MS Project Integration: Tips, 
Tricks and What's New for You 
Mindy Calderon 
Senior Instructor, North America 
CA Technologies 
ICX17E #CAWorld
Abstract 
 Have you scheduled in Microsoft Project (MSP) and are now presented with the "Tasks" to 
maintain a schedule in CA Clarity? Is your organization using CA Clarity but still wants to 
schedule in MS Project? Have you noticed that the logic in how CA Clarity schedules is different 
in MS Project? And most importantly - wouldn't it be awesome to be able to explain why CA 
Clarity and MS Project behave differently but ultimately get you the same result? The session 
will show you where and how MSP and CA Clarity bi-directionally map data, how to create and 
manage tasks, assignments and scheduling, as well as updating task status and work. It 
includes a broad discussion where and when data should be entered in Clarity and MS Project, 
on defining data elements and how to capture them. 
Mindy 
Calderon 
CA Technologies 
Senior Instructor 
2 © 2014 CA. ALL RIGHTS RESERVED.
Agenda 
INTEGRATION OVERVIEW 
CUSTOM VIEWS 
WORK BREAKDOWN STRUCTURE 
RESOURCES AND MS PROJECT 
Q & A 
3 © 2014 CA. ALL RIGHTS RESERVED.
Summary 
A Few Words to Describe MS Project Integration with Clarity 
Results 
MS Project and CA Clarity PPM bi-directionally maps data, manages tasks, assignments and scheduling as 
well as updating task status. The Clarity project acts as the ‘umbrella’ for PM methodology . The result is a 
project that follows Project Management and Scheduling standards. 
4 © 2014 CA. ALL RIGHTS RESERVED.
Definitions 
INTEGRATION – BIDIRECTIONAL DATA FLOW USING NEW XML DRIVER 
METHODOLOGY – CONSISTENT AND REPEATABLE SCHEDULING AND MANAGING PROCESSES 
* 
* 
This is NOT a Technical Session: Understand from a Functional Perspective 
5 © 2014 CA. ALL RIGHTS RESERVED.
Integration Overview
Identify the MS Project Integration 
 Schedule Projects 
– Microsoft Project 
 Set Scheduler Format attribute 
default to Microsoft Project 
 PICK ONE AND STICK WITH IT! 
– Per project 
7 © 2014 CA. ALL RIGHTS RESERVED.
Identify and Install the MSP Interface 
8 © 2014 CA. ALL RIGHTS RESERVED.
Bi-Directional 
 New xml file – same location as the .mpp file 
 Usually in the My Documents folder 
 Supportable – old integration no longer supported by Microsoft 
 When you launch a plan from the CA Clarity PPM 
screen, it exports this plan to your local client 
system. 
 After you complete updating your session from 
within Microsoft Project, you will select Save 
from the Clarity Integration toolbar to retain your 
updates 
9 © 2014 CA. ALL RIGHTS RESERVED.
Install the MSP Interface Tips 
10 © 2014 CA. ALL RIGHTS RESERVED.
Set Defaults and Options 
11 © 2014 CA. ALL RIGHTS RESERVED.
Set Defaults and Options Continued 
 Tips 
– At a minimum, you must set the File – Project 
Option defaults at the application level 
– Additionally, you will want to check and modify 
these settings on the individual projects that 
were created before you adjusted these File – 
Project Option defaults 
– These projects would have inherited the former 
default settings 
– Application Level Defaults allow all new projects 
to inherit the default settings. 
– Setting should also be reset for Legacy projects 
that are being brought into CA Clarity PPM 
12 © 2014 CA. ALL RIGHTS RESERVED.
Identify Field Mappings 
13 © 2014 CA. ALL RIGHTS RESERVED.
Custom Views and Creating a Project
Custom Views 
 Gantt Chart View 
̶ Add the Key Task Column 
̶ Add the Charge Code Column 
– Only if you let Users select 
 Task Usage View 
̶ actual work 
̶ remaining 
 Custom View 
̶ Combined View 
 Gantt Chart on the top 
 Task Usage on bottom 
Modify Existing Views to Create Custom Views 
15 © 2014 CA. ALL RIGHTS RESERVED.
Create Projects – RULE OF THUMB 
 Anything on the Properties Tab and Team Tab 
– Enter/Edit/Update in CA Clarity 
 Anything on the Tasks Tab 
– Enter/Edit/Update in MS Project 
Anything on the Tasks Tab 
Enter/Edit/Update in MS Project 
16 © 2014 CA. ALL RIGHTS RESERVED.
Resources and MS Project
Resources and MS Project 
 Staff a Plan 
– Should ALWAYS be done in CA Clarity 
– Resource Allocation button 
Holistic View of Availability 
Resource Planning Views 
18 © 2014 CA. ALL RIGHTS RESERVED.
The Four (4) A’s 
 Availability 
 Allocation 
 Assignment 
 Actuals 
Holistic View of Availability and Allocation 
Resource Planning Views 
19 © 2014 CA. ALL RIGHTS RESERVED.
Work Breakdown Structure 
There are often misunderstandings about the meanings 
of the terms “duration” and “work” 
A task has duration amount and work amount, 
which may not always be equivalent values
Define Work, Units and Duration 
 For a Fixed Units task, Microsoft Project recalculates Duration when you overwrite the Fixed Units value 
 For a Fixed Duration task, Microsoft Project recalculates Work when you overwrite the Fixed Duration value 
 For a Fixed Work task, Microsoft Project recalculates Duration when you overwrite the Fixed Work value 
21 © 2014 CA. ALL RIGHTS RESERVED.
Identify Task Management Guidelines 
Terminology Differences Between CA Clarity PPM and Microsoft Project 
22 © 2014 CA. ALL RIGHTS RESERVED.
Identify Task Management Guidelines 
Terminology Differences Between CA Clarity PPM and Microsoft Project Continued 
23 © 2014 CA. ALL RIGHTS RESERVED.
Determine the Schedule 
 Some of the common elements of 
Project Management get a bit more 
complicated when using CA Clarity and 
Microsoft Project together 
 Status = Complete 
– Microsoft Project 
 Zero out remaining work for all 
resource assignments 
– CA Clarity 
24 © 2014 CA. ALL RIGHTS RESERVED. 
 Zero-out the Estimate to Complete 
