Workplace Information
• Major Enterprise Projects
• Second Rotation as a DTE Energy Summer Student
• Expansion of Gas Compression and Transmission Systems in
Michigan
• Supervisors:
– Brad Surface: Platform Manager
– Brian Carr: Project Manager - Construction
Work Responsibility Information
• DTE Gas NEXUS Related
Expansion
– Willow Gate Station
– Willow Run Compressor Station
– Milford Compressor Station
Key Learnings
• CAPM Certification
– Certified Associate in Project
Management
• Demolition at Willow Gate Station
– Site Visitation
– Project Cost Estimate
– Develop Scope of Work
• Invaluable Meetings and Site
Walk-throughs
– Willow Gate Station Phase I
Pre-Construction Meeting
Process Improvements
• DTE Gas Equipment and Material Vendor List
– Refined a Vendor List to be used across MEP – Gas
– Can be Sorted by Utility or Material Category
– Contains All Contact Information for Ease of Communication
– 200+ Contacts
Process Improvements
• Engineering Item Tracking with Revisions
– Updated Item Tracking Log to Include Weekly History of Revisions
made by DTE Gas and EN Engineering
– Allows Management to Hold Engineers Accountable for Schedule
Variance
– Management can Review Performance of Team more smoothly
Questions?

Contenu connexe

Tendances

F1_Optimization_CTMC
F1_Optimization_CTMCF1_Optimization_CTMC
F1_Optimization_CTMC
vargasm1
 
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
GreenData.IO
 
CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar Behera
Tarun Behera
 
Constructability Report Grove 2.0
Constructability Report Grove 2.0Constructability Report Grove 2.0
Constructability Report Grove 2.0
Jamal Nelson, CCM
 
FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)
FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)
FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)
Mandeep Kaur
 
Mansour l menarid-presentation-rbm-m&e
Mansour l menarid-presentation-rbm-m&eMansour l menarid-presentation-rbm-m&e
Mansour l menarid-presentation-rbm-m&e
groundwatercop
 
Menarid: Fourth learning workshop
Menarid: Fourth learning workshopMenarid: Fourth learning workshop
Menarid: Fourth learning workshop
ICARDA
 
KIM ALLISON KELLEY 2016 - NEW - Linkedin Resume as 10262016
KIM ALLISON KELLEY 2016 - NEW - Linkedin Resume as 10262016KIM ALLISON KELLEY 2016 - NEW - Linkedin Resume as 10262016
KIM ALLISON KELLEY 2016 - NEW - Linkedin Resume as 10262016
Kim Kelley
 

Tendances (16)

F1_Optimization_CTMC
F1_Optimization_CTMCF1_Optimization_CTMC
F1_Optimization_CTMC
 
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
DeltaBahn - Improving Safety & Productivity in the American Oil Industry v2
 
May 20 Keystone fm+
May 20   Keystone fm+May 20   Keystone fm+
May 20 Keystone fm+
 
CV_Tarun Kumar Behera
CV_Tarun Kumar BeheraCV_Tarun Kumar Behera
CV_Tarun Kumar Behera
 
Daily Routine Of a Product Manager
Daily Routine Of a Product ManagerDaily Routine Of a Product Manager
Daily Routine Of a Product Manager
 
Constructability Report Grove 2.0
Constructability Report Grove 2.0Constructability Report Grove 2.0
Constructability Report Grove 2.0
 
Updated CV
Updated CVUpdated CV
Updated CV
 
Final April 18 LMKAIZEN
Final April 18 LMKAIZENFinal April 18 LMKAIZEN
Final April 18 LMKAIZEN
 
Methodologies of Project Progress Measurement
Methodologies of Project Progress MeasurementMethodologies of Project Progress Measurement
Methodologies of Project Progress Measurement
 
FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)
FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)
FANSHAWE-WALKWAY-By-Project-Revolutions_Latest (2)
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
205210 project driven supply chain (pdsc)
205210 project driven supply chain (pdsc)205210 project driven supply chain (pdsc)
205210 project driven supply chain (pdsc)
 
Mansour l menarid-presentation-rbm-m&e
Mansour l menarid-presentation-rbm-m&eMansour l menarid-presentation-rbm-m&e
Mansour l menarid-presentation-rbm-m&e
 
Menarid: Fourth learning workshop
Menarid: Fourth learning workshopMenarid: Fourth learning workshop
Menarid: Fourth learning workshop
 
Audit Funding Program Update
Audit Funding Program UpdateAudit Funding Program Update
Audit Funding Program Update
 
KIM ALLISON KELLEY 2016 - NEW - Linkedin Resume as 10262016
KIM ALLISON KELLEY 2016 - NEW - Linkedin Resume as 10262016KIM ALLISON KELLEY 2016 - NEW - Linkedin Resume as 10262016
KIM ALLISON KELLEY 2016 - NEW - Linkedin Resume as 10262016
 

En vedette

CourseProject_j.james-delarosa
CourseProject_j.james-delarosaCourseProject_j.james-delarosa
CourseProject_j.james-delarosa
Jess James
 
