The U.S. Department of Energy announces its intent to prepare an Environmental Impact Statement to assess the potential environmental impacts for the proposed action of providing Federal funding for the proposed Texas Clean Energy Project near Odessa, Texas.
NOI - Transmission Lines on Forest Service Lands (CO, UT, NE)
NOI - Texas Clean Energy
1. 30800 Federal Register / Vol. 75, No. 105 / Wednesday, June 2, 2010 / Notices
Access at: http://www.gpoaccess.gov/nara/ technologies used to generate electricity Displays and other information about
index.html. from fossil fuels, including natural gas. DOE’s proposed action and Summit’s
Summit proposes to build its IGCC project will be available, and
Authority: Section 1605 of the American plant adjacent to an oil field in Ector
Recovery and Reinvestment Act, Public Law representatives from DOE and Summit
111–5. County, Texas. The plant would use will be present at the informal session
coal as its feedstock. It would capture, to discuss the proposed project, DOE’s
Dated: May 28, 2010. in the form of CO2, about 90% of the CCPI program, and the EIS process.
Arne Duncan, carbon in the portion of its coal fuel
Secretary of Education. ADDRESSES: Written comments on the
supply used for power production. The
[FR Doc. 2010–13308 Filed 6–1–10; 8:45 am] plant would employ two gasifiers, scope of the EIS and requests to
feeding a single, combined-cycle power participate in the public scoping
BILLING CODE 4000–01–P
island to generate about 400 MW (gross) meeting should be addressed to: Mr.
of electricity, with the co-production of Mark L. McKoy, U.S. Department of
DEPARTMENT OF ENERGY sulfuric acid and urea (for fertilizer) or Energy, National Energy Technology
other chemicals. About 275 MW of Laboratory, 3610 Collins Ferry Road,
Notice of Intent To Prepare an electricity would be put onto the power P.O. Box 880, Morgantown, WV 26507–
Environmental Impact Statement for grid, with the remaining power used for 0880. Individuals and organizations
Texas Clean Energy Project, Ector commercial loads on the project site, who would like to provide oral or
County, TX such as urea production and CO2 electronic comments, or request copies
compression. During DOE of the Draft EIS, should contact Mr.
AGENCY: Department of Energy. McKoy by telephone (304–285–4426),
ACTION: Notice of Intent To Prepare An demonstration phase of the project, it
would permanently sequester CO2 at a toll-free telephone (1–800–432–8330
Environmental Impact Statement. (ext. 4426), fax (304–285–4403), e-mail
maximum rate of about 3 million tons
per year by piping it to Permian Basin (Summit.EIS@netl.doe.gov), or formal
SUMMARY: The U.S. Department of
oil fields, where it would be used by mail submitted to the address given
Energy (DOE or Department) announces
field operators for enhanced oil recovery above.
its intent to prepare an Environmental
Impact Statement (EIS) pursuant to the (EOR). Summit is owned jointly by the FOR FURTHER INFORMATION CONTACT: For
National Environmental Policy Act Summit Power Group, Inc. and CW further information about this project,
(NEPA), the Council on Environmental NextGen, Inc. (CWNI), a Clayton contact Mr. Mark L. McKoy, as
Quality (CEQ) NEPA regulations (40 Williams company. The project team described above. For general
CFR parts 1500–1508), and DOE NEPA includes Summit Power Group, Inc.; information on the DOE NEPA process,
implementing procedures (10 CFR part Blue Source, LLC; Siemens, AG; and please contact Ms. Carol M. Borgstrom,
1021), to assess the potential CWNI; among others. Director, Office of NEPA Policy and
environmental impacts for the proposed DOE issues this Notice of Intent (NOI) Compliance (GC–54), U.S. Department
action of providing Federal funding for to inform interested parties of the of Energy, 1000 Independence Avenue,
the proposed Texas Clean Energy pending EIS and to invite public SW., Washington, DC 20585–0103;
Project (TCEP) near Odessa, Texas. The comments on the proposed action, telephone: 202–586–4600; fax: 202–
project would comprise planning, including: (1) The proposed plans for 586–7031; or leave a toll-free message at
design, construction and operation by implementing the project, (2) the range 1–800–472–2756.
