novagold.com
NYSE-MKT, TSX: NG | March 2014
JTVIR 2014 metals & mining conference
cautionary statements
REGARDING FORWARD-LOOKING STATEMENTS
This presentation includes certain “forward-looking statements” within the meaning of applicable securities laws, including the United States Private Securities Litigation Reform Act of 1995. All
statements, other than statements of historical fact, included herein including, without limitation, statements relating to Donlin Gold’s future operating or financial performance, are forward-
looking statements. Forward-looking statements are frequently, but not always, identified by words such as “plans”, “expects”, “anticipates”, “believes”, “intends”, “estimates”, “potential”,
“possible” and similar expressions, or statements that events, conditions or results “will”, “may”, “could”, or “should” occur or be achieved. These forward-looking statements are set forth in the
slides pertaining to the implementation of the Donlin Gold second updated Feasibility Study and pertaining to the implementation of the Galore Creek Pre-Feasibility Study and may include
statements regarding perceived merit of properties; exploration results and budgets; mineral reserves and resource estimates; work programs; capital expenditures; timelines; strategic plans;
completion of transactions; market price of precious base metals; or other statements that are not statements of fact. Forward-looking statements involve various risks and uncertainties. There
can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that
could cause actual results to differ materially from our expectations include the uncertainties involving the need for additional financing to explore and develop properties and availability of
financing in the debt and capital markets; uncertainties involved in the interpretation of drilling results and geological tests and the estimation of reserves and resources; the need for continued
cooperation between NOVAGOLD and Barrick Gold in the exploration and development of the Donlin Gold property; the need for continued cooperation between NOVAGOLD and Teck
Resources Ltd. in the exploration and development of the Galore Creek property; the need for cooperation of government agencies and native groups in the development and operation of
properties; the need to obtain permits and governmental approvals; risks of construction and mining projects such as accidents, equipment breakdowns, bad weather, non-compliance with
environmental and permit requirements, unanticipated variation in geological structures, ore grades or recovery rates; unexpected cost increases; fluctuations in metal prices and currency
exchange rates; and other risk and uncertainties disclosed in reports and documents filed by NOVAGOLD with applicable securities regulatory authorities from time to time. The forward-
looking statements made herein reflect our beliefs, opinions and projections on the date the statements are made. Except as required by law, we assume no obligation to update the forward-
looking statements of beliefs, opinions, projections, or other factors, should they change.
REGARDING SCIENTIFIC AND TECHNICAL INFORMATION
Unless otherwise indicated, all reserve and resource estimates included in this presentation have been prepared in accordance with Canadian National Instrument 43-101 Standards of
Disclosure for Mineral Projects (“NI 43-101”) and the Canadian Institute of Mining, Metallurgy and Petroleum Definition Standards for Mineral Resources and Mineral Reserves (“CIM Definition
Standards”). Canadian standards, including NI 43-101, differ significantly from the requirements of the United States Securities and Exchange Commission (“SEC”), and reserve and resource
information in this presentation may not be comparable to similar information disclosed by U.S. companies. In particular, and without limiting the generality of the foregoing, the term “resource”
does not equate to the term “‘reserves”. Under U.S. standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be
economically and legally produced or extracted at the time the reserve determination is made. At this time, both of Donlin Gold and Galore Creek projects are without known reserves, as
defined under SEC Industry Guide 7. The SEC’s disclosure standards normally do not permit the inclusion of information concerning “measured mineral resources”, “indicated mineral
resources” or “inferred mineral resources” or other descriptions of the amount of mineralization in mineral deposits that do not constitute “reserves” by U.S. standards in documents filed with the
SEC. U.S. investors should also understand that “inferred mineral resources” have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal
feasibility. It cannot be assumed that all or any part of an “inferred mineral resource” will ever be upgraded to a higher category. Under Canadian rules, estimated “inferred mineral resources”
may not form the basis of feasibility or pre-feasibility studies except in rare cases. Investors are cautioned not to assume that all or any part of an “inferred mineral resource” exists or is
economically or legally mineable. Disclosure of “contained ounces” in a resource is permitted disclosure under Canadian regulations; however, the SEC normally only permits issuers to report
mineralization that does not constitute “reserves” by SEC standards as in-place tonnage and grade without reference to unit measures. The requirements of NI 43-101 for identification of
“reserves” are also not the same as those of the SEC, and reserves reported in compliance with NI 43-101 may not qualify as “reserves” under SEC standards. Accordingly, information
concerning mineral deposits set forth herein may not be comparable to information made public by companies that report in accordance with United States standards.
2
All dollar amounts quoted in this report are in U.S. currency unless otherwise noted.
EXCEPTIONAL IN SCALE, QUALITY, AND JURISDICTIONAL SAFETY
the NOVAGOLD opportunity
3
39Moz
gold resource1
̴ 9Blbs
copper resource1
Notes:
1) Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources inclusive of proven and probable
reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix.
̴ 8Moz
gold resource1
̴ 136Moz
silver resource1
Donlin Gold
Galore Creek
PROJECTS CONTINUE TO ADVANCE ON TIME AND ON BUDGET
recent achievements
4
Notes:
1) Outstanding Convertible Notes mature on May 1, 2015. The holders of the Notes had the right to require the Company to repurchase all or part of their Notes on May 1, 2013 (“put option”)
maintained a healthy balance sheet with receipt of $54M cash from warrants and
reduced convertible debt by $79M1
continued to advance permitting of Donlin Gold with completion of public scoping
and advanced preparation of preliminary draft environmental impact statement
Galore Creek 2013 exploration drill results identified extensions to
mineralization at Legacy zone
simplified company, significantly reduced expenditures
built a management team with expertise in permitting, developing and operating
large-scale projects
the right project – donlin gold
ARGUABLY THE WORLD’S MOST SIGNIFICANT GOLD PROJECT
partnerships grade
growthjurisdiction
longevity
size
5
donlin gold
WORLD’S BIGGEST UNDEVELOPED AND EARLY PRODUCTION GOLD PROJECTS
largest development-stage gold deposit
6
49.0
39.0
24.3
19.0
17.1 16.4 15.7
11.7
--
10
20
30
40
50
60
KSM Donlin Gold Hycroft Mine
Expansion
Metates Rosia
Montana
Detour Lake Livengood Canadian
Malarctic
M&IAuResources(Moz)
▸ Donlin Gold has one of the largest resources of its
peer group and it’s located in North America
LOMAverageAnnualProduction(Moz)
▸ Anticipated to be the leading gold producer
by a wide margin
Notes:
Donlin Gold data as per Donlin Creek Gold Project Alaska, USA, NI 43-101 Technical Report on Second “Updated Feasibility Study”, effective November 18, 2011, as amended January 20, 2012 (the “updated
feasibility study”). Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources inclusive of proven and probable reserves. See
“Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. Peer group data as per latest company documents, public filings and websites.
Comparison group based on large, open-pit, gold-focused development projects with Resources over 10 million ounces of gold. KSM data also includes an underground component.
1) 1.50Moz represents the projected annual gold production during first five full years of mine life, 1.10Moz represents the projected annual gold production during full life of mine.
1.101
0.659 0.657
0.594 0.578
0.508 0.483 0.449
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
Donlin Gold Metates Detour Lake Canadian
Malarctic
Livengood KSM Rosia Montana Hycroft Mine
Expansion
1.501
1.60
1.101 1.01
0.95 0.94
0.89 0.87
0.75 0.73 0.70
0.68
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
1.80
Grasberg Donlin Gold Pueblo Viejo Cortez Yanacocha Goldstrike Carlin Lihir Island Oyu Tolgoi Boddington Veladero
Notes:
Donlin Gold projected annual production represents 100% of which NOVAGOLD’s share represents 50%. All other production estimates, for the exception of Grasberg, are based on published 2014
average gold annual production guidance. Grasberg represents the published 2014 gold sales guidance.
1) 1.50Moz represents the projected annual gold production during first five full years of mine life, 1.10Moz represents the projected annual gold production during full life of mine.
Gold (M/oz)
LOCATION:
1.50
1
USA USADOMINICAN
REPUBLIC
INDONESIA PAPUA NEW
GUINEA
PERU AUSTRALIAMONGOLIA
poised to be world’s biggest gold mine
EXPECTED PRODUCTION RIVALS 10 LARGEST EXISTING GOLD MINES
7
USAUSA ARGENTINA
More than half of the industry’s top producing mines were initially
criticized for their high CAPEX requirements…but they were built
Today, these assets are low-cost operations that companies are
built upon…They are the back bone of the industry.
Large precious metals assets will be built by a consortium of
companies, much like base metals and oil and gas projects
large gold mines essential to industry
ALTHOUGH CAPITAL INTENSIVE, ONCE BUILT, MAJOR OPERATIONS PROVIDE
SIGNIFICANT RETURNS
8
Put simply, the industry has always needed large-scale
projects to sustain itself… this has not changed.
the right project – donlin gold
ARGUABLY THE WORLD’S MOST SIGNIFICANT GOLD PROJECT
partnerships grade
growthjurisdiction
longevity
size
9
donlin gold
2.24
1.05 1.04 1.02
0.61
0.55
0.50
0.31
--
0.50
1.00
1.50
2.00
2.50
Donlin Gold Canadian
Malarctic
Rosia Montana Detour Lake Livengood KSM Metates Hycroft Mill
Expansion
WORLD’S BIGGEST UNDEVELOPED AND EARLY PRODUCTION GOLD PROJECTS
highest-quality open-pit development-stage gold
deposit
10
M&I Au Grade (g/t)
Notes:
Donlin Gold data as per the updated feasibility study. Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources
inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix.
Peer group data as per latest company documents, public filings and websites. Comparison group based on large, open-pit, gold-focused development projects. KSM data includes an under
ground component.
▸ With capital constraints, only the best projects will find
funding
▸ With much higher grade, Donlin Gold is a robust project
able to weather any gold price cycle
DONLIN GOLD’S GRADE IS AT THE TOP OF THE LIST COMPARED TO WORLD’S
BIGGEST PRODUCERS
expected to emerge as one of the highest-grade
gold producers
11Notes:
Donlin Gold data as per the updated feasibility study. Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources are inclusive of
proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix.
Peer group data - 2012 annual average grade per tonne (combined proven & probable reserves and measured & indicated resources) for open-pit and underground material as per public filings.
2.56
2.24 2.22
1.95
1.90
1.37
1.32
1.02
0.89
0.84
0.78
0.00
0.50
1.00
1.50
2.00
2.50
3.00
Agnico
Eagle
Donlin Gold Gold Fields Polyus AngloGold
Ashanti
Barrick Harmony Eldorado Newmont Yamana GoldcorpDonlin
Gold
M&I Au Grade (g/t)
the right project – donlin gold
ARGUABLY THE WORLD’S MOST SIGNIFICANT GOLD PROJECT
partnerships grade
growthjurisdiction
longevity
size
12
donlin gold
RESOURCES MORE THAN DOUBLED FROM 2006 TO 2008
reserve & resource growth
13
16.6
29.4
35.3
37.9
39.0
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
2006 2007 2008 2009 2011
Notes:
Donlin Gold data as per NOVAGOLD public documents. Represents 100% of measured and indicated resources of which
NOVAGOLD’s share represents 50%. Measured and indicated resources are inclusive of proven and probable reserves. See
“Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the
appendix.
M&IAuResources(Moz)
39Moz
M&I RESOURCES
34Moz
P&P RESERVES @ $975/oz
inclusive of
grade of
2.24g/t
And there is opportunity for
continued growth once in
production…
PEA
FeasibilityStudy
UpdatedFeasibilityStudy
Focused on feasibility-level planning
and more recently permitting
MULTIPLE DRILL PROSPECTS AND TARGETS EXIST ALONG 8KM TREND
substantial exploration potential
▶ All current reserves and
resources are contained in the
Donlin Gold pit
• 39Moz M&I resources
inclusive of 34Moz P&P
reserves1
▶ Future mine situated in 3km
segment of 8km mineralized
trend
Notes:
1) Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources inclusive of proven and
probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix.
14
MULTIPLE DRILL PROSPECTS AND TARGETS EXIST ALONG 8KM TREND
substantial exploration potential
Notes:
See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix.
15
▶ Exploration upside:
• In-pit resource
conversion
• In-pit/deep-pit
exploration
• Near-pit targets
(East ACMA, Akivik
Zone and Snow)
• Additional resource
potential
Snow
Dome
Quartz Ophir
ACMA Lewis
39.0Moz
M&I Resource
6.0Moz
Inf Resource
5 km
Snow
Quartz
Dome
Ophir
ACMA
Lewis
Snow
Dome
the right project – donlin gold
ARGUABLY THE WORLD’S MOST SIGNIFICANT GOLD PROJECT
partnerships grade
growthjurisdiction
longevity
size
16
donlin gold
THREE DECADES OF LOW COST PRODUCTION
donlin gold
Climate of Declining Grades &
Escalating Costs…
▶ Global gold industry experienced
substantial cost escalation and a
decrease in grade over the last decade
due to…
• Operations mining significantly above
reserve grade
• Inflationary pressures
▶ Donlin Gold’s low cost profile…
• Contributes to meaningful cash flow
generation over the 27-year mine life
• A robust project that is highly
leveraged to gold price increases
17
$1,0111
$7352
0
200
400
600
800
1,000
1,200
Industry Average Donlin Gold Life of Mine
~$300
Less than current
industry average
All-InSustainingCost(AISC)
Donlin Gold
Life of Mine
Notes:
1) 2013A industry average AISC as per RBC Capital Markets report published 03/20/14. Industry average AISC includes total cash costs, sustaining capital,
corporate G&A, and exploration expenses reported during 2013.
2) Donlin Gold AISC includes total cash costs (US$585/oz - estimate as per updated feasibility study), sustaining capex, stripping capex (IFRS), corporate
G&A, reclamation, and community development (IFRS). Please see slide 40 of the appendix for a breakdown of the costs.
$US/oz
$6.2B
$9.2B
$11.6B
$14.6B
$19.2B
$27.0B
0
5,000
10,000
15,000
20,000
25,000
30,000
$1,200 $1,350 $1,500 $1,700 $2,000 $2,500
NPV(US$inmillions)
Gold Price (US$)
NPV at 0%NPV at 5%
NPV INCREASES ~20X WITH ~2X INCREASE IN GOLD PRICE
donlin gold has exceptional leverage to gold
▶ Even in a low-price environment,
the project has a positive return
that increases substantially with
higher gold prices
▶ Fast payback at a
broad range of gold prices
▶ Does not take into account:
• Value creation as project
progresses from permitting to
operation
• Significant exploration upside of
the mineralized trend
18
Notes:
Donlin Gold estimates as per updated feasibility study. All dollar figures are in USD and reflect after-tax net present value (at a 0%
and 5% discount rates) of the Donlin Gold project as of 1/1/2014. At a 5% discount rate, the net present value is: $547 m @ $1,200
gold; $1,922m @ $1,350 gold; $3,147m @ $1,500 gold; $4,581 m @ $1,700 gold; $6,722 m @ $2,000 gold; and $10,243 m @
$2,500 gold. Project development costs prior to 1/1/2014 are treated as sunk costs.
0
2
4
6
8
10
12
14
16
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
significant drop in discoveries since 2006
19
Notes:
Data as per SNL MEG’s MineSearch database, Company reports, SNL MEG estimates. Thomson Reuters. Number of discoveries data not yet available for 2013 and 2014.
NumberofGoldDiscoveries
Gold Discovered
Exploration Budget (US$M)
2012
highest year on
record for
exploration
spending and first
year in over two
decades with no
discoveries
2011
gold peaked
at US$1,920/oz
the right project – donlin gold
ARGUABLY THE WORLD’S MOST SIGNIFICANT GOLD PROJECT
partnerships grade
growthjurisdiction
longevity
size
20
donlin gold
Donlin Gold located in Alaska, one of
the safest jurisdictions in the world with
history of successful mining
development
GREAT JURISDICTION COMMITTED TO RESPONSIBLE RESOURCE DEVELOPMENT
the alaska advantage
▶ Alaska is the second largest U.S. gold-
producing State
▶ Well-defined permitting process
▶ Four large precious metals mines, one coal
mine & two base metals mines
▶ Numerous small-scale mines
▶ Natural resource projects integral to the
State’s economy
▶ Strong and time-tested community support
21
COMPANIES HAVE AND CONTINUE TO BUILD MUTUALLY-BENEFICIAL
PARTNERSHIPS IN ALASKA
state supporting development of resource industry
▶ Large Mine Permitting Team responsible for coordinating the permitting process
for large mining projects in the State
▶ Alaska Exploration Incentive Credit Program – up to $20 million deduction over a
15-year period for new mines
▶ Roads to Resources Program (R2R) – transportation and other infrastructure
initiatives to support the development of natural resources
State is committed to work with companies in facilitating cost-effective
access to projects and operations in Alaska
▶ Red Dog mine port & access road owned by State Economic Development
Agency – initially financed by State
▶ Ambler project - earlier-stage initiative in evaluating a 225 mile road to access the
