1. Samsung SDI EV Battery
Manufacturing Plan
Edmond Kwok
Chris Suk
SJSU ENGR297G
2. Overview
• Mission statement
• Demand forecast
• Product information
• Process flow
• Bill of material
• Equipment selection
• Plant layout
• Labor
• Yields and uptime
• Ramp plan
• Cost of goods
• Cost analysis: manual vs full automation assembly
SJSU ENGR297G
3. Mission Statement
Samsung SDI will build a third battery production line dedicated
to automotive applications to meet increasing EV demands.
Location: Ulsan, South Korea
Capacity: 5 GWh per year
Operation: 24/7/365, 3 shifts
Labor: Semi-automated
Supply capacity by 2020: ~100,000 EV per year
SJSU ENGR297G
4. SDI supplies batteries for…
BMW i3 – 22 kWh
BMW i8 (HEV) – 7.1 kWh
BMW X5 eDrive (future) – 9.0 kWh
BMW i5 (future?)
Chrysler Fiat 500e – 24 kWh
BMW CEO says they will make 100,000 electric vehicles a year by 2020
SJSU ENGR297G
5. EV Range
• 3-4 miles range per kWh
• 200 miles range is ideal
SJSU ENGR297G
24. Labor
Average wage – Ulsan, South Korea
Operator: $14.77 per hour
Manufacturing Supervision: $22.24 per hour
Manufacturing Engineer: $31.79 per hour
Overhead: 38%
Direct labor cost: $18,208,516
Indirect labor cost: $11,075,320
SJSU ENGR297G
32. Assembly: Manual vs Automation
Manual assembly
7 assembly lines
$1.75 million capital
49 operators
90% process yield
Automated assembly
3 automated lines
$9 million capital
3 operators
97% process yield
SJSU ENGR297G
33. Assembly: Manual vs Automation
Manual assembly
7 assembly lines
$1.75 million capital
49 operators
90% process yield
Automated assembly
3 automated lines
$9 million capital
3 operators
97% process yield
SJSU ENGR297G
34. Assembly: Manual vs Automation
Manual assembly
7 assembly lines
$1.75 million capital
49 operators
90% process yield
Automated assembly
3 automated lines
$9 million capital
3 operators
97% process yield
SJSU ENGR297G
35. Assembly: Manual vs Automation
Manual assembly
7 assembly lines
$1.75 million capital
49 operators
90% process yield
Automated assembly
3 automated lines
$9 million capital
3 operators
97% process yield
SJSU ENGR297G
36. Assembly: Manual vs Automation
Manual assembly
7 assembly lines
$1.75 million capital
49 operators
90% process yield
Automated assembly
3 automated lines
$9 million capital
3 operators
97% process yield
$53.5 million per year difference!
SJSU ENGR297G