• Serve a population of more than seven million across more than 11,000 square
km stretching from Hamilton and Kitchener-Waterloo in the west to Newcastle
and Peterborough in the east, and from Orangeville and Beaverton in the north
to Niagara Falls in the south.
• In operation since 1967, GO now carries more than 70 million passengers a year.
• The PRESTO card is the smart card fare payment system seamlessly connecting 11
transit agencies across the GTHA and Ottawa.
• PRESTO replaces the need for tickets, tokens, passes or cash.
• UP Express connects the country's two busiest transportation hubs: Toronto
Pearson International Airport and Union Station in downtown Toronto, offering a
25-minute journey from end to end, with trains departing every 15 minutes.
Regional transit map – connecting
the region
3 Metrolinx overview
Regional Transportation Plan
4
Vision: The GTHA will have a sustainable
transportation system that is aligned with land use,
and supports healthy and complete communities.
The system will provide safe, convenient and reliable
connections, and support a high quality of life, a
prosperous and competitive economy, and a
protected environment.
31 Priority Actions to Support the 5 Strategies
• Metrolinx published the first regional transportation
plan (RTP) for the Greater Toronto and Hamilton Area
(GTHA) in 2008.
• We are required to review the RTP at least every ten
years, in alignment with Ontario’s Growth Plan for the
Greater Golden Horseshoe.
• The legislative review of initial RTP led to the
development of the 2041 RTP. Key outcomes include:
o Quadrupling the number of people and doubling
the number of jobs within walking distance of
Frequent Rapid Transit
o 27x more kilometres of the Frequent Rapid
Transit
o In addition to the capital costs, successful
implementation will also require operating
funding for transit services, fare integration and
programs for walking and cycling
Metrolinx Overview
Community Benefits
5 Metrolinx overview
The objective of the Community
Benefits Program is that people
from historically disadvantaged
communities and equity-seeking
groups are positively impacted by
the Eglinton Crosstown.
Program has three streams:
1. Employment, Training and
Workforce Development
2. Social Enterprises and Social
Procurement
3. Investment (Community
Improvements)
Community Benefits
6 Metrolinx overview
Business support – shop local
campaign
7 Metrolinx overview
Parking
8 Metrolinx overview
416-782-8118 or 416-482-7411
24 hours/7days a week
www.thecrosstown.ca
crosstown@metrolinx.com
facebook.com/thecrosstown
twitter.com/crosstownTO
instagram.com/eglinton_crosstown
Crosstown West Office
1848 Eglinton Ave W (at Dufferin)
Crosstown East Office
660 Eglinton Ave E (at Bayview)
Stay in Touch
9
METROLINX OVERVIEW
Eglinton Maintenance and Storage Facility (EMSF)
• As part of the Crosstown LRT project, a
state-of-the-art maintenance and storage
facility near Ray Avenue and Industry Road
is being built.
• The facility sits on 42 acres of land and is
comprised of three facilities for LRT
operations. This includes a maintenance
building, storage for 76 LRT vehicles,
administration offices and training
facilities. It is designed with future growth
in mind, with the ability to house a total of
135 vehicles as ridership increases.
• The EMSF achieved ‘readiness to receive
delivery of Light RailVehicles’ on October
1st of 2018, marking delivery of the first
major milestone of the LRT project on time.
Train movements in the yard will begin as
early as November 2018. LRT Maintenance Bay
EMSF
Eglinton Maintenance and Storage Facility (EMSF)
LRT maintenance baysLRT Maintenance Bays
Railway Corridor – Renderings
Connections to
UPX and GO
Transit Kitchener
Lines
Railway Corridor – Upcoming Works
November 2018 - January 2019:Track RelocationWork*
• CP crews will be relocating the CP mainline track further east from its current position. Once complete, crews will begin
relocating the GOTransit track further east from its current position.
• Track relocation work involves saw-cutting, drilling rail, surfacing, ballast placement/regulating, and thermite welding. Portions
of the work will require compaction by means of mechanical roller causing vibrations.
January 2019 - Summer 2020: Rail Corridor Development (West Side)*
• After the track relocations are complete, work will begin on the west side of the Railway Corridor. and activities are scheduled
