Ce diaporama a bien été signalé.
Nous utilisons votre profil LinkedIn et vos données d’activité pour vous proposer des publicités personnalisées et pertinentes. Vous pouvez changer vos préférences de publicités à tout moment.

Pharmacy to Kennedy Construction Liaison Meeting - July 2020

2 271 vues

Publié le

deck

  • Soyez le premier à commenter

  • Soyez le premier à aimer ceci

Pharmacy to Kennedy Construction Liaison Meeting - July 2020

  1. 1. July 28, 2020 Eglinton Crosstown LRT Construction Liaison Committee Victoria Park Avenue to Kennedy Station
  2. 2. Section Three and Four At-Grade: O’Connor Stop to Ionview Stop
  3. 3. CONSTRUCTION ACTIVITIES 3 Location Activity Approx. Date & Duration O’Connor Stop • Final concrete works (curb) Early August, 2020 for one week Pharmacy Stop • East and west platform edge tile installation Ongoing through to early August 2020 Hakimi/Lebovic Stop • Shelter Installation (North) • Shelter Installation (South) Complete Early 2021 (1 shelter remaining) Golden Mile Stop • Stop construction: Formwork and rebar Through to late August 2020 Birchmount Stop • Rebar Installation • Concrete works Complete Ongoing through to mid August 2020 Ionview Stop • Excavation for north platform Early August, 2020 for one week Ionview Road to Kennedy Road – North Side • Permanent sidewalk and curb installation, boulevard restoration and driveway tie-ins. Through to mid August 2020 Birchmount Road to Kennedy Road – South Side • Permanent sidewalk and curb installation, boulevard restoration and driveway tie-ins. Early September – Late October 2020 Birchmount Road to Ionview Road • Track Work Ongoing through to early August 2020
  4. 4. ROSEMOUNT DRIVE AND EGLINTON AVE E 4 Early January – Mid August 2020 • North side closure for Massey Creek Construction • Reconnection of culvert – ongoing through to mid August 2020 MASSEY CREEK
  5. 5. BIRCHMOUNT ROAD TO KENNEDY ROAD LATE APRIL TO MID AUGUST 2020 – NORTH SIDE EARLY SEPTEMBER TO LATE OCTOBER 2020 – SOUTH SIDE 5 • Permanent sidewalk and curb installation, boulevard restoration and driveway tie-ins. • The work will impact the eastbound and westbound curb lanes, work will be completed in sections.
  6. 6. IONVIEW ROAD TO KENNEDY ROAD 6 • Boulevard restoration works include: • Removal of existing asphalt and curbs • Construction of new sidewalks and curbs • Driveway tie-ins to the newly widened road • Partial or full driveway closures of up to one week will be required to complete the work. • Driveway closures will be alternating, and vehicular access will be maintained for the duration of the work. Boulevard Restoration Works Ongoing through mid-August 2020
  7. 7. CONSTRUCTION PROGRESS PHOTOS 7 BIRCHMOUNT STOP NORTH – REBAR INSALLATION HAKIMI/LEBOVIC STOP WESTBOUND SHELTER INSTALLATION BIRCHMOUNT TO ROSEMOUNT TRACK WORK PHARMACY STOP– GRINDING FOR TACTILE PLATE INSTALLATION
  8. 8. Kennedy Station
  9. 9. KENNEDY STATION UPDATE 9 Location Activity Approx. Date & Duration Kennedy Station Main Entrance • Concrete works • Masonry works • Conduit installation, plumbing and sheet metal works • Structural steel and decking Ongoing through to late 2020 Kennedy Station – East of GO • Concrete works • Electrical and mechanical works Ongoing through to late 2020 Kennedy Station Concourse Level/Station Box • Excavation • Waterproofing • Concrete works Ongoing through to late 2020 Kennedy Portal (west of Kennedy Road) • Tunnel ventilation • Installation of light fixtures Ongoing through to late 2020 Kennedy Station West Portal and Go Platform • Backfill and concrete works • Curtain wall and glazing • Roofing and painting at shelters • Mechanical and electrical works Ongoing through to late 2020 Eglinton Ave E and Kennedy Road intersection • Decking Removal • Roadworks (four corners of the intersection) Complete Ongoing through late August 2020
  10. 10. CURRENT TRAFFIC CONFIGURATION EGLINTON AVENUE EAST AND KENNEDY ROAD INTERSECTION 10 • Crews will be performing road works within the four corners of the Eglinton Ave East and Kennedy Road intersection. • A shared through and right turn lane will be implemented for northbound and southbound traffic at the intersection. • Periodic crosswalk closures will be required to complete the work. A minimum of three crosswalks will be maintained all times. Signage will be installed directing pedestrians to available crosswalks. Mid July – Late August 2020
  11. 11. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR KENNEDY STATION AUGUST 17, 2020 11 • As part of GO Transit improvements at Kennedy GO Station, crews at Kennedy Station will be temporarily relocating the west GO Transit platform as early as August 17, 2020. • Pedestrians will be rerouted through the Kennedy TTC Station • This configuration will remain in place for approximately one year.
  12. 12. CONSTRUCTION PROGRESS PHOTOS 12 GO WEST PLATFORM FRAMING AND CURTAIN WALL STATION BOX ROOF SLAB

×