SlideShare une entreprise Scribd logo
1  sur  18
Télécharger pour lire hors ligne
January 6, 2021
Eglinton Crosstown LRT
Chaplin-Avenue CLC
Chaplin Station
CHAPLIN STATION UPDATE
3
Activity Location Approx. Date & Duration What to Expect
Early Morning Deliveries
Main and Tertiary
entrances
Weekly between 5:00 a.m. –
7:30 a.m. through spring
2021
• Noise from truck and
material hoisting
Tertiary Entrance
Construction
Periodic chipping, and
installation of structural steel
and panels
South side of Eglinton
Ave, east of Chaplin Cres
and adjacent Toronto Fire
Station 135
Underway into spring 2021
• Periodic noise and
vibration from chipping of
concrete and hardened
material
• Noise from construction
activity, such as use of
cranes, trucks, and other
equipment
• Closure of the Chaplin-
Russell Hill laneway behind
the Tertiary Entrance
through early March 2021
Main Entrance Construction
Concrete and formwork
North side of Eglinton Ave
between Chaplin Cres
and Gilgorm Rd
Underway into spring 2021
Station Box Construction
Rebar, concrete and formwork
Beneath Eglinton Ave Underway into spring 2021
CHAPLIN STATION UPDATE
4
Activity Location Approx. Date & Duration What to Expect
Watermain Reinstatement Work
Chaplin and Eglinton Ave
intersection
Underway through March 2021
• Chaplin Cres closure
beginning January 11, 2021
• Work will take place between
6:00 a.m. – 11:00 p.m.
• Closure of Chaplin Cres
between Eglinton Ave and the
Russell Hill-Chaplin laneway
from January 11 – February 28,
2021
• Temporary removal of on-
street parking on Russell Hill
and Tarlton Rds
• Noise from construction
activity, including a hydro-
excavation truck and excavator
• Water pressure interruption
during commission work in
mid-February 2021
• TTC 14 Glencairn route detour
CURRENT TRAFFIC CONFIGURATION
5
Until January 11, 2021
UPCOMING TRAFFIC CONFIGURATION – CHAPLIN CLOSURE
6
January 11 – February 28, 2021
TTC 14 GLENCAIRN DETOUR ROUTE
7
CONSTRUCTION PROGRESS PHOTOS
8
CONCOURSETERTIARY ENTRANCE
Avenue Station
AVENUE STATION UPDATE
10
Activity Location Approx. Date & Duration What to Expect
Final lining (waterproofing,
rebar installation, and
mechanical electrical works)
Throughout all station areas Underway through early 2021
• Deliveries at the main and
secondary entrances
Concrete Pours
Between the Main and Secondary
Entrances
Three times per week for approx.
12 – 18 hours through 2021
• Concrete truck activity
• Occupation of the westbound
curb lane during some pours
Eglinton Connects Streetscape
and Cycle Track
Eglinton Ave between Lascelles Blvd
and Duplex Ave
Underway through mid 2021
• Eglinton reduced to one lane in
each direction between
Lascelles Blvd & Duplex Ave
• Use of excavator, hydro-vac
and concrete trucks
Dewatering Well Maintenance
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021; 9:00
a.m. – 4:00 p.m.
• Road occupancy around well
• Use of hydro-vac truck
Monitoring Work
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021 • Short-term road occupancy
CURRENT TRAFFIC CONFIGURATION
11
Through September 2021
CURRENT TRAFFIC CONFIGURATION: LASCELLES BLVD TO DUPLEX AVE
12
Through mid-January 2021
UPCOMING TRAFFIC CONFIGURATION: LASCELLES BLVD TO DUPLEX AVE
13
As early as January 11, 2021 for approximately one (1) month
EGLINTON AVE FUTURE CONFIGURATION – ORIOLE PKWY TO LASCELLES BLVD
14
EGLINTON AVE FUTURE CONFIGURATION – LASCELLES BLVD – DUPLEX AVE
15
EGLINTON CONNECTS CONSTRUCTION OVERVIEW
16
Construction of the new Eglinton Streetscape and Cycle Track between Lascelles Blvd and Duplex Ave will
continue into 2021.
The Eglinton Connects Streetscape and Cycle Track is being constructed in coordination with the City of
Toronto’s Streetscape and Cycle Track Design.
Construction Hours:
• Monday – Saturday, 7:00 a.m. – 7:00 p.m. with periodic overnight work
Construction Activities:
• Excavation
• Utility Reinstatement
• Concrete Work
• Compaction and Paving
• Landscaping – installation of street furnishings, light poles, trees etc.
To accommodate this work, all street furnishings, bus shelters, and trees between Lascelles Blvd and Duplex Ave will be
removed. Notice will be provided in advance of removals.
Upon completion of Eglinton Connects, additional street furnishings and trees will be installed/planted along Eglinton Ave.
CONSTRUCTION PROGRESS PHOTOS
17
PLATFORM CONSTRUCTION –
STATION BOX
EGLINTON CONNECTS ROAD WORKS –
EGLINTON AVENUE BETWEEN DUPLEX AVE AND LASCELLES BLVD
Chaplin Station LRT Update

