5. 5
Eglinton Station: What to Expect in 2019
ACTIVITY AREA IMPACT DURATION
Shallow excavation
and decking
Eglinton west of Yonge
• Noise and vibration from excavation
activities
Through early 2019
Pile Installation,
shallow excavation,
and decking
South side of Eglinton
at Holly Street
• Noise and vibration from drilling activity Through early 2019
Stage 7 Traffic
Update
Duplex – Holly
• All crosswalks open up, Yonge opens to 4
lanes, and bike lanes added to Eglinton
2019
Berwick TTC Service
Building
Berwick Avenue at
Yonge Street
• Overnight work and noise due to crane and
other activities
• Weekend subway closures for TTC upgrades
• Tentatively February 9-10, March 2-3, 16-17,
23-24, April 6-7
• Additional weekend subway closures are
anticipated throughout 2019.
2019
Deep Excavation
TTC Bus Depot and
Salvation Army sites
• Noise and vibration from jackhammer
• Noise from Excavator
• 6am starts in December 2018
• 4am starts as early as January 2019
2019
TVS Pile Installation
Yonge Street north of
Eglinton
• Noise and vibration from drilling activity 3-4 months; 2019
6. 6
Eglinton Station – Deep Excavation Staging for 2019
Excavation
Activities
Excavation
Activities
• Deep excavation work will get underway between Duplex Avenue and Yonge Street.
– This work includes excavating to the bottom of the future station box (approximately 22
meters at the deepest point).
– Spoils from the excavation will be extracted and hauled from the existing TTC bus depot site
at the southeast corner of Duplex Avenue and Eglinton Avenue West, and the Salvation Army
site at the corner of Eglinton Avenue East and Cowbell Lane.
– In order to maintain schedule, excavation work will begin as early as 6:00 a.m. Monday –
Saturday on December 10, 2018, and 4:00 a.m. Monday – Saturday as early as January 2,
2019.
7. 7
Eglinton Station – Deep Excavation Noise Mitigation Plan
• Operation controls will include:
• White noise/broadband back-up alarms on all trucks and equipment.
• Loading soil only into the trucks (no large debris or rocks that would
create banging noises).
• Avoiding shaking of the excavator buckets.
• Lowering the drop height so soil/debris falls closer to the truck bed.
• Securing tailgates on trucks to limit banging noise.
• Limiting acceleration of the trucks as they ingress/egress.
• Turning off truck engines while they wait or are staging.
• Crosslinx will offer, upon request, noise mitigation instruments for
residents in the immediate vicinity of the work including noise
dampening drapes, white noise machines, and noise-cancelling
headphones.
• Crosslinx will continuously monitor for improvements and endeavor to
minimize noise throughout the delivery period.7
10. 10
Mount Pleasant Station Construction Update
ACTIVITY LOCATION APPROX. DATE AND DURATION
Pile Installation South side of Eglinton Ave E Complete
Shallow Excavation South side of Eglinton Ave E Through to early April 2019
Manhole Construction for Wet
Utilities (extended hours)
Southeast corner or Mt Pleasant Rd
and Eglinton Ave E
Through January 2019
Hydro Ductbank Work Mt Pleasant Rd and Eglinton Ave E Through March 2019
Taunton Road Watermain
Restoration
Southbound lane of Taunton Road at
Eglinton Ave E
Mid-January 2019 for three (3) weeks
Traffic Bridge Installation
Southeast corner or Mt Pleasant Rd
and Eglinton Ave E
As early as mid-February 2019
Traffic Change
Shift traffic on Mt Pleasant Rd to the
east
Late January 2019
Concrete Roof Pour Southwest Station Box Area As early as mid-February 2019
11. 11
Extended Hours for Manhole Construction
• As part of the new storm sewer system crews must install a
manhole at the southeast corner of the intersection
• To maintain schedule, crews will work extended hours, 6:00 a.m. –
1:00 a.m., Monday through Saturday, for approximately three (3)
weeks, beginning as early as Friday January 10, 2019
• Anticipated equipment and activities before 7:00 a.m. and after
11:00 p.m. include:
– mini-excavator and excavator
– forklift to move materials around the site
– hand tools
12. 12
Taunton Road Watermain Restoration Work
• As part of the new storm sewer system, crews must restore
the previously cut-and-capped watermain at Taunton Rd
and Eglinton Ave E
• To complete this works, crews must occupy the southbound
lane on Taunton Rd at Eglinton Ave; no eastbound right
turns onto Taunton Rd and no northbound right turns onto
Eglinton Ave will be permitted
• Work will begin as early as mid-January 2019 for
approximately three (3) weeks, working between 7:00 a.m.
and 7:00 p.m., Monday through Friday