SlideShare une entreprise Scribd logo
1  sur  16
Auto-reclosers
by
Debojyoti Mukherjee
Commercial ACRs are governed by the ANSI/IEEE C37.60, IEC 62271-111 and
IEC 62271-200 standards.
• 80-90% of the line faults are short lived (transient) and can be removed faster if the
disturbed phase is disconnected from the system momentarily so that the arc is
extinguished.
• If the fault is not cleared at first attempt then a double or triple attempt of isolation
and reclosure can be made. If the fault still persists then breaker is permanantly
opened.
• Auto-reclosing helps to maintain stability & synchronism in EHV systems.
Automatic Circuit Recloser (ACR)
• If recloser is unsuccessful the auto-reclose relay locks out the circuit breaker. Some
schemes provide a lockout relay with a flag, with provision of a contact for remote
alarm. The circuit breaker can then only be closed by hand.
• This action can be arranged to reset the auto-reclose relay element automatically.
CB lock-out
Block diagram of ACR
ACR operating schemes
Recloser timing
• The initial reclosure can be high speed (0.2 -0.5sec) or delayed for 3 - 5 seconds. This allows for
de-ionization time for fault arc.
• Typical schedule might be instantaneous, followed by 30sec, or 35sec, followed by 15sec. If the
circuit still continues to trip, the fault is declared as permanent and the recloser is locked out.
• Reclosers use three phase and single phase oil or vacuum circuit breakers for overhead
distribution lines.
• With underground network, faults tend to be more often permanent and reclosers are not
recommended.
• In case of large synchronous motors, distributed generators or induction motor loads, it is
recommended that sufficient time is allowed for under-frequency relays to trip these sources of
back emf out-of-the-circuit.
Application
Application Methodology Requirements
Renewable
Connection
Modern Recloser Controllers use ANSI 25
Synchrocheck, 59N Neutral Voltage
Displacement, Synchrophasors, ANSI
25A Auto-Synchronizer and other voltage
protection
Voltage Sensing on
both sides of Recloser
Substation
Circuit
Breakers
Using Reclosers installed in a Substation where
peak fault currents do not exceed the maximum
rated interrupting capacity, usually only Rural
Substations.
Typically maximum bus fault
currents below 16kA
Application
Application Methodology Requirements
Single
Wire Earth
Return
Network
Protection
A Single Phase Recloser unit
can be deployed. SWER network design topology
is discouraged in modern electrical engineering
due to safety reasons, but due to cost savings it is
sometimes deployed. Single Phase Recloser can
be used to improve safety on these lines
Single Phase Recloser
Single
Phase
Laterals
Permanent faults are typically 3 phase lockout,
despite the ability to lock single phases, as the
risk of circulating currents is
high.
Single Triple Recloser or Single
Phase Recloser System
Application
Application Methodology Requirements
Mid-
Feeder
Protection
Conventional recloser deployment Conventional
recloser
Fire
risk
mitigation
Not required as SEF protection pickup at 500mA
removes 80% risk of fire start.
Recloser with SGF/SEF
capability at 500mA.
Smart grid
distribution
network
automation
Centralized or distributed Remote communication
through SCADA or otherwise
configurable
from controller
Recloser control panel
1. Local human-machine interface
2. Indicator lights
3. Front panel push-buttons
4. Hot line tagging feature
5. Front mounted RS-232 port
6. Separate open and close
7. push-buttons
Recloser selection
Reclosers have to be selected by considering the following factors.
• Voltage Rating
• Continuous current Rating : This is the maximum load current the recloser has
to carry.
• Maximum Symmetrical Interrupting Rating: The maximum symmetrical fault
current should not exceed this rating.
• Minimum Tripping current : This is the minimum fault current that a recloser
will clear. It is equal to two times the continuous current rating. Usually
tolerance is ±10%. This decides the sensitivity of the recloser.
Source : IEEE Tutorial Course 80EH0157 - 8 - PWR
Rated Maximum Voltage
kV rms
Current Rating (Amperes)
Continuous Current
Rating
Symmetrical Interrupting
Rating
at Maximum Volts
Singlephase
recloser
15.5 50 1250
15.5 100 2000
15.5 280 4000
15.5 560 8000
27.0 100 2500
27.0 280 4000
38.0 560 8000
Threephaserecloser
15.0 50 1250
15.5 100 2000
15.5 280 4000
15.5 400 4000
15.5 560 8000
15.5 560 16000
EXAMPLE
Consider a three phase distribution
system with a single
phase tap as shown. Maximum load on
this single phase tap is 40A and that on
three phase line is 200A. Fault currents at
F1 ,F2 , F3 and F4 are also shown in the
Table . Select the ratings of reclosers at A
and B.
EXAMPLE
Recloser at B
Max. load current on this tap= 40A
Recloser max. current rating= 40x1.5= 60A (25-50% larger is taken considering load growth)
Max. single phase fault current at F3= 1750A
So, recloser marked in green is selected from table
Min. tripping current= continuous current rating x2m10%= 100x2m10%= 220A
Min. fault current in that line at F4= 250A
Thus 220A recloser will be able to protect entire line
Line voltage= 11kV hence recloser rated maximum voltage should be= 15.5 kV rms
EXAMPLE
Recloser at A
Max. load current on the three phase line= 200A
Recloser max. current rating= 200x1.25= 250A (25-50% larger is taken considering load growth)
Max. single phase fault current at F1= 3500A
So, recloser marked in red is selected from table
Min. tripping current= continuous current rating x2m10%= 280x2m10%= 616A
Min. fault current in that line at F2= 280A
Thus 280A recloser will NOT be able to protect entire line
Hence, in order to increase sensitivity ground relay can be added here.

