Fixed costs projects
              Practical experience
Agenda


   Pre-sale
   Planning
   Implementation
   Finishing
   SCRUM




                     2
On which phase a project
manager is starting a fixed-cost project?




                                            3
Pre sale


1. Pre-sale
   Needs
   Estimation
   Tips




                 4
Understand needs

   Learn
   Ask
   Draw
   Concept




                   5
Learning of customer needs

   The best way – face to face meeting
   Or video conference




                                          6
Ask as much as possible!

   Ask as much as possible
   Show examples




                              7
Make and present mock-up’s




                             8
Project concept

   Looking for existed solutions (Goal: cost reducing).
   Prepare a few options.
   Prototype




                                                           9
Estimation

   Do not forget
   Gaps in specification
   Risks




                            10
Estimation: Do not forget




                            11
Warranty effort




                  12
Buffer for small changes




                           13
Effort for meeting and ongoing
issues




                                 14
Effort for documentation




                           15
Pre sale effort




                  16
Example




          17
Gaps in the specification

   Assumptions
   “Will be implemented like …”
   Implement as T&M part.
   Notice:
       Bug fixing is also part of T&M!
       Additional management for managing T&M part




                                                      18
How to handle gaps in the
specification ?
   Example of assumptions:
       We assume that workflow module should contain about 10
        screens with complexity like “email configuration screen”
       Integration with python will implemented using simple
        interface: each python script should be presented like a
        function with hardcoded input and output parameters.
        Through admin part it is only possible change body of the
        script but not the interface. In the price is included
        integration of 2 scripts
       Will be implemented 2 reports with complexity like “Insured
        persons report”



                                                                  19
Risks

   List of risks:
       Description
       Probability
       Influence
       Mitigation plan
       Trigger
       Migration plan




                          20
Risk handling

   Share with the customer
   Include in price




                              21
How to include risk in the price

   Calculated risk cost (Rc)
   Probability (P. From 0 to 1)
   Risk reserve (Rr)
   Rr=Rc*P




                                   22
Tips& tricks

   Team/duration
   People involving
   Fixed cost magic
   Commercial correction




                            23
Project duration/team

   Split project on sub projects (as well sub-contracts)
   Build small teams




                                                            24
People involving

   Involve on pre-sale stage people who will take a part in
    the project implementation




                                                               25
Magic multiplier

   Magic multiplied based on experience
   For example:
       Effort=Estimated effort(dev)*2,2
           0,3 – Estimation error
           0,4 – Testing
           0,3 – Management
           0,2 – Communications etc.




                                           26
Commercial correction

   Effort -> $
   Stomach feeling
   Consulting with sales department
   Is it possible with final amount to finish the project?




                                                              27
Project planning


 2.   Planning




                   28
Communication plan




                     29
Time buffer before milestones




                                30
Reaction time of the customer




                                31
Acceptance criteria




                      32
Invoicing plan

     Lineal distribution
     Payment after milestone delivery
     Payment after project delivery




                                         33
On implementation


3. Implementation
   Risk review
   “Small changes”
   Change requests
   Reporting




                      34
Risks

   Plan of risks analyzing
   Update involved people (customer, sales, supervisor etc)




                                                          35
Small changes

   You have a buffer for them
   Efforts of small changes must be controlled
   Customer always needs much more
   Use batching strategy




                                                  36
Change requests

   Definition of CR must be created and agreed
   Don’t show real spent effort for CR (common JIRA)
   Strategies:
       Include
       Postpone




                                                        37
Including strategy

   The customer will be noticed concerning duration and
    budget changes before implementation




                                                           38
Important notice

   Effort spent for CR clarification will be included in final
    estimation




                                                                  39
Postpone

   CR’s cold be collected and realized as a minor release
   It is bad idea to implement CR’s separately




                                                             40
Important notice

   Estimated scope of work must be described in CR




                                                      41
Notice

   Use the similar approaches as on pre-sale stage:
       Assumptions
       T&M
       Like example




                                                       42
Reporting

   Should be introduced impact report
   You will be sure that the customer understands real
    deadline of the project




                                                          43
Project finishing


4. Finishing
   Acceptance
   Maintenance
   Experience sharing




                         44
Acceptance

   Should be defined acceptance criteria
   The customer should have restricted time for acceptance
   Should be defined responsible persons from customer
    side




                                                         45
Maintenance

   Right time for a maintenance proposal
   Do you want additional benefit? Organize resources in the
    most effective way!
   Propose a few options of reaction time and level of
    responsibility
   Jira




