Ben Roper
IT Director
July 11, 2013
 Basic internal process review conducted during FY 12
 Identified need to bring in system experts to conduct
formal needs analysis and assessment
 RFP 12-092 issued late FY 12 for ERP Consultant –
BerryDunn selected.
 Needs Assessment and Gap Analysis completed –
Recommendation to select new system
 Requirements identified
 RFP 13-078 released June 28, 2013 for ERP system
software and implementation services
 December 13, 2012 – Initial brief on ERP Project,
Approval of BerryDunn Consultant Contract Phase I&II
 March 28, 2013 – BerryDunn presented
Recommendations and Action Plan to Council
 April 25, 2013 – Berry Dunn Consultant Contract
Phase III – V approved by Council
 Periodic updates included in weekly Council Updates
ERP High and Low One-Time Cost Estimates ($)
Vendor Low Estimate High Estimate
Velocity (Lawson ERP Software) $3,367,475 $4,071,223
Tyler Technologies (MUNIS ERP Software) Not Provided $1,859,600
Microsoft (Dynamics AX 2012 ERP Software) $1,505,200 $2,535,840
Oracle (JD Edwards Enterprise One ERP Software) $760,000 $1,130,000
SunGard (ONESolution ERP Software) $645,000 Not Provided
Point Solution High and Low One-Time Cost Estimates ($)
Vendor Low Estimate High Estimate
Advanced Utilities (Utility Billing) $1,101,000 $1,514,000
EnerGov (Permitting and Land Management Suite) $450,000 $645,000
*From BerryDunn 3-28 presentation.
Total Estimated Costs by Cost Area
Functional Area Core Financials HR and Payroll
P&DS and
Revenue Utility Billing TOTAL
Software Licensing 500,000 100,000 325,000 155,000 1,080,000
Data Conversion 35,000 25,000 35,000 35,000 130,000
Professional Services 500,000 100,000 325,000 300,000 1,225,000
Training 100,000 30,000 90,000 85,000 305,000
Project Management 250,000 250,000 150,000 150,000 800,000
Project Oversight 130,000 130,000 75,000 75,000 410,000
Expenses (misc) 150,000 100,000 105,000 100,000 455,000
Annual Maintenance 100,000 20,000 70,000 30,000 220,000
4,625,000
10% $ 5,087,500
Staff Time$ 97,500
Total Project$ 5,185,000
 Required Experience
 8-10 yr Project Management experience
 Direct and relevant work experience in ERP project
management capacity
 B.A./B.S. in Business, Information Systems, Computer Science,
Public Administration, or in a related field with ERP
management experience
 Contracted Position
 PM Salary
 Firm overhead
 Misc items (computer, mileage or car allowance, cell phone)
 Estimated 2 1/2 – 3 ½ years
 Bring PM Contract to Council
 RFP Evaluations (due Aug 2nd )
 Vendor Demos (Oct 14-18, 23-25)
 Contract Negotiations
 Contract Award (Estimated Dec 13 – Jan 14)
 Implementation of Phase I (Core Financials)
Questions?
 According to Gartner, nearly 50 percent
of all ERP implementations fail to deliver
even one third of their expected business
benefits
 Lack of software fit.
 Unrealistic implementation expectations.
 Lack of executive buy-in and support.
 Propensity to customize software rather than
leverage standard functionality.
 Lack of ERP implementation expertise.

Contenu connexe

Tendances

Business and IT Management with ARIS and Alfabet - Joerg Klueckmann & Conrad ...
Business and IT Managementwith ARIS and Alfabet - Joerg Klueckmann & Conrad ...Business and IT Managementwith ARIS and Alfabet - Joerg Klueckmann & Conrad ...
Business and IT Management with ARIS and Alfabet - Joerg Klueckmann & Conrad ...
Software AG South Africa
 
Customer Success Story: Learn How Herman Miller Moderized Their HR
Customer Success Story: Learn How Herman Miller Moderized Their HRCustomer Success Story: Learn How Herman Miller Moderized Their HR
Customer Success Story: Learn How Herman Miller Moderized Their HR
Emtec Inc.
 