through to Summer 2020. Site access will be made via Brownsville Avenue, Hollis Street, and Locust Street.
• Construction activities include:
– LRT Tunnels (excavation, cast-in-place concrete, backfilling, grading, etc.)
– GO Bridge Expansion (shoring, excavation, CIP concrete, structural steel installation, etc.)
– GO Platforms (excavation, cast-in-place concrete, backfilling, grading, etc.)
*Work may be re-
scheduled due to
weather or other
unforeseen
circumstances.
Railway Corridor – Construction Progress Photos
SpurTrackPedestrianTunnelConstruction
CP BridgeGirder Installation
Mount Dennis Station – Renderings
Mount Dennis Station - Construction Progress Photos
• The track, elevators, and platform edges at Mount Dennis have all
been installed.
• Station construction continues with steel and façade installation.
• The Kodak building retrofit is ongoing with steel supports, interior
demolitions, and electrical well underway.
• TheTTC bus terminal progresses, with tunnel and vertical access
construction ongoing.
BusTerminal Construction
Kodak Building Retrofit
Station Construction
West Portal & Elevated Guideway - Renderings
West Portal & Elevated Guideway – UpcomingWorks
• Construction continues on the west portal with shoring activities and at the
elevated guideway with rebar, formwork, and concrete.
• In early 2019, traffic will open up to two lanes in each direction along Eglinton
Avenue West from Black Creek Drive to Bicknell Road.
West Portal & Elevated Guideway - Construction
Progress Photos
Looking East into the
Tunnel from Bicknell
Drive
Construction of the
Elevated Guideway
over Black Creek
Lagging Installation
Keelesdale Station – Renderings
Keelesdale Station - Construction Progress Photos
Forming StationWallsInvert Slab Concrete Pour
Rebar Installation
• Station construction at Keelesdale
progresses with rebar, concrete, and
waterproofing on a ongoing basis for slabs
and walls in the various portions of the
station box including all three entrances and
the pedestrian underpass connection.
22
FUTURE BRIDGE
CONNECTION TO
CALEDONIA GO
STATION*
*Future bridge connection is not part of the Crosstown LRT
construction scope of work.
Caledonia Station – AerialView Rendering
Caledonia Station – Ongoing and Upcoming Works
Ongoing
• The first invert slab (concrete) pour was completed in October 2018.
• Drilling of tie-backs, dewatering wells and rebar installation continues.
Upcoming
• Several concrete pours will continue for the course of 2019, forming the future
station structure.
Caledonia Station – Construction Progress Photos
Excavation and
Hauling
25
Fairbank Station – Renderings
26
Future Exterior Plaza
27
Fairbank Station – Ongoing and Upcoming Works
Ongoing
• Excavation is underway at
the Main Entrance,
Service Building and
southwest Station Box
areas.
• The first concrete roof
pour was completed in
October 2018 at the
southeast Station Box
area.
• Drilling of tie-backs and
rebar installation
continues.
Upcoming
• Overnight concrete pour
and intersection closure
will take place in late
November 2018.
Fairbank Station – Construction Progress Photos
Roof Construction
PreparationExcavation
Excavation
Oakwood Station – Renderings
*90% Design
Oakwood Station: Mined Station
• Oakwood Station is being constructed using a mined method known as Sequential Excavation Method or SEM.
• 24 hour mining is underway and will be ongoing to early 2020.
• The mining process includes three principal underground activities that occur in a continuous sequence.This creates
the large underground cavern that will house the station platform and concourse.
• Horizontal ‘pipe roof’ supports the ground above.
• Excavation of the materials below the ‘roof’.
• Support of underground surfaces by spraying the walls and ceiling with concrete.
Cross Cut
Access
Adit
Main
Entrance
Cavern
Secondary
Entrance
Approx. 150m to be mined underneath Eglinton Ave – between Oakwood Avenue and the Secondary Entrance
Oakwood Station – Ongoing and Upcoming Works
• Mining works are ongoing and advancing from the main entrance.
• Excavation of the secondary entrance is nearing completion and preliminary mining
works will begin in November 2018.
• The construction zones in the map below will support continued progress into 2019.
Main
Entrance
Secondary
Entrance
Oakwood Station – Construction Progress Photos
Secondary Entrance Secondary Entrance
Main Entrance
Main Entrance