Summit Texas Clean Energy, LLC of environmental issues and alternatives
to be analyzed, and (3) the analysis SUPPLEMENTARY INFORMATION:
(Summit) of a coal-fueled electric power
and chemicals production plant methods to be used or considered Background
integrated with carbon dioxide (CO2) during preparation of the EIS.
capture and geologic sequestration. DOE DATES: DOE invites comments on the Since the early 1970s, DOE and its
selected this project for an award of proposed scope and content of the EIS predecessor agencies have pursued
financial assistance through a from all interested parties. Comments research and development programs
competitive process under the Clean must be received by July 2, 2010, to that include large, technically complex
Coal Power Initiative (CCPI) program ensure consideration. Late comments projects in pursuit of innovation in a
(Round 3). will be considered to the extent wide variety of coal technologies
The EIS (DOE/EIS–0444) will inform practicable. In addition to accepting through the proof-of-concept stage.
DOE’s decision on whether to provide comments in writing (formal letters, However, helping a technology reach
financial assistance under its CCPI faxes and e-mails) and by telephone the proof-of-concept stage does not
program. DOE proposes to provide (See ADDRESSES below), DOE will ensure its continued development or
Summit with approximately $350 conduct a public scoping meeting in commercialization. Before a technology
million in funding for this project, which government agencies, private- can be considered seriously for
which would demonstrate the full sector organizations, and the general commercialization, it must be
integration of CO2 capture and public are invited to present oral demonstrated at a sufficient scale to
sequestration with a commercial, comments or suggestions with regard to prove its reliability and economically
integrated gasification combined-cycle the alternatives and issues to be competitive performance. The financial
(IGCC) poly-generation (electricity and considered in the EIS. The scoping risk associated with such large-scale
chemicals) plant. DOE’s contribution of meeting will be held beginning at 7 p.m. demonstration projects is often too high
$350 million would constitute about 20 on Thursday, June 17, 2010, in the for the private sector to assume in the
sroberts on DSKD5P82C1PROD with NOTICES
percent of the estimated total Saulsbury Meeting Room of the absence of strong incentives.
development and capital cost of the Electronics Technology Building at The CCPI program was established in
project, which is estimated to be $1.73 Odessa College, 201 West University 2002 as a government and private sector
billion (2009 dollars). TCEP would Blvd, Odessa, Texas 79764. The public partnership to implement the
employ advanced clean coal is also invited to learn more about the recommendation in President Bush’s
technologies to reduce the levels of CO2 proposed project at an informal session National Energy Policy to increase
emissions below that of conventional at this location beginning at 4 p.m. investment in clean coal technology.
VerDate Mar<15>2010 19:46 Jun 01, 2010 Jkt 220001 PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 E:FRFM02JNN1.SGM 02JNN1
2. Federal Register / Vol. 75, No. 105 / Wednesday, June 2, 2010 / Notices 30801
Through cooperative agreements with pipelines (with the construction of short electricity that can be generated from a
its private sector partners, the program new connector pipelines) where the CO2 quantity of coal. Both turbines would
advances clean coal technologies to could be used in EOR operations. Most generate electricity for sale, with a part
commercialization; these technologies likely, CO2 would be transported in an of the electricity diverted to service
often involve combustion existing regional CO2 pipeline network. other parts of the poly-generation plant
improvements, control system advances, A short, approximately two-mile, new and on-site commercial loads. At full
gasifier designs, pollution reductions CO2 pipeline could connect the power capacity, the plant would be expected to
(including greenhouse gas reduction), plant site to the nearest existing trunk use about 5,800 tons of low-sulfur coal
efficiency increases, fuel processing pipeline. per day (about 1.9 to 2.0 million tons
techniques and other improvements. per year). Coal would be delivered by
Proposed Plant
Congress established criteria for railroad trains from the Powder River
projects receiving financial assistance Summit would construct an IGCC Basin and would be bought through
under this program in Title IV of the poly-generation plant that is designed to contracts on the open market.
