SlideShare une entreprise Scribd logo
1  sur  48
Télécharger pour lire hors ligne
BASELINE SCHEDULING BASICS
                                              Part 1: April 5, 2007

                                                             Mark Boe, P.E., PSP
                                                                   Vice President
                                                          Capital Project Management, Inc.
                                                               mboe@cpmiteam.com

                                                               Chris Carson, PSP
                                                              Project Controls Manager
                                                                 Alpha Corporation
                                                        chris.carson@alphacorporation.com




The information in this presentation or publication was developed and prepared by the authors for the purpose of education about the subject. This presentation or
publication does not necessarily reflect the views of the Construction Management Association of America or constitute a position or policy of the Construction
Management Association of America (CMAA). This material was presented with the permission of the authors and is subject to copyright under applicable law. The
information contained herein is presented as descriptive of issues related to the subject at the time it was presented, but it has not been peer reviewed or approved by
CMAA. No part of this presentation or publication is to be reproduced or used without written permission from the author and CMAA.
Baseline Scheduling
How should you benefit from this session?
  Basic understanding of concepts and benefits
  Knowledge of types of schedules
  Understanding of terminology
  Recognition of data and processes needed to
  create schedules
  QC: What makes a good schedule
Introduction - Why Schedule?
Why schedule?
  Why? Benefit to project?
  Benefit to project management?
  Mandated by owner?
  Mandated by contractor influences?
    Senior management, bonding company,
    attorneys, subcontracts, materials release
Introduction - Why Schedule?
  Time = $
    Cost/budget control
    Change management control
  Pure management tool
    Forcing involvement of project management team
    Planning
    Monitoring
    Control
  Subcontractor & resource control
  Owner coordination & control
  Predictions/projections
  Claims avoidance, defend claims,
  documentation
  Specification requirements
Introduction - Background
Background & Types of Scheduling
  Scheduling methodologies
  Types of schedules
  Scheduling terminology
Background - Methodologies
Gantt, Bar Chart, and Line of Balance
Vertical Diagram Method “VDM” or Linear
    Visual system for repetitive tasks
Types of CPM Schedule Formats
  Arrow Diagram Method or “ADM”
    IJ Network
    Activity-on-Arrow
  Precedence Diagram Method “PDM”
    Activity-on-Node
    Current prevalent scheduling methodology
PDM: Typical Precedence
     Relationships

      1             9
          2               10

      3
                    11
          4
                          12

      5   6
                    13
                          14
      7   8
Definitions
Critical Path Method (CPM) – representation of a project
plan by a network that depicts the duration, sequence
and interrelation of the work activities.
Critical Path – longest path (or sequence) of activities,
driven by their relationships, lags, leads, calendars, and
constraints, through the project, that determines the total
duration of the project.
Total Float – the amount of time an activity can slip
without impacting project completion (contingency time).
Logic/Relationship Types – description of the
interrelation between the individual work activities
Introduction - CRITICAL PATH METHOD (CPM)
Sequential                         Relationship Types
                                                                    60




                                                                                  Relationship Types
                        FS                        FS
STUDS                             Electrical RI         Drywall
  20                                      20                20




Concurrent

       STUDS                 FF5




                                                                                     Capital Project Management, Inc.
             20
       SS5
             Electrical RI          FF7
                   20
             SS5
                                                        SS x = Start to Start
                   Drywall
                                                        FF x = Finish to Finish
                             20
                                                        xx 5 = Lag
                                       32
Definitions:
Early Start Date – the earliest date an activity can start,
  based on predecessor logic

Late Start Date – the latest date an activity may start in
  order to complete on time

Float – the number of days between early start and late
   start (or between early and late finish)
CPM Schedule Types
    Feasibility Studies
    Presentation
    Budgeting
    Conceptual or Schematic
    Milestone
    Summary
    Baseline
    Short Interval Look Ahead
.
Sheet 1of 1
Summary Schedule
Basic CPM Scheduling
        Exercise
Forward pass
Backward pass
Derivation of Early dates
Derivation of Late dates
Calculation of Total Float
Calculation of Free Float
CPM Scheduling Exercise
                                 Forward Pass




                                                                                      CPM Scheduling Exercise
    NTP

          1        10       11        15    21         30
    0                                                             31
1                                                                      30
              A                  B               C
              10                 5               10
                            11        20


                                 D




                                                                                      Capital Project Management, Inc.
                                 10



                                           KEY:                   ES – Early Start
    EF(p) + 1 = ES(s)                                             EF – Early Finish
                                                  ES        EF
                                                                  LS – Late Start

    ES + D + 1 = EF                                               LF – Late Finish
                                                            TF
                                                                  DUR – Duration
                                                             LF
                                                  LS              TF – Total Float
                                                       DUR
Forward Pass
    Establishes the Early Start and Early Finish dates




If you don’t want to learn formulas, the forward pass is common sense
identification of start and finish days.

The earliest that Activity B and Activity C can start is on the 11th day, the
day after Activity A finishes. The earliest day that Activity D can start is
on the 21st day, the earliest day after the later that either Activity B or
Activity C can finish.
CPM Scheduling Exercise
                                 Forward Pass




                                                                                      CPM Scheduling Exercise
                                    Backward Pass
    NTP

          1        10       11        15    21         30
                                                                  31
1                                                                      30
              A                  B               C
1                                                                 31   30
              10                 5               10
          1        10       16        20    21         30

                            11        20


                                 D




                                                                                      Capital Project Management, Inc.
                                 10
                            11        20




                                           KEY:                   ES – Early Start
    LS(s) - 1 = LF(p)                                             EF – Early Finish
                                                  ES        EF
                                                                  LS – Late Start