                                                                46
Save knowledge

   The risks will be reviewed (what happened/what not)
   Update internal knowledge base
   Will be defined and shared the best practices
   What components of the project could be reused in
    another projects




                                                          47
Bonus

   SCRUM+Fixed cost=own experience




                                      48
What works?

   Sprint
   Daily scrum
   Sprint planning
   Sprint review
   Retrospective
   Product Owner     Should be introduced proxy PO
   ScrumMaster
   Product backlog




                                                  49
What works?

   Sprint backlog
   Burn down
   Planning Poker
   Story points
   Definition of Done
   Velocity




                         50
More information here…

               We would be happy to
               answer any of your
               Questions?




                                      51

Contenu connexe

Tendances

Partes Fleet Risk Solutions
Partes Fleet Risk SolutionsPartes Fleet Risk Solutions
Partes Fleet Risk Solutionsdmeulenberghs
 
Macrosolutions Consulting Service: Project Maturity Assessment and Diagnosis
Macrosolutions Consulting Service: Project Maturity Assessment and DiagnosisMacrosolutions Consulting Service: Project Maturity Assessment and Diagnosis
Macrosolutions Consulting Service: Project Maturity Assessment and DiagnosisMacrosolutions SA
 
Macrosolutions Consulting Service: Resources and Investment Optimization thro...
Macrosolutions Consulting Service: Resources and Investment Optimization thro...Macrosolutions Consulting Service: Resources and Investment Optimization thro...
Macrosolutions Consulting Service: Resources and Investment Optimization thro...Macrosolutions SA
 
Macrosolutions Consulting Service: Portfolio and Investment Management
Macrosolutions Consulting Service: Portfolio and Investment ManagementMacrosolutions Consulting Service: Portfolio and Investment Management
Macrosolutions Consulting Service: Portfolio and Investment ManagementMacrosolutions SA
 
Functional memento méthodologie plus détaillé
Functional memento méthodologie plus détailléFunctional memento méthodologie plus détaillé
Functional memento méthodologie plus détailléMichel_Cousin
 
[AgileCMMI] Practical Experience Report: Application of Project Management ar...
[AgileCMMI] Practical Experience Report: Application of Project Management ar...[AgileCMMI] Practical Experience Report: Application of Project Management ar...
[AgileCMMI] Practical Experience Report: Application of Project Management ar...davidobama
 
Agile Importance in Pharmaceutical Industry
Agile Importance in Pharmaceutical IndustryAgile Importance in Pharmaceutical Industry
Agile Importance in Pharmaceutical IndustryVijay Brzee
 
Macrosolutions Consulting Service: Projects, Programs and Portfolios Communic...
Macrosolutions Consulting Service: Projects, Programs and Portfolios Communic...Macrosolutions Consulting Service: Projects, Programs and Portfolios Communic...
Macrosolutions Consulting Service: Projects, Programs and Portfolios Communic...Macrosolutions SA
 
Credentials ICTS Newfield English 6
Credentials ICTS Newfield English 6Credentials ICTS Newfield English 6
Credentials ICTS Newfield English 6JorSer2009
 
Gaming Industry part 2- production
Gaming Industry  part 2- productionGaming Industry  part 2- production
Gaming Industry part 2- productionMotaz Agamawi
 
PMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based Prioritization
PMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based PrioritizationPMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based Prioritization
PMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based PrioritizationThanh Nguyen
 
Risk and Interdependency in Programs - G. Rotter
Risk and Interdependency in Programs - G. RotterRisk and Interdependency in Programs - G. Rotter
Risk and Interdependency in Programs - G. RotterGerhard Rotter
 
Compare project management tool - FMS vs Redmine
Compare project management tool - FMS vs RedmineCompare project management tool - FMS vs Redmine
Compare project management tool - FMS vs Redminemekongsolution
 

Tendances (14)

Partes Fleet Risk Solutions
Partes Fleet Risk SolutionsPartes Fleet Risk Solutions
Partes Fleet Risk Solutions
 
Macrosolutions Consulting Service: Project Maturity Assessment and Diagnosis
Macrosolutions Consulting Service: Project Maturity Assessment and DiagnosisMacrosolutions Consulting Service: Project Maturity Assessment and Diagnosis
Macrosolutions Consulting Service: Project Maturity Assessment and Diagnosis
 
Ch3 proj.mgt
Ch3 proj.mgtCh3 proj.mgt
Ch3 proj.mgt
 
Macrosolutions Consulting Service: Resources and Investment Optimization thro...
Macrosolutions Consulting Service: Resources and Investment Optimization thro...Macrosolutions Consulting Service: Resources and Investment Optimization thro...
Macrosolutions Consulting Service: Resources and Investment Optimization thro...
 
