3. EGLINTON STATION UPDATE
3CENTRAL WEST WORKS MONTHLY MEETING
Activity Location Approx. Date/Duration
Extended Hours for Deep
Excavation
Beneath the TTC box
Underway through August 2020
Monday – Friday, 24 hours
TTC Line 1 Facility Services
Building Construction
• South side of Berwick Ave at
Yonge St
• Periodic closures of Berwick
Ave between Duplex Ave
and Yonge St
• Periodic closures of the
westbound lane and north
sidewalk on Hillsdale Ave
bridge b/w Yonge St and
Duplex Ave
Periodically through 2020;
subject to TTC approval
Next scheduled closures:
• July 18, 2020
Tunnel Ventilation Shaft
Construction
Center of Yonge St between
Eglinton Ave and Roehampton
Ave
Underway through December
2020
Concrete Pour Former TTC Bus Depot site
Wednesday July 8, 2020 at 4:00
a.m. for approx. eight (8) hours
Elevator Construction
2200 Yonge St (former Smoke’s
Poutinerie)
Underway through fall 2020
4. RESUMPTION EXTENDED CONSTRUCTION HOURS FOR DEEP EXCAVATION
4
• Since 2019 crews at Eglinton Station have been working extended construction hours to
accelerate station construction
• In late June 2020, crews resumed extended construction hours to complete deep excavation
beneath the TTC box 15 metres below Eglinton Ave
• Using an excavator, soil is removed and stockpiled below Eglinton Ave until it is later loaded
into trucks and hauled to an off-site facility
• Excavation beneath the TTC box takes place Monday – Friday, 24 hours through August 2020
• Due to the location of this work and absence of associated surface works, limited noise is
generated during the overnight period
CENTRAL WEST WORKS MONTHLY MEETING
8. MOUNT PLEASANT STATION UPDATE
8INSERT FOOTER
Activity Location Approx. Start Date & Duration
Tunnel Segment Demolition and
Removal
Station box and entrances
Underway for approximately
one (1) month
Deep Excavation and Tieback
Installation
Underneath the station roof
Underway for approximately
two (2) months
Utility Reinstatement
North side of Eglinton Avenue W
and at the intersection
Underway for approximately
four (4) months
Scaffold Removal and Façade
Restoration
Eglinton Junior Public School Complete!
Concrete Works Secondary Entrance
Underway for approximately
seven (7) months
Concrete Works Station Box and Main Entrance
Late-July 2020 for
approximately twelve (12)
months