Energy Policy Act of 2005 (Pub. L. 109– capture approximately 90 percent of its The plant would minimize emissions
58) (EPACT 2005). Under this statute, CO2, and sequester it through use in of sulfur oxides, nitrogen oxides,
CCPI projects must ‘‘advance efficiency, EOR operations. Summit, or another mercury, and particulates as compared
environmental performance and cost entity, would operate the plant to to conventional coal-fueled power
competitiveness well beyond the level demonstrate the commercial feasibility plants. In compliance with Texas House
of technologies that are in commercial of a fully integrated, coal-fueled 400 Bill 469, the project would be required
service’’ (Pub. L. 109–58, Sec. 402(a)). In MW-equivalent generating unit that to meet stringent emissions limits: 0.034
February 2009, the American Recovery would produce 275 MW of electricity pounds of NOX per million BTUs, 0.04
and Reinvestment Act of 2009 (Pub. L. for the power grid (with additional pounds of SOX per million BTUs, 95
111–5, 123 Stat. 115 (Feb. 17, 2009)) amounts for on-site commercial loads percent reduction in mercury emissions,
(ARRA) appropriated $3.4 billion to and plant use) plus sulfuric acid, urea and 0.015 pounds of particulates per
DOE for ‘‘Fossil Energy Research and and perhaps other chemicals such as million BTUs. The project’s air permit
Development;’’ the Department intends ammonia, methanol or substitute application with the Texas Commission
to use a significant portion of these natural gas. Following the on Environmental Quality (TCEQ)
funds to provide financial assistance to demonstration phase, the project would includes even lower emissions limits
CCPI projects. continue long-term commercial than those required by HB 469.
operations with continuing sales of Emissions of carbon monoxide and
Purpose and Need for Agency Action power, urea, captured CO2 and other volatile organic compounds would be
The purpose and need for the DOE chemical products. controlled.
action are to advance the CCPI program The new plant would consist of two Steam from the gasification and
by funding projects that have the best gasifiers, a gas processing and cleanup syngas processing could be condensed,
chance of achieving the program’s system, a syngas-fueled combustion treated, and recycled into the gasifier or
objectives as established by Congress: turbine, a heat-recovery steam generator, added to the plant’s cooling water
the commercialization of clean coal a steam turbine, a sulfur recovery plant, circuit. Slag from the gasifiers would be
technologies that advance efficiency, a chemicals production plant, and sold for beneficial uses. Other solid
environmental performance, and cost associated facilities. The system is materials generated by the various plant
designed with duplicate, over-sized processes would be accumulated on site
competitiveness well beyond the level
gasifiers to ensure full-time availability and made available for beneficial use,
of technologies that are currently in
of syngas production, with sufficient recycling or, if these options are not
commercial service.
supply for both the production of available, disposed of in accordance
Summit’s Proposed Project electricity (more than 75 percent) and with applicable laws.
chemicals (less than 25 percent). The chemical plant would use the
Site of Proposed Project: Penwell, Texas The plant proposed by Summit would Haber process to convert syngas into
The proposed site is located on 600 gasify coal to produce ‘‘synthesis gas’’ ammonia and the Bosch-Meiser process
acres, approximately 15 miles southwest (or ‘‘syngas’’—mostly carbon monoxide to convert ammonia into urea for
of the city of Odessa in Ector County, (CO), hydrogen gas (H2), CO2 and fertilizer. With equipment additions or
Texas. The site is on flat land north of steam), which would be processed to changes, other chemicals could be
the town of Penwell and Interstate increase the H2 content (by converting produced.
