SlideShare une entreprise Scribd logo
1  sur  21
Télécharger pour lire hors ligne
November 4, 2021
Eglinton Crosstown LRT
Construction Liaison Meeting
Brentcliffe Road to Victoria Park Avenue
METROLINX LAND ACKNOWLEDGMENT
2
Let us take a moment to acknowledge that we are on the traditional territory of Indigenous
Peoples including the Anishnabeg, the Haudenosaunee and the Wendat peoples.
We are all Treaty people. Many of us have come here as settlers and immigrants … in this
generation or generations past.
Metrolinx declares its commitment to building meaningful relationships with Indigenous Peoples.
We acknowledge the historic and continued impacts of colonization and the need to work towards
meaningful reconciliation with the original caretakers of this land.
We acknowledge that Metrolinx operates on lands covered by 20 Treaties, and that we have a
responsibility to recognize and value the rights of Indigenous Nations and Peoples and conduct
business in a matter that is built on the foundation of trust, respect and collaboration.
Section One At-Grade:
Brentcliffe Portal to Sunnybrook Park Stop
SECTION ONE AT-GRADE UPDATE
4
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021
Noise Barrier and Soil Nail Wall removal Brentcliffe intersection – SE side Fall 2021
Landscaping along Eglinton Brentcliffe – Kennedy Fall 2021
• Brentcliffe Retaining Wall
construction
• Landscape Restoration Works
North side of Eglinton Ave, east of
Brentcliffe Rd
• Completed September 2021
• Ongoing through Fall 2021
• Platform ramps & curbs
• Electrical finishes
Sunnybrook Park Stop
Ongoing through Fall 2021
• Multi-use path construction -
Landscaping works
Serena Gundy Park – West of Leslie St. • Fall 2021
EAST TESTING & COMMISSIONING
5
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021.
• Dynamic Testing began August 24, 2021, and
will last for approximately six weeks.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
RETAINING WALL CONSTRUCTION
NORTH SIDE OF EGLINTON AVENUE
EAST OF BRENTCLIFFE ROAD
6
• This retaining wall is required to hold the embankment created from
the widened Eglinton Ave.
• Retaining wall construction was completed in September 2021
• Monitoring of the slope continues and there have been no recent
issues with the movement. Residents on Thursfield Crescent have full
use of their backyards.
• The City provided revised comments on the restoration design and approved planting trees in soil depths
that are less than the by-law requirements, which means trees will be included in the restoration plan.
• CTS reviewed and incorporated the City’s comments; the final restoration plan has been approved the City.
• CTS has shared the restoration plan with Elected Officials and Thursfield residents.
• CTS expects to begin the restoration works in Fall 2021.
FINAL ROAD RESTORATION
BRENTCLIFFE – KENNEDY
7
• Final Road Restoration works began in August 2021 and will last through Fall 2021
• The approximate timeline for road restoration of the At-Grade is:
o August: Aga Khan – Wynford
o September: Swift – VP; Eglinton Square - Warden
o October: Warden – Ionview; Don Mills – DVP ; Victoria Park Intersection
o November 8: Wynford – Swift
o November 9: Eglinton Square
o November 10 – 11: Birchmount – Rosemount
o 2022: Ionview - Kennedy
o 2022: Leslie – Aga Khan
• More specific details regarding the dates and locations of road restoration works will be
communicated to the public as they become available
NOISE BARRIER WALL AND SOIL NAIL WALL REMOVAL
8
• The noise barrier and soil nail walls, located on
the south side of Eglinton Avenue East, east of
Brentcliffe Rd., were erected in 2014 to facilitate
the construction of the east portal.
• As early as Fall 2021, CTS will begin removing
the noise barrier wall and exposed segment of
the soil nail wall. This work is expected to last
approximately one (1) month
• More detailed information about this work will
be communicated to the residents before the
work begins.
RAMP CONSTRUCTION, WEST OF LESLIE STREET
MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK
9
• Installation of topsoil, sodding, and landscaping works are taking place through Fall 2021 as part of the final
restoration plan
Landscaping through Fall 2021
CONSTRUCTION PROGRESS PHOTOS
10
INSTALLATION AND SLOPE
BRENTCLIFFE RETAINING WALL
Science Centre Station
SCIENCE CENTRE STATION UPDATE
12
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021
Finishing Activities:
• Floor tiling, ceiling grid & tile
installation, mechanical and electrical
finishes, handrail installation
Station Box Ongoing through Fall 2021
Finishing Activities:
• Wall & floor tiling, ceiling grid & tile
installation, electrical finishes, sliding
door finishes, canopy Installation
• Bike storage
Bus Terminal
Ongoing through Fall 2021
Finishing Activities:
• Floor tiling, ceiling grid & tile
installation, electrical finishes, sliding
door finishes
Main Entrance Ongoing through Fall 2021
EAST TESTING & COMMISSIONING
13
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021.
• Dynamic Testing began August 24, 2021, and
will last for approximately six weeks.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
SCIENCE CENTRE TRAFFIC CONFIGURATION
14
August 2021
CONSTRUCTION PROGRESS PHOTOS
15
CONCRETE CAULKING
MAIN ENTRANCE
CANOPY TILING
BUS TERMINAL
Section Two At-Grade
Aga Khan Park & Museum Stop to O’Connor Stop
SECTION TWO AT-GRADE UPDATE
17
Activity Location Approx. Date & Duration
Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021
Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021
Final Paving
• Don Mills – DVP
• Wynford - Swift
• Eglinton Square intersections
• Completed October 2021
• November 8, 2021
• November 9, 2021
Landscaping along Eglinton Brentcliffe – Kennedy Fall 2021
• Platform ramps & curbs
• Electrical finishes
Aga Khan Park & Museum Stop
• Ongoing through Fall 2021
•
• Platform ramps & curbs
• Electrical finishes
Sloane Stop
• Ongoing through Fall 2021
•
• Platform ramps & curbs
• Electrical finishes
O’Connor Stop
• Ongoing through Fall 2021
•
EAST TESTING & COMMISSIONING
18
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east
end of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and
Kennedy Road through December 2021.
• Dynamic Testing began August 24, 2021, and
will last for approximately six weeks.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
FINAL ROAD RESTORATION
BRENTCLIFFE – KENNEDY
19
• Final Road Restoration works began in August 2021 and will last through Fall 2021
• The approximate timeline for road restoration of the At-Grade is:
o August: Aga Khan – Wynford
o September: Swift – VP; Eglinton Square - Warden
o October: Warden – Ionview; Don Mills – DVP ; Victoria Park Intersection
o November 8: Wynford – Swift
o November 9: Eglinton Square
o November 10 – 11: Birchmount – Rosemount
o 2022: Ionview - Kennedy
o 2022: Leslie – Aga Khan
• More specific details regarding the dates and locations of road restoration works will be
communicated to the public as they become available
CONSTRUCTION PROGRESS PHOTOS
20
INSTALLATION OF COLORED CONCRETE RAMPS
STOPS LANDSCAPING
SWIFT – SLOANE
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021

