Ce diaporama a bien été signalé.
Nous utilisons votre profil LinkedIn et vos données d’activité pour vous proposer des publicités personnalisées et pertinentes. Vous pouvez changer vos préférences de publicités à tout moment.

Avenue & Chaplin CLC - Construction Update: January 6, 2021

744 vues

Publié le

Presentation material from the January 6, 2021 Avenue & Chaplin CLC

  • Soyez le premier à commenter

  • Soyez le premier à aimer ceci

Avenue & Chaplin CLC - Construction Update: January 6, 2021

  1. 1. January 6, 2021 Eglinton Crosstown LRT Chaplin-Avenue CLC
  2. 2. Chaplin Station
  3. 3. CHAPLIN STATION UPDATE 3 Activity Location Approx. Date & Duration What to Expect Early Morning Deliveries Main and Tertiary entrances Weekly between 5:00 a.m. – 7:30 a.m. through spring 2021 • Noise from truck and material hoisting Tertiary Entrance Construction Periodic chipping, and installation of structural steel and panels South side of Eglinton Ave, east of Chaplin Cres and adjacent Toronto Fire Station 135 Underway into spring 2021 • Periodic noise and vibration from chipping of concrete and hardened material • Noise from construction activity, such as use of cranes, trucks, and other equipment • Closure of the Chaplin- Russell Hill laneway behind the Tertiary Entrance through early March 2021 Main Entrance Construction Concrete and formwork North side of Eglinton Ave between Chaplin Cres and Gilgorm Rd Underway into spring 2021 Station Box Construction Rebar, concrete and formwork Beneath Eglinton Ave Underway into spring 2021
  4. 4. CHAPLIN STATION UPDATE 4 Activity Location Approx. Date & Duration What to Expect Watermain Reinstatement Work Chaplin and Eglinton Ave intersection Underway through March 2021 • Chaplin Cres closure beginning January 11, 2021 • Work will take place between 6:00 a.m. – 11:00 p.m. • Closure of Chaplin Cres between Eglinton Ave and the Russell Hill-Chaplin laneway from January 11 – February 28, 2021 • Temporary removal of on- street parking on Russell Hill and Tarlton Rds • Noise from construction activity, including a hydro- excavation truck and excavator • Water pressure interruption during commission work in mid-February 2021 • TTC 14 Glencairn route detour
  5. 5. CURRENT TRAFFIC CONFIGURATION 5 Until January 11, 2021
  6. 6. UPCOMING TRAFFIC CONFIGURATION – CHAPLIN CLOSURE 6 January 11 – February 28, 2021
  7. 7. TTC 14 GLENCAIRN DETOUR ROUTE 7
  8. 8. CONSTRUCTION PROGRESS PHOTOS 8 CONCOURSETERTIARY ENTRANCE
  9. 9. Avenue Station
  10. 10. AVENUE STATION UPDATE 10 Activity Location Approx. Date & Duration What to Expect Final lining (waterproofing, rebar installation, and mechanical electrical works) Throughout all station areas Underway through early 2021 • Deliveries at the main and secondary entrances Concrete Pours Between the Main and Secondary Entrances Three times per week for approx. 12 – 18 hours through 2021 • Concrete truck activity • Occupation of the westbound curb lane during some pours Eglinton Connects Streetscape and Cycle Track Eglinton Ave between Lascelles Blvd and Duplex Ave Underway through mid 2021 • Eglinton reduced to one lane in each direction between Lascelles Blvd & Duplex Ave • Use of excavator, hydro-vac and concrete trucks Dewatering Well Maintenance Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021; 9:00 a.m. – 4:00 p.m. • Road occupancy around well • Use of hydro-vac truck Monitoring Work Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021 • Short-term road occupancy
  11. 11. CURRENT TRAFFIC CONFIGURATION 11 Through September 2021
  12. 12. CURRENT TRAFFIC CONFIGURATION: LASCELLES BLVD TO DUPLEX AVE 12 Through mid-January 2021
  13. 13. UPCOMING TRAFFIC CONFIGURATION: LASCELLES BLVD TO DUPLEX AVE 13 As early as January 11, 2021 for approximately one (1) month
  14. 14. EGLINTON AVE FUTURE CONFIGURATION – ORIOLE PKWY TO LASCELLES BLVD 14
  15. 15. EGLINTON AVE FUTURE CONFIGURATION – LASCELLES BLVD – DUPLEX AVE 15
  16. 16. EGLINTON CONNECTS CONSTRUCTION OVERVIEW 16 Construction of the new Eglinton Streetscape and Cycle Track between Lascelles Blvd and Duplex Ave will continue into 2021. The Eglinton Connects Streetscape and Cycle Track is being constructed in coordination with the City of Toronto’s Streetscape and Cycle Track Design. Construction Hours: • Monday – Saturday, 7:00 a.m. – 7:00 p.m. with periodic overnight work Construction Activities: • Excavation • Utility Reinstatement • Concrete Work • Compaction and Paving • Landscaping – installation of street furnishings, light poles, trees etc. To accommodate this work, all street furnishings, bus shelters, and trees between Lascelles Blvd and Duplex Ave will be removed. Notice will be provided in advance of removals. Upon completion of Eglinton Connects, additional street furnishings and trees will be installed/planted along Eglinton Ave.
  17. 17. CONSTRUCTION PROGRESS PHOTOS 17 PLATFORM CONSTRUCTION – STATION BOX EGLINTON CONNECTS ROAD WORKS – EGLINTON AVENUE BETWEEN DUPLEX AVE AND LASCELLES BLVD

×