Contenu connexe

Tendances

Energy management by maximum demand controller
Energy management by maximum demand controllerEnergy management by maximum demand controller
Energy management by maximum demand controller
International Journal of Innovations in Engineering and Science (IJIES)
 
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
jbpatel7290
 
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission lineMatlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
pamu17
 
Directional relay & Differential relay.pptx
Directional relay & Differential relay.pptxDirectional relay & Differential relay.pptx
Directional relay & Differential relay.pptx
UtthejNani1
 
Transformer differential protection
Transformer differential protection Transformer differential protection
Transformer differential protection
michaeljmack
 

Tendances (20)

Protection schemes and zones
Protection schemes and zonesProtection schemes and zones
Protection schemes and zones
 
1.substation layouts
1.substation  layouts1.substation  layouts
1.substation layouts
 
EXCITATION SYSTEMS
EXCITATION SYSTEMSEXCITATION SYSTEMS
EXCITATION SYSTEMS
 
Energy management by maximum demand controller
Energy management by maximum demand controllerEnergy management by maximum demand controller
Energy management by maximum demand controller
 
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
 
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission lineMatlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
 
Power system Protection Services in India
Power system Protection Services in IndiaPower system Protection Services in India
Power system Protection Services in India
 
Sag in overhead transmission line, sag calculation & string chart
Sag in overhead transmission line, sag   calculation & string chartSag in overhead transmission line, sag   calculation & string chart
Sag in overhead transmission line, sag calculation & string chart
 
Protective relaying
Protective relayingProtective relaying
Protective relaying
 
Directional relay & Differential relay.pptx
Directional relay & Differential relay.pptxDirectional relay & Differential relay.pptx
Directional relay & Differential relay.pptx
 
Protection
ProtectionProtection
Protection
 
Sag and tension
Sag and tensionSag and tension
Sag and tension
 
Power System Protection basics
Power System Protection basicsPower System Protection basics
Power System Protection basics
 
Deregulation in power industry
Deregulation in power industryDeregulation in power industry
Deregulation in power industry
 
Differential Protection Relay
DifferentialProtection RelayDifferentialProtection Relay
Differential Protection Relay
 
Overvoltage phenomenon
Overvoltage phenomenonOvervoltage phenomenon
Overvoltage phenomenon
 
Power Quality & Power Quality Problems
Power Quality & Power Quality ProblemsPower Quality & Power Quality Problems
Power Quality & Power Quality Problems
 