Contenu connexe

Tendances

Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Crosstown TO
 
Cedarvale & Forest Hill Construction Update (July 30, 2021)
Cedarvale & Forest Hill Construction Update (July 30, 2021)Cedarvale & Forest Hill Construction Update (July 30, 2021)
Cedarvale & Forest Hill Construction Update (July 30, 2021)Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Crosstown TO
 
Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Crosstown TO
 
Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Crosstown TO
 
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018Crosstown TO
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Crosstown TO
 
Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Crosstown TO
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Crosstown TO
 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Crosstown TO
 
Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019Crosstown TO
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020Crosstown TO
 
Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Crosstown TO
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Crosstown TO
 

Tendances (20)

Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
 
Cedarvale & Forest Hill Construction Update (July 30, 2021)
Cedarvale & Forest Hill Construction Update (July 30, 2021)Cedarvale & Forest Hill Construction Update (July 30, 2021)
Cedarvale & Forest Hill Construction Update (July 30, 2021)
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
 
Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019
 
Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021
 
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
 
Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)
 
Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
 
Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November
 

Similaire à Chaplin Station LRT Update

Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Crosstown TO
 
Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Crosstown TO
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Crosstown TO
 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Crosstown TO
 
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptxChaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxCrosstown TO
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021 Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
 
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptxChaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptxCrosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Crosstown TO
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November Crosstown TO
 
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfCrosstown TO
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Crosstown TO
 
Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Crosstown TO
 
Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Crosstown TO
 
CLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCrosstown TO
 

Similaire à Chaplin Station LRT Update (20)

Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
 
Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
 
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptxChaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptxChaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
Chaplin-Avenue CLC - Sept 14, 2022 compressed .pptx
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
 
Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021
 
Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021Leaside and Laird CLC - January 11, 2021
Leaside and Laird CLC - January 11, 2021
 
CLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCLC Eglinton and Mount Pleasant
CLC Eglinton and Mount Pleasant
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
 

Plus de Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfCrosstown TO
 

Plus de Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
 

Dernier

2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos WebinarLinda Reinstein
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Call Girls in Nagpur High Profile
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...nservice241
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.Christina Parmionova
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...tanu pandey
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Call Girls in Nagpur High Profile
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...tanu pandey
 
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Call Girls in Nagpur High Profile
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...aartirawatdelhi
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...ranjana rawat
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Christina Parmionova
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29JSchaus & Associates
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30JSchaus & Associates
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...MOHANI PANDEY
 

Dernier (20)