Ambler mining district
22
AMENABLE TERRAIN AND CLIMATE
the right location for mining
23
▸ Excellent setting for mining:
• Rolling hills
• Low precipitation
~20 inches annually
• Elevation range from
150 to 640 meters
▸ Year-round operation
▶ Donlin Gold is not proximate
to major population areas
▶ Located on private land
designated for mining
the right project – donlin gold
ARGUABLY THE WORLD’S MOST SIGNIFICANT GOLD PROJECT
partnerships grade
growthjurisdiction
longevity
size
24
donlin gold
JURISDICTIONAL SAFETY IS MORE THAN GEOGRAPHIC LOCATION
the right stakeholders
Committed Stakeholders
▶ Calista Corporation
▶ The Kuskokwim Corporation
“Calista would like to take this opportunity
to assert and inform the U.S. Army Corps of
Engineers and the public of its legislated
mandate under ANCSA. Calista and TKC
are not only stakeholders, but are the
legislatively mandated landowners charged
with the responsibility of seeing the project
to fruition in an environmentally responsible
manner.”
– June MacAtee, Calista Corporation VP
25
NATIVE CORPORATIONS WANT TO LEAD THE ECONOMIC DEVELOPMENT OF
THEIR REGIONS
mining an integral part of communities
▶ ANCSA established 40 years ago; resolved
legal issues related to Native title claims
▶ Lands valuable for resource potential
selected by Regional Corporations under
ANCSA
▶ Native corporations have an owner’s interest
in the development of the selected lands to
support the economic prosperity of their
shareholders
▶ Mining is compatible and consistent with
subsistence lifestyles
Donlin Gold has the support of the land
owners through a 20+ year relationship
26
EARNING OUR SOCIAL LICENSE AND FORMING LASTING RELATIONSHIPS
working together to build a better future
27
▶ Personal contact
• Active outreach effort to more than 60 remote communities in the region
• Village meetings, camp presentations, mine visits
▶ Communications
• Broad and diverse reach, many materials translated into Yup’ik
• Monthly newsletter, radio announcements, social media, website
▶ Community investments
• Serving to help create a culture that will last for generations
• Safety initiatives, community wellness, economic opportunities
▶ Workforce and skills development
• Promote and enhance youth education
• Encourage local hire
• School programs, internships, scholarships
donlin gold development timeline
28
1.5Moz/year
first five full years1
1.1Moz/year
life of mine1
16 years ̴ 4 27+ years
EXPLORATION&
ENVIRONMENTAL
STUDIES
PERMITTING
ENGINEERING&
CONSTRUCTION
OPERATION
WE ARE HERE
1.5Moz/year
first five full years1
1.1Moz/year
life of mine1
̴ 4
Notes:
1) Donlin Gold data as per the updated feasibility study. Projected annual production represents 100% of which NOVAGOLD’s share represents 50%.
ADVANCING TOWARD A CONSTRUCTION DECISION
DONLIN GOLD ADVANCES ON PERMITTING PATH
permitting milestones
29
published Notice of Intent
public scoping period (Dec. 14/12 - March 29/13)
submit permit applications to federal and state regulatory agencies
preliminary draft EIS (PDEIS) end of 2014
draft EIS
public comment period
final EIS/record of decision
permit issuance
~2
years
PROCEEDING ON SCHEDULE AS PER EIS TIMELINE
current work
▶ Maintaining strong working relationships with the agencies and providing input
throughout the permitting and EIS processes
▶ EIS process and current activities
• Alternatives development addressing mine, pipeline and transportation
components expected to be completed Q1 2014
• PDEIS well underway including defining the baseline conditions and
analyzing consequences expected to be completed by end of 2014
• Draft EIS anticipated in Q1 2015
▶ Major permit application submittals and agency reviews – well underway
• Air quality
• Water discharge and usage
• Pipeline plan of development
• Wetlands
• Dam safety
30
we are here
DONLIN GOLD’S SCALE, QUALITY AND JURISDICTIONAL SAFETY WILL MAKE IT
ONE OF THE MOST COVETED PRECIOUS METALS ASSETS IN THE WORLD
31
“…A quiet haven of permitting peace in a volatile
precious metals sector” John Bridges1
Notes:
The above graph is an illustration that depicts historical share price performance trends of companies and how they relate to the various milestones in an asset’s life cycle. It is not intended to be
representative of the Company’s historical or future financial or share price performance, or indicative of the Company's anticipated timeline to production.
1) North America Equity Research, John Bridges, JP Morgan Chase & Co, 2/17/14
A COMPELLING INVESTMENT OPPORTUNITY WHEN ONE CONSIDERS THE
IMPENDING INDUSTRY PRODUCTION CLIFF
ENHANCING VALUE WHILE EVALUATING OPPORTUNITIES TO MONETIZE ASSET
galore creek
▶ Completed the 2013 drilling program under
budget, exceeding objectives with 11,600
meters drilled
• Confirmed significant mineralization at the
recently discovered Legacy zone
• Identified areas for potential resource
growth
▶ 2014 activities:
• Execute capital efficient work plan
incorporating 2012 and 2013 drill results to
advance the project toward next-level mine
planning and design
• Technical studies:
• Water and waste management
• Site layout
• Ongoing environmental monitoring
32Notes:
1) Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources inclusive of proven and probable
reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix.
9Blbs
copper
8Moz
gold
136Moz
silver
0.5%
copper
0.3g/t
gold
5.2g/t
silver
M&I Resources1
AMONG HIGHEST COPPER GRADE COMPARED TO NORTH AMERICAN ASSETS
galore creek grade peer comparisons
33
P&P + M&I grade (Cu%)
Notes:
Data as per SNL MEG’s MineSearch database, Company reports, SNL MEG estimates.
0.50
0.45
0.42
0.40
0.32
0.30
0.27
0.24
0.21
0.18 0.18
0.00
0.10
0.20
0.30
0.40
0.50
0.60
Galore
Creek
Pebble Rosemont Catface Red Chris Berg Schaft
Creek
New
Prosperity
KSM Mount
Milligan
Casino
CLEAR FOCUS BEGINS WITH STRONG FUNDING TO EXECUTE ON ALL FRONTS
financial obligations have decreased substantially
34
$0
$20
$40
$60
$80
$100
$120
$140
2012 Act(1) 2013 Act 2014 Bud
DiscOps G&A Donlin Gold Galore Creek Interest & other
1
- 70%
- 23%
Notes:
1) 2014 anticipated budget expenditure disclosed on
February 11, 2014
2) Market Capitalization as of March 25, 2014 based
on 316.7 million shares issued and outstanding.
3) Includes US$ 110 million in term deposits as of
November 30, 2013.
4) The Notes mature on May 1, 2015.
market cap2
$1,210
cash and term
deposits3
$190
convertible notes4
$16
in millions of U.S. dollars
reducedby~$100M
26.7%
11.3%
6.9%
2.2%1.7%
51%
INSTITUTIONAL QUALITY INVESTMENT
the NOVAGOLD opportunity
35
Institutional
Ownership
80%
held by top
5 shareholders(1)
49%
Notes:
Shareholder positions are based on the latest 13-F filings.
committed
to Shareholder Value
Electrum Strategic
Resources LP
Paulson & Co.
Inc
The Baupost
Group, L.L.C.
Tocqueville Asset
Management
Sun Valley
Gold, LLC
Other
why NOVAGOLD? why now?
WELL POSITIONED TO DELIVER ON ALL CORPORATE OBJECTIVES
36
toptier, high-quality assets
strongbalance sheet
supportive, loyal, and engaged stakeholders
bestand safest leverage to gold
rightpeople to bring project up value chain
novagold.com
appendix
▶ Donlin Gold LLC is the operating company
▶ 50/50 ownership by NOVAGOLD and Barrick Gold
▶ Board of Directors has two representatives from each company
• Chairman rotates every year
• Each company has the right to appoint the Donlin Gold General Manager every two years
▶ Operates under agreements with Alaska Native Claims Settlement Act (ANCSA) landowners
• Calista Corporation (Subsurface minerals and surface lease)
• The Kuskokwim Corporation (Surface use agreement)
▶ Project office in Anchorage
• 36 full-time employees and 2 contractors
▶ Strong track record for local hiring
ADVANCING DONLIN GOLD UP THE VALUE CHAIN
project overview
38
DONLIN GOLD SLATED TO BE A STATE-OF-THE-ART SIGNIFICANT MINE
project highlights
39
Reserves: 33.9 Moz Au (505M tonnes ore)1
Resources: 5.1 Moz M&I (excluding P&P) and 6.0 Moz Inferred1
Mine Life: ~27 years
Production: Year 1-5,1.5 Moz/year; LOM,1.1 Moz/year
Operation: Open-pit, conventional truck & shovel
Milling: 53.5k tonnes/day, sulfide flotation, pressure
oxidation (POX), carbon-in-leach recovery (CIL)
Strip ratio: 5.5 = 2.8B tonnes waste rock
Tailings: Fully lined storage facility
Power: 153MW average site-generated load, fueled by natural gas
transported via a 315-mile pipeline
Logistics: All consumables supplied by Kuskokwim River transportation
system with port near Jungjuk Creek
See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve and Resource Base” table with footnotes.
donlin gold
LOW OPERATING CASH COSTS AND ALL-IN SUSTAINING COSTS
40
Open-pit mining1 228
Processing 257
G&A, royalties, land & other2 100
Total $585
Open-pit mining1 133
Processing 208
G&A, royalties, land & other2 68
Total $409
Life of Mine Cash Costs Per Ounce
First Five Years Cash Costs Per Ounce
Notes:
Donlin Gold estimates as per the updated feasibility study.
1) Net of deferred costs
2) Based on US$1,200/oz gold price
Life of Mine All-in Sustaining Costs Per Ounce
Cash costs 585
Sustaining capex 50
Stripping capex (IFRS) 46
Corporate administration 27
Reclamation 22
Community development (IFRS) 5
Total $735
First Five Years All-in Sustaining Costs Per Ounce
Cash costs 409
Sustaining capex 45
Stripping capex (IFRS) 0
Corporate administration 21
Reclamation 17
Community development (IFRS) 4
Total $496
41
($10,000)
($5,000)
$0
$5,000
$10,000
$15,000
$20,000
$25,000
$30,000
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
2035
2036
2037
2038
2039
2040
2041
2042
2043
2044
2045
2046
CumulativeNetCashFlow(US$millions)'
$1,200/oz Au $1,500/oz Au $1,700/oz Au $2,000/oz Au $2,500/oz Au
$6,025
$11,459
$14,444
$19,075
$26,803
~4.5x
leverage
NetCashFlow(millions)
All Amounts in US Dollars
Rich Ore Body With a 27-Year Mine Life
and Extensive Exploration Upside
Notes:
Donlin Gold estimates as per the updated feasibility study.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
LEVERAGE TO GOLD & FAST PAYBACK AT A BROAD RANGE OF GOLD PRICES
donlin gold expected to generate substantial cash
flows
donlin gold
WELL POSITIONED TO SHARE UPFRONT COSTS WITH THIRD PARTIES
Areas US$M1 Opportunities1
Mining 345 Leasing equipment ~$170M
Site preparation/roads 236
Process facilities 1,326 Oxygen plant could be built by third party ~$130M
Tailings 120
Utilities 1,302
Ancillary buildings 304
Off-site facilities 243
Total Direct Costs 3,876
Owners’ cost 414
Indirect Costs 1,405
Contingency 984 Healthy Contingency
Total Owner’s & Indirect
Costs, and Contingency
2,803
Total Project Cost 6,679 >$1B potential capital reductions
Gas pipeline could be built by third party $834M
1) Represents 100% of project’s capital expenditures 42
ROBUST ECONOMICS HIGHLY LEVERAGED TO GOLD PRICES
donlin gold key performance indicators
43
Gold Price
Unit $1,000/oz $1,200/oz
Base Case
$1,700/oz $2,000/oz $2,500/oz
Average annual
after-tax cash flow
(first full five years)
$M 670 950 1,500 1,785 2,185
Average annual
after-tax cash flow (LOM)
$M 350 500 815 990 1,275
NPV (5%) after-tax1 $M (1,340) 550 4,580 6,720 10,240
NPV (0%) after-tax1 $M 2,100 6,200 14,620 19,250 26,975
IRR after-tax1 % 2.3 6.0 12.3 15.1 19.1
Payback period Years 19.1 9.2 5.3 4.4 3.5
Notes:
Donlin Gold estimates as per the updated feasibility study. All dollar figures are in USD and reflect after-tax net present value (at a 0% and 5% discount rates) of the Donlin Gold Project as of
1/1/2014. At a 5% discount rate, the net present value is: $547 m @ $1,200 gold; $4,581 m @ $1,700 gold; $6,722 m @ $2,000 gold; and $10,243 m @ $2,500 gold. Project development costs prior
to that date are treated as sunk costs.
All amounts in US dollars
1) NPVs and IRRs as at January 1, 2014. Project development costs prior to that date are treated as sunk costs.
donlin gold: standard technology
Donlin Gold Pueblo Viejo Detour Lake
Capital Expenditures US$6.7B1 ~US$4.0B2 C$1.5B4
Location Alaska, US Sanchez Ramirez, Dominican
Republic
Ontario, Canada
Mining Method Open Pit Open Pit Open Pit
Project Status Permitting Commercial Operation Start Up
Total M&I Resources
(inclusive of reserves)
39.0 Moz 36.3 Moz 23.3 Moz
Nameplate Design Throughput (tpd) 53,500 24,000 61,000
M&I Grade (g/t) 2.24 2.41 1.07
Recovery (%) 89.8 92 91
Strip Ratio 5.5 1.2 3.7
Expected Average Annual Production
(oz)
1,500,000 3 1,042,000 – 1,125,000 3 ~650,000
Processing Method Flotation/Autoclaving/Leaching Autoclave/Leaching/Ag/Cu Recovery Gravity Concentration/High-Intensity Leaching
Ball Mill Underflow & Gravity Tails Leaching
Number of Autoclaves 2 medium 4 large N/A
Key Infrastructure Natural gas pipeline/Power plant
Oxygen plant
Power plant and Transmission Line/
Oxygen plant/Lime Kilns/Limestone
Grinding
180 km 230kV Transmission Line
Mine Life 27 years 25 years 22 years
WELL ESTABLISHED MINING AND MINERAL PROCESSING METHODOLOGY
Notes:
Donlin Gold estimates as per the updated feasibility study. Peer data as per company documents, public filings and websites. Represents 100% of measured and indicated resources of which NOVAGOLD’s
share represents 50%. Measured and indicated resources inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base”
with footnotes in the appendix.
1) Capital expenditure shown on a 100% project basis.
2) Capital expenditure of US$3.7B disclosed in Barrick Gold’s press release dated 01/15/13, plus a net incremental cost of approximately US$300M for the power plant.
3) Production expected for first full five years of operation.
4) Revised at end of 3Q 2012, as per press release dated 11/8/12.
44
WEST COAST RIVER BARGE UP KUSKOKWIM RIVER WITH TWO PORT FACILITIES
logistics & supply chain
45
PROPOSED PIPELINE TIES INTO EXISTING INFRASTRUCTURE AT COOK INLET
powering the project
46
▸ Project would require 153MW of
electricity to power the mill &
facilities
▸ Fueled by natural gas transported
via a 315-mile-long, 14-inch
pipeline
▸ Donlin Gold has studied various pipeline
routes and collected baseline data on:
• Wetlands, stream crossings and aquatic
resources
• Cultural sites
• Seismic conditions
• The Iditarod Trail
LARGE PROJECTS HAVE BEEN SUCCESSFULLY PERMITTED
permitting in the U.S.
47
Project Name Location Metal Time Description
Red Dog Mine Alaska Lead/zinc ~2 years
• Expansion
• EIS completed in 2009
• Development started on schedule in 2010
Fort Knox Alaska Gold ~3 years
• Expansion – new heap leach facility
• Permitting completed in 2007
Pogo Alaska Gold ~3 years
• New mine
• Permitting completed in 2004
• Operations began in 2006
Rochester Mine Nevada Silver ~1 year
• Expansion – new heap leach & mine reopening
• EA/permitting completed in 2011
Cortez Gold Nevada Gold ~3 years
• Major pit expansion
• EIS/permitting completed in 2008/2009
Goldstrike Nevada Gold ~2 years
• Major pit expansion
• Waste rock and tailings facilities
• ROD approving the project was in 2009
Hycroft Gold Nevada Gold ~2 years
• Reactivation
• EIS/permitting completed in 2012
Climax Molybdenum Colorado Molybdenum ~5 years
• Re-opening
• State permitting completed in 2012
• New production began in 2012
48
ONLY THREE PROJECTS IN THE WORLD ARE SLATED TO PRODUCE >1MOZ/YEAR
mines the size of donlin gold are scarce
Notes:
Donlin Gold projected annual production represents 100% of which NOVAGOLD’s share represents 50%. All other
production estimates, with the exception of Grasberg, are based on published 2014 average gold annual production
guidance. Grasberg represents the published 2014 gold sales guidance. Excludes Newmont’s Nevada operations that
consist of multiple mines. Analysis includes life of mine data for Donlin Gold.
1) If put into production as contemplated by the updated feasibility study.
156 MINES
>100 Koz
21 MINES
>500 Koz
8 MINES
>800 Koz
3 MINES/
Projects
>1 Moz
GRASBERG
Indonesia
PUEBLO VIEJO
Dominican Republic
DONLIN GOLD
USA
▸ 1.5 Moz/year in first five full years1
▸ 1.1 Moz/year LOM1
Donlin Gold:
Only undeveloped asset in this category in North America
1
GALORE CREEK, AN EXCEPTIONAL ASSET
project overview
49
▶ Galore Creek Mining Corporation (GCMC) is the operating company
▸ 50/50 ownership by NOVAGOLD and Teck Resources Inc.
▸ Management Committee has two representatives from each company
• Chairman rotates every year
▸ Project is located within the Tahltan Nation Territory and operates under a
Participation Agreement
▸ All mineral claims are on Crown land
▸ Project office in Vancouver
• Abundance of technical strength to draw from within Teck
▸ Strong track record for Tahltan hiring at project site as well as contracting and
procurement with Tahltan businesses and joint ventures
GALORE CREEK TO BE ONE OF CANADA’S LARGEST COPPER MINES
project highlights
50
Reserves: 6.8 Blb Cu; 5.5 Moz Au; 102 Moz Ag 1
Resources: 8.9 Blb Cu; 8.0 Moz Au; 136 Moz Ag (inclusive of reserves) 1
Mine Life: ~18 years
Production: Year 1-5, 400 Mlb/year Cu; LOM, 340 Mlb/year Cu
Operation: Open-pit, conventional truck & shovel
Milling: +80k tonnes/day, conventional crush, grind, and Cu/Au/Ag flotation
concentration, plant located in West More Valley
Strip ratio: 2.2 = 1.1B tonnes waste rock
Tailings: storage facility located in West More Valley next to plant
Power: BC Hydro currently constructing the Northwest Transmission Line from
near Terrace, BC to Bob Quinn to promote remote industrial
development, Galore Creek to tie into the NTL
Logistics: Port facilities to be built near Stewart, BC
Notes:
See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve and Resource Base” table with footnotes.
ROBUST ECONOMICS HIGHLY LEVERAGED TO METAL PRICES
galore creek key performance indicators
51
Unit Metal Prices
Copper
Gold
Silver
US$/lb
US$/oz
US$/oz
2.00
900
15.00
2.65
1,100
18.50
3.00
1,100
20.00
3.50
1,200
25.00
4.00
1,300
30.00
LOM after-tax cash flow $M 1,514 5,118 6,641 9,223 11,812
NPV (5%) after-tax1 $M (969) 988 1,794 3,134 4,458
NPV (7%) after-tax1 $M (1,431) 137 778 1,837 2,877
IRR after-tax1 % 2.4 7.4 9.2 11.9 14.3
Payback period Years 13.2 7.8 6.1 4.1 3.3
Notes:
Galore Creek estimates as per the 2011 Pre-Feasibility Study. All dollar figures are in CAD. See “Cautionary Note Concerning Reserve & Resource Estimates” and