Highway I–20. The proposed power CO and H2O into H2 plus CO2) and Other notable equipment would
plant property is arid, non-arable brush cleaned of particulates and acid gases to include coal storage facilities, a coal
(mesquite-lotebush-juniper) and range produce a H2-rich, carbon-lean fuel. The preparation plant and coal feed system,
land. Surrounding areas are or were H2-rich fuel would power the gas air separators, stacks, mechanical draft
used primarily for ranching to the north combustion turbine, and CO2 emissions cooling tower (dry cooling is planned
and east and oil production to the west would be minimal (only a fraction of for the power generation facilities and
and south, with some scattered those of a natural gas power plant) as a wet cooling for other portions of the
industrial facilities (quarry, cement result of the hydrogen-rich, carbon-lean plant), a unit for converting captured
plant, etc.) within sight to the east and fuel. Hot exhaust gas from the gas sulfur dioxide into sulfuric acid for sale
south. There is an extensive junk yard combustion turbine would generate on the market, and a particulate
of abandoned oil and gas equipment steam from water in the heat recovery filtration system. The height of the
sroberts on DSKD5P82C1PROD with NOTICES
along the site’s southern border, on the steam generator to drive the steam tallest proposed stack would be
other side of a railroad. The site has turbine. Using a heat recovery steam approximately 140 feet above ground
access to coal delivery via rail along the generator and a steam turbine to capture level. Additionally, the plant would
southern border of the property, and it energy from the exhaust gases of the require the construction of a railroad
connects to I–20 via Farm-to-Market combustion turbine is the essence of the loop, coal unloading facilities, ash/slag
Road 1601. There are numerous oil combined-cycle approach and increases handling facilities, access roads,
fields within reach of existing CO2 both efficiency and the total amount of administration buildings, water and
VerDate Mar<15>2010 19:08 Jun 01, 2010 Jkt 220001 PO 00000 Frm 00032 Fmt 4703 Sfmt 4703 E:FRFM02JNN1.SGM 02JNN1
3. 30802 Federal Register / Vol. 75, No. 105 / Wednesday, June 2, 2010 / Notices
waste water treatment facilities, and a sequester about 3 million tons of CO2 facilities, including the capture and sale
waste water disposal well. An per year by transporting it in pipelines of CO2, would be expected to continue
underpass may be constructed beneath to oil fields in the Permian Basin of west for 30 to 50 years. Summit plans to start
the adjoining railroad. Texas for use in EOR operations. These construction during 2011 and
fields are well characterized, and some commercial operations (demonstration
Proposed Linear Facilities
already make extensive use of CO2 for phase) by late 2014. The schedule is
Linear facilities are the power EOR. As a consequence of EOR contingent upon Summit receiving the
transmission lines and pipelines that operations, most of the captured CO2 necessary permits (which would be
convey electricity and materials to and (more than 99 percent) would be preceded by hearings, public comment
from the plant. Electricity could be sequestered in deep underground opportunities and other events
conveyed to regional 345 kV geologic formations that would be
transmission lines via an approved mandated by applicable regulations and
monitored to verify the quantity and agency procedures) and financial
ERCOT (Electric Reliability Council of permanence of CO2 storage. The use of
Texas) grid extension but could also be closing on all the necessary funding
CO2 in this manner would continue the
transmitted via local interconnects with sources, including DOE’s financial
existing uses of the subject fields,
either of two 138 kV transmission lines, namely enhanced oil production using assistance. DOE’s decision to provide
one located approximately 0.7 miles to CO2. financial assistance for detailed design,
the north and the other located 1.8 miles The EOR process involves the procurement of expensive equipment,
to the south. Rights-of-ways (ROWs) repeated injection of CO2 to reduce the construction, and operations will be
would be approximately 200 ft wide. An oil’s viscosity and to move it through informed by the NEPA process.
