3. 3
Eglinton Station Updates
Complete
Demolition of the Salvation Army Community Church
Demolition of the abandoned TTC bus depot
Wet utilities stages 1-3 (of 4)
Toronto Hydro stages 1a, 1b
Summer/Fall 2017
• Water main and sanitary sewer relocation works are ongoing at the Yonge-
Eglinton intersection
• Toronto Hydro relocation (2b) ongoing on Duplex to Hillsdale to Yonge
• Shoring is underway at the Salvation Army and TTC bus depot sites and
along the south side of Eglinton (Three rigs now in operation)
– This is the major activity of 2017; maps attached for each stage
9. 9
Mount Pleasant Station Construction Update
Complete
Demolition at 280 and 280 Eglinton Ave E to make way for the Secondary Entrance
Demolition at 256-58 Eglinton Ave E to make way for the Main Entrance
Installation of geotechnical monitoring equipment
Long-term closure of Rawlinson Ave for site trailers and laydown area
Shoring at the Main Entrance
Installation of temporary traffic signals
Summer 2017
• Continue hydro utilities relocation
• Commence sewer relocation at the Secondary Entrance site
• Piling in the roadway, beginning on the northwest side of Eglinton Avenue East
• Resume piling at the Secondary Entrance
10. 10
Mount Pleasant Station Lookahead
Year Quarter Construction Activity
Approx.
Duration
2017
Q2-Q4
(April-December)
• Implement traffic staging on the north side of
Eglinton Ave E, and commence utilities relocation and
piling
• Implement traffic staging on the south side of
Eglinton Ave E, continue utilities relocation and piling
• 2 months
• 4 months
2018
Q1-Q2
(January-June)
• Shallow excavation and roof slab construction on the
south side of Eglinton Ave E
• 6 months
Q3-Q4
(July-December)
• Shallow excavation and roof slab construction on the
north side Eglinton Ave E
• 6 months