Major milestones achieved at Tanjung Bin 4
11 Jun 2015
After several months of hard work, the team at Tanjung Bin 4 have overcome huge obstacles and
are now celebrating two milestones that point the way to the plant’s completion.
 Unforeseeable ground movements impacted progress at the Tanjung Bin site causing 10 months
of delay to the project
 The entire project has been re-thought to mitigate the effects of the delay
 On 31 May and 03 June 2015, two pivotal milestones achieved – first fire on oil for the boiler, and
turbine on turning gear
For the last two years, we’ve heard little from the Alstom teams at Tanjung Bin, although they have been
working around the clock. They have shown not just endurance, but exceptional skill and resilience in
adapting to difficult conditions, after unforeseen physical conditions affected the Bunker Bay and Mill
foundations. Now that these significant milestones – first fire on oil for the boiler, and turbine on turning gear
– have been reached, the teams are ready to tell their story.
“Normally, we would communicate regularly on the progress of a project,” says Marc Villemin, Project
Director. “But with drastic changes and drawbacks taking place, we have been focussed on dealing with the
adversity to minimise the overall impact on the project completion date.”
Ground movement on the site – February 2013
The Tanjung Bin EPC project started on the 01 March 2012. The 1000MW ultra supercritical coal-fired
power plant is a turnkey project, with Alstom as the leader of a Consortium with its partners, Mudajaya and
Shin Eversendai, who collectively are supplying overall plant engineering, global procurement and logistics,
civil, electrical and mechanical construction, plus comprehensive commissioning.
The initial project plan put completion at 48 months, with an end-date of March 2016. All was progressing
smoothly until February 2013, when the soil movement was discovered which affected the foundations of
the bunker bay. This unforeseeable circumstance led to a complete demolition and reconstruction of the
bunker bay area, adding an extra 5 months to the project timeline.
Extra delays as more problems unfold
As a knock-on effect of the reconstruction, erection of the turbine hall was consequently delayed due to the
civil interface between the structures, and the main arterial routes for the electrical and piping links between
each of the buildings needed to be reconsidered. The entire site plan was compromised. These issues
added extra delay, putting the project 10 months behind schedule.
As well as the lost time, the team had to contend
with further soil movements as they worked to overcome the initial problem.
“We have had to completely re-think the project,” says Marc. “We had to re-design the foundations,
implement new technologies and completely re-sequence the erection of the whole plant. We had to invent
new methodologies of construction and to think laterally to overcome the obstructions.”
Teams worked harder, smarter and faster to make up lost time
The Alstom teams rose to the challenge, putting in hours of extra labour and working 24/7 to regain lost
time. They also stepped in where contractors and consortium partner teams were struggling, showing
leadership and initiative.
 The excavation plan for the entire site was revised due to the soil instability. Excavations were
limited in depth as much as possible.
 Critical areas were reprioritised, with some elements being descoped. The contractor workforce
was reinforced, with expertise deployed where it was needed most and work accelerated so teams
were operating 24 hours a day.
 The construction sequence of the different parts of the site was changed, effectively re-drawing the
entire plan for the project
First fire and turbine on barring
On May 31st, the teams celebrated the first fire on oil in Tanjung Bin’s boiler, and on June 3rd, the turbine
was successfully rotated on turning gear. After so much anticipation, it was a great relief when both
procedures went without a hitch.
“This achievement is the result of everybody’s hard work,” says Marc, “and I congratulate the site teams
who have been the ones implementing this success.”
Delays reduced significantly
There’s more good news for the team – the delay has now been reduced from 10 months to nearing 2
months. There is still some way to go, and staff will continue to work all-out to achieve the planned
synchronisation date of September 2015. There is lots more commissioning work to be done and the team
is focused on their next milestones – steam blow and firing the boiler on coal.
“These milestones are major steps towards the completion of the project. The challenge is not over and the
game far from being won, but with such a team and such motivation, I am confident we will make it,” says
Marc.
“Step by step, we are bringing the project back on course, despite the difficulties and challenges, and
leaving behind the unexpected events we had to face.”

Contenu connexe

Tendances

Al Qasr Mall presentation
Al Qasr Mall presentationAl Qasr Mall presentation
Al Qasr Mall presentationMamdouh Attia
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Crosstown TO
 
Leaside & Laird Construction Liason Committee Meeting
Leaside & Laird Construction Liason Committee MeetingLeaside & Laird Construction Liason Committee Meeting
Leaside & Laird Construction Liason Committee MeetingCrosstown TO
 
Williams pipelineprojectspotlight
Williams pipelineprojectspotlightWilliams pipelineprojectspotlight
Williams pipelineprojectspotlightISCT GROUP US LLC
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Fairfax County
 
Monthly Progress Report Sample
Monthly Progress Report SampleMonthly Progress Report Sample
Monthly Progress Report SampleElias Ibrahim
 
Proposed project could extend life of Marigold Mine - News4Nevada
Proposed project could extend life of Marigold Mine - News4NevadaProposed project could extend life of Marigold Mine - News4Nevada
Proposed project could extend life of Marigold Mine - News4NevadaRon Leiken
 
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...IRJET Journal
 
cpwss to piler and 8other habitations
cpwss to piler and 8other habitationscpwss to piler and 8other habitations
cpwss to piler and 8other habitationsPrasadreddy Nemmali
 
Cedarvale & Forest Hill Construction Update (January 2022)
Cedarvale & Forest Hill Construction Update (January 2022)Cedarvale & Forest Hill Construction Update (January 2022)
Cedarvale & Forest Hill Construction Update (January 2022)Crosstown TO
 