2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
 

Chaplin Station LRT Update

  • 1. January 6, 2021 Eglinton Crosstown LRT Chaplin-Avenue CLC
  • 3. CHAPLIN STATION UPDATE 3 Activity Location Approx. Date & Duration What to Expect Early Morning Deliveries Main and Tertiary entrances Weekly between 5:00 a.m. – 7:30 a.m. through spring 2021 • Noise from truck and material hoisting Tertiary Entrance Construction Periodic chipping, and installation of structural steel and panels South side of Eglinton Ave, east of Chaplin Cres and adjacent Toronto Fire Station 135 Underway into spring 2021 • Periodic noise and vibration from chipping of concrete and hardened material • Noise from construction activity, such as use of cranes, trucks, and other equipment • Closure of the Chaplin- Russell Hill laneway behind the Tertiary Entrance through early March 2021 Main Entrance Construction Concrete and formwork North side of Eglinton Ave between Chaplin Cres and Gilgorm Rd Underway into spring 2021 Station Box Construction Rebar, concrete and formwork Beneath Eglinton Ave Underway into spring 2021
  • 4. CHAPLIN STATION UPDATE 4 Activity Location Approx. Date & Duration What to Expect Watermain Reinstatement Work Chaplin and Eglinton Ave intersection Underway through March 2021 • Chaplin Cres closure beginning January 11, 2021 • Work will take place between 6:00 a.m. – 11:00 p.m. • Closure of Chaplin Cres between Eglinton Ave and the Russell Hill-Chaplin laneway from January 11 – February 28, 2021 • Temporary removal of on- street parking on Russell Hill and Tarlton Rds • Noise from construction activity, including a hydro- excavation truck and excavator • Water pressure interruption during commission work in mid-February 2021 • TTC 14 Glencairn route detour
  • 6. UPCOMING TRAFFIC CONFIGURATION – CHAPLIN CLOSURE 6 January 11 – February 28, 2021
  • 7. TTC 14 GLENCAIRN DETOUR ROUTE 7
  • 10. AVENUE STATION UPDATE 10 Activity Location Approx. Date & Duration What to Expect Final lining (waterproofing, rebar installation, and mechanical electrical works) Throughout all station areas Underway through early 2021 • Deliveries at the main and secondary entrances Concrete Pours Between the Main and Secondary Entrances Three times per week for approx. 12 – 18 hours through 2021 • Concrete truck activity • Occupation of the westbound curb lane during some pours Eglinton Connects Streetscape and Cycle Track Eglinton Ave between Lascelles Blvd and Duplex Ave Underway through mid 2021 • Eglinton reduced to one lane in each direction between Lascelles Blvd & Duplex Ave • Use of excavator, hydro-vac and concrete trucks Dewatering Well Maintenance Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021; 9:00 a.m. – 4:00 p.m. • Road occupancy around well • Use of hydro-vac truck Monitoring Work Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021 • Short-term road occupancy
  • 12. CURRENT TRAFFIC CONFIGURATION: LASCELLES BLVD TO DUPLEX AVE 12 Through mid-January 2021
  • 13. UPCOMING TRAFFIC CONFIGURATION: LASCELLES BLVD TO DUPLEX AVE 13 As early as January 11, 2021 for approximately one (1) month
  • 14. EGLINTON AVE FUTURE CONFIGURATION – ORIOLE PKWY TO LASCELLES BLVD 14
  • 15. EGLINTON AVE FUTURE CONFIGURATION – LASCELLES BLVD – DUPLEX AVE 15
  • 16. EGLINTON CONNECTS CONSTRUCTION OVERVIEW 16 Construction of the new Eglinton Streetscape and Cycle Track between Lascelles Blvd and Duplex Ave will continue into 2021. The Eglinton Connects Streetscape and Cycle Track is being constructed in coordination with the City of Toronto’s Streetscape and Cycle Track Design. Construction Hours: • Monday – Saturday, 7:00 a.m. – 7:00 p.m. with periodic overnight work Construction Activities: • Excavation • Utility Reinstatement • Concrete Work • Compaction and Paving • Landscaping – installation of street furnishings, light poles, trees etc. To accommodate this work, all street furnishings, bus shelters, and trees between Lascelles Blvd and Duplex Ave will be removed. Notice will be provided in advance of removals. Upon completion of Eglinton Connects, additional street furnishings and trees will be installed/planted along Eglinton Ave.
  • 17. CONSTRUCTION PROGRESS PHOTOS 17 PLATFORM CONSTRUCTION – STATION BOX EGLINTON CONNECTS ROAD WORKS – EGLINTON AVENUE BETWEEN DUPLEX AVE AND LASCELLES BLVD