Protection and control of Microgrid
Protection and control of MicrogridProtection and control of Microgrid
Protection and control of Microgrid
 
Alternator protection
Alternator protectionAlternator protection
Alternator protection
 
Transformer differential protection
Transformer differential protection Transformer differential protection
Transformer differential protection
 

Similaire à Auto reclosers

Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculations
Ronald Santos
 
Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"
michaeljmack
 
SHORT-CIRCUIT-CALCULATIONS-ANSI-VS-IEC-F (1).pptx
SHORT-CIRCUIT-CALCULATIONS-ANSI-VS-IEC-F (1).pptxSHORT-CIRCUIT-CALCULATIONS-ANSI-VS-IEC-F (1).pptx
SHORT-CIRCUIT-CALCULATIONS-ANSI-VS-IEC-F (1).pptx
JohnLeimarRodriguez
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
saurabhVEC
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
Dinesh Sarda
 

Similaire à Auto reclosers (20)

UNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMUNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEM
 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculations
 
Generator protection LEC 2
Generator protection  LEC 2Generator protection  LEC 2
Generator protection LEC 2
 
Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"
 
Power Distribution Report of THE NEOTIA UNIVERSITY CAMPUS
Power Distribution Report of  THE NEOTIA UNIVERSITY CAMPUSPower Distribution Report of  THE NEOTIA UNIVERSITY CAMPUS
Power Distribution Report of THE NEOTIA UNIVERSITY CAMPUS
 
Vignettes in Grounding
Vignettes in GroundingVignettes in Grounding
Vignettes in Grounding
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptx
 
SHORT-CIRCUIT-CALCULATIONS-ANSI-VS-IEC-F (1).pptx
SHORT-CIRCUIT-CALCULATIONS-ANSI-VS-IEC-F (1).pptxSHORT-CIRCUIT-CALCULATIONS-ANSI-VS-IEC-F (1).pptx
SHORT-CIRCUIT-CALCULATIONS-ANSI-VS-IEC-F (1).pptx
 
Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)
 
Auto recloser
Auto recloserAuto recloser
Auto recloser
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
 
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
 
Lecture 7 Relay Coordination.pptx
Lecture 7 Relay Coordination.pptxLecture 7 Relay Coordination.pptx
Lecture 7 Relay Coordination.pptx
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment Designers
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
Insulation co cordination design
Insulation co cordination designInsulation co cordination design
Insulation co cordination design
 
Numerical analysis of short circuit testing & verification of a MCCB.
Numerical analysis of short circuit testing & verification of a MCCB.Numerical analysis of short circuit testing & verification of a MCCB.
Numerical analysis of short circuit testing & verification of a MCCB.
 
Protection & switchgear
Protection & switchgear  Protection & switchgear
Protection & switchgear
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protection
 

Dernier

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 

Dernier (20)