    LF - D + 1 = LS                                               LF – Late Finish
                                                            TF
                                                                  DUR – Duration
                                                             LF
                                                  LS              TF – Total Float
                                                       DUR
Backward Pass
Establishes the Late Finish and Late Start dates




Working from the last day towards the beginning,
both Activity B and C cannot finish any later than the
day before Activity D starts, so both have a Late
Finish of Day 20, the day before Activity D starts on
the 21th day.
CPM Scheduling Exercise
                                                     Forward Pass




                                                                                                           CPM Scheduling Exercise
                                                        Backward Pass
        NTP                                               Float Calculation
                   1          10                11        15     21         30
1                                                                                          30
                        A                            B                C
                              0                           5                 0
1                                                                                          30
                        10                           5                10
                   1          10                16        20     21         30

                                                11        20


                                                     D    0




                                                                                                           Capital Project Management, Inc.
                                                     10
                                                11        20




Description   ES   EF    LS       LF   TF
                                                                KEY:                   ES – Early Start
    A          1   10     1       10   0                                               EF – Early Finish
                                                                       ES        EF
                                                                                       LS – Late Start
    B         11   15    16       20   5
                                                                                       LF – Late Finish
                                                                                 TF
    C         21   30    21       30   0
                                                                                       DUR – Duration
    D         11   20    11       20   0                                          LF
                                                                       LS              TF – Total Float
                                                                            DUR
CRITICAL PATH METHOD (CPM)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30




                                                                                          Time Scaled Logic Diagram
                                                                                   COMP
NTP


           A                                                     C
           10                                                    10




                                B
                                5



                                      D




                                                                                           Capital Project Management, Inc.
                                      10
CPM Schedule Creation
How should we do it?
  Lessons learned (what are typical
  conflicts)
  Schedule design
  Schedule development
  Schedule components
  Schedule logic
  Schedule settings
Typical Areas of Conflict
Stakeholders: Who uses the schedule?
Level of detail
Reasonableness of schedule
Clarity of schedule
Schedule Approval/Non-approval Issue standoff
Failure to Involve major trade Contractors
Failure to include Owner requirements (other
contracts, utilities, commissioning, etc.)
Early Completion Schedules
Ownership of float, contingency time
Schedule Development - Process
Assemble development team
Design the schedule
  Identify Level of detail required
  Identify output needed – Activity Code & WBS structures
  Identify scope of work - Activities (input from subs/primes)
Develop the schedule
  Calculate Durations (input from subs/primes)
  Assign logic (input from subs/primes)
  Input to computer
  Analyze and adjust
Finalize the schedule
  QC checklists & verification
  Seek buy-in and approval (includes team)
  Add resources and costs
Schedule Development -
Owner-Controlled, Design Related
  And Procurement Activities
Treat Owner activities like any other work activities
   Look in Contract for specification requirements
   Submittal approval times – specification or verify
   Consider re-submittal cycle for difficult or highly detailed
   activities
   Include all Owner scope of work (include permits, permanent
   telephone and other utilities, owner supplied equipment,
   other contracts, Health Department approvals, etc.)
Code Owner activities so they can be filtered and tracked
   Owner and Contractor are both interested parties
Ensure the successor activities are accurately defined
   Any delays related to these activities should be captured
   accurately for the protection of both the Owner and the
   Contractor
Schedule Development -
          Feasibility of
       Specified Schedule
Need real commitment to scheduling process
Requirement for schedule to be actually used
during performance
Must have buy-in from PM team, senior
management, subcontractors, suppliers, and
Owner
Must have resources to perform detailed
schedule updates and analyses
  Do it during project ($)
  Do it in claims environment – post project ($$$$)
Schedule Components –
Output - Type of Diagram
Bar Chart
Network Analysis System (CPM)
Most specs require multiple printouts
Require electronic file
Output types insignificant if you get the
disk - electronic file is the only way to go
Still need to understand means &
methods – rationale of construction
2002                                                                                                              2003                                                                      2004
                    JAN      FEB      MAR           APR    MAY       JUN          JUL        AUG            SEP      OCT    NOV      DEC      JAN       FEB     MAR     APR     MAY    JUN          JUL   AUG        SEP         OCT       NOV      DEC       JAN      FEB       MAR


                       0
                    ISSUE BID /        TRAILER                         CIP Foundations                                      Elevated Concrete                 Curtainwall System Installation                                           Acoustical Ceiling &
                    GMP DRAWINGS       MOBILIZATION                                                                         Floor Slabs                                                                                                 Device Installation




                                        0                               0                                                                                                                  0                                                           0
                                     AWARD            START          Shower/Toilet                          Structural Steel                Electrical Rough-in/Systems Cabling         F/R/P SOMD                         Valence H/C Unit         FMS Rough-in
                                     SITEWORK         EXCAVATION     Flange Rough-in - E1                   Erection/Deck/Detailing                                                     - Roof East                        Installation             - Flr.4 West




                               0                  0            0                                        0                                                                                                                                                   0
                            FOUNDATION         Safety       Site Clearing/Utility                    F/R/P SOMD -                 Spray Fireproofing          Alum Windows & Infills                                           Ceramic Tile              Spray Fireproofing
                            PERMIT             Fencing      Demolition                               Flr.1 East                                                                                                                Floors & Ceilings         Install - Flr.4 West




                       0                          0                             0                       0
                    Elec O/H Rough-in          Utility Location &            HVAC Testing            F/R/P SOMD -                   Plumbing Rough-in                                           Caulking & Sealants                              Hardwood Flooring
                    - Flr.1 East               Marking by Others             & Balancing             Flr.1 West                                                                                                                                  Installation




                                                  0            0                                  0                                                                                                                               0




Barchart Schedule
                                               Site/Bldg    Pull Systems Cable                 Spray Fireproofing                    Interior GWB Partitions                                                                   F/R/P SOMD            Doors & Hdwe
                                               Layout       - Flr.4 East                       Install- Bsmt. East                                                                                                             - Roof West           Installation




