Mount Pleasant Station Construction Update
ACTIVITY LOCATION APPROXIMATE DURATION
NOVEMBER – DECEMBER 2017
Support of Excavation (Piling)
• NE sidewalk closure
North side of Eglinton Ave E Ongoing into January 2018
Hydro Vault Construction
Southeast corner of Eglinton Ave E and Mt.
Pleasant Rd
One (1) week remaining
Watermain Service Work
• Overnight water shut-off (Nov 22)
North side of Eglinton Ave E Beginning the week of November 13
Launch Shaft Construction
• Taunton Rd closure at Eglinton Ave E
Taunton Rd at Eglinton Ave E Ongoing until early February 2018
Sewer Relocation
• NE sidewalk closure
Secondary Entrance As early as November 30 for one (1) week
JANUARY 2018
Receiving Shaft Construction
South side of Eglinton Ave E, east of
Brownlow Ave
Week of January 8 until early March 2018
Tunneling and Storm Sewer Installation South side of Eglinton Ave E Week of January 8 for three (3) weeks
14. Storm Sewer Installation
• Launch Shaft (at Taunton Road):
Began October 2017 until approximately early February 2018
• Receiving Shaft (east of Brownlow Avenue):
Beginning the week of January 8 until approximately early March 2018
• Tunneling and Storm Sewer Installation (24/7):
Beginning January 8 for approximately three (3) weeks
15. Support-in-Place (SIP) – Toronto Hydro
• SIP is an alternative method to relocating utility
infrastructure, whereby hydro infrastructure is
temporarily supported using concrete
encasement and steel beams
• Advantage of SIP is reduced impact to road users
and pedestrians as well as less power
interruptions for properties in the vicinity of the
future station
• The SIP method will be used at Mount Pleasant
during the shallow excavation periods