value, select ‘Completed’ from the 
drop-down in the ‘Status’ field 
 Remaining Work & Pending Estimate To 
Complete 
– Entry Precedence 
– Work Contour 
– Summary Tasks 
– Blank Task Names
Control the Project
Baseline the Project 
 A Baseline will create a point-in-time capture of your project plan that you 
can refer to, and measure against 
– Baselines can include either the full or partial project WBS 
 Update to existing baselines 
– Full baseline 
– Update partial (tasks) baseline 
26 © 2014 CA. ALL RIGHTS RESERVED.
Baseline the Project 
 CA Clarity PPM can only have one Baseline active, but Microsoft Project can view several at a time 
 Microsoft Project can store 11 baselines, while CA Clarity PPM can store as many as you need 
– If there are more than 11 project baselines stored in CA Clarity PPM, the latest 11 will download to Microsoft Project 
when you open the project 
 CA Clarity PPM has security rights associated with creating and modifying baselines 
– you will still be able to run the baseline functionality in Microsoft Project, but the data will not be saved to CA Clarity 
PPM 
27 © 2014 CA. ALL RIGHTS RESERVED.
Define Track Mode Settings  This setting permits or restricts a 
28 © 2014 CA. ALL RIGHTS RESERVED. 
specific project from accepting 
actuals from a timesheet and/or 
permits the project manager to 
enter actuals directly into the 
project plan 
 The Track Mode is found in two 
locations: 
– Project level: Properties > 
Schedule 
– Resource level: Properties
Define Track Mode Settings 
 The following chart contains rules surrounding the capture of 
actuals using CA Clarity PPM Timesheets in conjunction with 
Microsoft Project 
29 © 2014 CA. ALL RIGHTS RESERVED.
Tips 
 Resources can be open for time entry at the resource, project and project assignment 
level. If a resource is not open for time entry in all three places, they are not able to use 
CA Clarity PPM timesheets. 
 Time periods should be created and status (open or closed) should be managed by an 
application administrator 
 Timesheets are submitted, approved and posted in CA Clarity PPM Timesheets – only 
posted timesheets appear as actuals 
– Actuals on Timesheets, which have been saved but not yet posted, will appear as Pending Actuals 
in Microsoft Project. These can be viewed using MSP mapping 
– Do not update Actuals in Microsoft Project if the Track Mode is Clarity or Other 
30 © 2014 CA. ALL RIGHTS RESERVED.
Apply Actuals 
 Be Vigilant on Timesheets 
– When work begins on the project, actuals will begin to be recorded against the 
plan 
– Impress upon your team members to track their time accurately and on the 
appropriate day or your plan‘s finish date may unnecessarily be delayed 
 Tasks not reported on a time sheet may change due to the posting of the 
assigned resource‘s time sheet. CA Clarity PPM assumes that a person's 
time sheet is a complete accounting of the project work they completed 
that week. If a scheduled task did not appear on the time sheet, it implies 
no work was completed by the resource on that task, and must be 
rescheduled for the following week or beyond 
31 © 2014 CA. ALL RIGHTS RESERVED.
Pending Actuals 
 There are three possible values you may see: 
– ‘0’ indicates that you are looking at a Summary task 
– ‘-1’ indicates that there are no Pending Actuals entered on the 
timesheet as of that day 
– A value other than ‘0’ or ‘-1’ indicates that the value you see is the 
team member’s cumulative Pending Actuals up through that day in 
that time period 
32 © 2014 CA. ALL RIGHTS RESERVED.
Pending Estimates 
 There are three possible values you may see: 
– ‘0’ indicates that you are looking at a Summary task 
– ‘-1’ indicates that a Pending Estimate has not been entered for the task 
– A value other than ‘0’ or ‘-1’ indicates that the team member has 
entered a Pending Estimate to identify a revision to the remaining 
estimate for the task 
33 © 2014 CA. ALL RIGHTS RESERVED.
Apply Actuals 
34 © 2014 CA. ALL RIGHTS RESERVED.
% Work Complete vs % Complete 
 % Work Complete 
– % Work Complete is set to 100% automatically if 
Microsoft Project detects the task is complete via 
calculations. 
 Once the Remaining Work has been reduced to 
zero, either manually or by the actuals that 
have been booked, the system sets the % Work 
Complete to 100%. 
 It is calculated based on Actuals and Remaining 
Work 
 % Complete 
– % Complete set by the Project Manager’s actions. 
– It is set to 100% when the Project Manager says the 
35 © 2014 CA. ALL RIGHTS RESERVED. 
task is complete by manually changing the %. 
– CA Clarity PPM automatically sets the value to 1% for 
Started Tasks and the Project Manager sets it to 100% 
when task is completed. 
– It is not calculated based on Actuals 
 Summary task % Complete can be calculated by running 
the Update % Complete Job
For More Information 
Insert appropriate screenshot and text overlay 
from following “More Info Graphics” slide here; 
Management Cloud 
ensure it links to correct page 
To learn more about Management Cloud, 
please visit: 
http://bit.ly/1wEnPhz 
36 © 2014 CA. ALL RIGHTS RESERVED.
For Informational Purposes Only 
Terms of this Presentation 
© 2014 CA. All rights reserved. All trademarks referenced herein belong to their respective companies. 
This presentation provided at CA World 2014 is intended for information purposes only and does not form any type of warranty. 
Some of the specific slides with customer references relate to customer's specific use and experience of CA products and solutions so actual 
results may vary. 
37 © 2014 CA. ALL RIGHTS RESERVED.