                                          0                    0                                  0                                                                                                                  0                                 0
                                       Temporay Power       Pull Systems Cable                 Spray Fireproofing                          CMU Masonry & Stonework                                                Stl Deck/Studs/Struc Stl          Spray Fireproofing
                                       Req'd Onsite         - Flr.4 West                       Install- Bsmt. West                                                                                                Detailing - Roof East             Install - Flr.3 West



   With Logic          0                                 0                                                      0                                                                               0                                   0                              0
                    Plumbing Piping                   Excav/Sheet/Shore - (Stm                               Shower/Toilet                 HVAC Rough-in                                     F/R/P/C/S Elevator                  Stl Deck/Studs/Struc Stl       Caulking &
                    In-Wall Rough-in - E1             Tunnel / Scully Hall)                                  Flange Rough-in - E3                                                            Pit/Int. Col. Ftgs - West           Detailing - Roof West          Sealants - East




                        0                                0                            0                                   0                                                                                                              0                        0
                     OH Sanitary Piping               Bulk                         Shower/Toilet                       Form/Reinf/Embeds            EPDM & Slate Siding Roofing Installation                                          Spray Fireproofing       Sprinkler Heads
                     Rough-in - Bsmt East             Excavation                   Flange Rough-in - E4                Footings - West                                                                                                Install - Flr.3 East     - Flr.4 West




                                          0                                         0                                     0                                                                                                              0                        0
                                       Form/Reinf/Embeds                         Shower/Toilet Flange                  Form/Reinf/Cure/Strip           Fire Protection System                                                         Spray Fireproofing       Sprinkler Heads
                                       Footings - East                           Rough-in - Flr.3 West                 Fdn Wall - East                                                                                                Install - Flr.4 East     - Flr.4 East




                                                                                                              BASE                                                                                        Sheet    1 of    2
                    Plot Date        30OCT03                               Activity Bar/Early Dates
                                                                           Critical Activity
                                                                                                                                             Acme Constructors, Inc..
                    Data Date        24APR02                               Progress Bar                                                                                                                                        Date           Revision              Checked   Approved
                    Project Start     4DEC00                               Milestone/Flag Activity
                                                                                                                                       Wala Wala University - New Dormitory
                                                                           Connecting Activity on Sheet x
                    Project Finish   31MAR04    *                x


                                                                                                                                                      TL-14
                    (c) Primavera Systems, Inc.




                                                                                                                                                                               Time Scaled
                                                                                                                                                                              Logic Diagram
Schedule Components -
Type of Diagram (continued.)
Must be clear on what is required
H.I. Homa Co. case
  Contract unclear on whether CPM
  required
  Government’s insistence on CPM
  schedule was constructive change
  entitling contractor to added
  compensation
Schedule Components -
  Number of Activities
Depends on the nature, size and complexity of
the project
Need enough activities to reflect intricacies and
interdependencies
Too few activities will require use of SS and FS
lagged activities; harder to analyze
High level of detail will make updates more time
consuming
High level of detail will allow better monitoring &
updating
Schedule Components -
  Resource Loading
Only way to confirm validity of an activity’s
duration
Resources/Productivity = Duration
Even without resource loading, determination
of durations must be made through resource
calculations (even if based on experience)
Effective use of resource loading requires
detailed schedule
Out of sequence work during updates can
warp resource reports
Schedule Components -
Resource Loading (cont.)
A 5 worker crew, with crew productivity of 4
windows per day will install 40 windows in
10 days
Two 5 worker crews with the same
productivity will install 40 windows in 5
days
Notes should be kept to record how
durations were derived
Keep in mind: 100 crews with productivity
of 4 windows per day will NOT install 400
windows in a day.
Schedule Components –
         Cost Loading
Used for Progress Payments
Owners should retain ability to adjust schedules that
are excessively front loaded
Separate overhead & profit from direct costs
Cost loading lends itself to reasonable scope deletion
with resulting predetermined costs & time
Separate large materials delivery activities so
progress can be monitored (labor & materials
production should be a linear curve)
Use cost metrics (earned value) as another check on
progress evaluation
Update percent complete (track cost) separately from
remaining duration (track time).
Schedule Components - Control
   of Record Schedule and
          Updating
  DON’T OVERWRITE last period schedule!!!
  Who will maintain the schedule?
  Joint updating meetings
  Determine in advance what constitutes
  normal updating or schedule revising
  Owner approval of logic changes (revising)
  Determine level of detail required for each
  different stakeholder
  Identify process for schedule recovery
  discussions when lack of progress is reported
Schedule Logic - Approval
Who approves and when
Owner leverage in approval process even
though Contractor may own the schedule
Owner’s entitlement to backup data
Approval creates rebuttable presumption of
reasonableness
In the absence of formal approval, a working
schedule that represents the work will likely be
acceptable as the initial schedule for analysis
purposes
Schedule Logic - Approval
              (continued.)