Impact analysis of process improvement on it service quality
Impact analysis of process improvement on it service qualityImpact analysis of process improvement on it service quality
Impact analysis of process improvement on it service quality
IESS
 
Nate King Resume 8-2014 AV
Nate King Resume 8-2014 AVNate King Resume 8-2014 AV
Nate King Resume 8-2014 AV
Nate King
 

Tendances (20)

Business and IT Management with ARIS and Alfabet - Joerg Klueckmann & Conrad ...
Business and IT Managementwith ARIS and Alfabet - Joerg Klueckmann & Conrad ...Business and IT Managementwith ARIS and Alfabet - Joerg Klueckmann & Conrad ...
Business and IT Management with ARIS and Alfabet - Joerg Klueckmann & Conrad ...
 
Cisco Systems Case Study: The Architecture Review Process Improving the IT P...
Cisco Systems Case Study: The Architecture Review  Process Improving the IT P...Cisco Systems Case Study: The Architecture Review  Process Improving the IT P...
Cisco Systems Case Study: The Architecture Review Process Improving the IT P...
 
On Demand Support
On Demand SupportOn Demand Support
On Demand Support
 
Customer Success Story: Learn How Herman Miller Moderized Their HR
Customer Success Story: Learn How Herman Miller Moderized Their HRCustomer Success Story: Learn How Herman Miller Moderized Their HR
Customer Success Story: Learn How Herman Miller Moderized Their HR
 
How to select A good itsm tool
How to select A good itsm toolHow to select A good itsm tool
How to select A good itsm tool
 
Large Scale Deployment of FME in a Telecommunications Company
Large Scale Deployment of FME in a Telecommunications CompanyLarge Scale Deployment of FME in a Telecommunications Company
Large Scale Deployment of FME in a Telecommunications Company
 
Atanu Bhaumik
Atanu BhaumikAtanu Bhaumik
Atanu Bhaumik
 
ITIL Foundation card Game
ITIL Foundation card GameITIL Foundation card Game
ITIL Foundation card Game
 
ERP Implementation
ERP ImplementationERP Implementation
ERP Implementation
 
Different Types of IT Outsourcing Services
Different Types of IT Outsourcing ServicesDifferent Types of IT Outsourcing Services
Different Types of IT Outsourcing Services
 
PTC IoT AR Revolution
PTC IoT AR RevolutionPTC IoT AR Revolution
PTC IoT AR Revolution
 
Itil introduction
Itil introductionItil introduction
Itil introduction
 
(ONLINE) ITIL Indonesia Community – Meetup “ITIL Introduction: Incident and P...
(ONLINE) ITIL Indonesia Community – Meetup “ITIL Introduction: Incident and P...(ONLINE) ITIL Indonesia Community – Meetup “ITIL Introduction: Incident and P...
(ONLINE) ITIL Indonesia Community – Meetup “ITIL Introduction: Incident and P...
 
Impact analysis of process improvement on it service quality
Impact analysis of process improvement on it service qualityImpact analysis of process improvement on it service quality
Impact analysis of process improvement on it service quality
 
Mindshare company presentation rev 9.0
Mindshare company presentation rev 9.0 Mindshare company presentation rev 9.0
Mindshare company presentation rev 9.0
 
Nate King Resume 8-2014 AV
Nate King Resume 8-2014 AVNate King Resume 8-2014 AV
Nate King Resume 8-2014 AV
 
(ONLINE) ITIL Indonesia Community - An Introduction to IT Change Management
(ONLINE) ITIL Indonesia Community - An Introduction to IT Change Management(ONLINE) ITIL Indonesia Community - An Introduction to IT Change Management
(ONLINE) ITIL Indonesia Community - An Introduction to IT Change Management
 
Integrating Operational Response Automation Into Your Code - AWS Boston Meetu...
Integrating Operational Response Automation Into Your Code - AWS Boston Meetu...Integrating Operational Response Automation Into Your Code - AWS Boston Meetu...
Integrating Operational Response Automation Into Your Code - AWS Boston Meetu...
 