Contenu connexe

Tendances

Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
Primavera Project Management
Primavera Project ManagementPrimavera Project Management
Primavera Project ManagementTotalSoft
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-schedulingsaurabhshertukde
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricksp6academy
 
TILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceTILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceM. Tuna
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxGracePentinio1
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorialKetut Swandana
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sAbhik Tushar Das
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual Abbas Tahir
 
Tilos for linear project
Tilos for linear projectTilos for linear project
Tilos for linear projectThanh Hoang Lam
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010Ong-Art Sanpinit
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overviewMaher Almohamad
 
Maximo Training - Work Management
Maximo Training - Work ManagementMaximo Training - Work Management
Maximo Training - Work ManagementBruno Portaluri
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementMauro Jasse
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 

Tendances (20)

Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Primavera Project Management
Primavera Project ManagementPrimavera Project Management
Primavera Project Management
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-scheduling
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
TILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceTILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with Confidence
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorial
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
 
Tilos for linear project
Tilos for linear projectTilos for linear project
Tilos for linear project
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
 
Maximo Training - Work Management
Maximo Training - Work ManagementMaximo Training - Work Management
Maximo Training - Work Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 

En vedette

CA Project & Portfolio Management and MS Project Integration: Tips, Tricks an...
CA Project & Portfolio Management and MS Project Integration: Tips, Tricks an...CA Project & Portfolio Management and MS Project Integration: Tips, Tricks an...
CA Project & Portfolio Management and MS Project Integration: Tips, Tricks an...CA Technologies
 
Rego University: Integrating MSP with CA PPM (CA Clarity PPM)
Rego University: Integrating MSP with CA PPM (CA Clarity PPM)Rego University: Integrating MSP with CA PPM (CA Clarity PPM)
Rego University: Integrating MSP with CA PPM (CA Clarity PPM)Rego Consulting
 
Ca Clarity PPM Project Management User Guide
Ca Clarity PPM Project Management User GuideCa Clarity PPM Project Management User Guide
Ca Clarity PPM Project Management User Guidepiercens
 
Tech Talk: CA Agile Central Made Easy
Tech Talk: CA Agile Central Made EasyTech Talk: CA Agile Central Made Easy
Tech Talk: CA Agile Central Made EasyCA Technologies
 
CA PPM 15.1 Panel Session: Improving Customers’ Lives With the Latest Release
CA PPM 15.1 Panel Session: Improving Customers’ Lives With the Latest ReleaseCA PPM 15.1 Panel Session: Improving Customers’ Lives With the Latest Release
CA PPM 15.1 Panel Session: Improving Customers’ Lives With the Latest ReleaseCA Technologies
 
Clarity MS Project and Open Workbench
Clarity MS Project and Open WorkbenchClarity MS Project and Open Workbench
Clarity MS Project and Open WorkbenchYolanda Williams
 
CA PPM 14.x Agile Integrations
CA PPM14.x Agile IntegrationsCA PPM14.x Agile Integrations
CA PPM 14.x Agile IntegrationsCA Technologies
 
Tech Talk: Agile 101: You've Got Scrum Teams. So What?
Tech Talk: Agile 101: You've Got Scrum Teams. So What?Tech Talk: Agile 101: You've Got Scrum Teams. So What?
Tech Talk: Agile 101: You've Got Scrum Teams. So What?CA Technologies
 
CA Project & Portfolio Management Resource Management Best Practices
CA Project & Portfolio Management Resource Management Best PracticesCA Project & Portfolio Management Resource Management Best Practices
CA Project & Portfolio Management Resource Management Best PracticesCA Technologies
 
Tech Talk: How to Create and Steer an Agile Business
Tech Talk: How to Create and Steer an Agile BusinessTech Talk: How to Create and Steer an Agile Business
Tech Talk: How to Create and Steer an Agile BusinessCA Technologies
 
Microsoft project 2010 (final)
Microsoft project 2010 (final)Microsoft project 2010 (final)
Microsoft project 2010 (final)Isai Perez
 
Ms project 2010 tutorial 1
Ms project 2010 tutorial   1Ms project 2010 tutorial   1
Ms project 2010 tutorial 1learningquotient
 

En vedette (12)

CA Project & Portfolio Management and MS Project Integration: Tips, Tricks an...
CA Project & Portfolio Management and MS Project Integration: Tips, Tricks an...CA Project & Portfolio Management and MS Project Integration: Tips, Tricks an...
CA Project & Portfolio Management and MS Project Integration: Tips, Tricks an...
 