Contenu connexe

Tendances

Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Crosstown TO
 
Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown Update
Crosstown TO
 

Tendances (20)

Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021
 
Leaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 PresentationLeaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 Presentation
 
CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022 CLC Pharmacy to Kennedy - January 25, 2022
CLC Pharmacy to Kennedy - January 25, 2022
 
Fairbank-Oakwood Construction Update - January 2022
Fairbank-Oakwood Construction Update - January 2022Fairbank-Oakwood Construction Update - January 2022
Fairbank-Oakwood Construction Update - January 2022
 
Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022Western Works CLC - Construction Update: January 18, 2022
Western Works CLC - Construction Update: January 18, 2022
 
CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021
 
Chaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee MeetingChaplin & Avenue Construction Liaison Committee Meeting
Chaplin & Avenue Construction Liaison Committee Meeting
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Nov 2019
 
Eglinton Crosstown Update
Eglinton Crosstown UpdateEglinton Crosstown Update
Eglinton Crosstown Update
 
Cedarvale & Forest Hill Construction Update (January 2022)
Cedarvale & Forest Hill Construction Update (January 2022)Cedarvale & Forest Hill Construction Update (January 2022)
Cedarvale & Forest Hill Construction Update (January 2022)
 
Pharmacy kennedy clc meeting - deck - march 26,2019
Pharmacy   kennedy clc meeting - deck - march 26,2019Pharmacy   kennedy clc meeting - deck - march 26,2019
Pharmacy kennedy clc meeting - deck - march 26,2019
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
 

Similaire à Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021

CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 

Similaire à Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021 (20)

Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November  Pharmacy to Kennedy CLC - November
Pharmacy to Kennedy CLC - November
 
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdfCLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
CLC Deck - Brentcliffe to Victoria Park - September 1, 2022 - Updated.pdf
 
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdfCLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - May 5 2022.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - March 3 2022.pdf
 
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptxCLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
CLC Pharmacy to Kennedy - March 29, 2022 Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdfCLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - July 7 2022.pdf
 
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
 
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting  - ...
Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - ...
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptxChaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021
 

Plus de Crosstown TO

Plus de Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfEglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
 
Test
TestTest
Test
 
Leaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdfLeaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdf
 
