sub-station uppcl
 
PPT ON 220KV GSS
PPT ON 220KV GSSPPT ON 220KV GSS
PPT ON 220KV GSS
 
Summer internship at pgcil
Summer internship at pgcilSummer internship at pgcil
Summer internship at pgcil
 
PPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATIONPPT ON 33/11KV SUBSTATION
PPT ON 33/11KV SUBSTATION
 
Electric substation
Electric substation Electric substation
Electric substation
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
Summer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul MehraSummer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul Mehra
 
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
 
substation 220 kv
substation 220 kv substation 220 kv
substation 220 kv
 
Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakir
 
REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION REPORT ON 33/11KV SUBSTATION
REPORT ON 33/11KV SUBSTATION
 

En vedette (8)

132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL132KV SUBSTATION UPPTCL
132KV SUBSTATION UPPTCL
 
Madan mohan malaviya
Madan mohan malaviyaMadan mohan malaviya
Madan mohan malaviya
 
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
 
bsnl project report
 bsnl project report bsnl project report
bsnl project report
 
Uttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training reportUttar pradesh power corparation ltd. training report
Uttar pradesh power corparation ltd. training report
 
Summer training from BSNL
Summer training from BSNLSummer training from BSNL
Summer training from BSNL
 
New final bsnl training report
New final bsnl training report New final bsnl training report
New final bsnl training report
 
BSNL Industrial Training ppt 2014.
BSNL Industrial Training ppt 2014.BSNL Industrial Training ppt 2014.
BSNL Industrial Training ppt 2014.
 

Similaire à Industrial summer training on 220 kv substation ppt

Similaire à Industrial summer training on 220 kv substation ppt (20)

PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptx
 
finalseminar.docx
finalseminar.docxfinalseminar.docx
finalseminar.docx
 
Visit to 400 kV substation, Hadala
Visit to 400 kV substation, HadalaVisit to 400 kV substation, Hadala
Visit to 400 kV substation, Hadala
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training Report
 
200280109010_Internship Power Point Presentation.pptx
200280109010_Internship Power Point Presentation.pptx200280109010_Internship Power Point Presentation.pptx
200280109010_Internship Power Point Presentation.pptx
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
 
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG  INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
 
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
 
Vocational training
Vocational trainingVocational training
Vocational training
 
132 kV uppcl
132 kV uppcl132 kV uppcl
132 kV uppcl
 
Trainingreport 132 KV
Trainingreport 132 KVTrainingreport 132 KV
Trainingreport 132 KV
 
A PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITYA PPT ON 220 KV GSS HINDAUN CITY
A PPT ON 220 KV GSS HINDAUN CITY
 
internship report of 220/132 kV substation
internship report of 220/132 kV substationinternship report of 220/132 kV substation
internship report of 220/132 kV substation
 
220 kv gss
220 kv gss220 kv gss
220 kv gss
 
DLW Varanasi Training report
DLW Varanasi Training reportDLW Varanasi Training report
DLW Varanasi Training report
 
220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)220kv gss pindwara(sirohi)
220kv gss pindwara(sirohi)
 
400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf 400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf
 
Bharat singh 1
Bharat singh 1Bharat singh 1
Bharat singh 1
 

Dernier

DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
chumtiyababu
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Dernier (20)

Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 

Industrial summer training on 220 kv substation ppt

  • 1. DEPARTMENT OF ELECTRICAL ENGINEERING KIPM-COLLEGE OF ENGINEERING AND TECHNOLOGY, GIDA,GKP INDUSTRIAL SUMMER TRAINING 220/132 KV SUBSTATION BARAHUWA ASHUTOSH SRIVASTAVA (1375120016) B.TECH (IV YEAR) (EE)
  • 2. TABLE OF CONTENT  Introduction  Single Line Diagram  220 KV Sub-Station  Panel Section  Yard Section  Battery Room  Components of Substation  Conclusion  References
  • 3. INTRODUCTION Uttar Pradesh Power Corporation Limited (UPPCL) is the company responsible for electricity transmission and distribution within the Indian state of Uttar Pradesh .Its chairman is Mr. Sanjay Agarwal. UPPCL Barahuwa 220 KV substation was established in 1979. UPPCL Barahuwa substation is basically contains two substation one of 220/132 KV & other one of 132/33 KV.
  • 5. There are three sections of substation: • One incoming section of 220 KV • Two outgoing sections of 132 & 33 KV • 220 KV INCOMMING SECTION: There are four incoming lines of 220 KV- * GKP CKT-1(MOTIRAM ADDA) * GKP CKT-2(MOTIRAM ADDA) * PGCIL SAHJANWA(INDIAN GOV.) * NTPC TANDA(INDIAN GOV.)
  • 6. • 132 KV OUTGOING SECTION: There are seven outgoing lines of 132 KV- *MOHADDIPUR *MAU-1 *MAU-2(KAUDI RAM) *FCI-1 *FCI-2 *ANAND NAGAR *GIDA
  • 7. • 33 KV OUTGOING SECTION: There are ten outgoing lines of 33 KV- *RUSTAMPUR *PGCIL SAHJANWA *LAL-DIGGI *NAUSAD *HARPUR GANGTAHI *STATION TRANSFORMER-1 *STATION TRANSFORMER-2(COLONY) *SAHJANWA *GIDA *SPARE
  • 8. 220 KV SUB-STATION: IT IS DEVIDED INTO THREE PARTS: TWO MAIN PART IS- 1.PANEL SECTION -CONTROL PANEL -RELAYAND PROTECTION PANEL 2. YARD SECTION -220 KV SECTION -132 KV SECTION -33 KV SECTION ONE OTHER PART IS- 1.BATTERY ROOM
  • 9. PANEL SECTION  it is a room which contains all type of panels.  it has two sections:  Control Panel Section: It contain panels related to controlling of instruments. E.g. feeder panel, X-mer panel, etc.  Relay and Protection Panel Section: It contains panel related to relay system and protection systems. E.g. relay panel, line protection panel, etc.
  • 10. YARD SECTION 220 KV SECTION… • IT WORKS ON 220 KV. • THERE ARE THREE BUS BARS IN WHICH TWO IS MAIN BUS AND OTHER ONE IS TRANFER BUS. • IT HAS FOUR INCOMMING FEEDERS I.E. FROM PGCIL SAHJANWA, NTPC TANDA,GKP CKT-1 & GKP CKT-2.
  • 11. 132 KV… • IT WORKS ON 132 KV. •THERE ARE THREE BUS BARS IN WHICH TWO IS MAIN BUS AND OTHER ONE IS TRANFER BUS. •220 KV VOLTAGE IS CONVERTED TO 132 KV VOLTAGE USING FOUR TRANSFORMERS IN WHICH ONE OF 160 MVA & OTHER THREE ARE 100 MVA. • IN OTHER WORDS IT IS 220 KV/132KV SUBSTATION. •THIS LINE IS DIRECTLY FEDED TO MANY OTHER SUBSTATIONS LIKE MOHADDIPUR,GIDA ETC.
  • 12. 33 KV SECTION… • THIS SECTION WORKS ON 33 KV. • IT HAS TWO FEEDERS OF 33 KV. • ONE FROM 63 MVA TRANSFORMER & ONE FROM 40 MVA TRANSFORMER. • THESE TWO TRANSFORMERS CONVERTS 132 KV/33 KV. • IN OTHER WORDS IT IS 132 KV/33 KV SUSTATION. • THIS LINE IS DIRECTLY FEDED TO MANY INDUSTRIES AND DISTRIBUTORS LIKE GIDA,PGCIL ETC.
  • 13. BATTERY ROOM 110 DC SUPPLY REQUIRED FOR OPERATION OF CIRCUIT BREAKERS- •55 BATTERIES OF 2V , 300AH (TAURUS-HBL POWER SYSTEM LTD.){FOR REGULER USE} •55 BATTERIES OF 2V , 300AH(HBL POWER SYSTEM LTD.){FOR BACKUP} DC SUPPLY REQUIRED FOR OPERATION IN CONTROL ROOM- •BATTERIES OF 2V , 500 AH (EXIDE INDUSTRIAL)
  • 14. COMPONENTS OF SUB-STATION – •RELAY •CIRCUIT BREAKER •ISOLATOR •TRANSFORMER •CURRENT TRANSFORMER (CT) •POTENTIAL TRANFORMER (PT) •CAPACITOR VOLTAGE TRANSFORMER (CVT) •LIGHTENING ARRESTER( LA ) •FEEDER •BUS-BAR •INSULATOR •CAPACITOR BANK •WAVE TRAP
  • 15. RELAY A relay is an electrically operated switch. A relay is a sensing device which sense the abnormal condition and then produce an alarm or open the breaker contact. CIRCUIT BREAKER A circuit breaker is an automatically operated electrical switch designed to protect an electrical circuit from damage caused by over-current or overload or short circuit. ISOLATOR Isolator is used to ensure that an electrical circuit is completely de-energized for service or maintenance.
  • 16. TRANSFORMER A transformer is an electrical device that transfers electrical energy between two or more circuits through electromagnetic induction. There are eight step down transformer at substation: 220/132 KV TRANSFORMER- 1. 160 MVA(AREVA) 2. 100 MVA(MISTIBUSHI) 3. 100 MVA(MISTIBUSHI) 4. 100 MVA(TELK-TRANFORMERS & ELECTRICLS LIMITED KERALA) (NOT INSTALLED BUT UNDER PROCESS) 132/33 KV TRANSFORMER- 1. 63 MVA(ADITYA VIDYUT APPLIANCES LTD.) 2. 40 MVA(AREVA) 33000/400 VOLT TRANSFORMER- 1. 250 KVA(FOR SUB-STATION)(SWASTIK COPPER JAIPUR) 2. 250 KVA(FOR COLONY)(NGEF)
  • 17. CURRENT TRANSFORMER It is a step up transformer which is used to measure the current, by stepping up the voltage level. POTENTIAL TRANSFORMER It is a step down transformer which is used to measure the voltage, by stepping up the voltage level. CAPACITOR VOLTAGE TRANSFORMER A capacitor voltage transformer (CVT) is a transformer used to step down extra high voltage signals and provide a low voltage signal for voltage measurement & It also forms a carrier communication network through the transmission network.
  • 18. LIGHTENING ARRESTER It provides low impedance path for high frequency and high current supply. FEEDER A set of conductors that originate at a primary distribution centre and supply power to one or more secondary distribution centre. BUS-BAR An assembly of conductors for collecting electric currents and distributing them to outgoing feeders.
  • 19. INSULATOR A material of such low conductivity that the flow of current through it is negligible. CAPACITOR BANK It is used to componsate the power factor from lagging to leading nature. WAVETRAP Tripping the high frequency communication signal sent on the line from the remote substation and diverting them to the telecom panel in the substation control room.
  • 20. CONCLUSION An engineer needs to have not just theoretical but practical as well as and so every student is supposed to undergo practical training session after 3rd year where I have imbibed the knowledge about transmission, distribution and maintenance with economical issues related to it. At last I would like to say that practical training taken at 220 KV substation barahuwa has broadened my knowledge and widened my thinking as a professional.
  • 21. REFERENCES  www.slideshare.net  www.seminarprojects.org  www.scribd.com  www.projectsreport.org  www.fullreports.net
  • 22. At last i would say…… SAVE ENERGY,SAVE FUTURE THANK YOU..