Rego University: Integrating MSP with CA PPM (CA Clarity PPM)
Rego University: Integrating MSP with CA PPM (CA Clarity PPM)Rego University: Integrating MSP with CA PPM (CA Clarity PPM)
Rego University: Integrating MSP with CA PPM (CA Clarity PPM)
 
Ca Clarity PPM Project Management User Guide
Ca Clarity PPM Project Management User GuideCa Clarity PPM Project Management User Guide
Ca Clarity PPM Project Management User Guide
 
Tech Talk: CA Agile Central Made Easy
Tech Talk: CA Agile Central Made EasyTech Talk: CA Agile Central Made Easy
Tech Talk: CA Agile Central Made Easy
 
CA PPM 15.1 Panel Session: Improving Customers’ Lives With the Latest Release
CA PPM 15.1 Panel Session: Improving Customers’ Lives With the Latest ReleaseCA PPM 15.1 Panel Session: Improving Customers’ Lives With the Latest Release
CA PPM 15.1 Panel Session: Improving Customers’ Lives With the Latest Release
 
Clarity MS Project and Open Workbench
Clarity MS Project and Open WorkbenchClarity MS Project and Open Workbench
Clarity MS Project and Open Workbench
 
CA PPM 14.x Agile Integrations
CA PPM14.x Agile IntegrationsCA PPM14.x Agile Integrations
CA PPM 14.x Agile Integrations
 
Tech Talk: Agile 101: You've Got Scrum Teams. So What?
Tech Talk: Agile 101: You've Got Scrum Teams. So What?Tech Talk: Agile 101: You've Got Scrum Teams. So What?
Tech Talk: Agile 101: You've Got Scrum Teams. So What?
 
CA Project & Portfolio Management Resource Management Best Practices
CA Project & Portfolio Management Resource Management Best PracticesCA Project & Portfolio Management Resource Management Best Practices
CA Project & Portfolio Management Resource Management Best Practices
 
Tech Talk: How to Create and Steer an Agile Business
Tech Talk: How to Create and Steer an Agile BusinessTech Talk: How to Create and Steer an Agile Business
Tech Talk: How to Create and Steer an Agile Business
 
Microsoft project 2010 (final)
Microsoft project 2010 (final)Microsoft project 2010 (final)
Microsoft project 2010 (final)
 
Ms project 2010 tutorial 1
Ms project 2010 tutorial   1Ms project 2010 tutorial   1
Ms project 2010 tutorial 1
 

Similaire à MS Project Integration: Tips, Tricks and What's New for You

CA Project and Portfolio Management v14.x: MS Project Integration: Tips, Tric...
CA Project and Portfolio Management v14.x: MS Project Integration: Tips, Tric...CA Project and Portfolio Management v14.x: MS Project Integration: Tips, Tric...
CA Project and Portfolio Management v14.x: MS Project Integration: Tips, Tric...CA Technologies
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM Divante
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM Mati Polak
 
Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides SlideTeam
 
4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...
4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...
4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...IBM Rational
 
Lean planning with Oracle Primavera Cloud
Lean planning  with Oracle Primavera CloudLean planning  with Oracle Primavera Cloud
Lean planning with Oracle Primavera CloudPRMYAZILIM
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMPAndy Pham, PMP
 
Planning and Scheduling in Maximo: Best Practices and Coming Enhancements
Planning and Scheduling in Maximo: Best Practices and Coming EnhancementsPlanning and Scheduling in Maximo: Best Practices and Coming Enhancements
Planning and Scheduling in Maximo: Best Practices and Coming EnhancementsIBM Danmark
 
Project management
Project managementProject management
Project managementervinod
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxcarolinef5
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxdonaldp2
 
Scrum With Ms Project
Scrum With Ms ProjectScrum With Ms Project
Scrum With Ms Projectbobby
 
The Effective Management of Time
The Effective Management of TimeThe Effective Management of Time
The Effective Management of TimeInSync Conference
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)ShudipPal
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysGlen Alleman
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Glen Alleman
 

Similaire à MS Project Integration: Tips, Tricks and What's New for You (20)

CA Project and Portfolio Management v14.x: MS Project Integration: Tips, Tric...
CA Project and Portfolio Management v14.x: MS Project Integration: Tips, Tric...CA Project and Portfolio Management v14.x: MS Project Integration: Tips, Tric...
CA Project and Portfolio Management v14.x: MS Project Integration: Tips, Tric...
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM
 
Budgeting in SCRUM
Budgeting in SCRUM Budgeting in SCRUM
Budgeting in SCRUM
 
Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides
 
4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...
4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...
4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...
 
Lean planning with Oracle Primavera Cloud
Lean planning  with Oracle Primavera CloudLean planning  with Oracle Primavera Cloud
Lean planning with Oracle Primavera Cloud
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMP
 
Planning and Scheduling in Maximo: Best Practices and Coming Enhancements
Planning and Scheduling in Maximo: Best Practices and Coming EnhancementsPlanning and Scheduling in Maximo: Best Practices and Coming Enhancements
Planning and Scheduling in Maximo: Best Practices and Coming Enhancements
 
Project management
Project managementProject management
Project management
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 
DescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docxDescriptionThe Aires Corporation is highly desirous of implementi.docx
DescriptionThe Aires Corporation is highly desirous of implementi.docx
 
Scrum With Ms Project
Scrum With Ms ProjectScrum With Ms Project
Scrum With Ms Project
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
The Effective Management of Time
The Effective Management of TimeThe Effective Management of Time
The Effective Management of Time
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
Microsoft project 2010
Microsoft project 2010Microsoft project 2010
Microsoft project 2010
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two Days
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)
 
RajendraLK_13_Years_PeopleSoft
RajendraLK_13_Years_PeopleSoftRajendraLK_13_Years_PeopleSoft
RajendraLK_13_Years_PeopleSoft
 

Plus de CA Technologies

CA Mainframe Resource Intelligence
CA Mainframe Resource IntelligenceCA Mainframe Resource Intelligence
CA Mainframe Resource IntelligenceCA Technologies
 
Mainframe as a Service: Sample a Buffet of IBM z/OS® Platform Excellence
Mainframe as a Service: Sample a Buffet of IBM z/OS® Platform ExcellenceMainframe as a Service: Sample a Buffet of IBM z/OS® Platform Excellence
Mainframe as a Service: Sample a Buffet of IBM z/OS® Platform ExcellenceCA Technologies
 