“Reserve & Resource Base” with footnotes in the appendix.
1) NPVs and IRRs as of two years prior to significant project spend. Project development costs prior to that point are treated as sunk costs.
All amounts in CAD dollars
INDUSTRY LEADERS TO BRING DONLIN GOLD THROUGH PERMITTING & BEYOND
the NOVAGOLD team
52
Gregory Lang
President & CEO
▸ Former President of Barrick Gold North America
▸ 35 years experience building & operating major mines
▸ Intimate knowledge of Donlin Gold
David Deisley
Executive Vice President and
General Counsel
▸ Former EVP and General Counsel of Goldcorp
▸ Regional General Counsel for Barrick Gold North America
▸ Extensive track record in project permitting, corporate social responsibility,
mergers and acquisitions and corporate development
▸ 25 years of mining industry experience
David Ottewell
Vice President and Chief
Financial Officer
▸ Former VP and Corporate Controller of Newmont Mining Corporation
▸ 25 years of mining industry experience
▸ Diverse experience in all facets of financial management, from mine operations
to executive corporate financial management of premier gold producers
Mélanie Hennessey
Vice President, Corporate
Communications
▸ Held variety of executive and senior IR & corporate communications positions
with Goldcorp Inc., New Gold Inc., and Hecla Mining Company
▸ Leading NOVAGOLD’s internal and external communications functions
Ron Rimelman
Vice President, Environment,
Health, Safety & Sustainability
▸ 25+ years of environmental experience, managing environmental impact
assessments and permitting activities world-wide
▸ Leadership role on mine permitting and NEPA evaluations for mine projects in
Alaska since 1993
Richard Williams
Vice President, Engineering
and Development
▸ Former Project Director for the Pueblo Viejo project in the Dominican Republic
▸ 30 years of experience developing and operating major mines world-wide
▸ Particular expertise in autoclave technology
MANAGEMENT
NOVAGOLD board of directors
53
Dr. Thomas Kaplan
Chairman
Chairman and CIO of The Electrum Group LLC, a privately held natural resources
investor that controls a diversified portfolio of precious and base metals assets
Sharon Dowdall
Former Chief Legal Officer and Corporate Secretary with Franco-Nevada, transforming an
industry pioneer into one of the most successful precious metals enterprises in the world
Dr. Marc Faber
Publishes a monthly investment newsletter entitled The Gloom, Boom & Doom
Report and is the author of several books
Greg Lang
President & CEO
Former President of Barrick Gold North America, 35 years experience building &
operating major mines with intimate knowledge of Donlin Gold
Gil Leathley
COO and Director of Sunward Resources, former Senior Vice President and Chief
Operating Officer of the Company
Igor Levental
President of The Electrum Group LLC, former VP of Homestake Mining and International
Corona Corp.
Kalidas Madhavpeddi Former Executive with Phelps Dodge
Gerald McConnell Former Chairman and CEO of NOVAGOLD, CEO of Namibia Rare Earths Inc.
Clynton Nauman CEO of Alexco Resources, formerly with Viceroy Gold and Kennecott Minerals
Rick Van Nieuwenhuyse CEO of NovaCopper, founder and former CEO of NOVAGOLD
Anthony Walsh
Former President and Chief Executive Officer of Miramar Mining Corporation, which in
2007 was sold to Newmont Mining Company.
donlin gold management team
54
Stanley Foo
President/General
Manager
30+ years mining industry experience in exploration, mine geology, operations management, project management
and permitting; 12 years mine operations experience in NV including superintendent roles at Cortez and Bald Mtn;
15 years in Alaska in project management and permitting; Previous Project Manager roles with Donlin 1997-99,
2005-2007, served on Donlin Gold LLC board 2008-2010.
James Fueg
Study Manager
Led Donlin Gold’s recent feasibility studies and coordinates all engineering and technical work for project;
20+ years experience in mining, exploration and environmental science; 16 years in Alaska; at Donlin since 2004.
Robert Nick Enos
Environmental and
Permitting Manager
Leads permitting and environmental management for project; primary contact for reg. agencies; 20 years
experience in Alaska in geology, environmental science and permitting management; Previous experience
includes Greens Creek, Calista Corp., as environmental/permitting consultant; Joined Donlin in 2005.
Kurt Parkan
External Affairs
Manager
Leads Donlin Gold’s community affairs, communications, government relations and corporate social responsibility
functions; Nearly 30 years public affairs experience in Alaska; Previous roles: External Affairs Director of Nature
Conservancy of Alaska, Deputy Commissioner for Alaska Department of Transportation and Public Facilities,
Special Assistant to the Governor, Legislative Aide and as staff for Alaska House of Representatives Finance
Committee.
Meg Day
Human Resources
Manager
22 years human resources experience in the mining industry including 17 years in Alaska; Served in various
senior management positions in Alaska, Utah and Washington and has been involved in the start up of several
mines. Serves on Alaska Miners Association HR Committee, Society of HR Management and Advisory Board
member of University of Alaska.
Jan Halstead
Administrative and
Finance Manager
25+ years accounting and financial analysis experience in construction, investment, telecommunications;
Responsible for growth and development of Accounting, Administration, Purchasing and Contract functions for
Donlin Gold LLC.
COPPER
Tonnage
Mt
Grade*
%Cu
Metal content
Mlbs
NOVAGOLD share**
Mlbs
Reserves (100%)2
Proven 69.0 0.61 900.0 450.0
Probable 459.1 0.58 5,900.0 2,950.0
P&P 528.0 0.59 6,800.0 3,400.0
Resources (100%)4 inclusive of reserves
Measured 108.4 0.48 1,147.0 573.5
Indicated 706.3 0.50 7,786.0 3,893.0
M&I 814.7 0.50 8,933.0 4,466.5
Inferred 346.6 0.42 3,230.0 1,615.0
GOLD
Mt g/t Moz Moz
Reserves (100%)2
Proven 69.0 0.52 1.15 0.58
Probable 459.1 0.29 4.30 2.15
P&P 528.0 0.32 5.45 2.73
Resources (100%)4 inclusive of reserves
Measured 108.4 0.48 1.70 0.85
Indicated 706.3 0.28 6.40 3.20
M&I 814.7 0.31 8.00 4.00
Inferred 346.6 0.24 2.70 1.35
SILVER
Mt g/t Moz Moz
Reserves (100%)2
Proven 69.0 4.94 11.0 5.5
Probable 459.1 6.18 91.2 45.6
P&P 528.0 6.02 102.2 51.1
Resources (100%)4 inclusive of reserves
Measured 108.4 4.10 14.30 7.15
Indicated 706.3 5.38 122.10 61.05
M&I 814.7 5.21 136.40 68.20
Inferred 346.6 4.28 47.73 23.87
At April 30, 2012
Donlin Gold (NOVAGOLD 50%)
Galore Creek (NOVAGOLD 50%)
GOLD
Tonnage
Mt
Grade*
g/t
Metal content
Moz
NOVAGOLD share**
Moz
Reserves (100%)1
Proven 7.7 2.32 0.57 0.29
Probable 497.1 2.08 33.28 16.64
P&P 504.8 2.09 33.85 16.93
Resources (100%)3 inclusive of reserves
Measured 7.7 2.52 0.63 0.31
Indicated 533.6 2.24 38.38 19.19
M&I 541.3 2.24 39.01 19.50
Inferred 92.2 2.02 5.99 3.00
NOVAGOLD reserve/resource table
55
reserve/resource table (con’t)
Resources (100%)5,6 Tonnage Grade* Metal content NOVAGOLD share**
COPPER Mt %Cu Mlbs Mlbs
Inferred 53.7 0.50 592.0 414.4
GOLD Mt g/t Moz Moz
Inferred 53.7 0.73 1.26 0.88
SILVER Mt g/t Moz Moz
Inferred 53.7 10.60 18.36 12.85
Copper Canyon (NOVAGOLD 70%)
t = metric tonne
M = million
g/t = grams/tonne
* Reserve grade is diluted; resource
grade is in situ.
** NOVAGOLD share net after earn-ins
Approximate cut-off grades (see Resource Footnotes below):
Donlin Gold Reserves1: 0.57 g/t gold
Resources3: 0.46 g/t gold
Galore Creek Reserves2: C$10.08 NSR
Resources4: C$10.08 NSR
Copper Canyon Resources5,6: 0.6% copper equivalent
56
Notes:
a. These resource estimates have been prepared in accordance with NI43-101 and the CIM Definition Standard, unless otherwise noted.
b. See numbered footnotes below on resource information.
c. Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal content
d. Tonnage and grade measurements are in metric units. Contained gold and silver ounces are reported as troy ounces, contained copper pounds as imperial pounds
Resource Footnotes:
Mineral Reserves are contained within Measured and Indicated pit designs, and supported by a mine plan, featuring variable throughput rates, stockpiling and cut-off optimization. The pit designs and mine plan were optimized on diluted grades using the following economic and technical parameters: Metal price for
gold of US$975/oz; reference mining cost of US$1.67/t incremented US$0.0031/t/m with depth from the 220 m elevation (equates to an average mining cost of US$2.14/t), variable processing cost based on the formula 2.1874 x (S%) + 10.65 for each US$/t processed; general and administrative cost of US$2.27/t
processed; stockpile rehandle costs of US$0.19/t processed assuming that 45% of mill feed is rehandled; variable recoveries by rock type, ranging from 86.66% in shale to 94.17% in intrusive rocks in the Akivik domain; refining and freight charges of US$1.78/oz gold; royalty considerations of 4.5%; and variable pit
slope angles, ranging from 23º to 43º. Mineral Reserves are reported using an optimized net sales return value based on the following equation: Net Sales Return = Au grade * Recovery * (US$975/oz – (1.78 + (US$975/oz – 1.78) * 0.045)) - (10.65 + 2.1874 * (S%) + 2.27 + 0.19) and reported in US$/tonne. Assuming
an average recovery of 89.54% and an average S% grade of 1.07%, the marginal gold cutoff grade would be approximately 0.57 g/t, or the gold grade that would equate to a 0.001 NSR cutoff at these same values. The life of mine strip ratio is 5.48. The assumed life-of-mine throughput rate is 53.5 kt/d.
Mineral Reserves are contained within Measured and Indicated pit designs using metal prices for copper, gold and silver of US$2.50/lb, US$1,050/oz, and US$16.85/oz, respectively. Appropriate mining costs, processing costs, metal recoveries and inter ramp pit slope angles varing from 42º to 55º were used to
generate the pit phase designs. Mineral Reserves have been calculated using a 'cashflow grade' ($NSR/SAG mill hr) cut-off which was varied from year to year to optimize NPV. The net smelter return (NSR) was calculated as follows: NSR = Recoverable Revenue – TCRC (on a per tonne basis), where: NSR = Net
Smelter Return; TCRC = Transportation and Refining Costs; Recoverable Revenue = Revenue in Canadian dollars for recoverable copper, recoverable gold, and recoverable silver using metal prices of US$2.50/lb, US$1,050/oz, and US$16.85/oz for copper, gold, and silver, respectively, at an exchange rate of
CDN$1.1 to US$1.0; Cu Recovery = Recovery for copper based on mineral zone and total copper grade; for Mineral Reserves this NSR calculation includes mining dilution. SAG throughputs were modeled by correlation with alteration types. Cash flow grades were calculated as the product of NSR value in $/t and
throughput in t/hr. The life of mine strip ratio is 2.16.
Mineral Resources are contained within a conceptual Measured, Indicated and Inferred optimized pit shell using the following assumptions: gold price of US$1,200/oz; variable process cost based on 2.1874 * (sulphur grade) + 10.6485; administration cost of US$2.29/t; refining, freight & marketing (selling costs) of
US$1.85/oz recovered; stockpile rehandle costs of US$0.20/t processed assuming that 45% of mill feed is rehandled; variable royalty rate, based on royalty of 4.5% * (Au price – selling cost). Mineral Resources have been estimated using a constant Net Sales Return cut-off of US$0.001/t milled. The Net Sales Return
was calculated using the formula: Net Sales Return = Au grade * Recovery * (US$1200/oz – (1.85 + ((US$1200/oz – 1.85) * 0.045)) - (10.65 + 2.1874 * (S%) + 2.29 + 0.20)) and reported in US$/tonne. Mineral Resources are inclusive of Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have
demonstrated economic viability. Inferred Resources are in addition to Measured and Indicated Resources. Inferred Resources have a great amount of uncertainty as to their existence and whether they can be mined legally or economically. It cannot be assumed that all or any part of the Inferred Resources will ever
be upgraded to a higher category. See "Cautionary Note Concerning Reserve & Resource Estimates".
Mineral resources are contained within a conceptual Measured, Indicated and Inferred optimized pit shell using the same economic and technical parameters as used for Mineral Reserves. Tonnages are assigned based on proportion of the block below topography. The overburden/bedrock boundary has been
assigned on a whole block basis. Mineral resources have been estimated using a constant NSR cut-off of C$10.08/t milled. The Net Smelter Return (NSR) was calculated as follows: NSR = Recoverable Revenue – TCRC (on a per tonne basis), where: NSR = Diluted Net Smelter Return; TCRC = Transportation and
Refining Costs; Recoverable Revenue = Revenue in Canadian dollars for recoverable copper, recoverable gold, and recoverable silver using silver using the economic and technical parameters mentioned above. The mineral resource includes material within the conceptual M,I&I pit that is not scheduled for processing
in the mine plan but is above cutoff. Mineral Resources are inclusive of Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Inferred Resources are in addition to Measured and Indicated Resources. Inferred Resources have a great amount of uncertainty
as to their existence and whether they can be mined legally or economically. It cannot be assumed that all or any part of the Inferred Resources will ever be upgraded to a higher category. See "Cautionary Note Concerning Reserve & Resource Estimates".
The copper-equivalent grade was calculated as follows: CuEq = Recoverable Revenue ÷ 2204.62 * 100 ÷ 1.55. Where: CuEq = Copper equivalent grade; Recoverable Revenue = Revenue in US dollars for recoverable copper, recoverable gold and recoverable silver using metal prices of US$1.55/lb, US$650/oz, and
US$11/oz for copper, gold, and silver, respectively; for the purposes of the equivalency formula, Cu Recovery is assumed to be 100%. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Inferred Resources are in addition to Measured and Indicated Resources. Inferred
Resources have a great amount of uncertainty as to their existence and whether they can be mined legally or economically. It cannot be assumed that all or any part of the Inferred Resources will ever be upgraded to a higher category. See "Cautionary Note Concerning Reserve & Resource Estimates".
NOVAGOLD Canada Inc. has agreed to transfer its 60% joint venture interest in the Copper Canyon property to the Galore Creek Partnership, which is equally owned by NOVAGOLD Canada Inc. and a subsidiary of Teck Resources Limited. The remaining 40% joint venture interest in the Copper Canyon property is
owned by another wholly owned subsidiary of NOVAGOLD.
Cautionary Note Concerning Reserve & Resource Estimates
This summary table uses the term “resources”, “measured resources”, “indicated resources” and “inferred resources”. United States investors are advised that, while such terms are recognized and required by Canadian securities laws, the United States Securities and Exchange Commission (the “SEC”) does not
recognize them. Under United States standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. Mineral resources that are not mineral reserves
do not have demonstrated economic viability. United States investors are cautioned not to assume that all or any part of measured or indicated resources will ever be converted into reserves. Further, inferred resources have a great amount of uncertainty as to their existence and as to whether they can be mined
legally or economically. It cannot be assumed that all or any part of the inferred resources will ever be upgraded to a higher category. Therefore, United States investors are also cautioned not to assume that all or any part of the inferred resources exist, or that they can be mined legally or economically. Disclosure of
“contained ounces” is permitted disclosure under Canadian regulations, however, the SEC normally only permits issuers to report “resources” as in place tonnage and grade without reference to unit measures. Accordingly, information concerning descriptions of mineralization and resources contained in this release
may not be comparable to information made public by United States companies subject to the reporting and disclosure requirements of the SEC.
NI 43-101 is a rule developed by the Canadian Securities Administrators, which established standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Unless otherwise indicated, all resource estimates contained in this circular have been prepared in
accordance with NI 43-101 and the CIM Definition Standards.
Technical Reports and Qualified Persons
The documents referenced below provide supporting technical information for each of NOVAGOLD's projects.
Project Qualified Person(s) Most Recent Disclosure & Filing Date
Donlin Gold Tony Lipiec, P. Eng., AMEC Donlin Creek Gold Project
Gordon Seibel R.M. SME, AMEC Alaska, USA
Kirk Hanson P.E., AMEC NI 43-101 Technical Report on Second Updated Feasibility Study amended filing on January 23, 2012
Galore Creek Robert Gill, P.Eng., AMEC Galore Creek Copper–Gold Project,
Jay Melnyk, P.Eng., AMEC British Columbia, NI 43-101 Technical Report on Pre-Feasibility Study,
Greg Kulla, P.Geo., AMEC filed on September 12, 2011
Greg Wortman, P.Eng., AMEC
Dana Rogers, P.Eng., Lemley International
Heather White, B.Sc., P.Eng., who is a consultant to NOVAGOLD and a “qualified person” under NI 43-101, has approved the scientific and technical information included in this section related to: (i) Donlin Gold since the issuance of the technical report filed on January 23, 2012, and (ii) Galore Creek since the
issuance of the technical report filed on September 12, 2011.
reserve/resource table (con’t)
57
58
NOVAGOLD RESOURCES INC.
Suite 720 – 789 West Pender Street
Vancouver, BC
Canada V6C 1H2
T 604 669 6227 TF 1 866 669 6227 F 604 669 6272
www.novagold.com
info@novagold.com
Mélanie Hennessey
VP, Corporate Communications
melanie.hennessey@novagold.com
Erin O’Toole
Analyst, Investor Relations
erin.otoole@novagold.com
contact us

