SlideShare une entreprise Scribd logo
1  sur  16
Télécharger pour lire hors ligne
EGLINTON CROSSTOWN
Eglinton-Mount Pleasant
March 11, 2020
2
Action items from January CLC
1. Take corrective actions to address the pooling of water and formation of ice sheets identified on
the temporary walkway located on the north side of Eglinton Avenue, east of Mount Pleasant
Road, near the 300 Eglinton Avenue East entrance.
Ice was addressed by the site team following the meeting. Crews continue to monitor the area and
clear/salt the sidewalks as needed. Catch basins are expected to be reinstated within the next five
months.
2. Investigate why a flag person had not been used and determine the activities that the tractor
vehicle was involved in, in the driveway of 300 Eglinton Avenue East, on January 8, 2020.
Issue was investigated and it was determined that the vehicle was delivering materials to 300
Eglinton Avenue East, unrelated to Crosstown construction.
3. Liaise with Sterling Karamar Property Management to clarify who was responsible for
maintaining and clearing the 300 Eglington East walkway section where the floating / jersey
barriers were located.
CTS will continue to clear snow on the sidewalk in front of 300 Eglinton Avenue East and along
the walkways within the work zone.
3
Action items from January CLC
4. CTS to again address with the site team that noise was being heard by the community during the
overnight hours.
5. CTS to discuss with the site superintendent, the construction team and the sub-contractors that noisy
activities were not to be done after 11:00 p.m.
Extended construction hours are underway at many sites along alignment, including Mount Pleasant.
Deep excavation at Mount Pleasant takes place on a 24/6 basis. This includes, excavation, loading,
hauling, site maintenance and occasional utility works. However, the overnight period is generally
reserved for site maintenance/preparation and excavation. Mitigation measures are in place at the site-
level to minimize disruption. Residents experiencing sustained overnight disruption can contact the
Crosstown Community Office to discuss resident-based mitigation options.
6. CTS to review the wording of the notices to ensure they were accurate in regard to advising of the
remaining roof slab pours.
Wording adjusted for the remaining notices. Roof construction complete
7. CTS to instruct the work crews to stay within the work zone for the next concrete pours
Project team informed.
4
INFORMATION IS CURRENT AS OF MARCH 11, 2020
AND SUBJECT TO CHANGE
5
Agenda
• Eglinton Station Update
• Mount Pleasant Station Update
Eglinton Construction Updates
Eglinton Station Construction Look-ahead
Activity Location Approx. Date/Duration
Extended Hours Deep Excavation
TTC Bus Depot and Salvation Army
Sites
Underway through mid 2020
TTC Line 1 Facility Services Building
Construction
• South side of Berwick Ave at
Yonge St
• Periodic closures of Berwick Ave
between Duplex Ave and Yonge
St
• Periodic closures of the
westbound lane and north
sidewalk on Hillsdale Ave bridge
b/w Yonge St and Duplex Ave
Periodically through 2020; subject
to TTC approval
Next scheduled closures:
• Friday March 13 (7am-7pm)
• March 28-29, 2020
Tunnel Ventilation Shaft
Construction
Center of Yonge St between Eglinton
Ave and Roehampton Ave
Underway through June 2020
TBM Extraction
• Northbound curb lane of Duplex
Ave, north of Eglinton Ave
• Closure of Eglinton Ave b/w
Duplex Ave and Yonge St
Underway through April 2020
Current Traffic Configuration
Through March 2020
Upcoming Traffic Configuration
April 2020 through June 2020
TBM Extraction
• Crews will remove the tunnel boring
machines (TBMs) from the ground in
several loads beginning March 2020
• Five (5) remaining heavy loads will be
removed overnight between 3:00 a.m. –
5:00 a.m.; closure of Eglinton Ave
between Duplex Ave and Yonge St for
approx. 1-2 hours required
• TTC bus rerouting required during lifting
and loading of heavy loads
• Heavy loads will expected to travel
westbound on Eglinton Ave to Avenue
Rd with police escort
• Approx. 25 smaller loads to be removed
TBM Extraction
Construction Progress Photos
Mount Pleasant Construction Updates
Mount Pleasant Construction Activities
Activity Location Approx. Start Date & Duration
Shallow Excavation, Roof
Construction, and Utility Support
North side of Eglinton Avenue W Complete
Excavation and Tie-back Installation Main and Secondary Entrances
Underway approx. 1 month
remaining
Deep Excavation Underneath the station roof
February 2020 for approx. 5
months
Backfill and Utility Reinstatement North side of Eglinton Avenue W
February 2020 for approx. 5
months
Scaffold removal and façade
restoration
Eglinton Junior Public School
March 2020 – weather
permitting approx. 8 weeks
Current Traffic Configuration
Until May 2020
Mt Pleasant Station – Construction Progress Photos
Deep excavation – Below the roof
Excavation – Main Entrance