Case Study: How CA Went From 40 Days to Three Days Building Crystal-Clear Tes...
Case Study: How CA Went From 40 Days to Three Days Building Crystal-Clear Tes...Case Study: How CA Went From 40 Days to Three Days Building Crystal-Clear Tes...
Case Study: How CA Went From 40 Days to Three Days Building Crystal-Clear Tes...CA Technologies
 
Case Study: How The Home Depot Built Quality Into Software Development
Case Study: How The Home Depot Built Quality Into Software DevelopmentCase Study: How The Home Depot Built Quality Into Software Development
Case Study: How The Home Depot Built Quality Into Software DevelopmentCA Technologies
 
Pre-Con Ed: Privileged Identity Governance: Are You Certifying Privileged Use...
Pre-Con Ed: Privileged Identity Governance: Are You Certifying Privileged Use...Pre-Con Ed: Privileged Identity Governance: Are You Certifying Privileged Use...
Pre-Con Ed: Privileged Identity Governance: Are You Certifying Privileged Use...CA Technologies
 
Case Study: Privileged Access in a World on Time
Case Study: Privileged Access in a World on TimeCase Study: Privileged Access in a World on Time
Case Study: Privileged Access in a World on TimeCA Technologies
 
Case Study: How SGN Used Attack Path Mapping to Control Privileged Access in ...
Case Study: How SGN Used Attack Path Mapping to Control Privileged Access in ...Case Study: How SGN Used Attack Path Mapping to Control Privileged Access in ...
Case Study: How SGN Used Attack Path Mapping to Control Privileged Access in ...CA Technologies
 
Case Study: Putting Citizens at The Center of Digital Government
Case Study: Putting Citizens at The Center of Digital GovernmentCase Study: Putting Citizens at The Center of Digital Government
Case Study: Putting Citizens at The Center of Digital GovernmentCA Technologies
 
Making Security Work—Implementing a Transformational Security Program
Making Security Work—Implementing a Transformational Security ProgramMaking Security Work—Implementing a Transformational Security Program
Making Security Work—Implementing a Transformational Security ProgramCA Technologies
 
Keynote: Making Security a Competitive Advantage
Keynote: Making Security a Competitive AdvantageKeynote: Making Security a Competitive Advantage
Keynote: Making Security a Competitive AdvantageCA Technologies
 
Emerging Managed Services Opportunities in Identity and Access Management
Emerging Managed Services Opportunities in Identity and Access ManagementEmerging Managed Services Opportunities in Identity and Access Management
Emerging Managed Services Opportunities in Identity and Access ManagementCA Technologies
 
The Unmet Demand for Premium Cloud Monitoring Services—and How Service Provid...
The Unmet Demand for Premium Cloud Monitoring Services—and How Service Provid...The Unmet Demand for Premium Cloud Monitoring Services—and How Service Provid...
The Unmet Demand for Premium Cloud Monitoring Services—and How Service Provid...CA Technologies
 
Leveraging Monitoring Governance: How Service Providers Can Boost Operational...
Leveraging Monitoring Governance: How Service Providers Can Boost Operational...Leveraging Monitoring Governance: How Service Providers Can Boost Operational...
Leveraging Monitoring Governance: How Service Providers Can Boost Operational...CA Technologies
 
The Next Big Service Provider Opportunity—Beyond Infrastructure: Architecting...
The Next Big Service Provider Opportunity—Beyond Infrastructure: Architecting...The Next Big Service Provider Opportunity—Beyond Infrastructure: Architecting...
The Next Big Service Provider Opportunity—Beyond Infrastructure: Architecting...CA Technologies
 
Application Experience Analytics Services: The Strategic Digital Transformati...
Application Experience Analytics Services: The Strategic Digital Transformati...Application Experience Analytics Services: The Strategic Digital Transformati...
Application Experience Analytics Services: The Strategic Digital Transformati...CA Technologies
 
Application Experience Analytics Services: The Strategic Digital Transformati...
Application Experience Analytics Services: The Strategic Digital Transformati...Application Experience Analytics Services: The Strategic Digital Transformati...
Application Experience Analytics Services: The Strategic Digital Transformati...CA Technologies
 
Strategic Direction Session: Deliver Next-Gen IT Ops with CA Mainframe Operat...
Strategic Direction Session: Deliver Next-Gen IT Ops with CA Mainframe Operat...Strategic Direction Session: Deliver Next-Gen IT Ops with CA Mainframe Operat...
Strategic Direction Session: Deliver Next-Gen IT Ops with CA Mainframe Operat...CA Technologies
 
Strategic Direction Session: Enhancing Data Privacy with Data-Centric Securit...
Strategic Direction Session: Enhancing Data Privacy with Data-Centric Securit...Strategic Direction Session: Enhancing Data Privacy with Data-Centric Securit...
Strategic Direction Session: Enhancing Data Privacy with Data-Centric Securit...CA Technologies
 
Blockchain: Strategies for Moving From Hype to Realities of Deployment
Blockchain: Strategies for Moving From Hype to Realities of DeploymentBlockchain: Strategies for Moving From Hype to Realities of Deployment
Blockchain: Strategies for Moving From Hype to Realities of DeploymentCA Technologies
 
Establish Digital Trust as the Currency of Digital Enterprise
Establish Digital Trust as the Currency of Digital EnterpriseEstablish Digital Trust as the Currency of Digital Enterprise
Establish Digital Trust as the Currency of Digital EnterpriseCA Technologies
 