Contenu connexe

Tendances

International Precious Metals and Commodities Show - Munich
International Precious Metals and Commodities Show - Munich International Precious Metals and Commodities Show - Munich
International Precious Metals and Commodities Show - Munich NOVAGOLD
 
Vancouver Investment Resource Conference 2016
Vancouver Investment Resource Conference 2016 Vancouver Investment Resource Conference 2016
Vancouver Investment Resource Conference 2016 NOVAGOLD
 
Precious Metals Summit Zurich Corporate Presentation
Precious Metals Summit Zurich Corporate PresentationPrecious Metals Summit Zurich Corporate Presentation
Precious Metals Summit Zurich Corporate PresentationNOVAGOLD
 
Precious Metals Summit, Colorado
Precious Metals Summit, ColoradoPrecious Metals Summit, Colorado
Precious Metals Summit, ColoradoNOVAGOLD
 
Bank of America Merrill Lynch 20th Annual Canada Mining Conference
Bank of America Merrill Lynch 20th Annual Canada Mining ConferenceBank of America Merrill Lynch 20th Annual Canada Mining Conference
Bank of America Merrill Lynch 20th Annual Canada Mining ConferenceNOVAGOLD
 
NOVAGOLD Corporate Presentation – October 2016
NOVAGOLD Corporate Presentation – October 2016NOVAGOLD Corporate Presentation – October 2016
NOVAGOLD Corporate Presentation – October 2016NOVAGOLD
 
2014 Precious Metals Summit, Hong Kong
2014 Precious Metals Summit, Hong Kong2014 Precious Metals Summit, Hong Kong
2014 Precious Metals Summit, Hong KongNOVAGOLD
 
Denver Gold Forum, Colorado
Denver Gold Forum, ColoradoDenver Gold Forum, Colorado
Denver Gold Forum, ColoradoNOVAGOLD
 
September Mining Conferences
September Mining Conferences September Mining Conferences
September Mining Conferences NOVAGOLD
 
TD Securities' 2017 Mining Conference
TD Securities' 2017 Mining ConferenceTD Securities' 2017 Mining Conference
TD Securities' 2017 Mining ConferenceNOVAGOLD
 
BMO Global Metals & Mining Conference
BMO Global Metals & Mining ConferenceBMO Global Metals & Mining Conference
BMO Global Metals & Mining ConferenceNOVAGOLD
 
PDAC 2015 - Toronto
PDAC 2015 - TorontoPDAC 2015 - Toronto
PDAC 2015 - TorontoNOVAGOLD
 
NOVAGOLD Corporate Presentation - February 2015
NOVAGOLD Corporate Presentation - February 2015 NOVAGOLD Corporate Presentation - February 2015
NOVAGOLD Corporate Presentation - February 2015 NOVAGOLD
 
PDAC Convention 2014
PDAC Convention 2014 PDAC Convention 2014
PDAC Convention 2014 NOVAGOLD
 
NOVAGOLD 2013 Annual General and Special Meeting of Shareholders
NOVAGOLD 2013 Annual General and Special Meeting of ShareholdersNOVAGOLD 2013 Annual General and Special Meeting of Shareholders
NOVAGOLD 2013 Annual General and Special Meeting of ShareholdersNOVAGOLD
 
JTVIR Conference, NYC
JTVIR Conference, NYCJTVIR Conference, NYC
JTVIR Conference, NYCNOVAGOLD
 
Precious Metals Summit, Beaver Creek
Precious Metals Summit, Beaver Creek Precious Metals Summit, Beaver Creek
Precious Metals Summit, Beaver Creek NOVAGOLD
 
Denver Gold Forum 2015
Denver Gold Forum 2015 Denver Gold Forum 2015
Denver Gold Forum 2015 NOVAGOLD
 

Tendances (18)

International Precious Metals and Commodities Show - Munich
International Precious Metals and Commodities Show - Munich International Precious Metals and Commodities Show - Munich
International Precious Metals and Commodities Show - Munich
 
Vancouver Investment Resource Conference 2016
Vancouver Investment Resource Conference 2016 Vancouver Investment Resource Conference 2016
Vancouver Investment Resource Conference 2016
 
Precious Metals Summit Zurich Corporate Presentation
Precious Metals Summit Zurich Corporate PresentationPrecious Metals Summit Zurich Corporate Presentation
Precious Metals Summit Zurich Corporate Presentation
 
Precious Metals Summit, Colorado
Precious Metals Summit, ColoradoPrecious Metals Summit, Colorado
Precious Metals Summit, Colorado
 
Bank of America Merrill Lynch 20th Annual Canada Mining Conference
Bank of America Merrill Lynch 20th Annual Canada Mining ConferenceBank of America Merrill Lynch 20th Annual Canada Mining Conference
Bank of America Merrill Lynch 20th Annual Canada Mining Conference
 
NOVAGOLD Corporate Presentation – October 2016
NOVAGOLD Corporate Presentation – October 2016NOVAGOLD Corporate Presentation – October 2016
NOVAGOLD Corporate Presentation – October 2016
 
2014 Precious Metals Summit, Hong Kong
2014 Precious Metals Summit, Hong Kong2014 Precious Metals Summit, Hong Kong
2014 Precious Metals Summit, Hong Kong
 
Denver Gold Forum, Colorado
Denver Gold Forum, ColoradoDenver Gold Forum, Colorado
Denver Gold Forum, Colorado
 
September Mining Conferences
September Mining Conferences September Mining Conferences
September Mining Conferences
 
TD Securities' 2017 Mining Conference
TD Securities' 2017 Mining ConferenceTD Securities' 2017 Mining Conference
TD Securities' 2017 Mining Conference
 
BMO Global Metals & Mining Conference
BMO Global Metals & Mining ConferenceBMO Global Metals & Mining Conference
BMO Global Metals & Mining Conference
 
PDAC 2015 - Toronto
PDAC 2015 - TorontoPDAC 2015 - Toronto
PDAC 2015 - Toronto
 
NOVAGOLD Corporate Presentation - February 2015
NOVAGOLD Corporate Presentation - February 2015 NOVAGOLD Corporate Presentation - February 2015
NOVAGOLD Corporate Presentation - February 2015
 
PDAC Convention 2014
PDAC Convention 2014 PDAC Convention 2014
PDAC Convention 2014
 
NOVAGOLD 2013 Annual General and Special Meeting of Shareholders
NOVAGOLD 2013 Annual General and Special Meeting of ShareholdersNOVAGOLD 2013 Annual General and Special Meeting of Shareholders
NOVAGOLD 2013 Annual General and Special Meeting of Shareholders
 
JTVIR Conference, NYC
JTVIR Conference, NYCJTVIR Conference, NYC
JTVIR Conference, NYC
 
Precious Metals Summit, Beaver Creek
Precious Metals Summit, Beaver Creek Precious Metals Summit, Beaver Creek
Precious Metals Summit, Beaver Creek
 
Denver Gold Forum 2015
Denver Gold Forum 2015 Denver Gold Forum 2015
Denver Gold Forum 2015
 

En vedette

A germline mutation in the brca1 3'utr predicts stage iv breast cancer
A germline mutation in the brca1 3'utr predicts stage iv breast cancerA germline mutation in the brca1 3'utr predicts stage iv breast cancer
A germline mutation in the brca1 3'utr predicts stage iv breast cancerDavid W. Salzman
 
Intended institution
Intended institutionIntended institution
Intended institutionbuchsmedia
 
Presentation To San Francisco Executives Association 4 8 2011 Double Your Sal...
Presentation To San Francisco Executives Association 4 8 2011 Double Your Sal...Presentation To San Francisco Executives Association 4 8 2011 Double Your Sal...
Presentation To San Francisco Executives Association 4 8 2011 Double Your Sal...Zoom Industries
 
The State of the Energy Industry
The State of the Energy IndustryThe State of the Energy Industry
The State of the Energy IndustryScottMadden, Inc.
 
Australians working in Asia: how to make the most of your offshore assignment
Australians working in Asia: how to make the most of your offshore assignment Australians working in Asia: how to make the most of your offshore assignment
Australians working in Asia: how to make the most of your offshore assignment Stacey Martin
 
Using a private cloud to automate and govern enterprise development
Using a private cloud to automate and govern enterprise developmentUsing a private cloud to automate and govern enterprise development
Using a private cloud to automate and govern enterprise developmentWSO2
 
Auren News March 2012
Auren News March 2012Auren News March 2012
Auren News March 2012abudic
 
How to deliver_a_fantastic_power_point_presentation.pptx_submit.pptxsubmit (1)
How to deliver_a_fantastic_power_point_presentation.pptx_submit.pptxsubmit (1)How to deliver_a_fantastic_power_point_presentation.pptx_submit.pptxsubmit (1)
How to deliver_a_fantastic_power_point_presentation.pptx_submit.pptxsubmit (1)Kathleen Clark
 
Biosimilars -- Wave of the Future or Child of the Privileged Few?
Biosimilars -- Wave of the Future or Child of the Privileged Few?Biosimilars -- Wave of the Future or Child of the Privileged Few?
Biosimilars -- Wave of the Future or Child of the Privileged Few?Michael Swit
 
Guidelines for preparing the master´s thesis
Guidelines for preparing the master´s thesisGuidelines for preparing the master´s thesis
Guidelines for preparing the master´s thesisnelfea
 
01 roland top storage trends_praha_02
01 roland top storage trends_praha_0201 roland top storage trends_praha_02
01 roland top storage trends_praha_02IDC_CEMA
 
Sample employment contract
Sample employment contractSample employment contract
Sample employment contractJohn Vaughn, CMI
 
Jonathan neufeld nuts and bolts
Jonathan neufeld   nuts and boltsJonathan neufeld   nuts and bolts
Jonathan neufeld nuts and boltsSamantha Haas
 
Research Data Management
Research Data ManagementResearch Data Management
Research Data ManagementJamie Bisset
 
CSS Box Model and Dimensions
CSS Box Model and DimensionsCSS Box Model and Dimensions
CSS Box Model and DimensionsGerson Abesamis
 

En vedette (20)

A germline mutation in the brca1 3'utr predicts stage iv breast cancer
A germline mutation in the brca1 3'utr predicts stage iv breast cancerA germline mutation in the brca1 3'utr predicts stage iv breast cancer
A germline mutation in the brca1 3'utr predicts stage iv breast cancer
 
Intended institution
Intended institutionIntended institution
Intended institution
 
Presentation To San Francisco Executives Association 4 8 2011 Double Your Sal...
Presentation To San Francisco Executives Association 4 8 2011 Double Your Sal...Presentation To San Francisco Executives Association 4 8 2011 Double Your Sal...
Presentation To San Francisco Executives Association 4 8 2011 Double Your Sal...
 
The State of the Energy Industry
The State of the Energy IndustryThe State of the Energy Industry
The State of the Energy Industry
 
Australians working in Asia: how to make the most of your offshore assignment
Australians working in Asia: how to make the most of your offshore assignment Australians working in Asia: how to make the most of your offshore assignment
Australians working in Asia: how to make the most of your offshore assignment
 
Using a private cloud to automate and govern enterprise development
Using a private cloud to automate and govern enterprise developmentUsing a private cloud to automate and govern enterprise development
Using a private cloud to automate and govern enterprise development
 
Auren News March 2012
Auren News March 2012Auren News March 2012
Auren News March 2012
 
D053019025
D053019025D053019025
D053019025
 
East & west midlands
East & west midlandsEast & west midlands
East & west midlands
 
Wlan design for high density environments clark vitek
Wlan design for high density environments clark vitekWlan design for high density environments clark vitek
Wlan design for high density environments clark vitek
 
Assessment of various control band systems
Assessment of various control band systemsAssessment of various control band systems
Assessment of various control band systems
 
How to deliver_a_fantastic_power_point_presentation.pptx_submit.pptxsubmit (1)
How to deliver_a_fantastic_power_point_presentation.pptx_submit.pptxsubmit (1)How to deliver_a_fantastic_power_point_presentation.pptx_submit.pptxsubmit (1)
How to deliver_a_fantastic_power_point_presentation.pptx_submit.pptxsubmit (1)
 
Re-design
Re-designRe-design
Re-design
 
Biosimilars -- Wave of the Future or Child of the Privileged Few?
Biosimilars -- Wave of the Future or Child of the Privileged Few?Biosimilars -- Wave of the Future or Child of the Privileged Few?
Biosimilars -- Wave of the Future or Child of the Privileged Few?
 
