SlideShare une entreprise Scribd logo
1  sur  11
Télécharger pour lire hors ligne
September 30, 2020
Eglinton Crosstown-LRT
Cedarvale – Forest Hill CLC
Cedarvale Station
CEDARVALE STATION UPDATE
3
CEDARVALE –FOREST HILL CLC
Activity Location Approx. Date & Duration
Deep Excavation & Tieback Installation Station’s Main Entrance Complete!
Major Concrete Pours Throughout all station areas
Underway throughout 2020 into 2021
Starting as early as 5:00 a.m. ranging from 12-18
hours
Geotechnical Monitoring
Eastbound curb lane of Eglinton Ave between
Winnett Ave and Allen Rd N
Through early 2021
Tuesdays between 11:00 a.m. – 2:00 p.m.
Pedestrian Tunnel Construction Area surrounding Eglinton West Station
Underway through 2021
Monday – Saturday; 6:00 a.m. – 2:00 a.m.
Eglinton West Station Support of
Excavation and Underpinning Works
Eglinton West Station
Underway through 2020
Monday – Saturday; 6:00 a.m. – 5:00 p.m.
Eglinton West Station Bus Loop Closure
for Roof Construction
Eglinton West Station Underway – Fall 2020
Temporary Traffic Deck Removal, Roof
Construction, and Permanent Utility
Installation
Eglinton Avenue West March 29, 2020 – early 2021
CURRENT TRAFFIC CONFIGURATION
4
Through Fall 2020
CEDARVALE –FOREST HILL CLC
CONSTRUCTION PROGRESS PHOTOS
5
CEDARVALE –FOREST HILL CLC
CONCRETE POUR FOR LAST
MAIN STATION INVERT SLAB
REMOVAL OF TEMPORARY SUPPORT BEAMS
UNDERNEATH THE TTC STATION BOX
Forest Hill Station
FOREST HILL STATION UPDATE
7
Activity Location Approx. Date & Duration
Deep Excavation
Beneath the station roof from the Main
Entrance
Complete
Main Entrance Construction
Excavation, installation of struts, lagging
and tie-backs
Northeast corner of Bathurst St and
Eglinton Ave
Underway through 2020
Secondary Entrance Construction
Formwork, rebar, conduit installation
and beam excavation
North side of Eglinton Ave, west of
Bathurst St
Underway through fall 2020
Station Box Construction
Waterproofing, shotcrete application
and duct bank construction
Beneath Eglinton Ave Underway through 2020
Concrete Pours Secondary Entrance
Periodically through fall 2020
Upcoming pours:
• October 5, 2020
Traffic Configuration Change Secondary Entrance
Monday October 5, 2020
*date subject to change
CURRENT TRAFFIC CONFIGURATION
8
Until October 5, 2020
UPCOMING TRAFFIC CONFIGURATION
9
October 5, 2020 – February 2021
CONSTRUCTION PROGRESS PHOTOS
10
REBAR INSTALLATION
SECONDARY ENTRANCE
WALL CONSTRUCTION
Cedarvale & Forest Hill Construction Update (September 30, 2020)

Contenu connexe

Tendances

Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Crosstown TO
 
Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Crosstown TO
 
Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Crosstown TO
 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Crosstown TO
 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018Crosstown TO
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meetingCrosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Crosstown TO
 
Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018
Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018
Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Crosstown TO
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Crosstown TO
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019Crosstown TO
 
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Fairbank-Oakwood Construction Update - January 2021
Fairbank-Oakwood Construction Update - January 2021Fairbank-Oakwood Construction Update - January 2021
Fairbank-Oakwood Construction Update - January 2021Crosstown TO
 

Tendances (20)

Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)
 
Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021
 
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018Cedarvale & Forest Hill Construction Liaison Committee - July 2018
Cedarvale & Forest Hill Construction Liaison Committee - July 2018
 
Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019
 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)
 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
 
Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018
Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018
Cedarvale & Forest Hill Construction Liaison Committee Meeting - February 2018
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Mar 25, 2020
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - May 2019
 
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
 
Fairbank-Oakwood Construction Update - January 2021
Fairbank-Oakwood Construction Update - January 2021Fairbank-Oakwood Construction Update - January 2021
Fairbank-Oakwood Construction Update - January 2021
 