Plus de CA Technologies (20)

CA Mainframe Resource Intelligence
CA Mainframe Resource IntelligenceCA Mainframe Resource Intelligence
CA Mainframe Resource Intelligence
 
Mainframe as a Service: Sample a Buffet of IBM z/OS® Platform Excellence
Mainframe as a Service: Sample a Buffet of IBM z/OS® Platform ExcellenceMainframe as a Service: Sample a Buffet of IBM z/OS® Platform Excellence
Mainframe as a Service: Sample a Buffet of IBM z/OS® Platform Excellence
 
Case Study: How CA Went From 40 Days to Three Days Building Crystal-Clear Tes...
Case Study: How CA Went From 40 Days to Three Days Building Crystal-Clear Tes...Case Study: How CA Went From 40 Days to Three Days Building Crystal-Clear Tes...
Case Study: How CA Went From 40 Days to Three Days Building Crystal-Clear Tes...
 
Case Study: How The Home Depot Built Quality Into Software Development
Case Study: How The Home Depot Built Quality Into Software DevelopmentCase Study: How The Home Depot Built Quality Into Software Development
Case Study: How The Home Depot Built Quality Into Software Development
 
Pre-Con Ed: Privileged Identity Governance: Are You Certifying Privileged Use...
Pre-Con Ed: Privileged Identity Governance: Are You Certifying Privileged Use...Pre-Con Ed: Privileged Identity Governance: Are You Certifying Privileged Use...
Pre-Con Ed: Privileged Identity Governance: Are You Certifying Privileged Use...
 
Case Study: Privileged Access in a World on Time
Case Study: Privileged Access in a World on TimeCase Study: Privileged Access in a World on Time
Case Study: Privileged Access in a World on Time
 
Case Study: How SGN Used Attack Path Mapping to Control Privileged Access in ...
Case Study: How SGN Used Attack Path Mapping to Control Privileged Access in ...Case Study: How SGN Used Attack Path Mapping to Control Privileged Access in ...
Case Study: How SGN Used Attack Path Mapping to Control Privileged Access in ...
 
Case Study: Putting Citizens at The Center of Digital Government
Case Study: Putting Citizens at The Center of Digital GovernmentCase Study: Putting Citizens at The Center of Digital Government
Case Study: Putting Citizens at The Center of Digital Government
 
Making Security Work—Implementing a Transformational Security Program
Making Security Work—Implementing a Transformational Security ProgramMaking Security Work—Implementing a Transformational Security Program
Making Security Work—Implementing a Transformational Security Program
 
Keynote: Making Security a Competitive Advantage
Keynote: Making Security a Competitive AdvantageKeynote: Making Security a Competitive Advantage
Keynote: Making Security a Competitive Advantage
 
Emerging Managed Services Opportunities in Identity and Access Management
Emerging Managed Services Opportunities in Identity and Access ManagementEmerging Managed Services Opportunities in Identity and Access Management
Emerging Managed Services Opportunities in Identity and Access Management
 
The Unmet Demand for Premium Cloud Monitoring Services—and How Service Provid...
The Unmet Demand for Premium Cloud Monitoring Services—and How Service Provid...The Unmet Demand for Premium Cloud Monitoring Services—and How Service Provid...
The Unmet Demand for Premium Cloud Monitoring Services—and How Service Provid...
 
Leveraging Monitoring Governance: How Service Providers Can Boost Operational...
Leveraging Monitoring Governance: How Service Providers Can Boost Operational...Leveraging Monitoring Governance: How Service Providers Can Boost Operational...
Leveraging Monitoring Governance: How Service Providers Can Boost Operational...
 
The Next Big Service Provider Opportunity—Beyond Infrastructure: Architecting...
The Next Big Service Provider Opportunity—Beyond Infrastructure: Architecting...The Next Big Service Provider Opportunity—Beyond Infrastructure: Architecting...
The Next Big Service Provider Opportunity—Beyond Infrastructure: Architecting...
 
Application Experience Analytics Services: The Strategic Digital Transformati...
Application Experience Analytics Services: The Strategic Digital Transformati...Application Experience Analytics Services: The Strategic Digital Transformati...
Application Experience Analytics Services: The Strategic Digital Transformati...
 
Application Experience Analytics Services: The Strategic Digital Transformati...
Application Experience Analytics Services: The Strategic Digital Transformati...Application Experience Analytics Services: The Strategic Digital Transformati...
Application Experience Analytics Services: The Strategic Digital Transformati...
 
Strategic Direction Session: Deliver Next-Gen IT Ops with CA Mainframe Operat...
Strategic Direction Session: Deliver Next-Gen IT Ops with CA Mainframe Operat...Strategic Direction Session: Deliver Next-Gen IT Ops with CA Mainframe Operat...
Strategic Direction Session: Deliver Next-Gen IT Ops with CA Mainframe Operat...
 
Strategic Direction Session: Enhancing Data Privacy with Data-Centric Securit...
Strategic Direction Session: Enhancing Data Privacy with Data-Centric Securit...Strategic Direction Session: Enhancing Data Privacy with Data-Centric Securit...
Strategic Direction Session: Enhancing Data Privacy with Data-Centric Securit...
 