Leaside-Laird CLC - March 14 2022 - v2.pdf
Leaside-Laird CLC - March 14 2022 - v2.pdfLeaside-Laird CLC - March 14 2022 - v2.pdf
Leaside-Laird CLC - March 14 2022 - v2.pdf
 

Dernier

Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Chandigarh Call girls 9053900678 Call girls in Chandigarh
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls in Sarita Vihar Delhi Just Call 👉👉9873777170 Independent Female ...
Call Girls in  Sarita Vihar Delhi Just Call 👉👉9873777170  Independent Female ...Call Girls in  Sarita Vihar Delhi Just Call 👉👉9873777170  Independent Female ...
Call Girls in Sarita Vihar Delhi Just Call 👉👉9873777170 Independent Female ...
adilkhan87451
 

Dernier (20)

Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
Hinjewadi * VIP Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service ...
 
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental Crisis
 
Chakan ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Chakan ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Chakan ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Chakan ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
 
VIP Model Call Girls Baramati ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Baramati ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Baramati ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Baramati ( Pune ) Call ON 8005736733 Starting From 5K to...
 
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition PlansSustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
 
Pimple Gurav ) Call Girls Service Pune | 8005736733 Independent Escorts & Dat...
Pimple Gurav ) Call Girls Service Pune | 8005736733 Independent Escorts & Dat...Pimple Gurav ) Call Girls Service Pune | 8005736733 Independent Escorts & Dat...
Pimple Gurav ) Call Girls Service Pune | 8005736733 Independent Escorts & Dat...
 
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
call girls in Raghubir Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service ...
 
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
 
Call Girls in Sarita Vihar Delhi Just Call 👉👉9873777170 Independent Female ...
Call Girls in  Sarita Vihar Delhi Just Call 👉👉9873777170  Independent Female ...Call Girls in  Sarita Vihar Delhi Just Call 👉👉9873777170  Independent Female ...
Call Girls in Sarita Vihar Delhi Just Call 👉👉9873777170 Independent Female ...
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 

Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021

  • 1. November 4, 2021 Eglinton Crosstown LRT Construction Liaison Meeting Brentcliffe Road to Victoria Park Avenue
  • 2. METROLINX LAND ACKNOWLEDGMENT 2 Let us take a moment to acknowledge that we are on the traditional territory of Indigenous Peoples including the Anishnabeg, the Haudenosaunee and the Wendat peoples. We are all Treaty people. Many of us have come here as settlers and immigrants … in this generation or generations past. Metrolinx declares its commitment to building meaningful relationships with Indigenous Peoples. We acknowledge the historic and continued impacts of colonization and the need to work towards meaningful reconciliation with the original caretakers of this land. We acknowledge that Metrolinx operates on lands covered by 20 Treaties, and that we have a responsibility to recognize and value the rights of Indigenous Nations and Peoples and conduct business in a matter that is built on the foundation of trust, respect and collaboration.
  • 3. Section One At-Grade: Brentcliffe Portal to Sunnybrook Park Stop
  • 4. SECTION ONE AT-GRADE UPDATE 4 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021 Noise Barrier and Soil Nail Wall removal Brentcliffe intersection – SE side Fall 2021 Landscaping along Eglinton Brentcliffe – Kennedy Fall 2021 • Brentcliffe Retaining Wall construction • Landscape Restoration Works North side of Eglinton Ave, east of Brentcliffe Rd • Completed September 2021 • Ongoing through Fall 2021 • Platform ramps & curbs • Electrical finishes Sunnybrook Park Stop Ongoing through Fall 2021 • Multi-use path construction - Landscaping works Serena Gundy Park – West of Leslie St. • Fall 2021
  • 5. EAST TESTING & COMMISSIONING 5 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021. • Dynamic Testing began August 24, 2021, and will last for approximately six weeks. • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 6. RETAINING WALL CONSTRUCTION NORTH SIDE OF EGLINTON AVENUE EAST OF BRENTCLIFFE ROAD 6 • This retaining wall is required to hold the embankment created from the widened Eglinton Ave. • Retaining wall construction was completed in September 2021 • Monitoring of the slope continues and there have been no recent issues with the movement. Residents on Thursfield Crescent have full use of their backyards. • The City provided revised comments on the restoration design and approved planting trees in soil depths that are less than the by-law requirements, which means trees will be included in the restoration plan. • CTS reviewed and incorporated the City’s comments; the final restoration plan has been approved the City. • CTS has shared the restoration plan with Elected Officials and Thursfield residents. • CTS expects to begin the restoration works in Fall 2021.
  • 7. FINAL ROAD RESTORATION BRENTCLIFFE – KENNEDY 7 • Final Road Restoration works began in August 2021 and will last through Fall 2021 • The approximate timeline for road restoration of the At-Grade is: o August: Aga Khan – Wynford o September: Swift – VP; Eglinton Square - Warden o October: Warden – Ionview; Don Mills – DVP ; Victoria Park Intersection o November 8: Wynford – Swift o November 9: Eglinton Square o November 10 – 11: Birchmount – Rosemount o 2022: Ionview - Kennedy o 2022: Leslie – Aga Khan • More specific details regarding the dates and locations of road restoration works will be communicated to the public as they become available
  • 8. NOISE BARRIER WALL AND SOIL NAIL WALL REMOVAL 8 • The noise barrier and soil nail walls, located on the south side of Eglinton Avenue East, east of Brentcliffe Rd., were erected in 2014 to facilitate the construction of the east portal. • As early as Fall 2021, CTS will begin removing the noise barrier wall and exposed segment of the soil nail wall. This work is expected to last approximately one (1) month • More detailed information about this work will be communicated to the residents before the work begins.
  • 9. RAMP CONSTRUCTION, WEST OF LESLIE STREET MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK 9 • Installation of topsoil, sodding, and landscaping works are taking place through Fall 2021 as part of the final restoration plan Landscaping through Fall 2021
  • 10. CONSTRUCTION PROGRESS PHOTOS 10 INSTALLATION AND SLOPE BRENTCLIFFE RETAINING WALL
  • 12. SCIENCE CENTRE STATION UPDATE 12 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021 Finishing Activities: • Floor tiling, ceiling grid & tile installation, mechanical and electrical finishes, handrail installation Station Box Ongoing through Fall 2021 Finishing Activities: • Wall & floor tiling, ceiling grid & tile installation, electrical finishes, sliding door finishes, canopy Installation • Bike storage Bus Terminal Ongoing through Fall 2021 Finishing Activities: • Floor tiling, ceiling grid & tile installation, electrical finishes, sliding door finishes Main Entrance Ongoing through Fall 2021
  • 13. EAST TESTING & COMMISSIONING 13 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021. • Dynamic Testing began August 24, 2021, and will last for approximately six weeks. • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 14. SCIENCE CENTRE TRAFFIC CONFIGURATION 14 August 2021
  • 15. CONSTRUCTION PROGRESS PHOTOS 15 CONCRETE CAULKING MAIN ENTRANCE CANOPY TILING BUS TERMINAL
  • 16. Section Two At-Grade Aga Khan Park & Museum Stop to O’Connor Stop
  • 17. SECTION TWO AT-GRADE UPDATE 17 Activity Location Approx. Date & Duration Vehicle Testing Brentcliffe – Kennedy Ongoing through December 2021 Road Restoration Brentcliffe – Kennedy August 2021 – Fall 2021 Final Paving • Don Mills – DVP • Wynford - Swift • Eglinton Square intersections • Completed October 2021 • November 8, 2021 • November 9, 2021 Landscaping along Eglinton Brentcliffe – Kennedy Fall 2021 • Platform ramps & curbs • Electrical finishes Aga Khan Park & Museum Stop • Ongoing through Fall 2021 • • Platform ramps & curbs • Electrical finishes Sloane Stop • Ongoing through Fall 2021 • • Platform ramps & curbs • Electrical finishes O’Connor Stop • Ongoing through Fall 2021 •
  • 18. EAST TESTING & COMMISSIONING 18 • On May 25, 26, 27, 31 and June 1 and 2, 6 light rail vehicles (LRVs) were delivered to the east end of the alignment. • Testing and commissioning activities will be conducted between Brentcliffe Road and Kennedy Road through December 2021. • Dynamic Testing began August 24, 2021, and will last for approximately six weeks. • The LRVs will run mainly on the surface along a track in the center of Eglinton Avenue.
  • 19. FINAL ROAD RESTORATION BRENTCLIFFE – KENNEDY 19 • Final Road Restoration works began in August 2021 and will last through Fall 2021 • The approximate timeline for road restoration of the At-Grade is: o August: Aga Khan – Wynford o September: Swift – VP; Eglinton Square - Warden o October: Warden – Ionview; Don Mills – DVP ; Victoria Park Intersection o November 8: Wynford – Swift o November 9: Eglinton Square o November 10 – 11: Birchmount – Rosemount o 2022: Ionview - Kennedy o 2022: Leslie – Aga Khan • More specific details regarding the dates and locations of road restoration works will be communicated to the public as they become available
  • 20. CONSTRUCTION PROGRESS PHOTOS 20 INSTALLATION OF COLORED CONCRETE RAMPS STOPS LANDSCAPING SWIFT – SLOANE