(ONLINE) ITIL Indonesia Community - IT Operation Practical Approach
(ONLINE) ITIL Indonesia Community - IT Operation Practical Approach(ONLINE) ITIL Indonesia Community - IT Operation Practical Approach
(ONLINE) ITIL Indonesia Community - IT Operation Practical Approach
 
Maximo Field Service Management
Maximo Field Service ManagementMaximo Field Service Management
Maximo Field Service Management
 

Similaire à ERP Update

IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)
jimmcdonaldpmp
 
The Bill for IT: IT Service Costing, Showbacks & Chargebacks with Profitabili...
The Bill for IT: IT Service Costing, Showbacks & Chargebacks with Profitabili...The Bill for IT: IT Service Costing, Showbacks & Chargebacks with Profitabili...
The Bill for IT: IT Service Costing, Showbacks & Chargebacks with Profitabili...
Joseph Alaimo Jr
 
Portfolio - Badre Maktari - Generic
Portfolio - Badre Maktari - GenericPortfolio - Badre Maktari - Generic
Portfolio - Badre Maktari - Generic
Badre Maktari
 
Tailor PeopleSoft Business Processes to Fit Your Needs – Without Customizations!
Tailor PeopleSoft Business Processes to Fit Your Needs – Without Customizations!Tailor PeopleSoft Business Processes to Fit Your Needs – Without Customizations!
Tailor PeopleSoft Business Processes to Fit Your Needs – Without Customizations!
Smart ERP Solutions, Inc.
 

Similaire à ERP Update (20)

Co Dig Gov Perf Mgmt 08
Co Dig Gov Perf Mgmt 08Co Dig Gov Perf Mgmt 08
Co Dig Gov Perf Mgmt 08
 
ClearCost Introduction 2015
ClearCost Introduction 2015ClearCost Introduction 2015
ClearCost Introduction 2015
 
Improve Performance with Enhanced Insight into Profitability and Costs using ...
Improve Performance with Enhanced Insight into Profitability and Costs using ...Improve Performance with Enhanced Insight into Profitability and Costs using ...
Improve Performance with Enhanced Insight into Profitability and Costs using ...
 
IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)IT PMO Charter (Linkedin)
IT PMO Charter (Linkedin)
 
ERP Software Report
ERP Software ReportERP Software Report
ERP Software Report
 
BPM Implementation (downloadable)
BPM Implementation (downloadable)BPM Implementation (downloadable)
BPM Implementation (downloadable)
 
2009 11 Business Case For ‘Erp’ In Government
2009 11 Business Case For ‘Erp’ In Government2009 11 Business Case For ‘Erp’ In Government
2009 11 Business Case For ‘Erp’ In Government
 
2009 11 Business Case For ‘Erp’ In Government
2009 11 Business Case For ‘Erp’ In Government2009 11 Business Case For ‘Erp’ In Government
2009 11 Business Case For ‘Erp’ In Government
 
The Bill for IT: IT Service Costing, Showbacks & Chargebacks with Profitabili...
The Bill for IT: IT Service Costing, Showbacks & Chargebacks with Profitabili...The Bill for IT: IT Service Costing, Showbacks & Chargebacks with Profitabili...
The Bill for IT: IT Service Costing, Showbacks & Chargebacks with Profitabili...
 
The Bill for IT: IT Service Costing, Showback, & Chargebacks with PCMCS
The Bill for IT:  IT Service Costing, Showback, & Chargebacks with PCMCSThe Bill for IT:  IT Service Costing, Showback, & Chargebacks with PCMCS
The Bill for IT: IT Service Costing, Showback, & Chargebacks with PCMCS
 
Improve Performance with Enhanced Insight into Profitability and Costs Utiliz...
Improve Performance with Enhanced Insight into Profitability and Costs Utiliz...Improve Performance with Enhanced Insight into Profitability and Costs Utiliz...
Improve Performance with Enhanced Insight into Profitability and Costs Utiliz...
 
Oracle EPM Day Boston - Improving Performance with Enhanced Insight into Pro...
Oracle EPM Day Boston -  Improving Performance with Enhanced Insight into Pro...Oracle EPM Day Boston -  Improving Performance with Enhanced Insight into Pro...
Oracle EPM Day Boston - Improving Performance with Enhanced Insight into Pro...
 