electrical substation would be the reservoir. During EOR operations, Connected and Cumulative Actions
constructed to facilitate the connection pore space left by the extracted oil is
to the grid. occupied by the injected CO2, Under the cooperative agreement
Process water would be obtained from sequestering it in the geologic between DOE and Summit, DOE would
local wastewater treatment facilities formation. Reservoirs are not over- share in the cost of the power and
(using effluent from the Gulf Coast pressurized from CO2 for EOR chemical plant, supporting facilities and
Authority, the City of Odessa, and/or operations, because fluid volumes are site infrastructure (including that
the City of Midland) or from a re- removed from the reservoirs in amounts required for sequestration monitoring,
charging aquifer in the region. Other corresponding to those injected in the verification and accounting (MVA), and
water supply options may be considered reservoirs. the costs associated with implementing
during the project planning. The water and documenting the results of the
Summit’s Technology Alternatives
would be conveyed by one or more new
Summit has proposed to use Siemens demonstration test plan during the
pipelines constructed on a combination
SFG–500 gasifiers and a Siemens F-class demonstration phase). Under this
of existing and new ROWs over
combined-cycle power island. As plans agreement, DOE would not share in the
distances ranging between about 10
miles and 54 miles. progress, Summit will make a final costs of normal plant operations during
Wastewater would be processed in a selection of air separation technology, the demonstration phase. For activities
new on-site wastewater treatment plant. water/gas shift reactor technology, acid that would not occur if not for this
The plant would be designed for zero gas removal system technology (for project, DOE will consider these as
liquid discharge. capturing both CO2 and acid gases, such connected actions and will evaluate
Natural gas, which would be used to as H2S), sulfur recovery technology (e.g., them in the EIS.
start the plant, would be obtained from Claus process), and urea production DOE will consider the cumulative
an existing pipeline that traverses the technology (e.g., combination of the impacts of both the cost-shared
proposed project site or from a gas line Haber ammonia production process and activities and other activities, along
located either to the north or to the Bosch-Meiser urea production process). with any other connected actions,
south of the site. Natural gas also may Summit has proposed to use only including those of third parties.
be used to fuel the power island commercially proven, fully warranted Cumulative impacts analysis will
initially, while the remainder of the equipment to reduce risks and costs. include the analysis of pollutant
plant is under construction. The technological advancement is in the emissions (including greenhouse gas
The plant may deliver its CO2 to the integration of all these components. A emissions) and other incremental
existing Central Basin CO2 pipeline, competitive process would be used to
impacts that, when added to past,
which is less than two miles to the east select vendors and manufacturers (other
present and reasonably foreseeable
of the proposed plant site. In this than for the Siemens-supplied
future impacts, may have significant
option, a short new pipeline would be equipment). A wide variety of chemicals
effects on the human environment. DOE
constructed eastwards along new ROW. could be produced, depending on
will not consider impacts associated
Alternatively, new pipelines could be chemical processing equipment
constructed to either existing oil fields installed. Current plans indicate market with the purchase of commodities (such
or to other existing pipelines. New viability for the production and sale of as coal) on the open market, coal
ROWs would require widths of 100 ft urea (for fertilizer), ammonia, methanol mining, or the transportation of coal as
for construction and approximately 50 ft and substitute natural gas (SNG). a general industrial activity (as
for pipeline operations. Sales and distinguished from the delivery of coal
Proposed Project Schedule to the project site, specifically), given
conveyance options for CO2 are
sroberts on DSKD5P82C1PROD with NOTICES
currently under consideration and The project proposed by Summit these impacts are generally well known
negotiation. includes the planning, design, and would occur regardless of DOE’s
construction, initial start-up, and early decision regarding financial assistance
Proposed Use of CO2 for Enhanced Oil operation of the plant and associated for this project. No coal for this project
Recovery and Sequestration facilities for a period of three years would come from ‘‘mountaintop
During DOE’s demonstration phase of under the DOE demonstration phase. removal’’ forms of mining, which are not
plant operations, the project would Thereafter the plant and associated practiced in the Powder River Basin.
VerDate Mar<15>2010 19:08 Jun 01, 2010 Jkt 220001 PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 E:FRFM02JNN1.SGM 02JNN1
4. Federal Register / Vol. 75, No. 105 / Wednesday, June 2, 2010 / Notices 30803
Alternatives, Including the Proposed given to environmental factors. DOE FutureGen (reference: DOE/EIS–0394).