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 

Auto reclosers

  • 2. Commercial ACRs are governed by the ANSI/IEEE C37.60, IEC 62271-111 and IEC 62271-200 standards.
  • 3. • 80-90% of the line faults are short lived (transient) and can be removed faster if the disturbed phase is disconnected from the system momentarily so that the arc is extinguished. • If the fault is not cleared at first attempt then a double or triple attempt of isolation and reclosure can be made. If the fault still persists then breaker is permanantly opened. • Auto-reclosing helps to maintain stability & synchronism in EHV systems. Automatic Circuit Recloser (ACR) • If recloser is unsuccessful the auto-reclose relay locks out the circuit breaker. Some schemes provide a lockout relay with a flag, with provision of a contact for remote alarm. The circuit breaker can then only be closed by hand. • This action can be arranged to reset the auto-reclose relay element automatically. CB lock-out
  • 7. • The initial reclosure can be high speed (0.2 -0.5sec) or delayed for 3 - 5 seconds. This allows for de-ionization time for fault arc. • Typical schedule might be instantaneous, followed by 30sec, or 35sec, followed by 15sec. If the circuit still continues to trip, the fault is declared as permanent and the recloser is locked out. • Reclosers use three phase and single phase oil or vacuum circuit breakers for overhead distribution lines. • With underground network, faults tend to be more often permanent and reclosers are not recommended. • In case of large synchronous motors, distributed generators or induction motor loads, it is recommended that sufficient time is allowed for under-frequency relays to trip these sources of back emf out-of-the-circuit.
  • 8. Application Application Methodology Requirements Renewable Connection Modern Recloser Controllers use ANSI 25 Synchrocheck, 59N Neutral Voltage Displacement, Synchrophasors, ANSI 25A Auto-Synchronizer and other voltage protection Voltage Sensing on both sides of Recloser Substation Circuit Breakers Using Reclosers installed in a Substation where peak fault currents do not exceed the maximum rated interrupting capacity, usually only Rural Substations. Typically maximum bus fault currents below 16kA
  • 9. Application Application Methodology Requirements Single Wire Earth Return Network Protection A Single Phase Recloser unit can be deployed. SWER network design topology is discouraged in modern electrical engineering due to safety reasons, but due to cost savings it is sometimes deployed. Single Phase Recloser can be used to improve safety on these lines Single Phase Recloser Single Phase Laterals Permanent faults are typically 3 phase lockout, despite the ability to lock single phases, as the risk of circulating currents is high. Single Triple Recloser or Single Phase Recloser System
  • 10. Application Application Methodology Requirements Mid- Feeder Protection Conventional recloser deployment Conventional recloser Fire risk mitigation Not required as SEF protection pickup at 500mA removes 80% risk of fire start. Recloser with SGF/SEF capability at 500mA. Smart grid distribution network automation Centralized or distributed Remote communication through SCADA or otherwise configurable from controller
  • 11. Recloser control panel 1. Local human-machine interface 2. Indicator lights 3. Front panel push-buttons 4. Hot line tagging feature 5. Front mounted RS-232 port 6. Separate open and close 7. push-buttons
  • 12. Recloser selection Reclosers have to be selected by considering the following factors. • Voltage Rating • Continuous current Rating : This is the maximum load current the recloser has to carry. • Maximum Symmetrical Interrupting Rating: The maximum symmetrical fault current should not exceed this rating. • Minimum Tripping current : This is the minimum fault current that a recloser will clear. It is equal to two times the continuous current rating. Usually tolerance is ±10%. This decides the sensitivity of the recloser.
  • 13. Source : IEEE Tutorial Course 80EH0157 - 8 - PWR Rated Maximum Voltage kV rms Current Rating (Amperes) Continuous Current Rating Symmetrical Interrupting Rating at Maximum Volts Singlephase recloser 15.5 50 1250 15.5 100 2000 15.5 280 4000 15.5 560 8000 27.0 100 2500 27.0 280 4000 38.0 560 8000 Threephaserecloser 15.0 50 1250 15.5 100 2000 15.5 280 4000 15.5 400 4000 15.5 560 8000 15.5 560 16000
  • 14. EXAMPLE Consider a three phase distribution system with a single phase tap as shown. Maximum load on this single phase tap is 40A and that on three phase line is 200A. Fault currents at F1 ,F2 , F3 and F4 are also shown in the Table . Select the ratings of reclosers at A and B.
  • 15. EXAMPLE Recloser at B Max. load current on this tap= 40A Recloser max. current rating= 40x1.5= 60A (25-50% larger is taken considering load growth) Max. single phase fault current at F3= 1750A So, recloser marked in green is selected from table Min. tripping current= continuous current rating x2m10%= 100x2m10%= 220A Min. fault current in that line at F4= 250A Thus 220A recloser will be able to protect entire line Line voltage= 11kV hence recloser rated maximum voltage should be= 15.5 kV rms
  • 16. EXAMPLE Recloser at A Max. load current on the three phase line= 200A Recloser max. current rating= 200x1.25= 250A (25-50% larger is taken considering load growth) Max. single phase fault current at F1= 3500A So, recloser marked in red is selected from table Min. tripping current= continuous current rating x2m10%= 280x2m10%= 616A Min. fault current in that line at F2= 280A Thus 280A recloser will NOT be able to protect entire line Hence, in order to increase sensitivity ground relay can be added here.