HOG_SPRING_2015_EN
HOG_SPRING_2015_ENHOG_SPRING_2015_EN
HOG_SPRING_2015_EN
Duarte Pita
 
Product Catalogue for International Businesses
Product Catalogue for International BusinessesProduct Catalogue for International Businesses
Product Catalogue for International Businesses
Ruairidh. Jackson
 

En vedette (16)

UBICACIÓN CENTRO EDUCACIÓN INFANTIL
UBICACIÓN CENTRO EDUCACIÓN INFANTILUBICACIÓN CENTRO EDUCACIÓN INFANTIL
UBICACIÓN CENTRO EDUCACIÓN INFANTIL
 
Attractiveness fit webinar
Attractiveness fit webinarAttractiveness fit webinar
Attractiveness fit webinar
 
Location Assessment- Sourcing In India
Location Assessment- Sourcing In IndiaLocation Assessment- Sourcing In India
Location Assessment- Sourcing In India
 
Sourcing in argentina – story of a struggling empire.ebook
Sourcing in argentina – story of a struggling empire.ebookSourcing in argentina – story of a struggling empire.ebook
Sourcing in argentina – story of a struggling empire.ebook
 
A Three-Stage Approach to Effective Contract Renegotiations
A Three-Stage Approach to Effective Contract RenegotiationsA Three-Stage Approach to Effective Contract Renegotiations
A Three-Stage Approach to Effective Contract Renegotiations
 
CourseProject_j.james-delarosa
CourseProject_j.james-delarosaCourseProject_j.james-delarosa
CourseProject_j.james-delarosa
 
Ciudadanías, observación barrio Dindalito
Ciudadanías, observación barrio DindalitoCiudadanías, observación barrio Dindalito
Ciudadanías, observación barrio Dindalito
 
my resume
my resumemy resume
my resume
 
How to Source Digital Initiatives to Drive Revenue Generation
How to Source Digital Initiatives to Drive Revenue GenerationHow to Source Digital Initiatives to Drive Revenue Generation
How to Source Digital Initiatives to Drive Revenue Generation
 
How Will These Global Trends Affect Your Operations?
How Will These Global Trends Affect Your Operations?How Will These Global Trends Affect Your Operations?
How Will These Global Trends Affect Your Operations?
 
Selecting a Sourcing Location in Latin America
Selecting a Sourcing Location in Latin AmericaSelecting a Sourcing Location in Latin America
Selecting a Sourcing Location in Latin America
 
HOG_SPRING_2015_EN
HOG_SPRING_2015_ENHOG_SPRING_2015_EN
HOG_SPRING_2015_EN
 
reflejos
reflejosreflejos
reflejos
 
What to Watch: Global Risk Update, Q1 2015
What to Watch: Global Risk Update, Q1 2015What to Watch: Global Risk Update, Q1 2015
What to Watch: Global Risk Update, Q1 2015
 
Product Catalogue for International Businesses
Product Catalogue for International BusinessesProduct Catalogue for International Businesses
Product Catalogue for International Businesses
 
Assessing Your Supply Risk Maturity to Enhance Overall Performance
Assessing Your Supply Risk Maturity to Enhance Overall PerformanceAssessing Your Supply Risk Maturity to Enhance Overall Performance
Assessing Your Supply Risk Maturity to Enhance Overall Performance
 

Similaire à Summer Student Presentation 2016 Charlie Morgan

Drew Whitney Final Presentation
Drew Whitney Final PresentationDrew Whitney Final Presentation
Drew Whitney Final Presentation
Drew Whitney
 
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
Egyptian Engineers Association
 
Project management
Project managementProject management
Project management
Srija Kumar
 
Kalyan Chunchu Resume
Kalyan Chunchu Resume Kalyan Chunchu Resume
Kalyan Chunchu Resume
Kalyan Chunchu
 
ayed cv.newest one 23.11.2011
ayed cv.newest one 23.11.2011ayed cv.newest one 23.11.2011
ayed cv.newest one 23.11.2011
Iyad Hassan
 
Resume 2016 - Product Scheduler
Resume 2016 - Product SchedulerResume 2016 - Product Scheduler
Resume 2016 - Product Scheduler
Tim Chau
 

Similaire à Summer Student Presentation 2016 Charlie Morgan (20)

2022 presentation on Caltrans sampling and test methods
2022 presentation on Caltrans sampling and test methods2022 presentation on Caltrans sampling and test methods
2022 presentation on Caltrans sampling and test methods
 
Matt's New Resume
Matt's New ResumeMatt's New Resume
Matt's New Resume
 
Local Agency Asphalt Specification
Local Agency Asphalt SpecificationLocal Agency Asphalt Specification
Local Agency Asphalt Specification
 
Drew Whitney Final Presentation
Drew Whitney Final PresentationDrew Whitney Final Presentation
Drew Whitney Final Presentation
 
Caltrans Independent Assurance Update for stakeholders
Caltrans Independent Assurance Update for stakeholdersCaltrans Independent Assurance Update for stakeholders
Caltrans Independent Assurance Update for stakeholders
 
Technical evaluation in cpv systems
Technical evaluation in cpv systemsTechnical evaluation in cpv systems
Technical evaluation in cpv systems
 