Action will make the synopsis available to the In particular, Summit sought a site
NEPA requires that agencies evaluate public by posting it on NETL’s Web site. where CO2 sales options were readily
the reasonable alternatives to their After DOE selects a project for an available and the market was strong and
proposed action. The purpose and need award, the range of reasonable dependable so that there would be no
alternatives becomes the project as reliance on pending legislation for CO2
for agency action determines the range
proposed by the applicant, any capture and sequestration and no need
of reasonable alternatives. In this case,
alternatives still under consideration by for a long CO2 pipeline that might not
the purpose and need for DOE’s
the applicant or that are reasonable be built. The EIS will briefly describe
proposed action—providing cost-shared
within the confines of the project as Summit’s site selection process.
funding for Summit’s project—is to
proposed (e.g., the particular location of However, DOE does not plan to analyze
advance the CCPI program by funding
the plant on the parcel of land proposed in detail any alternative sites considered
projects that have the best chance of
for the project) and a ‘‘no action’’ and dismissed by Summit because
achieving the program’s objectives as
alternative. Regarding a no action Summit is no longer considering these
established by Congress: The
alternative, DOE assumes for purposes other alternatives and because they were
commercialization of clean coal of the EIS that, if it decides to withhold
technologies that advance efficiency, not part of the proposal that Summit
financial assistance, the project would offered and DOE accepted.
environmental performance, and cost not proceed.
competitiveness well beyond the level DOE currently plans to evaluate the Floodplains and Wetlands
of technologies that are currently in project as proposed by Summit (with
service. The footprint of the proposed plant
and without any mitigating conditions would not affect any wetlands or
DOE’s NEPA regulations include a that DOE may identify as reasonable and
process for identifying and analyzing floodplains. Wetland and floodplain
appropriate); alternatives to Summit’s impacts, if any, from construction of
reasonable alternatives in the context of proposal that it is still considering (e.g.,
providing financial assistance through a pipelines and transmission lines would
water sources, sales options for CO2, be identified during the preparation of
competitive selection of projects and the ROWs for linear facilities); and
proposed by entities outside the federal the EIS and described in the EIS. In the
the no action alternative. DOE and event that the EIS identifies wetlands
government. The range of reasonable Summit will consider other reasonable
alternatives in competitions for grants, and floodplains that would be affected
alternatives suggested during the by the proposed project, including its
loans, loan guarantees, and other scoping period.
financial support is defined initially by linear facilities and connected actions,
Under the no action alternative, DOE
the range of responsive proposals DOE will prepare a floodplain and
would not provide funding to Summit.
received by DOE. Unlike projects wetland assessment in accordance with
In the absence of financial assistance
undertaken by DOE itself, the its regulations at 10 CFR part 1022 and
from DOE, Summit could reasonably
Department cannot mandate what include the assessment in the EIS.