Blockchain: Strategies for Moving From Hype to Realities of Deployment
Blockchain: Strategies for Moving From Hype to Realities of DeploymentBlockchain: Strategies for Moving From Hype to Realities of Deployment
Blockchain: Strategies for Moving From Hype to Realities of Deployment
 
Establish Digital Trust as the Currency of Digital Enterprise
Establish Digital Trust as the Currency of Digital EnterpriseEstablish Digital Trust as the Currency of Digital Enterprise
Establish Digital Trust as the Currency of Digital Enterprise
 

Dernier

08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 

Dernier (20)

08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 

MS Project Integration: Tips, Tricks and What's New for You

  • 1. ca Intellicenter MS Project Integration: Tips, Tricks and What's New for You Mindy Calderon Senior Instructor, North America CA Technologies ICX17E #CAWorld
  • 2. Abstract  Have you scheduled in Microsoft Project (MSP) and are now presented with the "Tasks" to maintain a schedule in CA Clarity? Is your organization using CA Clarity but still wants to schedule in MS Project? Have you noticed that the logic in how CA Clarity schedules is different in MS Project? And most importantly - wouldn't it be awesome to be able to explain why CA Clarity and MS Project behave differently but ultimately get you the same result? The session will show you where and how MSP and CA Clarity bi-directionally map data, how to create and manage tasks, assignments and scheduling, as well as updating task status and work. It includes a broad discussion where and when data should be entered in Clarity and MS Project, on defining data elements and how to capture them. Mindy Calderon CA Technologies Senior Instructor 2 © 2014 CA. ALL RIGHTS RESERVED.
  • 3. Agenda INTEGRATION OVERVIEW CUSTOM VIEWS WORK BREAKDOWN STRUCTURE RESOURCES AND MS PROJECT Q & A 3 © 2014 CA. ALL RIGHTS RESERVED.
  • 4. Summary A Few Words to Describe MS Project Integration with Clarity Results MS Project and CA Clarity PPM bi-directionally maps data, manages tasks, assignments and scheduling as well as updating task status. The Clarity project acts as the ‘umbrella’ for PM methodology . The result is a project that follows Project Management and Scheduling standards. 4 © 2014 CA. ALL RIGHTS RESERVED.
  • 5. Definitions INTEGRATION – BIDIRECTIONAL DATA FLOW USING NEW XML DRIVER METHODOLOGY – CONSISTENT AND REPEATABLE SCHEDULING AND MANAGING PROCESSES * * This is NOT a Technical Session: Understand from a Functional Perspective 5 © 2014 CA. ALL RIGHTS RESERVED.
  • 7. Identify the MS Project Integration  Schedule Projects – Microsoft Project  Set Scheduler Format attribute default to Microsoft Project  PICK ONE AND STICK WITH IT! – Per project 7 © 2014 CA. ALL RIGHTS RESERVED.
  • 8. Identify and Install the MSP Interface 8 © 2014 CA. ALL RIGHTS RESERVED.
  • 9. Bi-Directional  New xml file – same location as the .mpp file  Usually in the My Documents folder  Supportable – old integration no longer supported by Microsoft  When you launch a plan from the CA Clarity PPM screen, it exports this plan to your local client system.  After you complete updating your session from within Microsoft Project, you will select Save from the Clarity Integration toolbar to retain your updates 9 © 2014 CA. ALL RIGHTS RESERVED.
  • 10. Install the MSP Interface Tips 10 © 2014 CA. ALL RIGHTS RESERVED.
  • 11. Set Defaults and Options 11 © 2014 CA. ALL RIGHTS RESERVED.
  • 12. Set Defaults and Options Continued  Tips – At a minimum, you must set the File – Project Option defaults at the application level – Additionally, you will want to check and modify these settings on the individual projects that were created before you adjusted these File – Project Option defaults – These projects would have inherited the former default settings – Application Level Defaults allow all new projects to inherit the default settings. – Setting should also be reset for Legacy projects that are being brought into CA Clarity PPM 12 © 2014 CA. ALL RIGHTS RESERVED.
  • 13. Identify Field Mappings 13 © 2014 CA. ALL RIGHTS RESERVED.
  • 14. Custom Views and Creating a Project
  • 15. Custom Views  Gantt Chart View ̶ Add the Key Task Column ̶ Add the Charge Code Column – Only if you let Users select  Task Usage View ̶ actual work ̶ remaining  Custom View ̶ Combined View  Gantt Chart on the top  Task Usage on bottom Modify Existing Views to Create Custom Views 15 © 2014 CA. ALL RIGHTS RESERVED.
  • 16. Create Projects – RULE OF THUMB  Anything on the Properties Tab and Team Tab – Enter/Edit/Update in CA Clarity  Anything on the Tasks Tab – Enter/Edit/Update in MS Project Anything on the Tasks Tab Enter/Edit/Update in MS Project 16 © 2014 CA. ALL RIGHTS RESERVED.
  • 17. Resources and MS Project
  • 18. Resources and MS Project  Staff a Plan – Should ALWAYS be done in CA Clarity – Resource Allocation button Holistic View of Availability Resource Planning Views 18 © 2014 CA. ALL RIGHTS RESERVED.
  • 19. The Four (4) A’s  Availability  Allocation  Assignment  Actuals Holistic View of Availability and Allocation Resource Planning Views 19 © 2014 CA. ALL RIGHTS RESERVED.
  • 20. Work Breakdown Structure There are often misunderstandings about the meanings of the terms “duration” and “work” A task has duration amount and work amount, which may not always be equivalent values
  • 21. Define Work, Units and Duration  For a Fixed Units task, Microsoft Project recalculates Duration when you overwrite the Fixed Units value  For a Fixed Duration task, Microsoft Project recalculates Work when you overwrite the Fixed Duration value  For a Fixed Work task, Microsoft Project recalculates Duration when you overwrite the Fixed Work value 21 © 2014 CA. ALL RIGHTS RESERVED.
  • 22. Identify Task Management Guidelines Terminology Differences Between CA Clarity PPM and Microsoft Project 22 © 2014 CA. ALL RIGHTS RESERVED.