Guidelines for preparing the master´s thesis
Guidelines for preparing the master´s thesisGuidelines for preparing the master´s thesis
Guidelines for preparing the master´s thesis
 
01 roland top storage trends_praha_02
01 roland top storage trends_praha_0201 roland top storage trends_praha_02
01 roland top storage trends_praha_02
 
Sample employment contract
Sample employment contractSample employment contract
Sample employment contract
 
Jonathan neufeld nuts and bolts
Jonathan neufeld   nuts and boltsJonathan neufeld   nuts and bolts
Jonathan neufeld nuts and bolts
 
Research Data Management
Research Data ManagementResearch Data Management
Research Data Management
 
CSS Box Model and Dimensions
CSS Box Model and DimensionsCSS Box Model and Dimensions
CSS Box Model and Dimensions
 

Similaire à Ngppt jtvir conference_final

NOVAGOLD - Denver Gold Forum, Colorado
NOVAGOLD - Denver Gold Forum, ColoradoNOVAGOLD - Denver Gold Forum, Colorado
NOVAGOLD - Denver Gold Forum, ColoradoCompany Spotlight
 
NOVAGOLD - Precious Metals Summit, Colorado
NOVAGOLD - Precious Metals Summit, ColoradoNOVAGOLD - Precious Metals Summit, Colorado
NOVAGOLD - Precious Metals Summit, ColoradoCompany Spotlight
 
Precious Metals Summit, Zurich
Precious Metals Summit, ZurichPrecious Metals Summit, Zurich
Precious Metals Summit, ZurichNOVAGOLD
 
BMO Capital Markets 2014 Global Metals & Mining Conference
BMO Capital Markets 2014 Global Metals & Mining ConferenceBMO Capital Markets 2014 Global Metals & Mining Conference
BMO Capital Markets 2014 Global Metals & Mining ConferenceNOVAGOLD
 
Vancouver Resource Investment Conference
Vancouver Resource Investment ConferenceVancouver Resource Investment Conference
Vancouver Resource Investment ConferenceNOVAGOLD
 
2014 06-18 ngppt-nyssa_presentation_final
2014 06-18 ngppt-nyssa_presentation_final2014 06-18 ngppt-nyssa_presentation_final
2014 06-18 ngppt-nyssa_presentation_finalCompany Spotlight
 
NYSSA Metals & Mining Conference
NYSSA Metals & Mining Conference NYSSA Metals & Mining Conference
NYSSA Metals & Mining Conference NOVAGOLD
 
Goldman Sachs Global Metals & Mining Conference
Goldman Sachs Global Metals & Mining Conference Goldman Sachs Global Metals & Mining Conference
Goldman Sachs Global Metals & Mining Conference NOVAGOLD
 
Vancouver Investment Resource Conference 2018
Vancouver Investment Resource Conference 2018 Vancouver Investment Resource Conference 2018
Vancouver Investment Resource Conference 2018 NOVAGOLD
 
NOVAGOLD November 2017 Mining Conferences
NOVAGOLD November 2017 Mining ConferencesNOVAGOLD November 2017 Mining Conferences
NOVAGOLD November 2017 Mining ConferencesNOVAGOLD
 
NOVAGOLD Corporate Presentation - September 2017
NOVAGOLD Corporate Presentation - September 2017NOVAGOLD Corporate Presentation - September 2017
NOVAGOLD Corporate Presentation - September 2017NOVAGOLD
 
Jefferies Industrials Conference, NYC
Jefferies Industrials Conference, NYC Jefferies Industrials Conference, NYC
Jefferies Industrials Conference, NYC NOVAGOLD
 
TD Securities' 2018 Mining Conference
TD Securities' 2018 Mining ConferenceTD Securities' 2018 Mining Conference
TD Securities' 2018 Mining ConferenceNOVAGOLD
 
Vancouver Resource Investment Conference 2014
Vancouver Resource Investment Conference 2014Vancouver Resource Investment Conference 2014
Vancouver Resource Investment Conference 2014NOVAGOLD
 

Similaire à Ngppt jtvir conference_final (14)

NOVAGOLD - Denver Gold Forum, Colorado
NOVAGOLD - Denver Gold Forum, ColoradoNOVAGOLD - Denver Gold Forum, Colorado
NOVAGOLD - Denver Gold Forum, Colorado
 
NOVAGOLD - Precious Metals Summit, Colorado
NOVAGOLD - Precious Metals Summit, ColoradoNOVAGOLD - Precious Metals Summit, Colorado
NOVAGOLD - Precious Metals Summit, Colorado
 
Precious Metals Summit, Zurich
Precious Metals Summit, ZurichPrecious Metals Summit, Zurich
Precious Metals Summit, Zurich
 
BMO Capital Markets 2014 Global Metals & Mining Conference
BMO Capital Markets 2014 Global Metals & Mining ConferenceBMO Capital Markets 2014 Global Metals & Mining Conference
BMO Capital Markets 2014 Global Metals & Mining Conference
 
Vancouver Resource Investment Conference
Vancouver Resource Investment ConferenceVancouver Resource Investment Conference
Vancouver Resource Investment Conference
 
2014 06-18 ngppt-nyssa_presentation_final
2014 06-18 ngppt-nyssa_presentation_final2014 06-18 ngppt-nyssa_presentation_final
2014 06-18 ngppt-nyssa_presentation_final
 
NYSSA Metals & Mining Conference
NYSSA Metals & Mining Conference NYSSA Metals & Mining Conference
NYSSA Metals & Mining Conference
 
Goldman Sachs Global Metals & Mining Conference
Goldman Sachs Global Metals & Mining Conference Goldman Sachs Global Metals & Mining Conference
Goldman Sachs Global Metals & Mining Conference
 
Vancouver Investment Resource Conference 2018
Vancouver Investment Resource Conference 2018 Vancouver Investment Resource Conference 2018
Vancouver Investment Resource Conference 2018
 
NOVAGOLD November 2017 Mining Conferences
NOVAGOLD November 2017 Mining ConferencesNOVAGOLD November 2017 Mining Conferences
NOVAGOLD November 2017 Mining Conferences
 
NOVAGOLD Corporate Presentation - September 2017
NOVAGOLD Corporate Presentation - September 2017NOVAGOLD Corporate Presentation - September 2017
NOVAGOLD Corporate Presentation - September 2017
 
Jefferies Industrials Conference, NYC
Jefferies Industrials Conference, NYC Jefferies Industrials Conference, NYC
Jefferies Industrials Conference, NYC
 
TD Securities' 2018 Mining Conference
TD Securities' 2018 Mining ConferenceTD Securities' 2018 Mining Conference
TD Securities' 2018 Mining Conference
 
Vancouver Resource Investment Conference 2014
Vancouver Resource Investment Conference 2014Vancouver Resource Investment Conference 2014
Vancouver Resource Investment Conference 2014
 

Plus de Company Spotlight

Presentation Clayton Valley, NevadaFrom Drilling to PEA in under 2 Years
Presentation Clayton Valley, NevadaFrom Drilling to PEA in under 2 YearsPresentation Clayton Valley, NevadaFrom Drilling to PEA in under 2 Years
Presentation Clayton Valley, NevadaFrom Drilling to PEA in under 2 YearsCompany Spotlight
 
Cypress Development Corp. Investor Presentation
Cypress Development Corp. Investor PresentationCypress Development Corp. Investor Presentation
Cypress Development Corp. Investor PresentationCompany Spotlight
 
Aben Resources Ltd. Corporate Presentation
Aben Resources Ltd. Corporate PresentationAben Resources Ltd. Corporate Presentation
Aben Resources Ltd. Corporate PresentationCompany Spotlight
 
Cypress Development Corp. Corporate Presentation
Cypress Development Corp. Corporate PresentationCypress Development Corp. Corporate Presentation
Cypress Development Corp. Corporate PresentationCompany Spotlight
 
Cypress Development Corp. Presentation
Cypress Development Corp. PresentationCypress Development Corp. Presentation
Cypress Development Corp. PresentationCompany Spotlight
 
Aben Resources Ltd. Presentation
Aben Resources Ltd. PresentationAben Resources Ltd. Presentation
Aben Resources Ltd. PresentationCompany Spotlight
 
Aben Resources Ltd. Corporate Presentation
Aben Resources Ltd. Corporate PresentationAben Resources Ltd. Corporate Presentation
Aben Resources Ltd. Corporate PresentationCompany Spotlight
 
Cypress Development Corp. Presentation
Cypress Development Corp. PresentationCypress Development Corp. Presentation
Cypress Development Corp. PresentationCompany Spotlight
 
Aben Resources Ltd. Presentation
Aben Resources Ltd. PresentationAben Resources Ltd. Presentation
Aben Resources Ltd. PresentationCompany Spotlight
 
Cypress Development Corp. Corporate Presentation
Cypress Development Corp. Corporate PresentationCypress Development Corp. Corporate Presentation
Cypress Development Corp. Corporate PresentationCompany Spotlight
 
TerraX Minerals - Corporate Presentation
TerraX Minerals - Corporate PresentationTerraX Minerals - Corporate Presentation
TerraX Minerals - Corporate PresentationCompany Spotlight
 
Aben Resources Ltd. Corporate Presentation
Aben Resources Ltd. Corporate PresentationAben Resources Ltd. Corporate Presentation
Aben Resources Ltd. Corporate PresentationCompany Spotlight
 
TerraX Minerals, Inc. Corporate Presentation
TerraX Minerals, Inc. Corporate PresentationTerraX Minerals, Inc. Corporate Presentation
TerraX Minerals, Inc. Corporate PresentationCompany Spotlight
 
Cypress Development Corp. Presentation
Cypress Development Corp. PresentationCypress Development Corp. Presentation
Cypress Development Corp. PresentationCompany Spotlight
 
Cypress Development Corp. Corporate Presentation
Cypress Development Corp. Corporate PresentationCypress Development Corp. Corporate Presentation
Cypress Development Corp. Corporate PresentationCompany Spotlight
 

Plus de Company Spotlight (20)

Presentation Clayton Valley, NevadaFrom Drilling to PEA in under 2 Years
Presentation Clayton Valley, NevadaFrom Drilling to PEA in under 2 YearsPresentation Clayton Valley, NevadaFrom Drilling to PEA in under 2 Years
Presentation Clayton Valley, NevadaFrom Drilling to PEA in under 2 Years
 
Aben resources presentation
Aben resources presentationAben resources presentation
Aben resources presentation
 
Aben Resources Ltd.
Aben Resources Ltd.Aben Resources Ltd.
Aben Resources Ltd.
 
Cypress Development Corp. Investor Presentation
Cypress Development Corp. Investor PresentationCypress Development Corp. Investor Presentation
Cypress Development Corp. Investor Presentation
 
Aben Resources Ltd. Corporate Presentation
Aben Resources Ltd. Corporate PresentationAben Resources Ltd. Corporate Presentation
Aben Resources Ltd. Corporate Presentation
 
Cypress Development Corp. Corporate Presentation
Cypress Development Corp. Corporate PresentationCypress Development Corp. Corporate Presentation
Cypress Development Corp. Corporate Presentation
 
Aben Resources Ltd.
Aben Resources Ltd.Aben Resources Ltd.
Aben Resources Ltd.
 
Cypress Development Corp. Presentation
Cypress Development Corp. PresentationCypress Development Corp. Presentation
Cypress Development Corp. Presentation
 
Aben Resources Ltd. Presentation
Aben Resources Ltd. PresentationAben Resources Ltd. Presentation
Aben Resources Ltd. Presentation
 
Aben Resources Ltd. Corporate Presentation
Aben Resources Ltd. Corporate PresentationAben Resources Ltd. Corporate Presentation
Aben Resources Ltd. Corporate Presentation
 
Cypress Development Corp. Presentation
Cypress Development Corp. PresentationCypress Development Corp. Presentation
Cypress Development Corp. Presentation
 
Aben Resources Ltd. Presentation
Aben Resources Ltd. PresentationAben Resources Ltd. Presentation
Aben Resources Ltd. Presentation
 
Cypress Development Corp. Corporate Presentation
Cypress Development Corp. Corporate PresentationCypress Development Corp. Corporate Presentation
Cypress Development Corp. Corporate Presentation
 
TerraX Minerals - Corporate Presentation
TerraX Minerals - Corporate PresentationTerraX Minerals - Corporate Presentation
TerraX Minerals - Corporate Presentation
 
Aben Resources Ltd. Corporate Presentation
Aben Resources Ltd. Corporate PresentationAben Resources Ltd. Corporate Presentation
Aben Resources Ltd. Corporate Presentation
 
Cypress Development Corp
Cypress Development CorpCypress Development Corp
Cypress Development Corp
 
TerraX Minerals, Inc. Corporate Presentation
TerraX Minerals, Inc. Corporate PresentationTerraX Minerals, Inc. Corporate Presentation
TerraX Minerals, Inc. Corporate Presentation
 
Cypress Development Corp. Presentation
Cypress Development Corp. PresentationCypress Development Corp. Presentation
Cypress Development Corp. Presentation
 
Cypress Development Corp
Cypress Development CorpCypress Development Corp
Cypress Development Corp
 
Cypress Development Corp. Corporate Presentation
Cypress Development Corp. Corporate PresentationCypress Development Corp. Corporate Presentation
Cypress Development Corp. Corporate Presentation
 

Dernier

Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 

Dernier (20)

Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 

Ngppt jtvir conference_final

  • 1. novagold.com NYSE-MKT, TSX: NG | March 2014 JTVIR 2014 metals & mining conference
  • 2. cautionary statements REGARDING FORWARD-LOOKING STATEMENTS This presentation includes certain “forward-looking statements” within the meaning of applicable securities laws, including the United States Private Securities Litigation Reform Act of 1995. All statements, other than statements of historical fact, included herein including, without limitation, statements relating to Donlin Gold’s future operating or financial performance, are forward- looking statements. Forward-looking statements are frequently, but not always, identified by words such as “plans”, “expects”, “anticipates”, “believes”, “intends”, “estimates”, “potential”, “possible” and similar expressions, or statements that events, conditions or results “will”, “may”, “could”, or “should” occur or be achieved. These forward-looking statements are set forth in the slides pertaining to the implementation of the Donlin Gold second updated Feasibility Study and pertaining to the implementation of the Galore Creek Pre-Feasibility Study and may include statements regarding perceived merit of properties; exploration results and budgets; mineral reserves and resource estimates; work programs; capital expenditures; timelines; strategic plans; completion of transactions; market price of precious base metals; or other statements that are not statements of fact. Forward-looking statements involve various risks and uncertainties. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from our expectations include the uncertainties involving the need for additional financing to explore and develop properties and availability of financing in the debt and capital markets; uncertainties involved in the interpretation of drilling results and geological tests and the estimation of reserves and resources; the need for continued cooperation between NOVAGOLD and Barrick Gold in the exploration and development of the Donlin Gold property; the need for continued cooperation between NOVAGOLD and Teck Resources Ltd. in the exploration and development of the Galore Creek property; the need for cooperation of government agencies and native groups in the development and operation of properties; the need to obtain permits and governmental approvals; risks of construction and mining projects such as accidents, equipment breakdowns, bad weather, non-compliance with environmental and permit requirements, unanticipated variation in geological structures, ore grades or recovery rates; unexpected cost increases; fluctuations in metal prices and currency exchange rates; and other risk and uncertainties disclosed in reports and documents filed by NOVAGOLD with applicable securities regulatory authorities from time to time. The forward- looking statements made herein reflect our beliefs, opinions and projections on the date the statements are made. Except as required by law, we assume no obligation to update the forward- looking statements of beliefs, opinions, projections, or other factors, should they change. REGARDING SCIENTIFIC AND TECHNICAL INFORMATION Unless otherwise indicated, all reserve and resource estimates included in this presentation have been prepared in accordance with Canadian National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”) and the Canadian Institute of Mining, Metallurgy and Petroleum Definition Standards for Mineral Resources and Mineral Reserves (“CIM Definition Standards”). Canadian standards, including NI 43-101, differ significantly from the requirements of the United States Securities and Exchange Commission (“SEC”), and reserve and resource information in this presentation may not be comparable to similar information disclosed by U.S. companies. In particular, and without limiting the generality of the foregoing, the term “resource” does not equate to the term “‘reserves”. Under U.S. standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. At this time, both of Donlin Gold and Galore Creek projects are without known reserves, as defined under SEC Industry Guide 7. The SEC’s disclosure standards normally do not permit the inclusion of information concerning “measured mineral resources”, “indicated mineral resources” or “inferred mineral resources” or other descriptions of the amount of mineralization in mineral deposits that do not constitute “reserves” by U.S. standards in documents filed with the SEC. U.S. investors should also understand that “inferred mineral resources” have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an “inferred mineral resource” will ever be upgraded to a higher category. Under Canadian rules, estimated “inferred mineral resources” may not form the basis of feasibility or pre-feasibility studies except in rare cases. Investors are cautioned not to assume that all or any part of an “inferred mineral resource” exists or is economically or legally mineable. Disclosure of “contained ounces” in a resource is permitted disclosure under Canadian regulations; however, the SEC normally only permits issuers to report mineralization that does not constitute “reserves” by SEC standards as in-place tonnage and grade without reference to unit measures. The requirements of NI 43-101 for identification of “reserves” are also not the same as those of the SEC, and reserves reported in compliance with NI 43-101 may not qualify as “reserves” under SEC standards. Accordingly, information concerning mineral deposits set forth herein may not be comparable to information made public by companies that report in accordance with United States standards. 2 All dollar amounts quoted in this report are in U.S. currency unless otherwise noted.
  • 3. EXCEPTIONAL IN SCALE, QUALITY, AND JURISDICTIONAL SAFETY the NOVAGOLD opportunity 3 39Moz gold resource1 ̴ 9Blbs copper resource1 Notes: 1) Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. ̴ 8Moz gold resource1 ̴ 136Moz silver resource1 Donlin Gold Galore Creek
  • 4. PROJECTS CONTINUE TO ADVANCE ON TIME AND ON BUDGET recent achievements 4 Notes: 1) Outstanding Convertible Notes mature on May 1, 2015. The holders of the Notes had the right to require the Company to repurchase all or part of their Notes on May 1, 2013 (“put option”) maintained a healthy balance sheet with receipt of $54M cash from warrants and reduced convertible debt by $79M1 continued to advance permitting of Donlin Gold with completion of public scoping and advanced preparation of preliminary draft environmental impact statement Galore Creek 2013 exploration drill results identified extensions to mineralization at Legacy zone simplified company, significantly reduced expenditures built a management team with expertise in permitting, developing and operating large-scale projects
  • 5. the right project – donlin gold ARGUABLY THE WORLD’S MOST SIGNIFICANT GOLD PROJECT partnerships grade growthjurisdiction longevity size 5 donlin gold
  • 6. WORLD’S BIGGEST UNDEVELOPED AND EARLY PRODUCTION GOLD PROJECTS largest development-stage gold deposit 6 49.0 39.0 24.3 19.0 17.1 16.4 15.7 11.7 -- 10 20 30 40 50 60 KSM Donlin Gold Hycroft Mine Expansion Metates Rosia Montana Detour Lake Livengood Canadian Malarctic M&IAuResources(Moz) ▸ Donlin Gold has one of the largest resources of its peer group and it’s located in North America LOMAverageAnnualProduction(Moz) ▸ Anticipated to be the leading gold producer by a wide margin Notes: Donlin Gold data as per Donlin Creek Gold Project Alaska, USA, NI 43-101 Technical Report on Second “Updated Feasibility Study”, effective November 18, 2011, as amended January 20, 2012 (the “updated feasibility study”). Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. Peer group data as per latest company documents, public filings and websites. Comparison group based on large, open-pit, gold-focused development projects with Resources over 10 million ounces of gold. KSM data also includes an underground component. 1) 1.50Moz represents the projected annual gold production during first five full years of mine life, 1.10Moz represents the projected annual gold production during full life of mine. 1.101 0.659 0.657 0.594 0.578 0.508 0.483 0.449 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 Donlin Gold Metates Detour Lake Canadian Malarctic Livengood KSM Rosia Montana Hycroft Mine Expansion 1.501
  • 7. 1.60 1.101 1.01 0.95 0.94 0.89 0.87 0.75 0.73 0.70 0.68 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 Grasberg Donlin Gold Pueblo Viejo Cortez Yanacocha Goldstrike Carlin Lihir Island Oyu Tolgoi Boddington Veladero Notes: Donlin Gold projected annual production represents 100% of which NOVAGOLD’s share represents 50%. All other production estimates, for the exception of Grasberg, are based on published 2014 average gold annual production guidance. Grasberg represents the published 2014 gold sales guidance. 1) 1.50Moz represents the projected annual gold production during first five full years of mine life, 1.10Moz represents the projected annual gold production during full life of mine. Gold (M/oz) LOCATION: 1.50 1 USA USADOMINICAN REPUBLIC INDONESIA PAPUA NEW GUINEA PERU AUSTRALIAMONGOLIA poised to be world’s biggest gold mine EXPECTED PRODUCTION RIVALS 10 LARGEST EXISTING GOLD MINES 7 USAUSA ARGENTINA
  • 8. More than half of the industry’s top producing mines were initially criticized for their high CAPEX requirements…but they were built Today, these assets are low-cost operations that companies are built upon…They are the back bone of the industry. Large precious metals assets will be built by a consortium of companies, much like base metals and oil and gas projects large gold mines essential to industry ALTHOUGH CAPITAL INTENSIVE, ONCE BUILT, MAJOR OPERATIONS PROVIDE SIGNIFICANT RETURNS 8 Put simply, the industry has always needed large-scale projects to sustain itself… this has not changed.
  • 9. the right project – donlin gold ARGUABLY THE WORLD’S MOST SIGNIFICANT GOLD PROJECT partnerships grade growthjurisdiction longevity size 9 donlin gold
  • 10. 2.24 1.05 1.04 1.02 0.61 0.55 0.50 0.31 -- 0.50 1.00 1.50 2.00 2.50 Donlin Gold Canadian Malarctic Rosia Montana Detour Lake Livengood KSM Metates Hycroft Mill Expansion WORLD’S BIGGEST UNDEVELOPED AND EARLY PRODUCTION GOLD PROJECTS highest-quality open-pit development-stage gold deposit 10 M&I Au Grade (g/t) Notes: Donlin Gold data as per the updated feasibility study. Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. Peer group data as per latest company documents, public filings and websites. Comparison group based on large, open-pit, gold-focused development projects. KSM data includes an under ground component. ▸ With capital constraints, only the best projects will find funding ▸ With much higher grade, Donlin Gold is a robust project able to weather any gold price cycle
  • 11. DONLIN GOLD’S GRADE IS AT THE TOP OF THE LIST COMPARED TO WORLD’S BIGGEST PRODUCERS expected to emerge as one of the highest-grade gold producers 11Notes: Donlin Gold data as per the updated feasibility study. Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources are inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. Peer group data - 2012 annual average grade per tonne (combined proven & probable reserves and measured & indicated resources) for open-pit and underground material as per public filings. 2.56 2.24 2.22 1.95 1.90 1.37 1.32 1.02 0.89 0.84 0.78 0.00 0.50 1.00 1.50 2.00 2.50 3.00 Agnico Eagle Donlin Gold Gold Fields Polyus AngloGold Ashanti Barrick Harmony Eldorado Newmont Yamana GoldcorpDonlin Gold M&I Au Grade (g/t)
  • 12. the right project – donlin gold ARGUABLY THE WORLD’S MOST SIGNIFICANT GOLD PROJECT partnerships grade growthjurisdiction longevity size 12 donlin gold
  • 13. RESOURCES MORE THAN DOUBLED FROM 2006 TO 2008 reserve & resource growth 13 16.6 29.4 35.3 37.9 39.0 0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 2006 2007 2008 2009 2011 Notes: Donlin Gold data as per NOVAGOLD public documents. Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources are inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. M&IAuResources(Moz) 39Moz M&I RESOURCES 34Moz P&P RESERVES @ $975/oz inclusive of grade of 2.24g/t And there is opportunity for continued growth once in production… PEA FeasibilityStudy UpdatedFeasibilityStudy Focused on feasibility-level planning and more recently permitting
  • 14. MULTIPLE DRILL PROSPECTS AND TARGETS EXIST ALONG 8KM TREND substantial exploration potential ▶ All current reserves and resources are contained in the Donlin Gold pit • 39Moz M&I resources inclusive of 34Moz P&P reserves1 ▶ Future mine situated in 3km segment of 8km mineralized trend Notes: 1) Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. 14
  • 15. MULTIPLE DRILL PROSPECTS AND TARGETS EXIST ALONG 8KM TREND substantial exploration potential Notes: See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. 15 ▶ Exploration upside: • In-pit resource conversion • In-pit/deep-pit exploration • Near-pit targets (East ACMA, Akivik Zone and Snow) • Additional resource potential Snow Dome Quartz Ophir ACMA Lewis 39.0Moz M&I Resource 6.0Moz Inf Resource 5 km Snow Quartz Dome Ophir ACMA Lewis Snow Dome
  • 16. the right project – donlin gold ARGUABLY THE WORLD’S MOST SIGNIFICANT GOLD PROJECT partnerships grade growthjurisdiction longevity size 16 donlin gold
  • 17. THREE DECADES OF LOW COST PRODUCTION donlin gold Climate of Declining Grades & Escalating Costs… ▶ Global gold industry experienced substantial cost escalation and a decrease in grade over the last decade due to… • Operations mining significantly above reserve grade • Inflationary pressures ▶ Donlin Gold’s low cost profile… • Contributes to meaningful cash flow generation over the 27-year mine life • A robust project that is highly leveraged to gold price increases 17 $1,0111 $7352 0 200 400 600 800 1,000 1,200 Industry Average Donlin Gold Life of Mine ~$300 Less than current industry average All-InSustainingCost(AISC) Donlin Gold Life of Mine Notes: 1) 2013A industry average AISC as per RBC Capital Markets report published 03/20/14. Industry average AISC includes total cash costs, sustaining capital, corporate G&A, and exploration expenses reported during 2013. 2) Donlin Gold AISC includes total cash costs (US$585/oz - estimate as per updated feasibility study), sustaining capex, stripping capex (IFRS), corporate G&A, reclamation, and community development (IFRS). Please see slide 40 of the appendix for a breakdown of the costs. $US/oz
  • 18. $6.2B $9.2B $11.6B $14.6B $19.2B $27.0B 0 5,000 10,000 15,000 20,000 25,000 30,000 $1,200 $1,350 $1,500 $1,700 $2,000 $2,500 NPV(US$inmillions) Gold Price (US$) NPV at 0%NPV at 5% NPV INCREASES ~20X WITH ~2X INCREASE IN GOLD PRICE donlin gold has exceptional leverage to gold ▶ Even in a low-price environment, the project has a positive return that increases substantially with higher gold prices ▶ Fast payback at a broad range of gold prices ▶ Does not take into account: • Value creation as project progresses from permitting to operation • Significant exploration upside of the mineralized trend 18 Notes: Donlin Gold estimates as per updated feasibility study. All dollar figures are in USD and reflect after-tax net present value (at a 0% and 5% discount rates) of the Donlin Gold project as of 1/1/2014. At a 5% discount rate, the net present value is: $547 m @ $1,200 gold; $1,922m @ $1,350 gold; $3,147m @ $1,500 gold; $4,581 m @ $1,700 gold; $6,722 m @ $2,000 gold; and $10,243 m @ $2,500 gold. Project development costs prior to 1/1/2014 are treated as sunk costs.
  • 19. 0 2 4 6 8 10 12 14 16 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000 10,000 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 significant drop in discoveries since 2006 19 Notes: Data as per SNL MEG’s MineSearch database, Company reports, SNL MEG estimates. Thomson Reuters. Number of discoveries data not yet available for 2013 and 2014. NumberofGoldDiscoveries Gold Discovered Exploration Budget (US$M) 2012 highest year on record for exploration spending and first year in over two decades with no discoveries 2011 gold peaked at US$1,920/oz
  • 20. the right project – donlin gold ARGUABLY THE WORLD’S MOST SIGNIFICANT GOLD PROJECT partnerships grade growthjurisdiction longevity size 20 donlin gold
  • 21. Donlin Gold located in Alaska, one of the safest jurisdictions in the world with history of successful mining development GREAT JURISDICTION COMMITTED TO RESPONSIBLE RESOURCE DEVELOPMENT the alaska advantage ▶ Alaska is the second largest U.S. gold- producing State ▶ Well-defined permitting process ▶ Four large precious metals mines, one coal mine & two base metals mines ▶ Numerous small-scale mines ▶ Natural resource projects integral to the State’s economy ▶ Strong and time-tested community support 21
  • 22. COMPANIES HAVE AND CONTINUE TO BUILD MUTUALLY-BENEFICIAL PARTNERSHIPS IN ALASKA state supporting development of resource industry ▶ Large Mine Permitting Team responsible for coordinating the permitting process for large mining projects in the State ▶ Alaska Exploration Incentive Credit Program – up to $20 million deduction over a 15-year period for new mines ▶ Roads to Resources Program (R2R) – transportation and other infrastructure initiatives to support the development of natural resources State is committed to work with companies in facilitating cost-effective access to projects and operations in Alaska ▶ Red Dog mine port & access road owned by State Economic Development Agency – initially financed by State ▶ Ambler project - earlier-stage initiative in evaluating a 225 mile road to access the Ambler mining district 22
  • 23. AMENABLE TERRAIN AND CLIMATE the right location for mining 23 ▸ Excellent setting for mining: • Rolling hills • Low precipitation ~20 inches annually • Elevation range from 150 to 640 meters ▸ Year-round operation ▶ Donlin Gold is not proximate to major population areas ▶ Located on private land designated for mining