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
 
The Commercial Energy Codes Support Program
The Commercial Energy Codes Support ProgramThe Commercial Energy Codes Support Program
The Commercial Energy Codes Support Program
 
205740 integration of the southern delivery system
205740 integration of the southern delivery system205740 integration of the southern delivery system
205740 integration of the southern delivery system
 
Project management
Project managementProject management
Project management
 
CWood-Resume
CWood-ResumeCWood-Resume
CWood-Resume
 
Kalyan Chunchu Resume
Kalyan Chunchu Resume Kalyan Chunchu Resume
Kalyan Chunchu Resume
 
Thermo Fischer Scientific - Marnus Du Toit - Plastic Engineering Day 2021
Thermo Fischer Scientific - Marnus Du Toit - Plastic Engineering Day 2021Thermo Fischer Scientific - Marnus Du Toit - Plastic Engineering Day 2021
Thermo Fischer Scientific - Marnus Du Toit - Plastic Engineering Day 2021
 
ayed cv.newest one 23.11.2011
ayed cv.newest one 23.11.2011ayed cv.newest one 23.11.2011
ayed cv.newest one 23.11.2011
 
Ms Julie Owen key note address on LA Metro
Ms Julie Owen key note address on LA MetroMs Julie Owen key note address on LA Metro
Ms Julie Owen key note address on LA Metro
 
Caltrans Construction Materials Perspective
Caltrans Construction Materials PerspectiveCaltrans Construction Materials Perspective
Caltrans Construction Materials Perspective
 
Prakash Resume
Prakash ResumePrakash Resume
Prakash Resume
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Resume 2016 - Product Scheduler
Resume 2016 - Product SchedulerResume 2016 - Product Scheduler
Resume 2016 - Product Scheduler
 
Development Services Technology Update
Development Services Technology UpdateDevelopment Services Technology Update
Development Services Technology Update
 

Summer Student Presentation 2016 Charlie Morgan

  • 1. Summer Student Presentation Charlie Morgan Major Enterprise Projects July 25th, 2016
  • 2. Education • Michigan State University • Class Standing: Junior • Major: Applied Engineering Sciences – Concentration in Technical Sales • Graduation: May 2018 2
  • 3. Workplace Information • Major Enterprise Projects • Second Rotation as a DTE Energy Summer Student • Expansion of Gas Compression and Transmission Systems in Michigan • Supervisors: – Brad Surface: Platform Manager – Brian Carr: Project Manager - Construction
  • 4. Work Responsibility Information • DTE Gas NEXUS Related Expansion – Willow Gate Station – Willow Run Compressor Station – Milford Compressor Station
  • 5. Key Learnings • CAPM Certification – Certified Associate in Project Management • Demolition at Willow Gate Station – Site Visitation – Project Cost Estimate – Develop Scope of Work • Invaluable Meetings and Site Walk-throughs – Willow Gate Station Phase I Pre-Construction Meeting
  • 6. Process Improvements • DTE Gas Equipment and Material Vendor List – Refined a Vendor List to be used across MEP – Gas – Can be Sorted by Utility or Material Category – Contains All Contact Information for Ease of Communication – 200+ Contacts
  • 7. Process Improvements • Engineering Item Tracking with Revisions – Updated Item Tracking Log to Include Weekly History of Revisions made by DTE Gas and EN Engineering – Allows Management to Hold Engineers Accountable for Schedule Variance – Management can Review Performance of Team more smoothly

Notes de l'éditeur

  1. Second Rotation – Worked with Wind Development Last Summer under Matt Wagner
  2. NEXUS Gas Transmission Pipeline (255 Miles) Ranging from Kensington, Ohio to Ypsilanti, Michigan. To be completed in 2017. Expansion of stations in order to meet requirements of gas flow volume of 1.5 Billion cubic feet/day and pressure of 858 PSI. WGS: Major Natural gas Hub for DTE Gas located in Southeast Michigan. Interconnect to major interstate pipelines and local Markets. New Equipment includes 3 heaters, pipes, valves, and fittings. WRCS: Compresses gas to assist in transportation of gas to major interstate pipelines and transmission systems. Adding 4 units: 3 reciprocating units and 1 turbine. MCS: Compresses gas to assist in transportation of gas to major interstate pipelines and transmission systems. Adding 3 new compressor units, with a 4th unit as a bid option. (Adding 14 new buildings across all 3 sites, ranging from compression to administration buildings.)
  3. CAPM requires a secondary degree and 23 course hours which were provided by DTE through Aspire. Demo Consultation: Adamo Group and Homrich. Meetings: Professional experience learned through observing how meetings were conducted from Brian and Brad. Walk-throughs of all 3 Stations to learn basics of gas compression and transmission.
  4. Consulting Engineer forwarded weekly Item Tracking Reports to PM with updated predictions of receivables date. Adding an original planned column and revision column shows schedule variance and allows management to review performance more easily. In this example, the RFQ issued completion date was revised and pushed back 7 times for WRCS and MCS, showing inconsistency in performance from DTE Engineers.