Similaire à Cedarvale & Forest Hill Construction Update (September 30, 2020)

Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Crosstown TO
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Crosstown TO
 
Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Crosstown TO
 
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020Crosstown TO
 
Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Crosstown TO
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Crosstown TO
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Crosstown TO
 
Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020Crosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 

Similaire à Cedarvale & Forest Hill Construction Update (September 30, 2020) (20)

Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
 
Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020
 
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
 
Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - Jan 2020
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 

Plus de Crosstown TO

Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfEglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfCrosstown TO
 
Leaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdfLeaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdfCrosstown TO
 

Plus de Crosstown TO (20)

Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
 
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfEglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
 
Test
TestTest
Test
 
Leaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdfLeaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdf
 

Dernier

2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos WebinarLinda Reinstein
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30JSchaus & Associates
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024ARCResearch
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxtsionhagos36
 
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...MOHANI PANDEY
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Christina Parmionova
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...CedZabala
 
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Call Girls in Nagpur High Profile
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.Christina Parmionova
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...anilsa9823
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...ranjana rawat
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxSwastiRanjanNayak
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Dipal Arora
 

Dernier (20)

2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
 
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Dapodi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.
 
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Russian Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
 
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(NEHA) Bhosari Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 

Cedarvale & Forest Hill Construction Update (September 30, 2020)

  • 1. September 30, 2020 Eglinton Crosstown-LRT Cedarvale – Forest Hill CLC
  • 3. CEDARVALE STATION UPDATE 3 CEDARVALE –FOREST HILL CLC Activity Location Approx. Date & Duration Deep Excavation & Tieback Installation Station’s Main Entrance Complete! Major Concrete Pours Throughout all station areas Underway throughout 2020 into 2021 Starting as early as 5:00 a.m. ranging from 12-18 hours Geotechnical Monitoring Eastbound curb lane of Eglinton Ave between Winnett Ave and Allen Rd N Through early 2021 Tuesdays between 11:00 a.m. – 2:00 p.m. Pedestrian Tunnel Construction Area surrounding Eglinton West Station Underway through 2021 Monday – Saturday; 6:00 a.m. – 2:00 a.m. Eglinton West Station Support of Excavation and Underpinning Works Eglinton West Station Underway through 2020 Monday – Saturday; 6:00 a.m. – 5:00 p.m. Eglinton West Station Bus Loop Closure for Roof Construction Eglinton West Station Underway – Fall 2020 Temporary Traffic Deck Removal, Roof Construction, and Permanent Utility Installation Eglinton Avenue West March 29, 2020 – early 2021
  • 4. CURRENT TRAFFIC CONFIGURATION 4 Through Fall 2020 CEDARVALE –FOREST HILL CLC
  • 5. CONSTRUCTION PROGRESS PHOTOS 5 CEDARVALE –FOREST HILL CLC CONCRETE POUR FOR LAST MAIN STATION INVERT SLAB REMOVAL OF TEMPORARY SUPPORT BEAMS UNDERNEATH THE TTC STATION BOX
  • 7. FOREST HILL STATION UPDATE 7 Activity Location Approx. Date & Duration Deep Excavation Beneath the station roof from the Main Entrance Complete Main Entrance Construction Excavation, installation of struts, lagging and tie-backs Northeast corner of Bathurst St and Eglinton Ave Underway through 2020 Secondary Entrance Construction Formwork, rebar, conduit installation and beam excavation North side of Eglinton Ave, west of Bathurst St Underway through fall 2020 Station Box Construction Waterproofing, shotcrete application and duct bank construction Beneath Eglinton Ave Underway through 2020 Concrete Pours Secondary Entrance Periodically through fall 2020 Upcoming pours: • October 5, 2020 Traffic Configuration Change Secondary Entrance Monday October 5, 2020 *date subject to change
  • 9. UPCOMING TRAFFIC CONFIGURATION 9 October 5, 2020 – February 2021
  • 10. CONSTRUCTION PROGRESS PHOTOS 10 REBAR INSTALLATION SECONDARY ENTRANCE WALL CONSTRUCTION