Macrosolutions Consulting Service: Portfolio and Investment Management
Macrosolutions Consulting Service: Portfolio and Investment ManagementMacrosolutions Consulting Service: Portfolio and Investment Management
Macrosolutions Consulting Service: Portfolio and Investment Management
 
Functional memento méthodologie plus détaillé
Functional memento méthodologie plus détailléFunctional memento méthodologie plus détaillé
Functional memento méthodologie plus détaillé
 
[AgileCMMI] Practical Experience Report: Application of Project Management ar...
[AgileCMMI] Practical Experience Report: Application of Project Management ar...[AgileCMMI] Practical Experience Report: Application of Project Management ar...
[AgileCMMI] Practical Experience Report: Application of Project Management ar...
 
Agile Importance in Pharmaceutical Industry
Agile Importance in Pharmaceutical IndustryAgile Importance in Pharmaceutical Industry
Agile Importance in Pharmaceutical Industry
 
Macrosolutions Consulting Service: Projects, Programs and Portfolios Communic...
Macrosolutions Consulting Service: Projects, Programs and Portfolios Communic...Macrosolutions Consulting Service: Projects, Programs and Portfolios Communic...
Macrosolutions Consulting Service: Projects, Programs and Portfolios Communic...
 
Credentials ICTS Newfield English 6
Credentials ICTS Newfield English 6Credentials ICTS Newfield English 6
Credentials ICTS Newfield English 6
 
Gaming Industry part 2- production
Gaming Industry  part 2- productionGaming Industry  part 2- production
Gaming Industry part 2- production
 
PMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based Prioritization
PMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based PrioritizationPMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based Prioritization
PMI-ACP Lesson 08 Nugget 2 Agile & Scrum - Value-Based Prioritization
 
Risk and Interdependency in Programs - G. Rotter
Risk and Interdependency in Programs - G. RotterRisk and Interdependency in Programs - G. Rotter
Risk and Interdependency in Programs - G. Rotter
 
Compare project management tool - FMS vs Redmine
Compare project management tool - FMS vs RedmineCompare project management tool - FMS vs Redmine
Compare project management tool - FMS vs Redmine
 

Similaire à PracticeLeadersManagement&Communication18042012YuriyKudin-Fixed cost projects presentation_

Operational final (2)
Operational final (2)Operational final (2)
Operational final (2)Nauman khan
 
Technical Debt
Technical DebtTechnical Debt
Technical DebtGary Short
 
Project management in Agile Way
Project management in Agile WayProject management in Agile Way
Project management in Agile WayC.T.Co
 
404 lecture powerpointdesign
404 lecture powerpointdesign404 lecture powerpointdesign
404 lecture powerpointdesignKawaldeep Singh
 
Dollars and Dates are Killing Agile
Dollars and Dates are Killing AgileDollars and Dates are Killing Agile
Dollars and Dates are Killing AgileRally Software
 
Dollars and dates are killing agile final
Dollars and dates are killing agile finalDollars and dates are killing agile final
Dollars and dates are killing agile finaldrewz lin
 
Bim execution plan
Bim execution planBim execution plan
Bim execution planOmar Selim
 
Agile Development Process & Scrum
Agile Development Process & ScrumAgile Development Process & Scrum
Agile Development Process & ScrumOtavio Ferreira
 
Mb0049 project management (2)
Mb0049   project management (2)Mb0049   project management (2)
Mb0049 project management (2)smumbahelp
 
Technical Debt - PHPBenelux
Technical Debt - PHPBeneluxTechnical Debt - PHPBenelux
Technical Debt - PHPBeneluxenaramore
 
Project Management Essentials
Project Management EssentialsProject Management Essentials
Project Management EssentialsQBI Institute
 
Bim execution plan
Bim execution planBim execution plan
Bim execution planOmar Selim
 
Devnology back toschool software reengineering
Devnology back toschool software reengineeringDevnology back toschool software reengineering
Devnology back toschool software reengineeringDevnology
 
Panteene pro v project plan
Panteene pro v project planPanteene pro v project plan
Panteene pro v project planHagi Sahib
 