pursue two options. It could build the
outside entities propose, where they project without DOE funding; the Preliminary Identification of
propose their project, or how they impacts of this option would be Environmental Issues
propose to do it, beyond expressing essentially the same as those of DOE’s
basic requirements in the funding DOE intends to address the issues
proposed action, except any DOE-
opportunity announcement; and these required mitigations would not be listed below when considering the
express requirements must be limited to imposed. Or, Summit could choose not potential impacts resulting from the
those that further the program’s to pursue its project, and there would be construction and operation of Summit’s
objectives. DOE’s decision is then no impacts from the project. This latter proposed project and any connected
limited to selecting among the option would not contribute to the goal actions. This list is neither intended to
applications that meet the program’s of the CCPI program, which is to be inclusive nor a predetermined set of
goals. accelerate commercial deployment of potential impacts. DOE invites
Recognizing that the range of advanced coal technologies that provide comments on whether this is the correct
reasonable alternatives in the context of the United States with clean, reliable, list of important issues that should be
financial assistance and contracting is and affordable energy. However, as considered in the EIS. The
determined by the number and nature of required by NEPA, DOE analyzes this environmental issues include:
the proposals received, section 216 of option as the no action alternative for • Air quality impacts: Potential for air
DOE’s NEPA regulations requires the the purpose of making a meaningful emissions during construction and
Department to prepare an comparison between the impacts of DOE operation of the power plant and
‘‘environmental critique’’ that assesses providing financial assistance and appurtenant facilities to impact local
the environmental impacts and issues withholding that assistance. sensitive receptors, local environmental
relating to each of the proposals that the Alternatives considered by Summit in conditions, and special-use areas,
DOE selecting official considers for an developing its proposed project will be including contributions to smog and
award. See 10 CFR 1021.216. This discussed in the EIS. Summit haze, impacts from dust and any
official considers these impacts and considered a number of sites (six in significant vapor plumes, and
issues, along with other aspects of the Texas alone) and determined that the consequences of greenhouse gas
proposals (such as technical merit and only reasonable site for continued emissions;
financial ability) and the program’s consideration is the one at Penwell. • Water resource impacts: Potential
sroberts on DSKD5P82C1PROD with NOTICES
objectives, in making awards. DOE Summit’s consideration included impacts from water utilization and
prepared a critique of the proposals that market opportunities and conditions, evaporation;
were deemed suitable for selection in local infrastructure, physical suitability • Infrastructure and land use impacts:
this round of awards for the CCPI of the sites, and environmental Potential environmental and
program. DOE will prepare an concerns. Two of the sites had already socioeconomic impacts associated with
‘‘environmental synopsis,’’ based on the been environmentally reviewed and the project, including delivery of feed
critique, to document consideration cleared for a very similar project, materials and distribution of products
VerDate Mar<15>2010 19:08 Jun 01, 2010 Jkt 220001 PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 E:FRFM02JNN1.SGM 02JNN1
5. 30804 Federal Register / Vol. 75, No. 105 / Wednesday, June 2, 2010 / Notices
(e.g., power transmission lines, EIS. The public scoping period will end DEPARTMENT OF ENERGY
pipelines); on July 2, 2010. Interested government
• Visual impacts associated with agencies, private-sector organizations Biomass Research and Development
facility structures: View shed impacts, and individuals are encouraged to Technical Advisory Committee
impacts to scenic views (e.g., impacts submit comments or suggestions
AGENCY: Department of Energy, Office of
caused by the plant structures, water concerning the content of the EIS, issues
Energy Efficiency and Renewable
vapor plumes, flares, power and impacts that should be addressed,
Energy.
transmission lines, pipelines), internal and alternatives that should be
and external perception of the considered. Scoping comments should ACTION: Notice of open meeting.
community or locality; clearly describe specific issues or topics
SUMMARY: This notice announces an
• Solid waste impacts: Pollution that the EIS should address. Written, e-
open meeting of the Biomass Research
prevention and waste management mailed, faxed, or telephoned comments
and Development Technical Advisory
issues (generation, treatment, transport, should be received by July 2, 2010 (see
Committee under Section 9008(d) of the
storage, disposal or use), including the ADDRESSES).
Food, Conservation, and Energy Act of
handling of slag, water treatment sludge, DOE will conduct a public scoping
2008. The Federal Advisory Committee
sulfur by-products, and hazardous meeting beginning at 7 p.m. on
Act (Pub. L. 92–463, 86 Stat. 770)
materials; Thursday, June 17, 2010 in the
• Ecological impacts: Potential on-site requires that agencies publish these
Saulsbury Meeting Room of the
and off-site impacts to vegetation, notices in the Federal Register to allow
Electronics Technology Building at
terrestrial wildlife, aquatic wildlife, for public participation. This notice
Odessa College, 201 West University
threatened or endangered species, and announces the meeting of the Biomass
Blvd., Odessa, Texas 79764. The public
ecologically sensitive habitats; Research and Development Technical
is also invited to learn more about the
• Traffic issues: Potential impacts Advisory Committee.
proposed project at an informal session
from the construction and operation of at this location beginning at 4 p.m. DATES:
the facilities, including changes in local Anyone who wishes to speak at this June 23, 2010; 10:30 a.m. to 3:15 p.m.