Contenu connexe

Tendances

Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Crosstown TO
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Crosstown TO
 
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Crosstown TO
 
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Crosstown TO
 
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Meeting - June 2019
Eglinton and Mount Pleasant Construction Liaison Meeting - June 2019Eglinton and Mount Pleasant Construction Liaison Meeting - June 2019
Eglinton and Mount Pleasant Construction Liaison Meeting - June 2019
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Crosstown TO
 

Tendances (20)

Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021
 
Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021
 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
 
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
Cedarvale-Forest Hill Construction Liaison Committee Meeting - May 2018
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - July 2019
 
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020
 
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021
 
Eglinton and Mount Pleasant Construction Liaison Meeting - June 2019
Eglinton and Mount Pleasant Construction Liaison Meeting - June 2019Eglinton and Mount Pleasant Construction Liaison Meeting - June 2019
Eglinton and Mount Pleasant Construction Liaison Meeting - June 2019
 
Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021
 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House Presentation
 
Spring Virtual Open House: West - Mount Dennis to Cedarvale
Spring Virtual Open House: West - Mount Dennis to CedarvaleSpring Virtual Open House: West - Mount Dennis to Cedarvale
Spring Virtual Open House: West - Mount Dennis to Cedarvale
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - Nov 2019
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
 

Similaire à Eglinton & Mt Pleasant CLC - March 2020

Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Crosstown TO
 
Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018
Brittany Maxwell
 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
Crosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018
Crosstown TO
 
Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017
Crosstown TO
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Crosstown TO
 

Similaire à Eglinton & Mt Pleasant CLC - March 2020 (20)

Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
 
Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018Chaplin & Avenue CLC - Construction Update - February 7, 2018
Chaplin & Avenue CLC - Construction Update - February 7, 2018
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
 
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
Cedarvale & Forest Hill Construction Liaison Committee Meeting - Jan 29, 2020
 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018
 
Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
Leaside & Laird Stations Construction Liaison Committee Meeting - Feb 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 

Plus de Crosstown TO

Plus de Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 
Leaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdfLeaside-Laird CLC - Nov 14, 2022.pdf
Leaside-Laird CLC - Nov 14, 2022.pdf
 
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdfEglinton - Mt Pleasant CLC - November 9, 2022.pdf
Eglinton - Mt Pleasant CLC - November 9, 2022.pdf
 
Test
TestTest
Test
 
Leaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdfLeaside-Laird CLC - May 9 2022 - Revised.pdf
Leaside-Laird CLC - May 9 2022 - Revised.pdf
 

Dernier

Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Menggugurkan Kandungan 087776558899
 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
ScottMeyers35
 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
gajnagarg
 

Dernier (20)

Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...Just Call VIP Call Girls In  Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
Just Call VIP Call Girls In Bangalore Kr Puram ☎️ 6378878445 Independent Fem...
 
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budgetCall Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
 
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
unang digmaang pandaigdig tagalog version
unang digmaang pandaigdig tagalog versionunang digmaang pandaigdig tagalog version
unang digmaang pandaigdig tagalog version
 
NAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptx
 
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie WhitehouseTime, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
 
tOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTRtOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTR
 
Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!
 