Contenu connexe

Tendances

Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
Crosstown TO
 
Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018
Crosstown TO
 
Western Segment Open House - spring 2019
Western Segment Open House - spring 2019 Western Segment Open House - spring 2019
Western Segment Open House - spring 2019
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Crosstown TO
 
Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)
Crosstown TO
 
Central open house - oct 2019
Central open house - oct 2019Central open house - oct 2019
Central open house - oct 2019
Crosstown TO
 

Tendances (20)

Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting Pharmacy to Kennedy - November meeting
Pharmacy to Kennedy - November meeting
 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Eastern Works Open House - October 24, 2019
Eastern Works Open House  - October 24, 2019Eastern Works Open House  - October 24, 2019
Eastern Works Open House - October 24, 2019
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
 
Western works final
Western works final Western works final
Western works final
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
 
Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018
 
Central West Open House
Central West Open HouseCentral West Open House
Central West Open House
 
CLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCLC Eglinton and Mount Pleasant
CLC Eglinton and Mount Pleasant
 
Western Segment Open House - spring 2019
Western Segment Open House - spring 2019 Western Segment Open House - spring 2019
Western Segment Open House - spring 2019
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
 
Central West Fall Open House - Oct 28 2019
Central West Fall Open House - Oct 28 2019Central West Fall Open House - Oct 28 2019
Central West Fall Open House - Oct 28 2019
 
Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)Central West Open House (Cedarvale to Eglinton Stations)
Central West Open House (Cedarvale to Eglinton Stations)
 
Central open house - oct 2019
Central open house - oct 2019Central open house - oct 2019
Central open house - oct 2019
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 

Similaire à Fall18 Open House Western Segment Works

Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
Crosstown TO
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
Crosstown TO
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Crosstown TO
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
Crosstown TO
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
Crosstown TO
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
Crosstown TO
 
Central- West Open House - April 2018
Central- West Open House - April 2018Central- West Open House - April 2018
Central- West Open House - April 2018
Crosstown TO
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
Crosstown TO
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
Crosstown TO
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
Crosstown TO
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
Crosstown TO
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
Crosstown TO
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Crosstown TO
 
Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house
Crosstown TO
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
Crosstown TO
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
Crosstown TO
 

Similaire à Fall18 Open House Western Segment Works (20)

Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
 
Eastern Works Open House
Eastern Works Open House Eastern Works Open House
Eastern Works Open House
 
Central- West Open House - April 2018
Central- West Open House - April 2018Central- West Open House - April 2018
Central- West Open House - April 2018
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
 
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
Open House Meeting: Mount Dennis Station, Railway Corridor and Eglinton Maint...
 
Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house
 
Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017Kennedy Station and East At-Grade Section Open House - December 2017
Kennedy Station and East At-Grade Section Open House - December 2017
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 
Stations Presentation - Corridor Wide
Stations Presentation - Corridor WideStations Presentation - Corridor Wide
Stations Presentation - Corridor Wide
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation
 

Plus de Crosstown TO

Plus de Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Dernier

Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
ScottMeyers35
 

Dernier (20)

2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP process
 
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdfPeace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
Peace-Conflict-and-National-Adaptation-Plan-NAP-Processes-.pdf
 
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girls
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girlsPakistani Call girls in Sharjah 0505086370 Sharjah Call girls
Pakistani Call girls in Sharjah 0505086370 Sharjah Call girls
 
A Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental CrisisA Press for the Planet: Journalism in the face of the Environmental Crisis
A Press for the Planet: Journalism in the face of the Environmental Crisis
 
Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218
 
tOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTRtOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTR
 
31st World Press Freedom Day Conference in Santiago.
31st World Press Freedom Day Conference in Santiago.31st World Press Freedom Day Conference in Santiago.
31st World Press Freedom Day Conference in Santiago.
 
74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx74th Amendment of India PPT by Piyush(IC).pptx
74th Amendment of India PPT by Piyush(IC).pptx
 
2024 UNESCO/Guillermo Cano World Press Freedom Prize
2024 UNESCO/Guillermo Cano World Press Freedom Prize2024 UNESCO/Guillermo Cano World Press Freedom Prize
2024 UNESCO/Guillermo Cano World Press Freedom Prize
 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
 
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie WhitehouseTime, Stress & Work Life Balance for Clerks with Beckie Whitehouse
Time, Stress & Work Life Balance for Clerks with Beckie Whitehouse
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdf
 
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCC
 
Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!Make a difference in a girl's life by donating to her education!
Make a difference in a girl's life by donating to her education!
 
Vasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
Vasai Call Girls In 07506202331, Nalasopara Call Girls In MumbaiVasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
Vasai Call Girls In 07506202331, Nalasopara Call Girls In Mumbai
 
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budgetCall Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
Call Girls Basheerbagh ( 8250092165 ) Cheap rates call girls | Get low budget
 