traffic patterns, deterioration of roads, public scoping meeting should contact June 24, 2010; 10:30 a.m. to 3 p.m.
traffic hazards, and traffic controls; Mr. Mark L. McKoy, either by phone, ADDRESSES: Hyatt Arlington, 1325
• Historic and cultural resource fax, e-mail, or letter (see ADDRESSES). Wilson Boulevard, Arlington, Virginia
issues: Potential impacts, primarily Those who do not arrange in advance 22209, (703) 525–1234.
related to linear facilities and connected to speak may register at the meeting FOR FURTHER INFORMATION CONTACT:
actions; (preferably at the beginning of the Laura McCann, Designated Federal
• Fate and stability of sequestered meeting) and may speak after previously Officer for the Committee, Office of
CO2 (and other captured gases) during scheduled speakers. Speakers will be Energy Efficiency and Renewable
and after EOR usage; given approximately five minutes to Energy, U.S. Department of Energy,
• Health and safety issues associated present their comments. Those speakers 1000 Independence Avenue, SW.,
with CO2 capture, transport, and usage who want more than five minutes Washington, DC 20585; (202) 586–7766;
in EOR; should indicate the length of time e-mail: laura.mccann@ee.doe.gov or T.J.
• Marketability of products desired in their request. Depending on Heibel at (410) 997–7778 ext. 223; e-
(including by-products) and market the number of speakers, DOE may need mail: theibel@bcs-hq.com.
access to feedstocks; to limit all speakers to five minutes SUPPLEMENTARY INFORMATION:
• Socio-economic impacts, including initially and provide second
the creation of jobs and the impacts of Purpose of Meeting: To provide
opportunities as time permits. Speakers advice and guidance that promotes
State and local tax incentives; may also provide written materials to
• Disproportionate impacts on research and development leading to the
supplement their presentations. Oral production of biobased fuels and
minority and low-income populations; and written comments will be given
• Noise and light impacts: Potential biobased products.
equal consideration. Federal, State and Tentative Agenda: Agenda will
impacts from construction, local elected officials and tribal leaders
transportation of materials, and facility include the following:
may be given priority in the order of • Update on USDA Biomass R&D
operations; those making oral comments.
• Connected actions: Potential Activities.
DOE will begin the formal meeting
development of support facilities or • Update on DOE Biomass R&D
with an overview of Summit’s proposed
supporting infrastructure; Activities.
Texas Clean Energy Project. The
• Cumulative effects that result from • Presentation on DOE/USDA Joint
meeting will not be conducted as an
the incremental impacts of the proposed Solicitation Process.
evidentiary hearing, and speakers will
project when added to other past, • Presentation on DOE and USDA
not be cross-examined. However,
present, and reasonably foreseeable loan guarantee programs.
speakers may be asked questions to help
future projects; • Presentation on SC/NIFA joint
ensure that DOE fully understands the
• Compliance with regulatory comments or suggestions. A presiding
solicitation (genetics).
requirements and environmental • Update on Biomass R&D Board
officer will establish the order of
permitting; Activities.
speakers and provide any additional
• Environmental monitoring plans procedures necessary to conduct the
Public Participation: In keeping with
associated with the power plant and procedures, members of the public are
sroberts on DSKD5P82C1PROD with NOTICES
meeting.
with the CO2 sequestration sites. welcome to observe the business of the
Issued in Washington, DC, this 27th day of Biomass Research and Development
Public Scoping Process May, 2010. Technical Advisory Committee. To
To ensure identification of all issues James J. Markowsky, attend the meeting and/or to make oral
related to DOE’s proposed action and Assistant Secretary, Office of Fossil Energy. statements regarding any of the items on
Summit’s proposed project, DOE seeks [FR Doc. 2010–13215 Filed 6–1–10; 8:45 am] the agenda, you should contact Laura
public input to define the scope of the BILLING CODE 6450–01–P McCann at 202–586–7766; E-mail: