Identified Opportunities to
Increase Productivity
2
• Updated designs for packaging and cell
layouts for high labor content products
• SR560M and other carts and Stands
• DS-VW765-LAND – Video Wall
• Dedicated cells to run shop orders with
optimal crew sizes
Redesigned Layout for Carts & Stands
3
 Start of the Line: 1 Piece Carton
 Placed on Conveyor
 Components packed at tables
 Staples replace tape
 End of the Line: 1 Piece Carton  End of the Line: Pallet located next to
aisle for easy access by forklift
Projected Cost Savings
Redesigned Packaging and Layout for Carts
 Before Improvements:
 25 units/hour with a crew size of 7 people
 EAU = 7,136 units/year – 2,000 labor hours
 After Improvements:
 28 units/hour with a crew size of 6 people
 EAU = 7,136 units/year – 1,529 labor hours
 Total Labor Hours Saved = 471 hours
 Labor Rate = $42.14/hour
 Estimated Total Annual Savings = $ 19,850 4
Redesigned Packaging for Video Walls
5
Carton is too deep –
requires extra filler paper
Inserts need to be folded
Adapter Brackets Wrapped in
Paper and then put into Carton
 Before Improvements:
Redesigned Packaging for Video Walls
6
 After Improvement:
New Inserts for Adapter Brackets
Replaced Inserts with
Corner Protectors
Projected Cost Savings
Redesigned Packaging for Video Walls
Per Unit Per Year
(EAU=24K)
 Materials Savings = $1.55 $37,200
 Labor Savings = $2.95 $70,800
 Total Savings = $4.50 $108,000
Projected Annual Savings = $108,000
7
Projected Cost Savings
Total Projected Labor Savings
 Video Walls – New Packaging $108,000
 Carts and Stands-New Layout $19,850
 Extension Columns-New Methods $9,615
 Total Projected Labor Savings $137,465
 Total Projected Materials Savings $37,200
Projected Annual Savings $174,665
8
Projects In Process
Dedicated Cells to Utilize Optimal Crew Sizes
 Features:
 Shop Orders routed to specific cells based on Crew Size
 Cells are located across the aisle from staging areas
 Next Shop Order is setup prior to completion of current order
 Benefits
 Increases productivity since work load is balanced
 Scheduler schedules multiple orders
 Cell leader knows in advance the next orders to run
 Minimizes or eliminates downtime between orders
Cells with Dedicated Crew Sizes
10
Cell C011 - Optimal Crew Size = 3
Projects In Process
Work Cell Floor and Table Layout Template
 Features:
 Shows Material Handlers where to place containers of parts
 Shows Cell Leaders and Workers:
 what parts are required for each work station
 where to place parts at the work stations
 Benefits
 Allows Material Handlers to perform part of the setup
 Locates parts close to point-of-use
 Minimizes travel distances between containers and stations
 Minimizes or eliminates downtime between orders
12
Developing
Cell Floor &
Table Layout
Templates

Contenu connexe

Tendances

Presentation On Warehousing
Presentation On WarehousingPresentation On Warehousing
Presentation On WarehousingRRChandran
 
WAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENT
WAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENTWAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENT
WAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENTAjeesh Mk
 
Warehousing layout-design-and-processes-setup
Warehousing layout-design-and-processes-setupWarehousing layout-design-and-processes-setup
Warehousing layout-design-and-processes-setupPuneet Mishra
 
Shane Pool New
Shane Pool NewShane Pool New
Shane Pool NewShane Pool
 
Robert Spargur Resume 1
Robert Spargur Resume 1Robert Spargur Resume 1
Robert Spargur Resume 1Robert Spargur
 

Tendances (12)

Coralerp knitting
Coralerp knittingCoralerp knitting
Coralerp knitting
 
Warehouse
WarehouseWarehouse
Warehouse
 
Networking and Warehousing
Networking and WarehousingNetworking and Warehousing
Networking and Warehousing
 
Presentation On Warehousing
Presentation On WarehousingPresentation On Warehousing
Presentation On Warehousing
 
JWP-2015
JWP-2015JWP-2015
JWP-2015
 
WAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENT
WAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENTWAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENT
WAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENT
 
Warehousing layout-design-and-processes-setup
Warehousing layout-design-and-processes-setupWarehousing layout-design-and-processes-setup
Warehousing layout-design-and-processes-setup
 