Contractor’s termination for default upheld due
to its failure to produce an acceptable
schedule. Stone and Webster, 279 B.R. 748
(D. Del. 2002)
It is in every party’s best interest to get
schedule approved as quickly as possible
Discussion: Is constant manipulation & re-
submittal of baseline schedule a sign of claims
positioning? Are there risks in repeated re-
submittals of schedule?
Schedule Logic - Subcontractor
         Involvement
  Teamwork and commitment
  Schedule must be understandable to
  subcontractors
  Subcontractors must be part of any
  revision or recovery discussion
Schedule Logic - Float Use
       and Reporting
Reporting requirements for project float,
free float and activity specific float
Risk allocating provisions
Predecessor/Successor Reports
Total float
Ownership of float – check state case
law – in general, float belongs to project
Schedule Logic - Prohibition
on Schedule Manipulations
 Float sequestering (everything is critical)
 Critical Path manipulation (CP runs
 through all Owner controlled activities)
 Heavy constraint use (nothing is critical)
 Unidentified/unnecessary lags or leads
 Weather planning
 Develop a checklist for hot items
Schedule Settings
Schedule Calculations Methods
Work Calendars
Resource Calendars and Lags
Resource Constraints
Date Constraints
Schedule presentation
Schedule Settings - Options
Critical from Float or Longest Path
Float calculation: Start, finish, or most
critical
Out-of-sequence progress
  Retained Logic, Progress Override,
  Actual Dates
Continuous or Interruptible activities
SS lag from actual or early start
Work Calendars
Purpose
  Tailor the schedule to specific work or non-work
  periods
Examples
  Holiday periods
  Non-work periods (e.g., winter months for sitework
  activities)
  Adverse weather planning (based on NWS average
  records, 3 to 5 year averages)
  7 day activities vs. 5 day activities (curing or
  submittals)
  Fixed time periods (e.g., available work areas)
Work Calendar Best Practice
Use the least number of calendars that you
can, while reasonably modeling the project
Multiple calendars make analysis more
difficult
Multiple calendar use will amplify or reduce
the effects of delay
Calendars are a convenient and logical way
of modeling non-work periods and risk
predictions.
Scheduling Standards
What SHOULD we do?
  What’s being done (AACEI and PMI-COS) to set
  standards?
  Industry Standards
      PMI Practice Standard for Scheduling – in review
      AACEi – Recommended Practices – in development
  Best Practices
      PMI – College of Scheduling SEI project
      AACEi - Professional Practice Guides
  Practical limits
      Certifications
      Education
      Association Involvement
  Get involved with professional associations!!!!
Schedule Quality Control
How do we get a good schedule?
  Project team involvement
  Design the schedule before starting
  development
  Stakeholder buy-in
  Quality checklist
  Address contingency time and early
  completion
  Targeted reporting to Stakeholders
  Written narrative
Develop a QC Checklist
Schedule Quality Checklist
 Check for clean and reasonable Longest Path
 Appropriate calendars, applied appropriately
 Eliminate open ends in general
 Ensure reasonable ratio of LP activities to total activities
 Minimum necessary date constraints (can cause multiple LP)
 Minimum necessary lags
 All lags identified with purpose (change to activities if
 possible)
 All lagged or SS/FF activities have ends tied in logically
 Run histogram of trade activities to check good coverage
 Run Total Float check
 Good use of Activity Codes, organized for clarity
 Definitive Activity Descriptions
 Compare & evaluate Activity Durations
 Written narrative identifies rationale for decisions
Know the Project!
Know the…
 Contract Requirements
 Scope of the Work
 Basic CPM logic rules and how they are applied
 in the software
 Contractor means & methods
 Limitations & constraints
   Owner
   Contractor
   Site & industry
Characteristics Of A Useful
        Schedule
Schedule must model the project
Proper level of detail (limited number of critical
activities)
Summarize to one page
Team buy-in; all stakeholders involved in schedule
process
Describes superintendent’s plan (not the President’s
plan)
All activities tied to completion
Resource-based durations
Meet the specification
Include procurement activities (and coordination)
Written narrative to identify plan
BASELINE SCHEDULING BASICS
       Part 1: April 5, 2007
    See You May 6 for Part 2!

           Mark Boe, P.E., PSP
                   Vice President
          Capital Project Management, Inc.
               mboe@cpmiteam.com

             Chris Carson, PSP
               Project Controls Manager
                  Alpha Corporation
         chris.carson@alphacorporation.com

Contenu connexe

Tendances

Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay AnalysisChris Carson
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpChris Carson
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Controlguy_davis
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Construction delays
Construction delaysConstruction delays
Construction delaysSaida Njim
 

Tendances (20)

Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Claims
ClaimsClaims
Claims
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Platinum card for agile ev mr4
Platinum card for agile ev mr4Platinum card for agile ev mr4
Platinum card for agile ev mr4
 
Construction delays
Construction delaysConstruction delays
Construction delays
 

En vedette

Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop ConferenceChris Carson
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMIChris Carson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse WeatherChris Carson
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysiskatrin enders
 
Boost your bottom line with scalable it methodologies
Boost your bottom line with scalable it methodologiesBoost your bottom line with scalable it methodologies
Boost your bottom line with scalable it methodologiesNirtiSingla
 
A guide to create a quality project schedule
A guide to create a quality project scheduleA guide to create a quality project schedule
A guide to create a quality project scheduleNirtiSingla
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Building the baseline
Building the baselineBuilding the baseline
Building the baselineCarl Deala
 
Field Trash2007
Field Trash2007Field Trash2007
Field Trash2007vtsiri
 
Media Object File Flt Ops Adv Wx Seq07
Media Object File Flt Ops Adv Wx Seq07Media Object File Flt Ops Adv Wx Seq07
Media Object File Flt Ops Adv Wx Seq07syed viquar
 
OSHA record keeping update
OSHA record keeping  updateOSHA record keeping  update
OSHA record keeping updatevtsiri
 
Weather Protection
Weather ProtectionWeather Protection
Weather Protectionkeeckleber
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor SchedulingChris Carson
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationChris Carson
 
Railwayto greenwayfinalpresentation
Railwayto greenwayfinalpresentationRailwayto greenwayfinalpresentation
Railwayto greenwayfinalpresentationcander014
 
Big Dry Creek Greenway 2008
Big Dry Creek Greenway 2008Big Dry Creek Greenway 2008
Big Dry Creek Greenway 2008jmpflaum
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesChris Carson
 

En vedette (20)

Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Schedule Review
Schedule ReviewSchedule Review
Schedule Review
 
Boost your bottom line with scalable it methodologies
Boost your bottom line with scalable it methodologiesBoost your bottom line with scalable it methodologies
Boost your bottom line with scalable it methodologies
 
A guide to create a quality project schedule
A guide to create a quality project scheduleA guide to create a quality project schedule
A guide to create a quality project schedule
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Building the baseline
Building the baselineBuilding the baseline
Building the baseline
 
Field Trash2007
Field Trash2007Field Trash2007
Field Trash2007
 
Media Object File Flt Ops Adv Wx Seq07
Media Object File Flt Ops Adv Wx Seq07Media Object File Flt Ops Adv Wx Seq07
Media Object File Flt Ops Adv Wx Seq07
 
OSHA record keeping update
OSHA record keeping  updateOSHA record keeping  update
OSHA record keeping update
 
Weather Protection
Weather ProtectionWeather Protection
Weather Protection
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
111414 PRESENTATION: How to create a P50 Risk-based Baseline Schedule
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
Railwayto greenwayfinalpresentation
Railwayto greenwayfinalpresentationRailwayto greenwayfinalpresentation
Railwayto greenwayfinalpresentation
 
Big Dry Creek Greenway 2008
Big Dry Creek Greenway 2008Big Dry Creek Greenway 2008
Big Dry Creek Greenway 2008
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 

Similaire à BASIC SCHEDULING CONCEPTS

SPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxSPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxMuhammadAbubakar114879
 
OM_SECTION 4 PART C_STUDENT.ppt
OM_SECTION 4 PART C_STUDENT.pptOM_SECTION 4 PART C_STUDENT.ppt
OM_SECTION 4 PART C_STUDENT.pptPhmLanAnh23
 
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptxLec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptxNegeseTeklearegay
 
An Overview Of Basic Planning & Scheduling Concepts
An Overview Of Basic Planning & Scheduling ConceptsAn Overview Of Basic Planning & Scheduling Concepts
An Overview Of Basic Planning & Scheduling ConceptsShankar Ganesh Radhakrishnan
 
Mary.zimmerman
Mary.zimmermanMary.zimmerman
Mary.zimmermanNASAPMC
 
Lec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingLec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingSyed Hamza
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Sorge.les
Sorge.lesSorge.les
Sorge.lesNASAPMC
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02apocalypto1
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amandaNASAPMC
 
Vladi Fin09 Expert Guide How To Migrate From Bi Ip To Bpc
Vladi Fin09 Expert Guide How To Migrate From Bi Ip To BpcVladi Fin09 Expert Guide How To Migrate From Bi Ip To Bpc
Vladi Fin09 Expert Guide How To Migrate From Bi Ip To BpcLAZAR Consultants LLC
 
8 applying-es-to-critical-path-and-more
8 applying-es-to-critical-path-and-more8 applying-es-to-critical-path-and-more
8 applying-es-to-critical-path-and-moreatifaizan
 
Criticalchainprojectmanagement
CriticalchainprojectmanagementCriticalchainprojectmanagement
Criticalchainprojectmanagementkaton808
 

Similaire à BASIC SCHEDULING CONCEPTS (20)

Gantt PERT and CPM
Gantt PERT and CPMGantt PERT and CPM
Gantt PERT and CPM
 
SPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxSPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptx
 
OM_SECTION 4 PART C_STUDENT.ppt
OM_SECTION 4 PART C_STUDENT.pptOM_SECTION 4 PART C_STUDENT.ppt
OM_SECTION 4 PART C_STUDENT.ppt
 
Pmp memory-sheets
Pmp memory-sheetsPmp memory-sheets
Pmp memory-sheets
 
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptxLec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
Lec - 3 Construction_Management_Time_Estimation_2014_summer23.pptx
 
An Overview Of Basic Planning & Scheduling Concepts
An Overview Of Basic Planning & Scheduling ConceptsAn Overview Of Basic Planning & Scheduling Concepts
An Overview Of Basic Planning & Scheduling Concepts
 
Mary.zimmerman
Mary.zimmermanMary.zimmerman
Mary.zimmerman
 
Lec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingLec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project scheduling
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Bpp 3213 lecture 2
Bpp 3213 lecture 2Bpp 3213 lecture 2
Bpp 3213 lecture 2
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Pmp formulas v5
Pmp formulas v5Pmp formulas v5
Pmp formulas v5
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02
 
Mitskevich amanda
Mitskevich amandaMitskevich amanda
Mitskevich amanda
 
Vladi Fin09 Expert Guide How To Migrate From Bi Ip To Bpc
Vladi Fin09 Expert Guide How To Migrate From Bi Ip To BpcVladi Fin09 Expert Guide How To Migrate From Bi Ip To Bpc
Vladi Fin09 Expert Guide How To Migrate From Bi Ip To Bpc
 
Symons
SymonsSymons
Symons
 
8 applying-es-to-critical-path-and-more
8 applying-es-to-critical-path-and-more8 applying-es-to-critical-path-and-more
8 applying-es-to-critical-path-and-more
 
Criticalchainprojectmanagement
CriticalchainprojectmanagementCriticalchainprojectmanagement
Criticalchainprojectmanagement
 

Plus de Chris Carson

Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesChris Carson
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry SchedulingChris Carson
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodChris Carson
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotChris Carson
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminChris Carson
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...Chris Carson
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesChris Carson
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful MediationChris Carson
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule RevisionsChris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex ProjectChris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - AirportChris Carson
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony MistakesChris Carson
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.Chris Carson
 

Plus de Chris Carson (18)

Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.
 