KPI Partners E-Book: The Project Analytics Framework
KPI Partners E-Book: The Project Analytics FrameworkKPI Partners E-Book: The Project Analytics Framework
KPI Partners E-Book: The Project Analytics FrameworkKPI Partners
 

Similaire à PracticeLeadersManagement&Communication18042012YuriyKudin-Fixed cost projects presentation_ (20)

Project Management - Introduction
Project Management - IntroductionProject Management - Introduction
Project Management - Introduction
 
Operational final (2)
Operational final (2)Operational final (2)
Operational final (2)
 
Technical Debt
Technical DebtTechnical Debt
Technical Debt
 
LECT9.ppt
LECT9.pptLECT9.ppt
LECT9.ppt
 
Project management in Agile Way
Project management in Agile WayProject management in Agile Way
Project management in Agile Way
 
404 lecture powerpointdesign
404 lecture powerpointdesign404 lecture powerpointdesign
404 lecture powerpointdesign
 
Dollars and Dates are Killing Agile
Dollars and Dates are Killing AgileDollars and Dates are Killing Agile
Dollars and Dates are Killing Agile
 
Dollars and dates are killing agile final
Dollars and dates are killing agile finalDollars and dates are killing agile final
Dollars and dates are killing agile final
 
Bim execution plan
Bim execution planBim execution plan
Bim execution plan
 
Agile Development Process & Scrum
Agile Development Process & ScrumAgile Development Process & Scrum
Agile Development Process & Scrum
 
Mb0049 project management (2)
Mb0049   project management (2)Mb0049   project management (2)
Mb0049 project management (2)
 
Technical Debt - PHPBenelux
Technical Debt - PHPBeneluxTechnical Debt - PHPBenelux
Technical Debt - PHPBenelux
 
Harsh
HarshHarsh
Harsh
 
Project Management Essentials
Project Management EssentialsProject Management Essentials
Project Management Essentials
 
Project Management for the Accidental Project Manager
Project Management for the Accidental Project ManagerProject Management for the Accidental Project Manager
Project Management for the Accidental Project Manager
 
Bim execution plan
Bim execution planBim execution plan
Bim execution plan
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Devnology back toschool software reengineering
Devnology back toschool software reengineeringDevnology back toschool software reengineering
Devnology back toschool software reengineering
 
Panteene pro v project plan
Panteene pro v project planPanteene pro v project plan
Panteene pro v project plan
 
KPI Partners E-Book: The Project Analytics Framework
KPI Partners E-Book: The Project Analytics FrameworkKPI Partners E-Book: The Project Analytics Framework
KPI Partners E-Book: The Project Analytics Framework
 

Plus de Ciklum Ukraine

"How keep normal blood pressure using TDD" By Roman Loparev
"How keep normal blood pressure using TDD" By Roman Loparev"How keep normal blood pressure using TDD" By Roman Loparev
"How keep normal blood pressure using TDD" By Roman LoparevCiklum Ukraine
 
"Through the three circles of the it hell" by Roman Liashenko
"Through the three circles of the it hell" by Roman Liashenko"Through the three circles of the it hell" by Roman Liashenko
"Through the three circles of the it hell" by Roman LiashenkoCiklum Ukraine
 
Alex Pazhyn: Google_Material_Design
Alex Pazhyn: Google_Material_DesignAlex Pazhyn: Google_Material_Design
Alex Pazhyn: Google_Material_DesignCiklum Ukraine
 
Introduction to amazon web services for developers
Introduction to amazon web services for developersIntroduction to amazon web services for developers
Introduction to amazon web services for developersCiklum Ukraine
 
Your 1st Apple watch Application
Your 1st Apple watch ApplicationYour 1st Apple watch Application
Your 1st Apple watch ApplicationCiklum Ukraine
 
Test Driven Development
Test Driven DevelopmentTest Driven Development
Test Driven DevelopmentCiklum Ukraine
 
Back to the future: ux trends 2015
Back to the future: ux trends 2015Back to the future: ux trends 2015
Back to the future: ux trends 2015Ciklum Ukraine
 
Developing high load systems using C++
Developing high load systems using C++Developing high load systems using C++
Developing high load systems using C++Ciklum Ukraine
 
Collection view layout
Collection view layoutCollection view layout
Collection view layoutCiklum Ukraine
 
Introduction to auto layout
Introduction to auto layoutIntroduction to auto layout
Introduction to auto layoutCiklum Ukraine
 
