3. CONSTRUCTION ACTIVITIES
3
Location Activity Approx. Date & Duration
O’Connor Stop • Final concrete works (curb) Early August, 2020 for one week
Pharmacy Stop
• East and west platform edge tile
installation
Ongoing through to early August 2020
Hakimi/Lebovic Stop
• Shelter Installation (North)
• Shelter Installation (South)
Complete
Early 2021 (1 shelter remaining)
Golden Mile Stop
• Stop construction: Formwork and
rebar
Through to late August 2020
Birchmount Stop
• Rebar Installation
• Concrete works
Complete
Ongoing through to mid August 2020
Ionview Stop • Excavation for north platform Early August, 2020 for one week
Ionview Road to Kennedy Road – North Side
• Permanent sidewalk and curb
installation, boulevard restoration and
driveway tie-ins.
Through to mid August 2020
Birchmount Road to Kennedy Road – South
Side
• Permanent sidewalk and curb
installation, boulevard restoration and
driveway tie-ins.
Early September – Late October 2020
Birchmount Road to Ionview Road • Track Work Ongoing through to early August 2020
4. ROSEMOUNT DRIVE AND EGLINTON AVE E
4
Early January – Mid August 2020
• North side closure for Massey Creek Construction
• Reconnection of culvert – ongoing through to mid August 2020
MASSEY CREEK
5. BIRCHMOUNT ROAD TO KENNEDY ROAD
LATE APRIL TO MID AUGUST 2020 – NORTH SIDE
EARLY SEPTEMBER TO LATE OCTOBER 2020 – SOUTH SIDE
5
• Permanent sidewalk and curb installation, boulevard restoration and driveway tie-ins.
• The work will impact the eastbound and westbound curb lanes, work will be completed in sections.
6. IONVIEW ROAD TO KENNEDY ROAD
6
• Boulevard restoration works include:
• Removal of existing asphalt and
curbs
• Construction of new sidewalks and
curbs
• Driveway tie-ins to the newly
widened road
• Partial or full driveway closures of up to
one week will be required to complete
the work.
• Driveway closures will be alternating, and
vehicular access will be maintained for
the duration of the work.
Boulevard Restoration Works
Ongoing through mid-August 2020
7. CONSTRUCTION PROGRESS PHOTOS
7
BIRCHMOUNT STOP NORTH
– REBAR INSALLATION
HAKIMI/LEBOVIC STOP WESTBOUND
SHELTER INSTALLATION
BIRCHMOUNT TO ROSEMOUNT TRACK
WORK
PHARMACY STOP– GRINDING
FOR TACTILE PLATE
INSTALLATION
9. KENNEDY STATION UPDATE
9
Location Activity Approx. Date & Duration
Kennedy Station Main Entrance
• Concrete works
• Masonry works
• Conduit installation, plumbing and
sheet metal works
• Structural steel and decking
Ongoing through to late 2020
Kennedy Station – East of GO
• Concrete works
• Electrical and mechanical works
Ongoing through to late 2020
Kennedy Station Concourse Level/Station
Box
• Excavation
• Waterproofing
• Concrete works
Ongoing through to late 2020
Kennedy Portal (west of Kennedy Road)
• Tunnel ventilation
• Installation of light fixtures
Ongoing through to late 2020
Kennedy Station West Portal and Go
Platform
• Backfill and concrete works
• Curtain wall and glazing
• Roofing and painting at shelters
• Mechanical and electrical works
Ongoing through to late 2020
Eglinton Ave E and Kennedy Road
intersection
• Decking Removal
• Roadworks (four corners of the
intersection)
Complete
Ongoing through late August 2020
10. CURRENT TRAFFIC CONFIGURATION
EGLINTON AVENUE EAST AND KENNEDY ROAD INTERSECTION
10
• Crews will be performing road works within the
four corners of the Eglinton Ave East and
Kennedy Road intersection.
• A shared through and right turn lane will be
implemented for northbound and southbound
traffic at the intersection.
• Periodic crosswalk closures will be required to
complete the work. A minimum of three
crosswalks will be maintained all times. Signage
will be installed directing pedestrians to available
crosswalks.
Mid July – Late August 2020
11. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR
KENNEDY STATION
AUGUST 17, 2020
11
• As part of GO Transit improvements at
Kennedy GO Station, crews at Kennedy
Station will be temporarily relocating the
west GO Transit platform as early as August
17, 2020.
• Pedestrians will be rerouted through the
Kennedy TTC Station
• This configuration will remain in place for
approximately one year.