Dernier

Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
A305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdfA305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdftbatkhuu1
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 

Dernier (20)

Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
A305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdfA305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdf
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 

BASIC SCHEDULING CONCEPTS

  • 1. BASELINE SCHEDULING BASICS Part 1: April 5, 2007 Mark Boe, P.E., PSP Vice President Capital Project Management, Inc. mboe@cpmiteam.com Chris Carson, PSP Project Controls Manager Alpha Corporation chris.carson@alphacorporation.com The information in this presentation or publication was developed and prepared by the authors for the purpose of education about the subject. This presentation or publication does not necessarily reflect the views of the Construction Management Association of America or constitute a position or policy of the Construction Management Association of America (CMAA). This material was presented with the permission of the authors and is subject to copyright under applicable law. The information contained herein is presented as descriptive of issues related to the subject at the time it was presented, but it has not been peer reviewed or approved by CMAA. No part of this presentation or publication is to be reproduced or used without written permission from the author and CMAA.
  • 2. Baseline Scheduling How should you benefit from this session? Basic understanding of concepts and benefits Knowledge of types of schedules Understanding of terminology Recognition of data and processes needed to create schedules QC: What makes a good schedule
  • 3. Introduction - Why Schedule? Why schedule? Why? Benefit to project? Benefit to project management? Mandated by owner? Mandated by contractor influences? Senior management, bonding company, attorneys, subcontracts, materials release
  • 4. Introduction - Why Schedule? Time = $ Cost/budget control Change management control Pure management tool Forcing involvement of project management team Planning Monitoring Control Subcontractor & resource control Owner coordination & control Predictions/projections Claims avoidance, defend claims, documentation Specification requirements
  • 5. Introduction - Background Background & Types of Scheduling Scheduling methodologies Types of schedules Scheduling terminology
  • 6. Background - Methodologies Gantt, Bar Chart, and Line of Balance Vertical Diagram Method “VDM” or Linear Visual system for repetitive tasks Types of CPM Schedule Formats Arrow Diagram Method or “ADM” IJ Network Activity-on-Arrow Precedence Diagram Method “PDM” Activity-on-Node Current prevalent scheduling methodology
  • 7. PDM: Typical Precedence Relationships 1 9 2 10 3 11 4 12 5 6 13 14 7 8
  • 8. Definitions Critical Path Method (CPM) – representation of a project plan by a network that depicts the duration, sequence and interrelation of the work activities. Critical Path – longest path (or sequence) of activities, driven by their relationships, lags, leads, calendars, and constraints, through the project, that determines the total duration of the project. Total Float – the amount of time an activity can slip without impacting project completion (contingency time). Logic/Relationship Types – description of the interrelation between the individual work activities
  • 9. Introduction - CRITICAL PATH METHOD (CPM) Sequential Relationship Types 60 Relationship Types FS FS STUDS Electrical RI Drywall 20 20 20 Concurrent STUDS FF5 Capital Project Management, Inc. 20 SS5 Electrical RI FF7 20 SS5 SS x = Start to Start Drywall FF x = Finish to Finish 20 xx 5 = Lag 32
  • 10. Definitions: Early Start Date – the earliest date an activity can start, based on predecessor logic Late Start Date – the latest date an activity may start in order to complete on time Float – the number of days between early start and late start (or between early and late finish)
  • 11. CPM Schedule Types Feasibility Studies Presentation Budgeting Conceptual or Schematic Milestone Summary Baseline Short Interval Look Ahead .
  • 13. Basic CPM Scheduling Exercise Forward pass Backward pass Derivation of Early dates Derivation of Late dates Calculation of Total Float Calculation of Free Float
  • 14. CPM Scheduling Exercise Forward Pass CPM Scheduling Exercise NTP 1 10 11 15 21 30 0 31 1 30 A B C 10 5 10 11 20 D Capital Project Management, Inc. 10 KEY: ES – Early Start EF(p) + 1 = ES(s) EF – Early Finish ES EF LS – Late Start ES + D + 1 = EF LF – Late Finish TF DUR – Duration LF LS TF – Total Float DUR
  • 15. Forward Pass Establishes the Early Start and Early Finish dates If you don’t want to learn formulas, the forward pass is common sense identification of start and finish days. The earliest that Activity B and Activity C can start is on the 11th day, the day after Activity A finishes. The earliest day that Activity D can start is on the 21st day, the earliest day after the later that either Activity B or Activity C can finish.
  • 16. CPM Scheduling Exercise Forward Pass CPM Scheduling Exercise Backward Pass NTP 1 10 11 15 21 30 31 1 30 A B C 1 31 30 10 5 10 1 10 16 20 21 30 11 20 D Capital Project Management, Inc. 10 11 20 KEY: ES – Early Start LS(s) - 1 = LF(p) EF – Early Finish ES EF LS – Late Start LF - D + 1 = LS LF – Late Finish TF DUR – Duration LF LS TF – Total Float DUR
  • 17. Backward Pass Establishes the Late Finish and Late Start dates Working from the last day towards the beginning, both Activity B and C cannot finish any later than the day before Activity D starts, so both have a Late Finish of Day 20, the day before Activity D starts on the 21th day.
  • 18. CPM Scheduling Exercise Forward Pass CPM Scheduling Exercise Backward Pass NTP Float Calculation 1 10 11 15 21 30 1 30 A B C 0 5 0 1 30 10 5 10 1 10 16 20 21 30 11 20 D 0 Capital Project Management, Inc. 10 11 20 Description ES EF LS LF TF KEY: ES – Early Start A 1 10 1 10 0 EF – Early Finish ES EF LS – Late Start B 11 15 16 20 5 LF – Late Finish TF C 21 30 21 30 0 DUR – Duration D 11 20 11 20 0 LF LS TF – Total Float DUR
