1. November 4, 2021
Eglinton Crosstown LRT
Construction Liaison Meeting
Brentcliffe Road to Victoria Park Avenue
2. METROLINX LAND ACKNOWLEDGMENT
2
Let us take a moment to acknowledge that we are on the traditional territory of Indigenous
Peoples including the Anishnabeg, the Haudenosaunee and the Wendat peoples.
We are all Treaty people. Many of us have come here as settlers and immigrants … in this
generation or generations past.
Metrolinx declares its commitment to building meaningful relationships with Indigenous Peoples.
We acknowledge the historic and continued impacts of colonization and the need to work towards
meaningful reconciliation with the original caretakers of this land.
We acknowledge that Metrolinx operates on lands covered by 20 Treaties, and that we have a
responsibility to recognize and value the rights of Indigenous Nations and Peoples and conduct
business in a matter that is built on the foundation of trust, respect and collaboration.
4. SECTION ONE AT-GRADE UPDATE
4
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021
Noise Barrier and Soil Nail Wall removal Brentcliffe intersection – SE side Fall 2021
Landscaping along Eglinton Brentcliffe – Kennedy Fall 2021
• Brentcliffe Retaining Wall
construction
• Landscape Restoration Works
North side of Eglinton Ave, east of
Brentcliffe Rd
• Completed September 2021
• Ongoing through Fall 2021
• Platform ramps & curbs
• Electrical finishes
Sunnybrook Park Stop
Ongoing through Fall 2021
• Multi-use path construction -
Landscaping works
Serena Gundy Park – West of Leslie St. • Fall 2021
5. EAST TESTING & COMMISSIONING
5
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021.
• Dynamic Testing began August 24, 2021, and
will last for approximately six weeks.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
6. RETAINING WALL CONSTRUCTION
NORTH SIDE OF EGLINTON AVENUE
EAST OF BRENTCLIFFE ROAD
6
• This retaining wall is required to hold the embankment created from
the widened Eglinton Ave.
• Retaining wall construction was completed in September 2021
• Monitoring of the slope continues and there have been no recent
issues with the movement. Residents on Thursfield Crescent have full
use of their backyards.
• The City provided revised comments on the restoration design and approved planting trees in soil depths
that are less than the by-law requirements, which means trees will be included in the restoration plan.
• CTS reviewed and incorporated the City’s comments; the final restoration plan has been approved the City.
• CTS has shared the restoration plan with Elected Officials and Thursfield residents.
• CTS expects to begin the restoration works in Fall 2021.
7. FINAL ROAD RESTORATION
BRENTCLIFFE – KENNEDY
7
• Final Road Restoration works began in August 2021 and will last through Fall 2021
• The approximate timeline for road restoration of the At-Grade is:
o August: Aga Khan – Wynford
o September: Swift – VP; Eglinton Square - Warden
o October: Warden – Ionview; Don Mills – DVP ; Victoria Park Intersection
o November 8: Wynford – Swift
o November 9: Eglinton Square
o November 10 – 11: Birchmount – Rosemount
o 2022: Ionview - Kennedy
o 2022: Leslie – Aga Khan
• More specific details regarding the dates and locations of road restoration works will be
communicated to the public as they become available
8. NOISE BARRIER WALL AND SOIL NAIL WALL REMOVAL
8
• The noise barrier and soil nail walls, located on
the south side of Eglinton Avenue East, east of
Brentcliffe Rd., were erected in 2014 to facilitate
the construction of the east portal.
• As early as Fall 2021, CTS will begin removing
the noise barrier wall and exposed segment of
the soil nail wall. This work is expected to last
approximately one (1) month
• More detailed information about this work will
be communicated to the residents before the
work begins.
9. RAMP CONSTRUCTION, WEST OF LESLIE STREET
MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK
9
• Installation of topsoil, sodding, and landscaping works are taking place through Fall 2021 as part of the final
restoration plan
Landscaping through Fall 2021
12. SCIENCE CENTRE STATION UPDATE
12
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021
Finishing Activities:
• Floor tiling, ceiling grid & tile
installation, mechanical and electrical
finishes, handrail installation
Station Box Ongoing through Fall 2021
Finishing Activities:
• Wall & floor tiling, ceiling grid & tile
installation, electrical finishes, sliding
door finishes, canopy Installation
• Bike storage
Bus Terminal
Ongoing through Fall 2021
Finishing Activities:
• Floor tiling, ceiling grid & tile
installation, electrical finishes, sliding
door finishes
Main Entrance Ongoing through Fall 2021
13. EAST TESTING & COMMISSIONING
13
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021.
• Dynamic Testing began August 24, 2021, and
will last for approximately six weeks.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
17. SECTION TWO AT-GRADE UPDATE
17
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021
Final Paving
• Don Mills – DVP
• Wynford - Swift
• Eglinton Square intersections
• Completed October 2021
• November 8, 2021
• November 9, 2021
Landscaping along Eglinton Brentcliffe – Kennedy Fall 2021
• Platform ramps & curbs
• Electrical finishes
Aga Khan Park & Museum Stop
• Ongoing through Fall 2021
•
• Platform ramps & curbs
• Electrical finishes
Sloane Stop
• Ongoing through Fall 2021
•
• Platform ramps & curbs
• Electrical finishes
O’Connor Stop
• Ongoing through Fall 2021
•
18. EAST TESTING & COMMISSIONING
18
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021.
• Dynamic Testing began August 24, 2021, and
will last for approximately six weeks.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
19. FINAL ROAD RESTORATION
BRENTCLIFFE – KENNEDY
19
• Final Road Restoration works began in August 2021 and will last through Fall 2021
• The approximate timeline for road restoration of the At-Grade is:
o August: Aga Khan – Wynford
o September: Swift – VP; Eglinton Square - Warden
o October: Warden – Ionview; Don Mills – DVP ; Victoria Park Intersection
o November 8: Wynford – Swift
o November 9: Eglinton Square
o November 10 – 11: Birchmount – Rosemount
o 2022: Ionview - Kennedy
o 2022: Leslie – Aga Khan
• More specific details regarding the dates and locations of road restoration works will be
communicated to the public as they become available