Unit Testing: Special Cases
Unit Testing: Special CasesUnit Testing: Special Cases
Unit Testing: Special CasesCiklum Ukraine
 
Model-View-Controller: Tips&Tricks
Model-View-Controller: Tips&TricksModel-View-Controller: Tips&Tricks
Model-View-Controller: Tips&TricksCiklum Ukraine
 
Future of Outsourcing report published in The Times featuring Ciklum's CEO To...
Future of Outsourcing report published in The Times featuring Ciklum's CEO To...Future of Outsourcing report published in The Times featuring Ciklum's CEO To...
Future of Outsourcing report published in The Times featuring Ciklum's CEO To...Ciklum Ukraine
 
Михаил Попчук "Cкрытые резервы команд или 1+1=3"
Михаил Попчук "Cкрытые резервы команд или 1+1=3"Михаил Попчук "Cкрытые резервы команд или 1+1=3"
Михаил Попчук "Cкрытые резервы команд или 1+1=3"Ciklum Ukraine
 

Plus de Ciklum Ukraine (20)

"How keep normal blood pressure using TDD" By Roman Loparev
"How keep normal blood pressure using TDD" By Roman Loparev"How keep normal blood pressure using TDD" By Roman Loparev
"How keep normal blood pressure using TDD" By Roman Loparev
 
"Through the three circles of the it hell" by Roman Liashenko
"Through the three circles of the it hell" by Roman Liashenko"Through the three circles of the it hell" by Roman Liashenko
"Through the three circles of the it hell" by Roman Liashenko
 
Alex Pazhyn: Google_Material_Design
Alex Pazhyn: Google_Material_DesignAlex Pazhyn: Google_Material_Design
Alex Pazhyn: Google_Material_Design
 
Introduction to amazon web services for developers
Introduction to amazon web services for developersIntroduction to amazon web services for developers
Introduction to amazon web services for developers
 
Your 1st Apple watch Application
Your 1st Apple watch ApplicationYour 1st Apple watch Application
Your 1st Apple watch Application
 
Test Driven Development
Test Driven DevelopmentTest Driven Development
Test Driven Development
 
Back to the future: ux trends 2015
Back to the future: ux trends 2015Back to the future: ux trends 2015
Back to the future: ux trends 2015
 
Developing high load systems using C++
Developing high load systems using C++Developing high load systems using C++
Developing high load systems using C++
 
Collection view layout
Collection view layoutCollection view layout
Collection view layout
 
Introduction to auto layout
Introduction to auto layoutIntroduction to auto layout
Introduction to auto layout
 
Groovy on Android
Groovy on AndroidGroovy on Android
Groovy on Android
 
Unit Testing: Special Cases
Unit Testing: Special CasesUnit Testing: Special Cases
Unit Testing: Special Cases
 
Material design
Material designMaterial design
Material design
 
Kanban development
Kanban developmentKanban development
Kanban development
 
Mobile sketching
Mobile sketching Mobile sketching
Mobile sketching
 
More UX in our life
More UX in our lifeMore UX in our life
More UX in our life
 
Model-View-Controller: Tips&Tricks
Model-View-Controller: Tips&TricksModel-View-Controller: Tips&Tricks
Model-View-Controller: Tips&Tricks
 
Unit Tesing in iOS
Unit Tesing in iOSUnit Tesing in iOS
Unit Tesing in iOS
 
Future of Outsourcing report published in The Times featuring Ciklum's CEO To...
Future of Outsourcing report published in The Times featuring Ciklum's CEO To...Future of Outsourcing report published in The Times featuring Ciklum's CEO To...
Future of Outsourcing report published in The Times featuring Ciklum's CEO To...
 
Михаил Попчук "Cкрытые резервы команд или 1+1=3"
Михаил Попчук "Cкрытые резервы команд или 1+1=3"Михаил Попчук "Cкрытые резервы команд или 1+1=3"
Михаил Попчук "Cкрытые резервы команд или 1+1=3"
 

Dernier

Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 

Dernier (20)

Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 

PracticeLeadersManagement&Communication18042012YuriyKudin-Fixed cost projects presentation_