  • 19. CRITICAL PATH METHOD (CPM) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 Time Scaled Logic Diagram COMP NTP A C 10 10 B 5 D Capital Project Management, Inc. 10
  • 20. CPM Schedule Creation How should we do it? Lessons learned (what are typical conflicts) Schedule design Schedule development Schedule components Schedule logic Schedule settings
  • 21. Typical Areas of Conflict Stakeholders: Who uses the schedule? Level of detail Reasonableness of schedule Clarity of schedule Schedule Approval/Non-approval Issue standoff Failure to Involve major trade Contractors Failure to include Owner requirements (other contracts, utilities, commissioning, etc.) Early Completion Schedules Ownership of float, contingency time
  • 22. Schedule Development - Process Assemble development team Design the schedule Identify Level of detail required Identify output needed – Activity Code & WBS structures Identify scope of work - Activities (input from subs/primes) Develop the schedule Calculate Durations (input from subs/primes) Assign logic (input from subs/primes) Input to computer Analyze and adjust Finalize the schedule QC checklists & verification Seek buy-in and approval (includes team) Add resources and costs
  • 23. Schedule Development - Owner-Controlled, Design Related And Procurement Activities Treat Owner activities like any other work activities Look in Contract for specification requirements Submittal approval times – specification or verify Consider re-submittal cycle for difficult or highly detailed activities Include all Owner scope of work (include permits, permanent telephone and other utilities, owner supplied equipment, other contracts, Health Department approvals, etc.) Code Owner activities so they can be filtered and tracked Owner and Contractor are both interested parties Ensure the successor activities are accurately defined Any delays related to these activities should be captured accurately for the protection of both the Owner and the Contractor
  • 24. Schedule Development - Feasibility of Specified Schedule Need real commitment to scheduling process Requirement for schedule to be actually used during performance Must have buy-in from PM team, senior management, subcontractors, suppliers, and Owner Must have resources to perform detailed schedule updates and analyses Do it during project ($) Do it in claims environment – post project ($$$$)
  • 25. Schedule Components – Output - Type of Diagram Bar Chart Network Analysis System (CPM) Most specs require multiple printouts Require electronic file Output types insignificant if you get the disk - electronic file is the only way to go Still need to understand means & methods – rationale of construction
  • 26. 2002 2003 2004 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR 0 ISSUE BID / TRAILER CIP Foundations Elevated Concrete Curtainwall System Installation Acoustical Ceiling & GMP DRAWINGS MOBILIZATION Floor Slabs Device Installation 0 0 0 0 AWARD START Shower/Toilet Structural Steel Electrical Rough-in/Systems Cabling F/R/P SOMD Valence H/C Unit FMS Rough-in SITEWORK EXCAVATION Flange Rough-in - E1 Erection/Deck/Detailing - Roof East Installation - Flr.4 West 0 0 0 0 0 FOUNDATION Safety Site Clearing/Utility F/R/P SOMD - Spray Fireproofing Alum Windows & Infills Ceramic Tile Spray Fireproofing PERMIT Fencing Demolition Flr.1 East Floors & Ceilings Install - Flr.4 West 0 0 0 0 Elec O/H Rough-in Utility Location & HVAC Testing F/R/P SOMD - Plumbing Rough-in Caulking & Sealants Hardwood Flooring - Flr.1 East Marking by Others & Balancing Flr.1 West Installation 0 0 0 0 Barchart Schedule Site/Bldg Pull Systems Cable Spray Fireproofing Interior GWB Partitions F/R/P SOMD Doors & Hdwe Layout - Flr.4 East Install- Bsmt. East - Roof West Installation 0 0 0 0 0 Temporay Power Pull Systems Cable Spray Fireproofing CMU Masonry & Stonework Stl Deck/Studs/Struc Stl Spray Fireproofing Req'd Onsite - Flr.4 West Install- Bsmt. West Detailing - Roof East Install - Flr.3 West With Logic 0 0 0 0 0 0 Plumbing Piping Excav/Sheet/Shore - (Stm Shower/Toilet HVAC Rough-in F/R/P/C/S Elevator Stl Deck/Studs/Struc Stl Caulking & In-Wall Rough-in - E1 Tunnel / Scully Hall) Flange Rough-in - E3 Pit/Int. Col. Ftgs - West Detailing - Roof West Sealants - East 0 0 0 0 0 0 OH Sanitary Piping Bulk Shower/Toilet Form/Reinf/Embeds EPDM & Slate Siding Roofing Installation Spray Fireproofing Sprinkler Heads Rough-in - Bsmt East Excavation Flange Rough-in - E4 Footings - West Install - Flr.3 East - Flr.4 West 0 0 0 0 0 Form/Reinf/Embeds Shower/Toilet Flange Form/Reinf/Cure/Strip Fire Protection System Spray Fireproofing Sprinkler Heads Footings - East Rough-in - Flr.3 West Fdn Wall - East Install - Flr.4 East - Flr.4 East BASE Sheet 1 of 2 Plot Date 30OCT03 Activity Bar/Early Dates Critical Activity Acme Constructors, Inc.. Data Date 24APR02 Progress Bar Date Revision Checked Approved Project Start 4DEC00 Milestone/Flag Activity Wala Wala University - New Dormitory Connecting Activity on Sheet x Project Finish 31MAR04 * x TL-14 (c) Primavera Systems, Inc. Time Scaled Logic Diagram
  • 27. Schedule Components - Type of Diagram (continued.) Must be clear on what is required H.I. Homa Co. case Contract unclear on whether CPM required Government’s insistence on CPM schedule was constructive change entitling contractor to added compensation
  • 28. Schedule Components - Number of Activities Depends on the nature, size and complexity of the project Need enough activities to reflect intricacies and interdependencies Too few activities will require use of SS and FS lagged activities; harder to analyze High level of detail will make updates more time consuming High level of detail will allow better monitoring & updating
  • 29. Schedule Components - Resource Loading Only way to confirm validity of an activity’s duration Resources/Productivity = Duration Even without resource loading, determination of durations must be made through resource calculations (even if based on experience) Effective use of resource loading requires detailed schedule Out of sequence work during updates can warp resource reports