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
 
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girls
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girlsPakistani Call girls in Sharjah 0505086370 Sharjah Call girls
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girls
 
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
 
74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx
 
2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.
 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
 
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition PlansSustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
 

Eglinton & Mt Pleasant CLC - March 2020

  • 2. 2 Action items from January CLC 1. Take corrective actions to address the pooling of water and formation of ice sheets identified on the temporary walkway located on the north side of Eglinton Avenue, east of Mount Pleasant Road, near the 300 Eglinton Avenue East entrance. Ice was addressed by the site team following the meeting. Crews continue to monitor the area and clear/salt the sidewalks as needed. Catch basins are expected to be reinstated within the next five months. 2. Investigate why a flag person had not been used and determine the activities that the tractor vehicle was involved in, in the driveway of 300 Eglinton Avenue East, on January 8, 2020. Issue was investigated and it was determined that the vehicle was delivering materials to 300 Eglinton Avenue East, unrelated to Crosstown construction. 3. Liaise with Sterling Karamar Property Management to clarify who was responsible for maintaining and clearing the 300 Eglington East walkway section where the floating / jersey barriers were located. CTS will continue to clear snow on the sidewalk in front of 300 Eglinton Avenue East and along the walkways within the work zone.
  • 3. 3 Action items from January CLC 4. CTS to again address with the site team that noise was being heard by the community during the overnight hours. 5. CTS to discuss with the site superintendent, the construction team and the sub-contractors that noisy activities were not to be done after 11:00 p.m. Extended construction hours are underway at many sites along alignment, including Mount Pleasant. Deep excavation at Mount Pleasant takes place on a 24/6 basis. This includes, excavation, loading, hauling, site maintenance and occasional utility works. However, the overnight period is generally reserved for site maintenance/preparation and excavation. Mitigation measures are in place at the site- level to minimize disruption. Residents experiencing sustained overnight disruption can contact the Crosstown Community Office to discuss resident-based mitigation options. 6. CTS to review the wording of the notices to ensure they were accurate in regard to advising of the remaining roof slab pours. Wording adjusted for the remaining notices. Roof construction complete 7. CTS to instruct the work crews to stay within the work zone for the next concrete pours Project team informed.
  • 4. 4 INFORMATION IS CURRENT AS OF MARCH 11, 2020 AND SUBJECT TO CHANGE
  • 5. 5 Agenda • Eglinton Station Update • Mount Pleasant Station Update
  • 7. Eglinton Station Construction Look-ahead Activity Location Approx. Date/Duration Extended Hours Deep Excavation TTC Bus Depot and Salvation Army Sites Underway through mid 2020 TTC Line 1 Facility Services Building Construction • South side of Berwick Ave at Yonge St • Periodic closures of Berwick Ave between Duplex Ave and Yonge St • Periodic closures of the westbound lane and north sidewalk on Hillsdale Ave bridge b/w Yonge St and Duplex Ave Periodically through 2020; subject to TTC approval Next scheduled closures: • Friday March 13 (7am-7pm) • March 28-29, 2020 Tunnel Ventilation Shaft Construction Center of Yonge St between Eglinton Ave and Roehampton Ave Underway through June 2020 TBM Extraction • Northbound curb lane of Duplex Ave, north of Eglinton Ave • Closure of Eglinton Ave b/w Duplex Ave and Yonge St Underway through April 2020
  • 9. Upcoming Traffic Configuration April 2020 through June 2020
  • 10. TBM Extraction • Crews will remove the tunnel boring machines (TBMs) from the ground in several loads beginning March 2020 • Five (5) remaining heavy loads will be removed overnight between 3:00 a.m. – 5:00 a.m.; closure of Eglinton Ave between Duplex Ave and Yonge St for approx. 1-2 hours required • TTC bus rerouting required during lifting and loading of heavy loads • Heavy loads will expected to travel westbound on Eglinton Ave to Avenue Rd with police escort • Approx. 25 smaller loads to be removed
  • 14. Mount Pleasant Construction Activities Activity Location Approx. Start Date & Duration Shallow Excavation, Roof Construction, and Utility Support North side of Eglinton Avenue W Complete Excavation and Tie-back Installation Main and Secondary Entrances Underway approx. 1 month remaining Deep Excavation Underneath the station roof February 2020 for approx. 5 months Backfill and Utility Reinstatement North side of Eglinton Avenue W February 2020 for approx. 5 months Scaffold removal and façade restoration Eglinton Junior Public School March 2020 – weather permitting approx. 8 weeks
  • 16. Mt Pleasant Station – Construction Progress Photos Deep excavation – Below the roof Excavation – Main Entrance