Reinaldo Ragazzini (E)
Reinaldo Ragazzini (E)Reinaldo Ragazzini (E)
Reinaldo Ragazzini (E)
 
Project initiation
Project initiationProject initiation
Project initiation
 
Portfolio - Badre Maktari - Generic
Portfolio - Badre Maktari - GenericPortfolio - Badre Maktari - Generic
Portfolio - Badre Maktari - Generic
 
Tailor PeopleSoft Business Processes to Fit Your Needs – Without Customizations!
Tailor PeopleSoft Business Processes to Fit Your Needs – Without Customizations!Tailor PeopleSoft Business Processes to Fit Your Needs – Without Customizations!
Tailor PeopleSoft Business Processes to Fit Your Needs – Without Customizations!
 
Business Integra Profile 2008
Business Integra Profile 2008Business Integra Profile 2008
Business Integra Profile 2008
 
Ervin Patrick Loresco - CV
Ervin Patrick Loresco - CVErvin Patrick Loresco - CV
Ervin Patrick Loresco - CV
 
Australian Oracle Users Group - Middleware for Innovation
Australian Oracle Users Group - Middleware for InnovationAustralian Oracle Users Group - Middleware for Innovation
Australian Oracle Users Group - Middleware for Innovation
 
State of Delaware PeopleSoft 9.1 Upgrade Solutions
State of Delaware PeopleSoft 9.1 Upgrade SolutionsState of Delaware PeopleSoft 9.1 Upgrade Solutions
State of Delaware PeopleSoft 9.1 Upgrade Solutions
 

Plus de City of College Station

Plus de City of College Station (20)

Gus Roy Road Land Use Applicant Presentation
Gus Roy Road Land Use Applicant PresentationGus Roy Road Land Use Applicant Presentation
Gus Roy Road Land Use Applicant Presentation
 
2020 BVEDC Compliance Report
2020 BVEDC Compliance Report2020 BVEDC Compliance Report
2020 BVEDC Compliance Report
 
College Station Community Recreation Center Update
College Station Community Recreation Center UpdateCollege Station Community Recreation Center Update
College Station Community Recreation Center Update
 
Gus Roy Road Land Use
Gus Roy Road Land UseGus Roy Road Land Use
Gus Roy Road Land Use
 
Debt Parameters Ordinance
Debt Parameters OrdinanceDebt Parameters Ordinance
Debt Parameters Ordinance
 
Historical Marker No. 106
Historical Marker No. 106Historical Marker No. 106
Historical Marker No. 106
 
Historical Cemetery Project
Historical Cemetery ProjectHistorical Cemetery Project
Historical Cemetery Project
 
TxDOT Grant Resolution -- Harvey Mitchell Parkway Shared-Use Path
TxDOT Grant Resolution -- Harvey Mitchell Parkway Shared-Use PathTxDOT Grant Resolution -- Harvey Mitchell Parkway Shared-Use Path
TxDOT Grant Resolution -- Harvey Mitchell Parkway Shared-Use Path
 
Creek Meadows PUE Abandonment
Creek Meadows PUE AbandonmentCreek Meadows PUE Abandonment
Creek Meadows PUE Abandonment
 
Semi Annual Report on Impact Fees
Semi Annual Report on Impact FeesSemi Annual Report on Impact Fees
Semi Annual Report on Impact Fees
 
Name Change for Part of Royder Road
Name Change for Part of Royder Road Name Change for Part of Royder Road
Name Change for Part of Royder Road
 
Options to Preserve Neighborhood Integrity
Options to Preserve Neighborhood IntegrityOptions to Preserve Neighborhood Integrity
Options to Preserve Neighborhood Integrity
 
Northgate Study and Operations Plan
Northgate Study and Operations PlanNorthgate Study and Operations Plan
Northgate Study and Operations Plan
 
Lick Creek Hike & Bike Trail Midtown Crossing
Lick Creek Hike & Bike Trail Midtown CrossingLick Creek Hike & Bike Trail Midtown Crossing
Lick Creek Hike & Bike Trail Midtown Crossing
 
Housing of Fowl Animal Ordinance
Housing of Fowl Animal OrdinanceHousing of Fowl Animal Ordinance
Housing of Fowl Animal Ordinance
 