Fall18 Open House Western Segment Works

  • 1. Mission We connect our communities Vision Getting you there better, faster and easier Values Play as a team Think forward Serve with passion 1 Metrolinx overview
  • 2. go transit, up express, presto 2Metrolinx Overview • Serve a population of more than seven million across more than 11,000 square km stretching from Hamilton and Kitchener-Waterloo in the west to Newcastle and Peterborough in the east, and from Orangeville and Beaverton in the north to Niagara Falls in the south. • In operation since 1967, GO now carries more than 70 million passengers a year. • The PRESTO card is the smart card fare payment system seamlessly connecting 11 transit agencies across the GTHA and Ottawa. • PRESTO replaces the need for tickets, tokens, passes or cash. • UP Express connects the country's two busiest transportation hubs: Toronto Pearson International Airport and Union Station in downtown Toronto, offering a 25-minute journey from end to end, with trains departing every 15 minutes.
  • 3. Regional transit map – connecting the region 3 Metrolinx overview
  • 4. Regional Transportation Plan 4 Vision: The GTHA will have a sustainable transportation system that is aligned with land use, and supports healthy and complete communities. The system will provide safe, convenient and reliable connections, and support a high quality of life, a prosperous and competitive economy, and a protected environment. 31 Priority Actions to Support the 5 Strategies • Metrolinx published the first regional transportation plan (RTP) for the Greater Toronto and Hamilton Area (GTHA) in 2008. • We are required to review the RTP at least every ten years, in alignment with Ontario’s Growth Plan for the Greater Golden Horseshoe. • The legislative review of initial RTP led to the development of the 2041 RTP. Key outcomes include: o Quadrupling the number of people and doubling the number of jobs within walking distance of Frequent Rapid Transit o 27x more kilometres of the Frequent Rapid Transit o In addition to the capital costs, successful implementation will also require operating funding for transit services, fare integration and programs for walking and cycling Metrolinx Overview
  • 5. Community Benefits 5 Metrolinx overview The objective of the Community Benefits Program is that people from historically disadvantaged communities and equity-seeking groups are positively impacted by the Eglinton Crosstown. Program has three streams: 1. Employment, Training and Workforce Development 2. Social Enterprises and Social Procurement 3. Investment (Community Improvements)
  • 7. Business support – shop local campaign 7 Metrolinx overview
  • 9. 416-782-8118 or 416-482-7411 24 hours/7days a week www.thecrosstown.ca crosstown@metrolinx.com facebook.com/thecrosstown twitter.com/crosstownTO instagram.com/eglinton_crosstown Crosstown West Office 1848 Eglinton Ave W (at Dufferin) Crosstown East Office 660 Eglinton Ave E (at Bayview) Stay in Touch 9 METROLINX OVERVIEW
  • 10. Eglinton Maintenance and Storage Facility (EMSF) • As part of the Crosstown LRT project, a state-of-the-art maintenance and storage facility near Ray Avenue and Industry Road is being built. • The facility sits on 42 acres of land and is comprised of three facilities for LRT operations. This includes a maintenance building, storage for 76 LRT vehicles, administration offices and training facilities. It is designed with future growth in mind, with the ability to house a total of 135 vehicles as ridership increases. • The EMSF achieved ‘readiness to receive delivery of Light RailVehicles’ on October 1st of 2018, marking delivery of the first major milestone of the LRT project on time. Train movements in the yard will begin as early as November 2018. LRT Maintenance Bay EMSF
  • 11. Eglinton Maintenance and Storage Facility (EMSF) LRT maintenance baysLRT Maintenance Bays
  • 12. Railway Corridor – Renderings Connections to UPX and GO Transit Kitchener Lines
  • 13. Railway Corridor – Upcoming Works November 2018 - January 2019:Track RelocationWork* • CP crews will be relocating the CP mainline track further east from its current position. Once complete, crews will begin relocating the GOTransit track further east from its current position. • Track relocation work involves saw-cutting, drilling rail, surfacing, ballast placement/regulating, and thermite welding. Portions of the work will require compaction by means of mechanical roller causing vibrations. January 2019 - Summer 2020: Rail Corridor Development (West Side)* • After the track relocations are complete, work will begin on the west side of the Railway Corridor. and activities are scheduled through to Summer 2020. Site access will be made via Brownsville Avenue, Hollis Street, and Locust Street. • Construction activities include: – LRT Tunnels (excavation, cast-in-place concrete, backfilling, grading, etc.) – GO Bridge Expansion (shoring, excavation, CIP concrete, structural steel installation, etc.) – GO Platforms (excavation, cast-in-place concrete, backfilling, grading, etc.) *Work may be re- scheduled due to weather or other unforeseen circumstances.
  • 14. Railway Corridor – Construction Progress Photos SpurTrackPedestrianTunnelConstruction CP BridgeGirder Installation
  • 15. Mount Dennis Station – Renderings