  • 30. Schedule Components - Resource Loading (cont.) A 5 worker crew, with crew productivity of 4 windows per day will install 40 windows in 10 days Two 5 worker crews with the same productivity will install 40 windows in 5 days Notes should be kept to record how durations were derived Keep in mind: 100 crews with productivity of 4 windows per day will NOT install 400 windows in a day.
  • 31. Schedule Components – Cost Loading Used for Progress Payments Owners should retain ability to adjust schedules that are excessively front loaded Separate overhead & profit from direct costs Cost loading lends itself to reasonable scope deletion with resulting predetermined costs & time Separate large materials delivery activities so progress can be monitored (labor & materials production should be a linear curve) Use cost metrics (earned value) as another check on progress evaluation Update percent complete (track cost) separately from remaining duration (track time).
  • 32. Schedule Components - Control of Record Schedule and Updating DON’T OVERWRITE last period schedule!!! Who will maintain the schedule? Joint updating meetings Determine in advance what constitutes normal updating or schedule revising Owner approval of logic changes (revising) Determine level of detail required for each different stakeholder Identify process for schedule recovery discussions when lack of progress is reported
  • 33. Schedule Logic - Approval Who approves and when Owner leverage in approval process even though Contractor may own the schedule Owner’s entitlement to backup data Approval creates rebuttable presumption of reasonableness In the absence of formal approval, a working schedule that represents the work will likely be acceptable as the initial schedule for analysis purposes
  • 34. Schedule Logic - Approval (continued.) Contractor’s termination for default upheld due to its failure to produce an acceptable schedule. Stone and Webster, 279 B.R. 748 (D. Del. 2002) It is in every party’s best interest to get schedule approved as quickly as possible Discussion: Is constant manipulation & re- submittal of baseline schedule a sign of claims positioning? Are there risks in repeated re- submittals of schedule?
  • 35. Schedule Logic - Subcontractor Involvement Teamwork and commitment Schedule must be understandable to subcontractors Subcontractors must be part of any revision or recovery discussion
  • 36. Schedule Logic - Float Use and Reporting Reporting requirements for project float, free float and activity specific float Risk allocating provisions Predecessor/Successor Reports Total float Ownership of float – check state case law – in general, float belongs to project
  • 37. Schedule Logic - Prohibition on Schedule Manipulations Float sequestering (everything is critical) Critical Path manipulation (CP runs through all Owner controlled activities) Heavy constraint use (nothing is critical) Unidentified/unnecessary lags or leads Weather planning Develop a checklist for hot items
  • 38. Schedule Settings Schedule Calculations Methods Work Calendars Resource Calendars and Lags Resource Constraints Date Constraints Schedule presentation
  • 39. Schedule Settings - Options Critical from Float or Longest Path Float calculation: Start, finish, or most critical Out-of-sequence progress Retained Logic, Progress Override, Actual Dates Continuous or Interruptible activities SS lag from actual or early start
  • 40. Work Calendars Purpose Tailor the schedule to specific work or non-work periods Examples Holiday periods Non-work periods (e.g., winter months for sitework activities) Adverse weather planning (based on NWS average records, 3 to 5 year averages) 7 day activities vs. 5 day activities (curing or submittals) Fixed time periods (e.g., available work areas)
  • 41. Work Calendar Best Practice Use the least number of calendars that you can, while reasonably modeling the project Multiple calendars make analysis more difficult Multiple calendar use will amplify or reduce the effects of delay Calendars are a convenient and logical way of modeling non-work periods and risk predictions.
  • 42. Scheduling Standards What SHOULD we do? What’s being done (AACEI and PMI-COS) to set standards? Industry Standards PMI Practice Standard for Scheduling – in review AACEi – Recommended Practices – in development Best Practices PMI – College of Scheduling SEI project AACEi - Professional Practice Guides Practical limits Certifications Education Association Involvement Get involved with professional associations!!!!
  • 43. Schedule Quality Control How do we get a good schedule? Project team involvement Design the schedule before starting development Stakeholder buy-in Quality checklist Address contingency time and early completion Targeted reporting to Stakeholders Written narrative
  • 44. Develop a QC Checklist
  • 45. Schedule Quality Checklist Check for clean and reasonable Longest Path Appropriate calendars, applied appropriately Eliminate open ends in general Ensure reasonable ratio of LP activities to total activities Minimum necessary date constraints (can cause multiple LP) Minimum necessary lags All lags identified with purpose (change to activities if possible) All lagged or SS/FF activities have ends tied in logically Run histogram of trade activities to check good coverage Run Total Float check Good use of Activity Codes, organized for clarity Definitive Activity Descriptions Compare & evaluate Activity Durations Written narrative identifies rationale for decisions
  • 46. Know the Project! Know the… Contract Requirements Scope of the Work Basic CPM logic rules and how they are applied in the software Contractor means & methods Limitations & constraints Owner Contractor Site & industry
  • 47. Characteristics Of A Useful Schedule Schedule must model the project Proper level of detail (limited number of critical activities) Summarize to one page Team buy-in; all stakeholders involved in schedule process Describes superintendent’s plan (not the President’s plan) All activities tied to completion Resource-based durations Meet the specification Include procurement activities (and coordination) Written narrative to identify plan
  • 48. BASELINE SCHEDULING BASICS Part 1: April 5, 2007 See You May 6 for Part 2! Mark Boe, P.E., PSP Vice President Capital Project Management, Inc. mboe@cpmiteam.com Chris Carson, PSP Project Controls Manager Alpha Corporation chris.carson@alphacorporation.com