FY 21 Debt Issuance
FY 21 Debt IssuanceFY 21 Debt Issuance
FY 21 Debt Issuance
 
FY 21 City Council Strategic Plan
FY 21 City Council Strategic PlanFY 21 City Council Strategic Plan
FY 21 City Council Strategic Plan
 
Pet Sales Ordinance
Pet Sales OrdinancePet Sales Ordinance
Pet Sales Ordinance
 
Unlimited Potential Request for Rehabilitation Assistance
Unlimited Potential Request for Rehabilitation AssistanceUnlimited Potential Request for Rehabilitation Assistance
Unlimited Potential Request for Rehabilitation Assistance
 
Rental Registration Fee Consideration
Rental Registration Fee ConsiderationRental Registration Fee Consideration
Rental Registration Fee Consideration
 

Dernier

Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Victor Rentea
 

Dernier (20)

Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
Apidays New York 2024 - APIs in 2030: The Risk of Technological Sleepwalk by ...
 
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptx
 

ERP Update

  • 2.  Basic internal process review conducted during FY 12  Identified need to bring in system experts to conduct formal needs analysis and assessment  RFP 12-092 issued late FY 12 for ERP Consultant – BerryDunn selected.  Needs Assessment and Gap Analysis completed – Recommendation to select new system  Requirements identified  RFP 13-078 released June 28, 2013 for ERP system software and implementation services
  • 3.  December 13, 2012 – Initial brief on ERP Project, Approval of BerryDunn Consultant Contract Phase I&II  March 28, 2013 – BerryDunn presented Recommendations and Action Plan to Council  April 25, 2013 – Berry Dunn Consultant Contract Phase III – V approved by Council  Periodic updates included in weekly Council Updates
  • 4. ERP High and Low One-Time Cost Estimates ($) Vendor Low Estimate High Estimate Velocity (Lawson ERP Software) $3,367,475 $4,071,223 Tyler Technologies (MUNIS ERP Software) Not Provided $1,859,600 Microsoft (Dynamics AX 2012 ERP Software) $1,505,200 $2,535,840 Oracle (JD Edwards Enterprise One ERP Software) $760,000 $1,130,000 SunGard (ONESolution ERP Software) $645,000 Not Provided Point Solution High and Low One-Time Cost Estimates ($) Vendor Low Estimate High Estimate Advanced Utilities (Utility Billing) $1,101,000 $1,514,000 EnerGov (Permitting and Land Management Suite) $450,000 $645,000 *From BerryDunn 3-28 presentation.
  • 5. Total Estimated Costs by Cost Area Functional Area Core Financials HR and Payroll P&DS and Revenue Utility Billing TOTAL Software Licensing 500,000 100,000 325,000 155,000 1,080,000 Data Conversion 35,000 25,000 35,000 35,000 130,000 Professional Services 500,000 100,000 325,000 300,000 1,225,000 Training 100,000 30,000 90,000 85,000 305,000 Project Management 250,000 250,000 150,000 150,000 800,000 Project Oversight 130,000 130,000 75,000 75,000 410,000 Expenses (misc) 150,000 100,000 105,000 100,000 455,000 Annual Maintenance 100,000 20,000 70,000 30,000 220,000 4,625,000 10% $ 5,087,500 Staff Time$ 97,500 Total Project$ 5,185,000
  • 6.  Required Experience  8-10 yr Project Management experience  Direct and relevant work experience in ERP project management capacity  B.A./B.S. in Business, Information Systems, Computer Science, Public Administration, or in a related field with ERP management experience  Contracted Position  PM Salary  Firm overhead  Misc items (computer, mileage or car allowance, cell phone)  Estimated 2 1/2 – 3 ½ years
  • 7.  Bring PM Contract to Council  RFP Evaluations (due Aug 2nd )  Vendor Demos (Oct 14-18, 23-25)  Contract Negotiations  Contract Award (Estimated Dec 13 – Jan 14)  Implementation of Phase I (Core Financials)
  • 9.  According to Gartner, nearly 50 percent of all ERP implementations fail to deliver even one third of their expected business benefits  Lack of software fit.  Unrealistic implementation expectations.  Lack of executive buy-in and support.  Propensity to customize software rather than leverage standard functionality.  Lack of ERP implementation expertise.