  • 16. Mount Dennis Station - Construction Progress Photos • The track, elevators, and platform edges at Mount Dennis have all been installed. • Station construction continues with steel and façade installation. • The Kodak building retrofit is ongoing with steel supports, interior demolitions, and electrical well underway. • TheTTC bus terminal progresses, with tunnel and vertical access construction ongoing. BusTerminal Construction Kodak Building Retrofit Station Construction
  • 17. West Portal & Elevated Guideway - Renderings
  • 18. West Portal & Elevated Guideway – UpcomingWorks • Construction continues on the west portal with shoring activities and at the elevated guideway with rebar, formwork, and concrete. • In early 2019, traffic will open up to two lanes in each direction along Eglinton Avenue West from Black Creek Drive to Bicknell Road.
  • 19. West Portal & Elevated Guideway - Construction Progress Photos Looking East into the Tunnel from Bicknell Drive Construction of the Elevated Guideway over Black Creek Lagging Installation
  • 21. Keelesdale Station - Construction Progress Photos Forming StationWallsInvert Slab Concrete Pour Rebar Installation • Station construction at Keelesdale progresses with rebar, concrete, and waterproofing on a ongoing basis for slabs and walls in the various portions of the station box including all three entrances and the pedestrian underpass connection.
  • 22. 22 FUTURE BRIDGE CONNECTION TO CALEDONIA GO STATION* *Future bridge connection is not part of the Crosstown LRT construction scope of work. Caledonia Station – AerialView Rendering
  • 23. Caledonia Station – Ongoing and Upcoming Works Ongoing • The first invert slab (concrete) pour was completed in October 2018. • Drilling of tie-backs, dewatering wells and rebar installation continues. Upcoming • Several concrete pours will continue for the course of 2019, forming the future station structure.
  • 24. Caledonia Station – Construction Progress Photos Excavation and Hauling
  • 27. 27 Fairbank Station – Ongoing and Upcoming Works Ongoing • Excavation is underway at the Main Entrance, Service Building and southwest Station Box areas. • The first concrete roof pour was completed in October 2018 at the southeast Station Box area. • Drilling of tie-backs and rebar installation continues. Upcoming • Overnight concrete pour and intersection closure will take place in late November 2018.
  • 28. Fairbank Station – Construction Progress Photos Roof Construction PreparationExcavation Excavation
  • 29. Oakwood Station – Renderings *90% Design
  • 30. Oakwood Station: Mined Station • Oakwood Station is being constructed using a mined method known as Sequential Excavation Method or SEM. • 24 hour mining is underway and will be ongoing to early 2020. • The mining process includes three principal underground activities that occur in a continuous sequence.This creates the large underground cavern that will house the station platform and concourse. • Horizontal ‘pipe roof’ supports the ground above. • Excavation of the materials below the ‘roof’. • Support of underground surfaces by spraying the walls and ceiling with concrete. Cross Cut Access Adit Main Entrance Cavern Secondary Entrance Approx. 150m to be mined underneath Eglinton Ave – between Oakwood Avenue and the Secondary Entrance
  • 31. Oakwood Station – Ongoing and Upcoming Works • Mining works are ongoing and advancing from the main entrance. • Excavation of the secondary entrance is nearing completion and preliminary mining works will begin in November 2018. • The construction zones in the map below will support continued progress into 2019. Main Entrance Secondary Entrance
  • 32. Oakwood Station – Construction Progress Photos Secondary Entrance Secondary Entrance Main Entrance Main Entrance

Notes de l'éditeur

  1. Why was Metrolinx Created. Metrolinx was created in 2006 by the Province of Ontario with a mandate to create greater connection between the communities of the Greater Toronto and Hamilton Area, and now beyond to the Greater Golden Horseshoe. Our mission at Metrolinx is to implement an integrated transportation system that enhances prosperity, sustainability and quality of life in our region. We were created in response to the in-attention to rapid transit investment for 15 to 20 years in this fast growing urban region. We just had not kept up in the past. Since 2008, Metrolinx, guided by its Regional Transportation, The Big Move has worked to plan, design and build a regional transportation network that aims to enhance the quality of life, the environment and the prosperity of area residents. As we move forward to a new Regional Transportation Plan and the next 10 years, we ask ourselves: How will we meet the challenge of growth across the region, with a complete transportation system that includes rapid transit, walking and cycling infrastructure, efficient highways, improved goods movement, and systems for new forms of mobility? Given the changes we expect in terms of our population and economic growth, as well as the rapid uptake of new technologies, how can we expect the region to be transformed in 2041? We are developing a RAP that can perform well under a range of possibilities – in other words, we are working to build a resilient plan that looks forward towards the future.