2. 2
Action items from November CLC
ACTION: Management to investigate with the
condominium project to see if there was any
anticipated closure for pouring of cement.
No closure is anticipated by the Eglinton project team -
CTS cannot confirm the impact of construction
activities outside of the of Eglinton Crosstown project.
ACTION: Brittany to share the winter
maintenance plan as approved by CTS and City
of Toronto
See the following slides for CTS winter maintenance
maps.
9. Eglinton Station Construction Look-ahead
Activity Location Approx. Date/Duration
Extended Hours Deep Excavation
TTC Bus Depot and Salvation Army
Sites
Underway through mid 2020
TTC Line 1 Facility Services Building
Construction
• South side of Berwick Ave at
Yonge St
• Periodic closures of Berwick Ave
between Duplex Ave and Yonge
St
• Periodic closures of the
westbound lane and north
sidewalk on Hillsdale Ave bridge
b/w Yonge St and Duplex Ave
Periodically through 2020; subject
to TTC approval
Next closure of Berwick Ave
planned for Friday January 17 at
7:00 a.m. – Monday January 20 at
7:00 a.m.
Tunnel Ventilation Shaft
Construction
Center of Yonge St between Eglinton
Ave and Roehampton Ave
Underway through June 2020
TBM Extraction
• Close northbound curb lane on
Duplex Ave between TTC Bus
Depot site and Orchard View
Blvd
• North side of Eglinton Ave
between Duplex Ave and Yonge
St (existing work zone)
February 2020
13. Mount Pleasant Construction Activities
Activity Location Approx. Start Date & Duration
Shallow Excavation, Roof
Construction, and Utility Support
North side of Eglinton Avenue W
Underway approx. 1 month
remaining
Excavation and Tie-back Installation Main and Secondary Entrances
Underway approx. 2 months
remaining
Deep Excavation Underneath the station roof
February 2020 for approx. 5
months
Utility Reinstatement North side of Eglinton Avenue W
February 2020 for approx. 6
months
Scaffold removal and façade
restoration
Eglinton Junior Public School
March 2020 – weather
permitting approx. 8 weeks