Shane Pool New
Shane Pool NewShane Pool New
Shane Pool New
 
SAP EWM Cross Docking
SAP EWM Cross DockingSAP EWM Cross Docking
SAP EWM Cross Docking
 
MahoneyResume2017
MahoneyResume2017MahoneyResume2017
MahoneyResume2017
 
Upload
UploadUpload
Upload
 
Robert Spargur Resume 1
Robert Spargur Resume 1Robert Spargur Resume 1
Robert Spargur Resume 1
 

Similaire à Pack Line Process Improvement Project-Cart-VideoWall

PD cell Kaizen event presentation
PD cell Kaizen event presentationPD cell Kaizen event presentation
PD cell Kaizen event presentationGreg Williams
 
PD cell Kaizen event Linkedin
PD cell Kaizen event LinkedinPD cell Kaizen event Linkedin
PD cell Kaizen event LinkedinGreg Williams
 
Just In Time and Lean Operation Chapter Presentation
Just In Time and Lean Operation Chapter PresentationJust In Time and Lean Operation Chapter Presentation
Just In Time and Lean Operation Chapter PresentationSINGHZEE
 
Chap08- Facility Layout.pptx
Chap08- Facility Layout.pptxChap08- Facility Layout.pptx
Chap08- Facility Layout.pptxKritikaRaj30
 
Mba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aMba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aRai University
 
KAYA 3 Yr Plan FINAL with Notes
KAYA 3 Yr Plan FINAL with NotesKAYA 3 Yr Plan FINAL with Notes
KAYA 3 Yr Plan FINAL with NotesBryan Horton
 
3. capacity planning
3. capacity planning3. capacity planning
3. capacity planningSudipta Saha
 
Product, process, fixed and group layouts
Product, process, fixed and group layoutsProduct, process, fixed and group layouts
Product, process, fixed and group layoutsAjith Antony
 
Cellular Manufacturing
Cellular Manufacturing Cellular Manufacturing
Cellular Manufacturing sgrsoni45
 
Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industryGanesh TN
 
2013 Q A Presentation (2) (2)
2013 Q A Presentation (2) (2)2013 Q A Presentation (2) (2)
2013 Q A Presentation (2) (2)MICHAEL MORGAN
 
Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)Ishan Parekh
 
Commercial Overview SCS Session 1 Server Rack Strategies
Commercial Overview   SCS Session 1   Server Rack StrategiesCommercial Overview   SCS Session 1   Server Rack Strategies
Commercial Overview SCS Session 1 Server Rack Strategiespaul_mathews
 
Nokia manaus090828 final_presentation_vsa_v4
Nokia manaus090828 final_presentation_vsa_v4Nokia manaus090828 final_presentation_vsa_v4
Nokia manaus090828 final_presentation_vsa_v4CarlosMoura111
 
Retrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsRetrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsWIGreenBuilding
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysisvideoaakash15
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysisvideoaakash15
 
Mba ii pmom_unit-2.3 facility layout a
Mba ii pmom_unit-2.3 facility layout aMba ii pmom_unit-2.3 facility layout a
Mba ii pmom_unit-2.3 facility layout aRai University
 

Similaire à Pack Line Process Improvement Project-Cart-VideoWall (20)

PD cell Kaizen event presentation
PD cell Kaizen event presentationPD cell Kaizen event presentation
PD cell Kaizen event presentation
 
PD cell Kaizen event Linkedin
PD cell Kaizen event LinkedinPD cell Kaizen event Linkedin
PD cell Kaizen event Linkedin
 
Just In Time and Lean Operation Chapter Presentation
Just In Time and Lean Operation Chapter PresentationJust In Time and Lean Operation Chapter Presentation
Just In Time and Lean Operation Chapter Presentation
 
Chap08- Facility Layout.pptx
Chap08- Facility Layout.pptxChap08- Facility Layout.pptx
Chap08- Facility Layout.pptx
 
Thesis presentation
Thesis presentationThesis presentation
Thesis presentation
 
Inventory management1
Inventory management1Inventory management1
Inventory management1
 
Mba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aMba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection a
 
KAYA 3 Yr Plan FINAL with Notes
KAYA 3 Yr Plan FINAL with NotesKAYA 3 Yr Plan FINAL with Notes
KAYA 3 Yr Plan FINAL with Notes
 