  • 24. the right project – donlin gold ARGUABLY THE WORLD’S MOST SIGNIFICANT GOLD PROJECT partnerships grade growthjurisdiction longevity size 24 donlin gold
  • 25. JURISDICTIONAL SAFETY IS MORE THAN GEOGRAPHIC LOCATION the right stakeholders Committed Stakeholders ▶ Calista Corporation ▶ The Kuskokwim Corporation “Calista would like to take this opportunity to assert and inform the U.S. Army Corps of Engineers and the public of its legislated mandate under ANCSA. Calista and TKC are not only stakeholders, but are the legislatively mandated landowners charged with the responsibility of seeing the project to fruition in an environmentally responsible manner.” – June MacAtee, Calista Corporation VP 25
  • 26. NATIVE CORPORATIONS WANT TO LEAD THE ECONOMIC DEVELOPMENT OF THEIR REGIONS mining an integral part of communities ▶ ANCSA established 40 years ago; resolved legal issues related to Native title claims ▶ Lands valuable for resource potential selected by Regional Corporations under ANCSA ▶ Native corporations have an owner’s interest in the development of the selected lands to support the economic prosperity of their shareholders ▶ Mining is compatible and consistent with subsistence lifestyles Donlin Gold has the support of the land owners through a 20+ year relationship 26
  • 27. EARNING OUR SOCIAL LICENSE AND FORMING LASTING RELATIONSHIPS working together to build a better future 27 ▶ Personal contact • Active outreach effort to more than 60 remote communities in the region • Village meetings, camp presentations, mine visits ▶ Communications • Broad and diverse reach, many materials translated into Yup’ik • Monthly newsletter, radio announcements, social media, website ▶ Community investments • Serving to help create a culture that will last for generations • Safety initiatives, community wellness, economic opportunities ▶ Workforce and skills development • Promote and enhance youth education • Encourage local hire • School programs, internships, scholarships
  • 28. donlin gold development timeline 28 1.5Moz/year first five full years1 1.1Moz/year life of mine1 16 years ̴ 4 27+ years EXPLORATION& ENVIRONMENTAL STUDIES PERMITTING ENGINEERING& CONSTRUCTION OPERATION WE ARE HERE 1.5Moz/year first five full years1 1.1Moz/year life of mine1 ̴ 4 Notes: 1) Donlin Gold data as per the updated feasibility study. Projected annual production represents 100% of which NOVAGOLD’s share represents 50%. ADVANCING TOWARD A CONSTRUCTION DECISION
  • 29. DONLIN GOLD ADVANCES ON PERMITTING PATH permitting milestones 29 published Notice of Intent public scoping period (Dec. 14/12 - March 29/13) submit permit applications to federal and state regulatory agencies preliminary draft EIS (PDEIS) end of 2014 draft EIS public comment period final EIS/record of decision permit issuance ~2 years
  • 30. PROCEEDING ON SCHEDULE AS PER EIS TIMELINE current work ▶ Maintaining strong working relationships with the agencies and providing input throughout the permitting and EIS processes ▶ EIS process and current activities • Alternatives development addressing mine, pipeline and transportation components expected to be completed Q1 2014 • PDEIS well underway including defining the baseline conditions and analyzing consequences expected to be completed by end of 2014 • Draft EIS anticipated in Q1 2015 ▶ Major permit application submittals and agency reviews – well underway • Air quality • Water discharge and usage • Pipeline plan of development • Wetlands • Dam safety 30
  • 31. we are here DONLIN GOLD’S SCALE, QUALITY AND JURISDICTIONAL SAFETY WILL MAKE IT ONE OF THE MOST COVETED PRECIOUS METALS ASSETS IN THE WORLD 31 “…A quiet haven of permitting peace in a volatile precious metals sector” John Bridges1 Notes: The above graph is an illustration that depicts historical share price performance trends of companies and how they relate to the various milestones in an asset’s life cycle. It is not intended to be representative of the Company’s historical or future financial or share price performance, or indicative of the Company's anticipated timeline to production. 1) North America Equity Research, John Bridges, JP Morgan Chase & Co, 2/17/14 A COMPELLING INVESTMENT OPPORTUNITY WHEN ONE CONSIDERS THE IMPENDING INDUSTRY PRODUCTION CLIFF
  • 32. ENHANCING VALUE WHILE EVALUATING OPPORTUNITIES TO MONETIZE ASSET galore creek ▶ Completed the 2013 drilling program under budget, exceeding objectives with 11,600 meters drilled • Confirmed significant mineralization at the recently discovered Legacy zone • Identified areas for potential resource growth ▶ 2014 activities: • Execute capital efficient work plan incorporating 2012 and 2013 drill results to advance the project toward next-level mine planning and design • Technical studies: • Water and waste management • Site layout • Ongoing environmental monitoring 32Notes: 1) Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. 9Blbs copper 8Moz gold 136Moz silver 0.5% copper 0.3g/t gold 5.2g/t silver M&I Resources1
  • 33. AMONG HIGHEST COPPER GRADE COMPARED TO NORTH AMERICAN ASSETS galore creek grade peer comparisons 33 P&P + M&I grade (Cu%) Notes: Data as per SNL MEG’s MineSearch database, Company reports, SNL MEG estimates. 0.50 0.45 0.42 0.40 0.32 0.30 0.27 0.24 0.21 0.18 0.18 0.00 0.10 0.20 0.30 0.40 0.50 0.60 Galore Creek Pebble Rosemont Catface Red Chris Berg Schaft Creek New Prosperity KSM Mount Milligan Casino
  • 34. CLEAR FOCUS BEGINS WITH STRONG FUNDING TO EXECUTE ON ALL FRONTS financial obligations have decreased substantially 34 $0 $20 $40 $60 $80 $100 $120 $140 2012 Act(1) 2013 Act 2014 Bud DiscOps G&A Donlin Gold Galore Creek Interest & other 1 - 70% - 23% Notes: 1) 2014 anticipated budget expenditure disclosed on February 11, 2014 2) Market Capitalization as of March 25, 2014 based on 316.7 million shares issued and outstanding. 3) Includes US$ 110 million in term deposits as of November 30, 2013. 4) The Notes mature on May 1, 2015. market cap2 $1,210 cash and term deposits3 $190 convertible notes4 $16 in millions of U.S. dollars reducedby~$100M
  • 35. 26.7% 11.3% 6.9% 2.2%1.7% 51% INSTITUTIONAL QUALITY INVESTMENT the NOVAGOLD opportunity 35 Institutional Ownership 80% held by top 5 shareholders(1) 49% Notes: Shareholder positions are based on the latest 13-F filings. committed to Shareholder Value Electrum Strategic Resources LP Paulson & Co. Inc The Baupost Group, L.L.C. Tocqueville Asset Management Sun Valley Gold, LLC Other
  • 36. why NOVAGOLD? why now? WELL POSITIONED TO DELIVER ON ALL CORPORATE OBJECTIVES 36 toptier, high-quality assets strongbalance sheet supportive, loyal, and engaged stakeholders bestand safest leverage to gold rightpeople to bring project up value chain
  • 38. ▶ Donlin Gold LLC is the operating company ▶ 50/50 ownership by NOVAGOLD and Barrick Gold ▶ Board of Directors has two representatives from each company • Chairman rotates every year • Each company has the right to appoint the Donlin Gold General Manager every two years ▶ Operates under agreements with Alaska Native Claims Settlement Act (ANCSA) landowners • Calista Corporation (Subsurface minerals and surface lease) • The Kuskokwim Corporation (Surface use agreement) ▶ Project office in Anchorage • 36 full-time employees and 2 contractors ▶ Strong track record for local hiring ADVANCING DONLIN GOLD UP THE VALUE CHAIN project overview 38
  • 39. DONLIN GOLD SLATED TO BE A STATE-OF-THE-ART SIGNIFICANT MINE project highlights 39 Reserves: 33.9 Moz Au (505M tonnes ore)1 Resources: 5.1 Moz M&I (excluding P&P) and 6.0 Moz Inferred1 Mine Life: ~27 years Production: Year 1-5,1.5 Moz/year; LOM,1.1 Moz/year Operation: Open-pit, conventional truck & shovel Milling: 53.5k tonnes/day, sulfide flotation, pressure oxidation (POX), carbon-in-leach recovery (CIL) Strip ratio: 5.5 = 2.8B tonnes waste rock Tailings: Fully lined storage facility Power: 153MW average site-generated load, fueled by natural gas transported via a 315-mile pipeline Logistics: All consumables supplied by Kuskokwim River transportation system with port near Jungjuk Creek See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve and Resource Base” table with footnotes.
  • 40. donlin gold LOW OPERATING CASH COSTS AND ALL-IN SUSTAINING COSTS 40 Open-pit mining1 228 Processing 257 G&A, royalties, land & other2 100 Total $585 Open-pit mining1 133 Processing 208 G&A, royalties, land & other2 68 Total $409 Life of Mine Cash Costs Per Ounce First Five Years Cash Costs Per Ounce Notes: Donlin Gold estimates as per the updated feasibility study. 1) Net of deferred costs 2) Based on US$1,200/oz gold price Life of Mine All-in Sustaining Costs Per Ounce Cash costs 585 Sustaining capex 50 Stripping capex (IFRS) 46 Corporate administration 27 Reclamation 22 Community development (IFRS) 5 Total $735 First Five Years All-in Sustaining Costs Per Ounce Cash costs 409 Sustaining capex 45 Stripping capex (IFRS) 0 Corporate administration 21 Reclamation 17 Community development (IFRS) 4 Total $496
  • 41. 41 ($10,000) ($5,000) $0 $5,000 $10,000 $15,000 $20,000 $25,000 $30,000 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 CumulativeNetCashFlow(US$millions)' $1,200/oz Au $1,500/oz Au $1,700/oz Au $2,000/oz Au $2,500/oz Au $6,025 $11,459 $14,444 $19,075 $26,803 ~4.5x leverage NetCashFlow(millions) All Amounts in US Dollars Rich Ore Body With a 27-Year Mine Life and Extensive Exploration Upside Notes: Donlin Gold estimates as per the updated feasibility study. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 LEVERAGE TO GOLD & FAST PAYBACK AT A BROAD RANGE OF GOLD PRICES donlin gold expected to generate substantial cash flows
  • 42. donlin gold WELL POSITIONED TO SHARE UPFRONT COSTS WITH THIRD PARTIES Areas US$M1 Opportunities1 Mining 345 Leasing equipment ~$170M Site preparation/roads 236 Process facilities 1,326 Oxygen plant could be built by third party ~$130M Tailings 120 Utilities 1,302 Ancillary buildings 304 Off-site facilities 243 Total Direct Costs 3,876 Owners’ cost 414 Indirect Costs 1,405 Contingency 984 Healthy Contingency Total Owner’s & Indirect Costs, and Contingency 2,803 Total Project Cost 6,679 >$1B potential capital reductions Gas pipeline could be built by third party $834M 1) Represents 100% of project’s capital expenditures 42
  • 43. ROBUST ECONOMICS HIGHLY LEVERAGED TO GOLD PRICES donlin gold key performance indicators 43 Gold Price Unit $1,000/oz $1,200/oz Base Case $1,700/oz $2,000/oz $2,500/oz Average annual after-tax cash flow (first full five years) $M 670 950 1,500 1,785 2,185 Average annual after-tax cash flow (LOM) $M 350 500 815 990 1,275 NPV (5%) after-tax1 $M (1,340) 550 4,580 6,720 10,240 NPV (0%) after-tax1 $M 2,100 6,200 14,620 19,250 26,975 IRR after-tax1 % 2.3 6.0 12.3 15.1 19.1 Payback period Years 19.1 9.2 5.3 4.4 3.5 Notes: Donlin Gold estimates as per the updated feasibility study. All dollar figures are in USD and reflect after-tax net present value (at a 0% and 5% discount rates) of the Donlin Gold Project as of 1/1/2014. At a 5% discount rate, the net present value is: $547 m @ $1,200 gold; $4,581 m @ $1,700 gold; $6,722 m @ $2,000 gold; and $10,243 m @ $2,500 gold. Project development costs prior to that date are treated as sunk costs. All amounts in US dollars 1) NPVs and IRRs as at January 1, 2014. Project development costs prior to that date are treated as sunk costs.
  • 44. donlin gold: standard technology Donlin Gold Pueblo Viejo Detour Lake Capital Expenditures US$6.7B1 ~US$4.0B2 C$1.5B4 Location Alaska, US Sanchez Ramirez, Dominican Republic Ontario, Canada Mining Method Open Pit Open Pit Open Pit Project Status Permitting Commercial Operation Start Up Total M&I Resources (inclusive of reserves) 39.0 Moz 36.3 Moz 23.3 Moz Nameplate Design Throughput (tpd) 53,500 24,000 61,000 M&I Grade (g/t) 2.24 2.41 1.07 Recovery (%) 89.8 92 91 Strip Ratio 5.5 1.2 3.7 Expected Average Annual Production (oz) 1,500,000 3 1,042,000 – 1,125,000 3 ~650,000 Processing Method Flotation/Autoclaving/Leaching Autoclave/Leaching/Ag/Cu Recovery Gravity Concentration/High-Intensity Leaching Ball Mill Underflow & Gravity Tails Leaching Number of Autoclaves 2 medium 4 large N/A Key Infrastructure Natural gas pipeline/Power plant Oxygen plant Power plant and Transmission Line/ Oxygen plant/Lime Kilns/Limestone Grinding 180 km 230kV Transmission Line Mine Life 27 years 25 years 22 years WELL ESTABLISHED MINING AND MINERAL PROCESSING METHODOLOGY Notes: Donlin Gold estimates as per the updated feasibility study. Peer data as per company documents, public filings and websites. Represents 100% of measured and indicated resources of which NOVAGOLD’s share represents 50%. Measured and indicated resources inclusive of proven and probable reserves. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. 1) Capital expenditure shown on a 100% project basis. 2) Capital expenditure of US$3.7B disclosed in Barrick Gold’s press release dated 01/15/13, plus a net incremental cost of approximately US$300M for the power plant. 3) Production expected for first full five years of operation. 4) Revised at end of 3Q 2012, as per press release dated 11/8/12. 44
  • 45. WEST COAST RIVER BARGE UP KUSKOKWIM RIVER WITH TWO PORT FACILITIES logistics & supply chain 45
  • 46. PROPOSED PIPELINE TIES INTO EXISTING INFRASTRUCTURE AT COOK INLET powering the project 46 ▸ Project would require 153MW of electricity to power the mill & facilities ▸ Fueled by natural gas transported via a 315-mile-long, 14-inch pipeline ▸ Donlin Gold has studied various pipeline routes and collected baseline data on: • Wetlands, stream crossings and aquatic resources • Cultural sites • Seismic conditions • The Iditarod Trail
  • 47. LARGE PROJECTS HAVE BEEN SUCCESSFULLY PERMITTED permitting in the U.S. 47 Project Name Location Metal Time Description Red Dog Mine Alaska Lead/zinc ~2 years • Expansion • EIS completed in 2009 • Development started on schedule in 2010 Fort Knox Alaska Gold ~3 years • Expansion – new heap leach facility • Permitting completed in 2007 Pogo Alaska Gold ~3 years • New mine • Permitting completed in 2004 • Operations began in 2006 Rochester Mine Nevada Silver ~1 year • Expansion – new heap leach & mine reopening • EA/permitting completed in 2011 Cortez Gold Nevada Gold ~3 years • Major pit expansion • EIS/permitting completed in 2008/2009 Goldstrike Nevada Gold ~2 years • Major pit expansion • Waste rock and tailings facilities • ROD approving the project was in 2009 Hycroft Gold Nevada Gold ~2 years • Reactivation • EIS/permitting completed in 2012 Climax Molybdenum Colorado Molybdenum ~5 years • Re-opening • State permitting completed in 2012 • New production began in 2012
  • 48. 48 ONLY THREE PROJECTS IN THE WORLD ARE SLATED TO PRODUCE >1MOZ/YEAR mines the size of donlin gold are scarce Notes: Donlin Gold projected annual production represents 100% of which NOVAGOLD’s share represents 50%. All other production estimates, with the exception of Grasberg, are based on published 2014 average gold annual production guidance. Grasberg represents the published 2014 gold sales guidance. Excludes Newmont’s Nevada operations that consist of multiple mines. Analysis includes life of mine data for Donlin Gold. 1) If put into production as contemplated by the updated feasibility study. 156 MINES >100 Koz 21 MINES >500 Koz 8 MINES >800 Koz 3 MINES/ Projects >1 Moz GRASBERG Indonesia PUEBLO VIEJO Dominican Republic DONLIN GOLD USA ▸ 1.5 Moz/year in first five full years1 ▸ 1.1 Moz/year LOM1 Donlin Gold: Only undeveloped asset in this category in North America 1
  • 49. GALORE CREEK, AN EXCEPTIONAL ASSET project overview 49 ▶ Galore Creek Mining Corporation (GCMC) is the operating company ▸ 50/50 ownership by NOVAGOLD and Teck Resources Inc. ▸ Management Committee has two representatives from each company • Chairman rotates every year ▸ Project is located within the Tahltan Nation Territory and operates under a Participation Agreement ▸ All mineral claims are on Crown land ▸ Project office in Vancouver • Abundance of technical strength to draw from within Teck ▸ Strong track record for Tahltan hiring at project site as well as contracting and procurement with Tahltan businesses and joint ventures
  • 50. GALORE CREEK TO BE ONE OF CANADA’S LARGEST COPPER MINES project highlights 50 Reserves: 6.8 Blb Cu; 5.5 Moz Au; 102 Moz Ag 1 Resources: 8.9 Blb Cu; 8.0 Moz Au; 136 Moz Ag (inclusive of reserves) 1 Mine Life: ~18 years Production: Year 1-5, 400 Mlb/year Cu; LOM, 340 Mlb/year Cu Operation: Open-pit, conventional truck & shovel Milling: +80k tonnes/day, conventional crush, grind, and Cu/Au/Ag flotation concentration, plant located in West More Valley Strip ratio: 2.2 = 1.1B tonnes waste rock Tailings: storage facility located in West More Valley next to plant Power: BC Hydro currently constructing the Northwest Transmission Line from near Terrace, BC to Bob Quinn to promote remote industrial development, Galore Creek to tie into the NTL Logistics: Port facilities to be built near Stewart, BC Notes: See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve and Resource Base” table with footnotes.
  • 51. ROBUST ECONOMICS HIGHLY LEVERAGED TO METAL PRICES galore creek key performance indicators 51 Unit Metal Prices Copper Gold Silver US$/lb US$/oz US$/oz 2.00 900 15.00 2.65 1,100 18.50 3.00 1,100 20.00 3.50 1,200 25.00 4.00 1,300 30.00 LOM after-tax cash flow $M 1,514 5,118 6,641 9,223 11,812 NPV (5%) after-tax1 $M (969) 988 1,794 3,134 4,458 NPV (7%) after-tax1 $M (1,431) 137 778 1,837 2,877 IRR after-tax1 % 2.4 7.4 9.2 11.9 14.3 Payback period Years 13.2 7.8 6.1 4.1 3.3 Notes: Galore Creek estimates as per the 2011 Pre-Feasibility Study. All dollar figures are in CAD. See “Cautionary Note Concerning Reserve & Resource Estimates” and “Reserve & Resource Base” with footnotes in the appendix. 1) NPVs and IRRs as of two years prior to significant project spend. Project development costs prior to that point are treated as sunk costs. All amounts in CAD dollars
  • 52. INDUSTRY LEADERS TO BRING DONLIN GOLD THROUGH PERMITTING & BEYOND the NOVAGOLD team 52 Gregory Lang President & CEO ▸ Former President of Barrick Gold North America ▸ 35 years experience building & operating major mines ▸ Intimate knowledge of Donlin Gold David Deisley Executive Vice President and General Counsel ▸ Former EVP and General Counsel of Goldcorp ▸ Regional General Counsel for Barrick Gold North America ▸ Extensive track record in project permitting, corporate social responsibility, mergers and acquisitions and corporate development ▸ 25 years of mining industry experience David Ottewell Vice President and Chief Financial Officer ▸ Former VP and Corporate Controller of Newmont Mining Corporation ▸ 25 years of mining industry experience ▸ Diverse experience in all facets of financial management, from mine operations to executive corporate financial management of premier gold producers Mélanie Hennessey Vice President, Corporate Communications ▸ Held variety of executive and senior IR & corporate communications positions with Goldcorp Inc., New Gold Inc., and Hecla Mining Company ▸ Leading NOVAGOLD’s internal and external communications functions Ron Rimelman Vice President, Environment, Health, Safety & Sustainability ▸ 25+ years of environmental experience, managing environmental impact assessments and permitting activities world-wide ▸ Leadership role on mine permitting and NEPA evaluations for mine projects in Alaska since 1993 Richard Williams Vice President, Engineering and Development ▸ Former Project Director for the Pueblo Viejo project in the Dominican Republic ▸ 30 years of experience developing and operating major mines world-wide ▸ Particular expertise in autoclave technology MANAGEMENT
  • 53. NOVAGOLD board of directors 53 Dr. Thomas Kaplan Chairman Chairman and CIO of The Electrum Group LLC, a privately held natural resources investor that controls a diversified portfolio of precious and base metals assets Sharon Dowdall Former Chief Legal Officer and Corporate Secretary with Franco-Nevada, transforming an industry pioneer into one of the most successful precious metals enterprises in the world Dr. Marc Faber Publishes a monthly investment newsletter entitled The Gloom, Boom & Doom Report and is the author of several books Greg Lang President & CEO Former President of Barrick Gold North America, 35 years experience building & operating major mines with intimate knowledge of Donlin Gold Gil Leathley COO and Director of Sunward Resources, former Senior Vice President and Chief Operating Officer of the Company Igor Levental President of The Electrum Group LLC, former VP of Homestake Mining and International Corona Corp. Kalidas Madhavpeddi Former Executive with Phelps Dodge Gerald McConnell Former Chairman and CEO of NOVAGOLD, CEO of Namibia Rare Earths Inc. Clynton Nauman CEO of Alexco Resources, formerly with Viceroy Gold and Kennecott Minerals Rick Van Nieuwenhuyse CEO of NovaCopper, founder and former CEO of NOVAGOLD Anthony Walsh Former President and Chief Executive Officer of Miramar Mining Corporation, which in 2007 was sold to Newmont Mining Company.
  • 54. donlin gold management team 54 Stanley Foo President/General Manager 30+ years mining industry experience in exploration, mine geology, operations management, project management and permitting; 12 years mine operations experience in NV including superintendent roles at Cortez and Bald Mtn; 15 years in Alaska in project management and permitting; Previous Project Manager roles with Donlin 1997-99, 2005-2007, served on Donlin Gold LLC board 2008-2010. James Fueg Study Manager Led Donlin Gold’s recent feasibility studies and coordinates all engineering and technical work for project; 20+ years experience in mining, exploration and environmental science; 16 years in Alaska; at Donlin since 2004. Robert Nick Enos Environmental and Permitting Manager Leads permitting and environmental management for project; primary contact for reg. agencies; 20 years experience in Alaska in geology, environmental science and permitting management; Previous experience includes Greens Creek, Calista Corp., as environmental/permitting consultant; Joined Donlin in 2005. Kurt Parkan External Affairs Manager Leads Donlin Gold’s community affairs, communications, government relations and corporate social responsibility functions; Nearly 30 years public affairs experience in Alaska; Previous roles: External Affairs Director of Nature Conservancy of Alaska, Deputy Commissioner for Alaska Department of Transportation and Public Facilities, Special Assistant to the Governor, Legislative Aide and as staff for Alaska House of Representatives Finance Committee. Meg Day Human Resources Manager 22 years human resources experience in the mining industry including 17 years in Alaska; Served in various senior management positions in Alaska, Utah and Washington and has been involved in the start up of several mines. Serves on Alaska Miners Association HR Committee, Society of HR Management and Advisory Board member of University of Alaska. Jan Halstead Administrative and Finance Manager 25+ years accounting and financial analysis experience in construction, investment, telecommunications; Responsible for growth and development of Accounting, Administration, Purchasing and Contract functions for Donlin Gold LLC.
  • 55. COPPER Tonnage Mt Grade* %Cu Metal content Mlbs NOVAGOLD share** Mlbs Reserves (100%)2 Proven 69.0 0.61 900.0 450.0 Probable 459.1 0.58 5,900.0 2,950.0 P&P 528.0 0.59 6,800.0 3,400.0 Resources (100%)4 inclusive of reserves Measured 108.4 0.48 1,147.0 573.5 Indicated 706.3 0.50 7,786.0 3,893.0 M&I 814.7 0.50 8,933.0 4,466.5 Inferred 346.6 0.42 3,230.0 1,615.0 GOLD Mt g/t Moz Moz Reserves (100%)2 Proven 69.0 0.52 1.15 0.58 Probable 459.1 0.29 4.30 2.15 P&P 528.0 0.32 5.45 2.73 Resources (100%)4 inclusive of reserves Measured 108.4 0.48 1.70 0.85 Indicated 706.3 0.28 6.40 3.20 M&I 814.7 0.31 8.00 4.00 Inferred 346.6 0.24 2.70 1.35 SILVER Mt g/t Moz Moz Reserves (100%)2 Proven 69.0 4.94 11.0 5.5 Probable 459.1 6.18 91.2 45.6 P&P 528.0 6.02 102.2 51.1 Resources (100%)4 inclusive of reserves Measured 108.4 4.10 14.30 7.15 Indicated 706.3 5.38 122.10 61.05 M&I 814.7 5.21 136.40 68.20 Inferred 346.6 4.28 47.73 23.87 At April 30, 2012 Donlin Gold (NOVAGOLD 50%) Galore Creek (NOVAGOLD 50%) GOLD Tonnage Mt Grade* g/t Metal content Moz NOVAGOLD share** Moz Reserves (100%)1 Proven 7.7 2.32 0.57 0.29 Probable 497.1 2.08 33.28 16.64 P&P 504.8 2.09 33.85 16.93 Resources (100%)3 inclusive of reserves Measured 7.7 2.52 0.63 0.31 Indicated 533.6 2.24 38.38 19.19 M&I 541.3 2.24 39.01 19.50 Inferred 92.2 2.02 5.99 3.00 NOVAGOLD reserve/resource table 55
  • 56. reserve/resource table (con’t) Resources (100%)5,6 Tonnage Grade* Metal content NOVAGOLD share** COPPER Mt %Cu Mlbs Mlbs Inferred 53.7 0.50 592.0 414.4 GOLD Mt g/t Moz Moz Inferred 53.7 0.73 1.26 0.88 SILVER Mt g/t Moz Moz Inferred 53.7 10.60 18.36 12.85 Copper Canyon (NOVAGOLD 70%) t = metric tonne M = million g/t = grams/tonne * Reserve grade is diluted; resource grade is in situ. ** NOVAGOLD share net after earn-ins Approximate cut-off grades (see Resource Footnotes below): Donlin Gold Reserves1: 0.57 g/t gold Resources3: 0.46 g/t gold Galore Creek Reserves2: C$10.08 NSR Resources4: C$10.08 NSR Copper Canyon Resources5,6: 0.6% copper equivalent 56
  • 57. Notes: a. These resource estimates have been prepared in accordance with NI43-101 and the CIM Definition Standard, unless otherwise noted. b. See numbered footnotes below on resource information. c. Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal content d. Tonnage and grade measurements are in metric units. Contained gold and silver ounces are reported as troy ounces, contained copper pounds as imperial pounds Resource Footnotes: Mineral Reserves are contained within Measured and Indicated pit designs, and supported by a mine plan, featuring variable throughput rates, stockpiling and cut-off optimization. The pit designs and mine plan were optimized on diluted grades using the following economic and technical parameters: Metal price for gold of US$975/oz; reference mining cost of US$1.67/t incremented US$0.0031/t/m with depth from the 220 m elevation (equates to an average mining cost of US$2.14/t), variable processing cost based on the formula 2.1874 x (S%) + 10.65 for each US$/t processed; general and administrative cost of US$2.27/t processed; stockpile rehandle costs of US$0.19/t processed assuming that 45% of mill feed is rehandled; variable recoveries by rock type, ranging from 86.66% in shale to 94.17% in intrusive rocks in the Akivik domain; refining and freight charges of US$1.78/oz gold; royalty considerations of 4.5%; and variable pit slope angles, ranging from 23º to 43º. Mineral Reserves are reported using an optimized net sales return value based on the following equation: Net Sales Return = Au grade * Recovery * (US$975/oz – (1.78 + (US$975/oz – 1.78) * 0.045)) - (10.65 + 2.1874 * (S%) + 2.27 + 0.19) and reported in US$/tonne. Assuming an average recovery of 89.54% and an average S% grade of 1.07%, the marginal gold cutoff grade would be approximately 0.57 g/t, or the gold grade that would equate to a 0.001 NSR cutoff at these same values. The life of mine strip ratio is 5.48. The assumed life-of-mine throughput rate is 53.5 kt/d. Mineral Reserves are contained within Measured and Indicated pit designs using metal prices for copper, gold and silver of US$2.50/lb, US$1,050/oz, and US$16.85/oz, respectively. Appropriate mining costs, processing costs, metal recoveries and inter ramp pit slope angles varing from 42º to 55º were used to generate the pit phase designs. Mineral Reserves have been calculated using a 'cashflow grade' ($NSR/SAG mill hr) cut-off which was varied from year to year to optimize NPV. The net smelter return (NSR) was calculated as follows: NSR = Recoverable Revenue – TCRC (on a per tonne basis), where: NSR = Net Smelter Return; TCRC = Transportation and Refining Costs; Recoverable Revenue = Revenue in Canadian dollars for recoverable copper, recoverable gold, and recoverable silver using metal prices of US$2.50/lb, US$1,050/oz, and US$16.85/oz for copper, gold, and silver, respectively, at an exchange rate of CDN$1.1 to US$1.0; Cu Recovery = Recovery for copper based on mineral zone and total copper grade; for Mineral Reserves this NSR calculation includes mining dilution. SAG throughputs were modeled by correlation with alteration types. Cash flow grades were calculated as the product of NSR value in $/t and throughput in t/hr. The life of mine strip ratio is 2.16. Mineral Resources are contained within a conceptual Measured, Indicated and Inferred optimized pit shell using the following assumptions: gold price of US$1,200/oz; variable process cost based on 2.1874 * (sulphur grade) + 10.6485; administration cost of US$2.29/t; refining, freight & marketing (selling costs) of US$1.85/oz recovered; stockpile rehandle costs of US$0.20/t processed assuming that 45% of mill feed is rehandled; variable royalty rate, based on royalty of 4.5% * (Au price – selling cost). Mineral Resources have been estimated using a constant Net Sales Return cut-off of US$0.001/t milled. The Net Sales Return was calculated using the formula: Net Sales Return = Au grade * Recovery * (US$1200/oz – (1.85 + ((US$1200/oz – 1.85) * 0.045)) - (10.65 + 2.1874 * (S%) + 2.29 + 0.20)) and reported in US$/tonne. Mineral Resources are inclusive of Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Inferred Resources are in addition to Measured and Indicated Resources. Inferred Resources have a great amount of uncertainty as to their existence and whether they can be mined legally or economically. It cannot be assumed that all or any part of the Inferred Resources will ever be upgraded to a higher category. See "Cautionary Note Concerning Reserve & Resource Estimates". Mineral resources are contained within a conceptual Measured, Indicated and Inferred optimized pit shell using the same economic and technical parameters as used for Mineral Reserves. Tonnages are assigned based on proportion of the block below topography. The overburden/bedrock boundary has been assigned on a whole block basis. Mineral resources have been estimated using a constant NSR cut-off of C$10.08/t milled. The Net Smelter Return (NSR) was calculated as follows: NSR = Recoverable Revenue – TCRC (on a per tonne basis), where: NSR = Diluted Net Smelter Return; TCRC = Transportation and Refining Costs; Recoverable Revenue = Revenue in Canadian dollars for recoverable copper, recoverable gold, and recoverable silver using silver using the economic and technical parameters mentioned above. The mineral resource includes material within the conceptual M,I&I pit that is not scheduled for processing in the mine plan but is above cutoff. Mineral Resources are inclusive of Mineral Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Inferred Resources are in addition to Measured and Indicated Resources. Inferred Resources have a great amount of uncertainty as to their existence and whether they can be mined legally or economically. It cannot be assumed that all or any part of the Inferred Resources will ever be upgraded to a higher category. See "Cautionary Note Concerning Reserve & Resource Estimates". The copper-equivalent grade was calculated as follows: CuEq = Recoverable Revenue ÷ 2204.62 * 100 ÷ 1.55. Where: CuEq = Copper equivalent grade; Recoverable Revenue = Revenue in US dollars for recoverable copper, recoverable gold and recoverable silver using metal prices of US$1.55/lb, US$650/oz, and US$11/oz for copper, gold, and silver, respectively; for the purposes of the equivalency formula, Cu Recovery is assumed to be 100%. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Inferred Resources are in addition to Measured and Indicated Resources. Inferred Resources have a great amount of uncertainty as to their existence and whether they can be mined legally or economically. It cannot be assumed that all or any part of the Inferred Resources will ever be upgraded to a higher category. See "Cautionary Note Concerning Reserve & Resource Estimates". NOVAGOLD Canada Inc. has agreed to transfer its 60% joint venture interest in the Copper Canyon property to the Galore Creek Partnership, which is equally owned by NOVAGOLD Canada Inc. and a subsidiary of Teck Resources Limited. The remaining 40% joint venture interest in the Copper Canyon property is owned by another wholly owned subsidiary of NOVAGOLD. Cautionary Note Concerning Reserve & Resource Estimates This summary table uses the term “resources”, “measured resources”, “indicated resources” and “inferred resources”. United States investors are advised that, while such terms are recognized and required by Canadian securities laws, the United States Securities and Exchange Commission (the “SEC”) does not recognize them. Under United States standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. Mineral resources that are not mineral reserves do not have demonstrated economic viability. United States investors are cautioned not to assume that all or any part of measured or indicated resources will ever be converted into reserves. Further, inferred resources have a great amount of uncertainty as to their existence and as to whether they can be mined legally or economically. It cannot be assumed that all or any part of the inferred resources will ever be upgraded to a higher category. Therefore, United States investors are also cautioned not to assume that all or any part of the inferred resources exist, or that they can be mined legally or economically. Disclosure of “contained ounces” is permitted disclosure under Canadian regulations, however, the SEC normally only permits issuers to report “resources” as in place tonnage and grade without reference to unit measures. Accordingly, information concerning descriptions of mineralization and resources contained in this release may not be comparable to information made public by United States companies subject to the reporting and disclosure requirements of the SEC. NI 43-101 is a rule developed by the Canadian Securities Administrators, which established standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Unless otherwise indicated, all resource estimates contained in this circular have been prepared in accordance with NI 43-101 and the CIM Definition Standards. Technical Reports and Qualified Persons The documents referenced below provide supporting technical information for each of NOVAGOLD's projects. Project Qualified Person(s) Most Recent Disclosure & Filing Date Donlin Gold Tony Lipiec, P. Eng., AMEC Donlin Creek Gold Project Gordon Seibel R.M. SME, AMEC Alaska, USA Kirk Hanson P.E., AMEC NI 43-101 Technical Report on Second Updated Feasibility Study amended filing on January 23, 2012 Galore Creek Robert Gill, P.Eng., AMEC Galore Creek Copper–Gold Project, Jay Melnyk, P.Eng., AMEC British Columbia, NI 43-101 Technical Report on Pre-Feasibility Study, Greg Kulla, P.Geo., AMEC filed on September 12, 2011 Greg Wortman, P.Eng., AMEC Dana Rogers, P.Eng., Lemley International Heather White, B.Sc., P.Eng., who is a consultant to NOVAGOLD and a “qualified person” under NI 43-101, has approved the scientific and technical information included in this section related to: (i) Donlin Gold since the issuance of the technical report filed on January 23, 2012, and (ii) Galore Creek since the issuance of the technical report filed on September 12, 2011. reserve/resource table (con’t) 57
  • 58. 58 NOVAGOLD RESOURCES INC. Suite 720 – 789 West Pender Street Vancouver, BC Canada V6C 1H2 T 604 669 6227 TF 1 866 669 6227 F 604 669 6272 www.novagold.com info@novagold.com Mélanie Hennessey VP, Corporate Communications melanie.hennessey@novagold.com Erin O’Toole Analyst, Investor Relations erin.otoole@novagold.com contact us