5. Eglinton Station Construction Look-ahead
Activity Location Approx. Date/Duration
Extended Hours Deep
Excavation
TTC Bus Depot and Salvation
Army Sites
Underway through December
2020
TTC Line 1 Facility Services
Building Construction
• South side of Berwick Ave at
Yonge St
• Periodic closures of Berwick
Ave between Duplex Ave
and Yonge St
• Periodic closures of the
westbound lane and north
sidewalk on Hillsdale Ave
bridge b/w Yonge St and
Duplex Ave
Periodically through 2020;
subject to TTC approval
Next scheduled closures:
• May 30, 2020
Tunnel Ventilation Shaft
Construction
Center of Yonge St between
Eglinton Ave and Roehampton
Ave
Underway through December
2020
TTC Underpinning Works
Beneath Eglinton Ave/Eglinton
TTC Station Box
Underway through mid-May
2020
Hydro Utility Installation Berwick Ave Portal
As early as May 6, 2020 for
approx. two (2) weeks
9. Mount Pleasant Construction Activities
Activity Location Approx. Start Date & Duration
Excavation Secondary Entrance
Underway approx. 2 weeks
remaining
Deep excavation and tie-back
installation
Underneath the station roof
Underway approx. 3 months
remaining
Backfill and utility
reinstatement
North side of Eglinton Avenue
West
Underway approx. 3 months
remaining
Scaffold removal and façade
restoration
Eglinton Junior Public School
May 2020 – weather
permitting approx. 8 weeks
Concrete works Secondary Entrance
Late-May 2020 for approx.
six (6) months
Concrete works Main Box and Main Entrance
Late June 2020 for approx.
twelve (12) months