3. capacity planning
3. capacity planning3. capacity planning
3. capacity planning
 
Product, process, fixed and group layouts
Product, process, fixed and group layoutsProduct, process, fixed and group layouts
Product, process, fixed and group layouts
 
Cellular Manufacturing
Cellular Manufacturing Cellular Manufacturing
Cellular Manufacturing
 
Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industry
 
2013 Q A Presentation (2) (2)
2013 Q A Presentation (2) (2)2013 Q A Presentation (2) (2)
2013 Q A Presentation (2) (2)
 
Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)
 
Commercial Overview SCS Session 1 Server Rack Strategies
Commercial Overview   SCS Session 1   Server Rack StrategiesCommercial Overview   SCS Session 1   Server Rack Strategies
Commercial Overview SCS Session 1 Server Rack Strategies
 
Nokia manaus090828 final_presentation_vsa_v4
Nokia manaus090828 final_presentation_vsa_v4Nokia manaus090828 final_presentation_vsa_v4
Nokia manaus090828 final_presentation_vsa_v4
 
Retrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsRetrocommissioning of Existing Buildings
Retrocommissioning of Existing Buildings
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysis
 
Mba ii pmom_unit-2.3 facility layout a
Mba ii pmom_unit-2.3 facility layout aMba ii pmom_unit-2.3 facility layout a
Mba ii pmom_unit-2.3 facility layout a
 

Pack Line Process Improvement Project-Cart-VideoWall

  • 1. 1
  • 2. Identified Opportunities to Increase Productivity 2 • Updated designs for packaging and cell layouts for high labor content products • SR560M and other carts and Stands • DS-VW765-LAND – Video Wall • Dedicated cells to run shop orders with optimal crew sizes
  • 3. Redesigned Layout for Carts & Stands 3  Start of the Line: 1 Piece Carton  Placed on Conveyor  Components packed at tables  Staples replace tape  End of the Line: 1 Piece Carton  End of the Line: Pallet located next to aisle for easy access by forklift
  • 4. Projected Cost Savings Redesigned Packaging and Layout for Carts  Before Improvements:  25 units/hour with a crew size of 7 people  EAU = 7,136 units/year – 2,000 labor hours  After Improvements:  28 units/hour with a crew size of 6 people  EAU = 7,136 units/year – 1,529 labor hours  Total Labor Hours Saved = 471 hours  Labor Rate = $42.14/hour  Estimated Total Annual Savings = $ 19,850 4
  • 5. Redesigned Packaging for Video Walls 5 Carton is too deep – requires extra filler paper Inserts need to be folded Adapter Brackets Wrapped in Paper and then put into Carton  Before Improvements:
  • 6. Redesigned Packaging for Video Walls 6  After Improvement: New Inserts for Adapter Brackets Replaced Inserts with Corner Protectors
  • 7. Projected Cost Savings Redesigned Packaging for Video Walls Per Unit Per Year (EAU=24K)  Materials Savings = $1.55 $37,200  Labor Savings = $2.95 $70,800  Total Savings = $4.50 $108,000 Projected Annual Savings = $108,000 7
  • 8. Projected Cost Savings Total Projected Labor Savings  Video Walls – New Packaging $108,000  Carts and Stands-New Layout $19,850  Extension Columns-New Methods $9,615  Total Projected Labor Savings $137,465  Total Projected Materials Savings $37,200 Projected Annual Savings $174,665 8
  • 9. Projects In Process Dedicated Cells to Utilize Optimal Crew Sizes  Features:  Shop Orders routed to specific cells based on Crew Size  Cells are located across the aisle from staging areas  Next Shop Order is setup prior to completion of current order  Benefits  Increases productivity since work load is balanced  Scheduler schedules multiple orders  Cell leader knows in advance the next orders to run  Minimizes or eliminates downtime between orders
  • 10. Cells with Dedicated Crew Sizes 10 Cell C011 - Optimal Crew Size = 3
  • 11. Projects In Process Work Cell Floor and Table Layout Template  Features:  Shows Material Handlers where to place containers of parts  Shows Cell Leaders and Workers:  what parts are required for each work station  where to place parts at the work stations  Benefits  Allows Material Handlers to perform part of the setup  Locates parts close to point-of-use  Minimizes travel distances between containers and stations  Minimizes or eliminates downtime between orders