5. 5
Eglinton Station Update
Recently Completed
• First weekend of TTC subway closure works at Berwick Avenue
Ongoing
• Shoring west of Yonge Street, north and south side of Eglinton
• Toronto Hydro relocation 2B – Hillsdale, Yonge
Upcoming
• Toronto Hydro relocation 2A
– Eglinton Avenue East, Dunfield Avenue, Holly Avenue
• Weekend subway closures for TTC upgrades
– February 17/18 – not required; CTS has released the weekend closure to TTC
– February 24/25
– March 3/4
• Shoring on the north side of Eglinton Avenue at Yonge Street
17. 17
Mount Pleasant Station Construction Update
ACTIVITY LOCATION IMPACT DURATION
WINTER 2018
Support of Excavation
(Piling)
North side of Eglinton
Ave within work zone
• Noise and vibration
• Scaffolding
• Site lighting
Ongoing through March
2018
Storm Sewer Installation
To be completed in three
stages between Taunton
Rd and Brownlow Ave on
the south side of Eglinton
Ave
• Road closure
• Pedestrian rerouting
• Noise
• Site lighting
Resuming early March
2018 for approx. nine (9)
weeks
Sewer Relocation 801 Mt. Pleasant Rd
• South driveway closure
• Noise
Three (3) days remaining
Bell Utilities Relocation
and Guidewall
Construction
South side of Eglinton
Ave, east of Brownlow
Ave within work zone
• Noise
• Site lighting
Ongoing through April
2018
Traffic Change
Mt. Pleasant Rd and
Eglinton Ave (see map)
• Extend south work zone from
Brownlow Ave to Taunton Rd
• Shift lanes on Eglinton to center
Mid March 2018
Traffic Change – Support
of Excavation
Mt. Pleasant Rd and
Eglinton Ave (see map)
• Shift lanes on Eglinton Ave to the
north
• Extend south work zone further north
Early April 2018
18. 18
NEW Truck Staging Lane
• In February, crews erected a truck staging area
on Eglinton Ave E between Forman Ave and
Petman Ave to host trucks waiting to enter
Mount Pleasant Station
• The truck staging lane will be in place for the
duration on support of excavation, subject to
permit approval