  • 1. Fixed costs projects Practical experience
  • 2. Agenda  Pre-sale  Planning  Implementation  Finishing  SCRUM 2
  • 3. On which phase a project manager is starting a fixed-cost project? 3
  • 4. Pre sale 1. Pre-sale  Needs  Estimation  Tips 4
  • 5. Understand needs  Learn  Ask  Draw  Concept 5
  • 6. Learning of customer needs  The best way – face to face meeting  Or video conference 6
  • 7. Ask as much as possible!  Ask as much as possible  Show examples 7
  • 8. Make and present mock-up’s 8
  • 9. Project concept  Looking for existed solutions (Goal: cost reducing).  Prepare a few options.  Prototype 9
  • 10. Estimation  Do not forget  Gaps in specification  Risks 10
  • 11. Estimation: Do not forget 11
  • 13. Buffer for small changes 13
  • 14. Effort for meeting and ongoing issues 14
  • 17. Example 17
  • 18. Gaps in the specification  Assumptions  “Will be implemented like …”  Implement as T&M part.  Notice:  Bug fixing is also part of T&M!  Additional management for managing T&M part 18
  • 19. How to handle gaps in the specification ?  Example of assumptions:  We assume that workflow module should contain about 10 screens with complexity like “email configuration screen”  Integration with python will implemented using simple interface: each python script should be presented like a function with hardcoded input and output parameters. Through admin part it is only possible change body of the script but not the interface. In the price is included integration of 2 scripts  Will be implemented 2 reports with complexity like “Insured persons report” 19
  • 20. Risks  List of risks:  Description  Probability  Influence  Mitigation plan  Trigger  Migration plan 20
  • 21. Risk handling  Share with the customer  Include in price 21
  • 22. How to include risk in the price  Calculated risk cost (Rc)  Probability (P. From 0 to 1)  Risk reserve (Rr)  Rr=Rc*P 22
  • 23. Tips& tricks  Team/duration  People involving  Fixed cost magic  Commercial correction 23
  • 24. Project duration/team  Split project on sub projects (as well sub-contracts)  Build small teams 24
  • 25. People involving  Involve on pre-sale stage people who will take a part in the project implementation 25
  • 26. Magic multiplier  Magic multiplied based on experience  For example:  Effort=Estimated effort(dev)*2,2  0,3 – Estimation error  0,4 – Testing  0,3 – Management  0,2 – Communications etc. 26
  • 27. Commercial correction  Effort -> $  Stomach feeling  Consulting with sales department  Is it possible with final amount to finish the project? 27
  • 28. Project planning  2. Planning 28
  • 30. Time buffer before milestones 30
  • 31. Reaction time of the customer 31
  • 33. Invoicing plan  Lineal distribution  Payment after milestone delivery  Payment after project delivery 33
  • 34. On implementation 3. Implementation  Risk review  “Small changes”  Change requests  Reporting 34
  • 35. Risks  Plan of risks analyzing  Update involved people (customer, sales, supervisor etc) 35
  • 36. Small changes  You have a buffer for them  Efforts of small changes must be controlled  Customer always needs much more  Use batching strategy 36
  • 37. Change requests  Definition of CR must be created and agreed  Don’t show real spent effort for CR (common JIRA)  Strategies:  Include  Postpone 37
  • 38. Including strategy  The customer will be noticed concerning duration and budget changes before implementation 38
  • 39. Important notice  Effort spent for CR clarification will be included in final estimation 39
  • 40. Postpone  CR’s cold be collected and realized as a minor release  It is bad idea to implement CR’s separately 40
  • 41. Important notice  Estimated scope of work must be described in CR 41
  • 42. Notice  Use the similar approaches as on pre-sale stage:  Assumptions  T&M  Like example 42
  • 43. Reporting  Should be introduced impact report  You will be sure that the customer understands real deadline of the project 43
  • 44. Project finishing 4. Finishing  Acceptance  Maintenance  Experience sharing 44
  • 45. Acceptance  Should be defined acceptance criteria  The customer should have restricted time for acceptance  Should be defined responsible persons from customer side 45
  • 46. Maintenance  Right time for a maintenance proposal  Do you want additional benefit? Organize resources in the most effective way!  Propose a few options of reaction time and level of responsibility  Jira 46
  • 47. Save knowledge  The risks will be reviewed (what happened/what not)  Update internal knowledge base  Will be defined and shared the best practices  What components of the project could be reused in another projects 47
  • 48. Bonus  SCRUM+Fixed cost=own experience 48
  • 49. What works?  Sprint  Daily scrum  Sprint planning  Sprint review  Retrospective  Product Owner Should be introduced proxy PO  ScrumMaster  Product backlog 49
  • 50. What works?  Sprint backlog  Burn down  Planning Poker  Story points  Definition of Done  Velocity 50
  • 51. More information here… We would be happy to answer any of your Questions? 51