1. Digital Engineering
Balfour Beatty - Major Projects - Highways
Snapfile - OnTrack
Harry Parnell –
BIM Manager Highways and Infrastructure
2. M25 Smart Motorways - the project
2
Introduction
The M25 DBFO will be providing additional capacity on two sections of the M25.
The works will be between J5 and J7 (Section 2) and J23 to J27 (Section 5). The
works will be undertaken to the new HA standard for Managed Motorways called
MM- ALR (IAN 161/12).
Key features of the scheme:
a.) No Hardshoulder – ERA at 2.5km centres
b.) MS4 communication at max 1.5km centres
c.) Gateway and Enforcement Gantries
d.) CSB in central reserve
6. Management of Structure of Green File Quality Documents
– Snapfile OnTrack – Managing Quality and Outstanding Work
– Management – 0 defects – 0 pieces of Outstanding works
– Report – Manage (Allocate) – Repair – Signoff (Photos/data collection)
– Engineers, Inspectors, Supply Chain all on the system
Digitizing Processes for Outstanding Works /
Supply Chain / Sign Off
6
8. Collaboration
– Real time reporting also accelerated and improved the quality of
collaboration between site and office based staff
Sustainable
– Share of data capture more efficiently,
– Reducing trips travelling to and from site (full team reporting)
Time
– Helped towards the project being delivered 26 weeks ahead of
programme
Cost
– Estimated time Cost savings 2 – 3 weeks (£215,000 per week)
– Productivity with Supply Chain
– Traffic Management costs £10,000 versus £690 labour materials
Safety
– Engineers and Supply Chain fully briefed location / information
before going out on site to carry out the works
– Reduced times in and out of traffic management
Conclusion
8