  • 23. Identify Task Management Guidelines Terminology Differences Between CA Clarity PPM and Microsoft Project Continued 23 © 2014 CA. ALL RIGHTS RESERVED.
  • 24. Determine the Schedule  Some of the common elements of Project Management get a bit more complicated when using CA Clarity and Microsoft Project together  Status = Complete – Microsoft Project  Zero out remaining work for all resource assignments – CA Clarity 24 © 2014 CA. ALL RIGHTS RESERVED.  Zero-out the Estimate to Complete value, select ‘Completed’ from the drop-down in the ‘Status’ field  Remaining Work & Pending Estimate To Complete – Entry Precedence – Work Contour – Summary Tasks – Blank Task Names
  • 26. Baseline the Project  A Baseline will create a point-in-time capture of your project plan that you can refer to, and measure against – Baselines can include either the full or partial project WBS  Update to existing baselines – Full baseline – Update partial (tasks) baseline 26 © 2014 CA. ALL RIGHTS RESERVED.
  • 27. Baseline the Project  CA Clarity PPM can only have one Baseline active, but Microsoft Project can view several at a time  Microsoft Project can store 11 baselines, while CA Clarity PPM can store as many as you need – If there are more than 11 project baselines stored in CA Clarity PPM, the latest 11 will download to Microsoft Project when you open the project  CA Clarity PPM has security rights associated with creating and modifying baselines – you will still be able to run the baseline functionality in Microsoft Project, but the data will not be saved to CA Clarity PPM 27 © 2014 CA. ALL RIGHTS RESERVED.
  • 28. Define Track Mode Settings  This setting permits or restricts a 28 © 2014 CA. ALL RIGHTS RESERVED. specific project from accepting actuals from a timesheet and/or permits the project manager to enter actuals directly into the project plan  The Track Mode is found in two locations: – Project level: Properties > Schedule – Resource level: Properties
  • 29. Define Track Mode Settings  The following chart contains rules surrounding the capture of actuals using CA Clarity PPM Timesheets in conjunction with Microsoft Project 29 © 2014 CA. ALL RIGHTS RESERVED.
  • 30. Tips  Resources can be open for time entry at the resource, project and project assignment level. If a resource is not open for time entry in all three places, they are not able to use CA Clarity PPM timesheets.  Time periods should be created and status (open or closed) should be managed by an application administrator  Timesheets are submitted, approved and posted in CA Clarity PPM Timesheets – only posted timesheets appear as actuals – Actuals on Timesheets, which have been saved but not yet posted, will appear as Pending Actuals in Microsoft Project. These can be viewed using MSP mapping – Do not update Actuals in Microsoft Project if the Track Mode is Clarity or Other 30 © 2014 CA. ALL RIGHTS RESERVED.
  • 31. Apply Actuals  Be Vigilant on Timesheets – When work begins on the project, actuals will begin to be recorded against the plan – Impress upon your team members to track their time accurately and on the appropriate day or your plan‘s finish date may unnecessarily be delayed  Tasks not reported on a time sheet may change due to the posting of the assigned resource‘s time sheet. CA Clarity PPM assumes that a person's time sheet is a complete accounting of the project work they completed that week. If a scheduled task did not appear on the time sheet, it implies no work was completed by the resource on that task, and must be rescheduled for the following week or beyond 31 © 2014 CA. ALL RIGHTS RESERVED.
  • 32. Pending Actuals  There are three possible values you may see: – ‘0’ indicates that you are looking at a Summary task – ‘-1’ indicates that there are no Pending Actuals entered on the timesheet as of that day – A value other than ‘0’ or ‘-1’ indicates that the value you see is the team member’s cumulative Pending Actuals up through that day in that time period 32 © 2014 CA. ALL RIGHTS RESERVED.
  • 33. Pending Estimates  There are three possible values you may see: – ‘0’ indicates that you are looking at a Summary task – ‘-1’ indicates that a Pending Estimate has not been entered for the task – A value other than ‘0’ or ‘-1’ indicates that the team member has entered a Pending Estimate to identify a revision to the remaining estimate for the task 33 © 2014 CA. ALL RIGHTS RESERVED.
  • 34. Apply Actuals 34 © 2014 CA. ALL RIGHTS RESERVED.
  • 35. % Work Complete vs % Complete  % Work Complete – % Work Complete is set to 100% automatically if Microsoft Project detects the task is complete via calculations.  Once the Remaining Work has been reduced to zero, either manually or by the actuals that have been booked, the system sets the % Work Complete to 100%.  It is calculated based on Actuals and Remaining Work  % Complete – % Complete set by the Project Manager’s actions. – It is set to 100% when the Project Manager says the 35 © 2014 CA. ALL RIGHTS RESERVED. task is complete by manually changing the %. – CA Clarity PPM automatically sets the value to 1% for Started Tasks and the Project Manager sets it to 100% when task is completed. – It is not calculated based on Actuals  Summary task % Complete can be calculated by running the Update % Complete Job
  • 36. For More Information Insert appropriate screenshot and text overlay from following “More Info Graphics” slide here; Management Cloud ensure it links to correct page To learn more about Management Cloud, please visit: http://bit.ly/1wEnPhz 36 © 2014 CA. ALL RIGHTS RESERVED.
  • 37. For Informational Purposes Only Terms of this Presentation © 2014 CA. All rights reserved. All trademarks referenced herein belong to their respective companies. This presentation provided at CA World 2014 is intended for information purposes only and does not form any type of warranty. Some of the specific slides with customer references relate to customer's specific use and experience of CA products and solutions so actual results may vary. 37 © 2014 CA. ALL RIGHTS RESERVED.