CPAC Meeting 3-21-05
CPAC Meeting 3-21-05CPAC Meeting 3-21-05
CPAC Meeting 3-21-05HartTWI
 

Tendances (20)

T Elmaddah Portfolio
T Elmaddah PortfolioT Elmaddah Portfolio
T Elmaddah Portfolio
 
KASHIF DADA - Projects List
KASHIF DADA - Projects ListKASHIF DADA - Projects List
KASHIF DADA - Projects List
 
Al Qasr Mall presentation
Al Qasr Mall presentationAl Qasr Mall presentation
Al Qasr Mall presentation
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
 
Leaside & Laird Construction Liason Committee Meeting
Leaside & Laird Construction Liason Committee MeetingLeaside & Laird Construction Liason Committee Meeting
Leaside & Laird Construction Liason Committee Meeting
 
BAZYAN CCPP – Phase 1
BAZYAN CCPP – Phase 1BAZYAN CCPP – Phase 1
BAZYAN CCPP – Phase 1
 
Client Presentation
Client PresentationClient Presentation
Client Presentation
 
Winter 2012 Newsletter
Winter 2012 NewsletterWinter 2012 Newsletter
Winter 2012 Newsletter
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
[Belle] Resume
[Belle] Resume[Belle] Resume
[Belle] Resume
 
Williams pipelineprojectspotlight
Williams pipelineprojectspotlightWilliams pipelineprojectspotlight
Williams pipelineprojectspotlight
 
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
Hayfield Road Project Citizens Association Meeting Jan. 17, 2018
 
Monthly Progress Report Sample
Monthly Progress Report SampleMonthly Progress Report Sample
Monthly Progress Report Sample
 
Electromech
Electromech Electromech
Electromech
 
Proposed project could extend life of Marigold Mine - News4Nevada
Proposed project could extend life of Marigold Mine - News4NevadaProposed project could extend life of Marigold Mine - News4Nevada
Proposed project could extend life of Marigold Mine - News4Nevada
 
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
IRJET- Comparative Study of Top down & Bottom up Method Construction Schedule...
 
cpwss to piler and 8other habitations
cpwss to piler and 8other habitationscpwss to piler and 8other habitations
cpwss to piler and 8other habitations
 
Jan-Dec 2008
Jan-Dec 2008Jan-Dec 2008
Jan-Dec 2008
 
Cedarvale & Forest Hill Construction Update (January 2022)
Cedarvale & Forest Hill Construction Update (January 2022)Cedarvale & Forest Hill Construction Update (January 2022)
Cedarvale & Forest Hill Construction Update (January 2022)
 
CPAC Meeting 3-21-05
CPAC Meeting 3-21-05CPAC Meeting 3-21-05
CPAC Meeting 3-21-05
 

En vedette

Tha price of knowledge.doc
Tha price of knowledge.docTha price of knowledge.doc
Tha price of knowledge.docAmen-Ra!
 
علم التفسير من كتاب النقاية
علم التفسير من كتاب النقايةعلم التفسير من كتاب النقاية
علم التفسير من كتاب النقايةabuhuraira_algazawi
 
00 2015 acceder_plataforma
00 2015 acceder_plataforma00 2015 acceder_plataforma
00 2015 acceder_plataformaZuleika
 
[EB1 da Estalagem] BEST of Carnaval 2010
[EB1 da Estalagem] BEST of Carnaval 2010[EB1 da Estalagem] BEST of Carnaval 2010
[EB1 da Estalagem] BEST of Carnaval 2010AEC-Inglês
 
Thinking Highways - Distracted 12-09
Thinking Highways - Distracted 12-09Thinking Highways - Distracted 12-09
Thinking Highways - Distracted 12-09David Pickeral
 
Canva for iPad Tutorial
Canva for iPad TutorialCanva for iPad Tutorial
Canva for iPad TutorialGrace C.
 
Employee Training on California Labor Law
Employee Training on California Labor LawEmployee Training on California Labor Law
Employee Training on California Labor LawStacey Maffei, CPP
 
SB 1 Simple Present BE 1
SB 1 Simple Present BE 1SB 1 Simple Present BE 1
SB 1 Simple Present BE 1Ola763
 
Humasol info presentation 2015 2016
Humasol info presentation 2015 2016Humasol info presentation 2015 2016
Humasol info presentation 2015 2016Humasol_vzw
 
Holland Resume 9.8.15
Holland Resume 9.8.15Holland Resume 9.8.15
Holland Resume 9.8.15John Holland
 
SSTG: Consell de barri de Vallvidrera, el Tibidabo i les Planes
SSTG: Consell de barri de Vallvidrera, el Tibidabo i les PlanesSSTG: Consell de barri de Vallvidrera, el Tibidabo i les Planes
SSTG: Consell de barri de Vallvidrera, el Tibidabo i les PlanesAjuntament de Barcelona
 

En vedette (19)

Music video conventions
Music video conventions Music video conventions
Music video conventions
 
Tha price of knowledge.doc
Tha price of knowledge.docTha price of knowledge.doc
Tha price of knowledge.doc
 
علم التفسير من كتاب النقاية
علم التفسير من كتاب النقايةعلم التفسير من كتاب النقاية
علم التفسير من كتاب النقاية
 
00 2015 acceder_plataforma
00 2015 acceder_plataforma00 2015 acceder_plataforma
00 2015 acceder_plataforma
 
[EB1 da Estalagem] BEST of Carnaval 2010
[EB1 da Estalagem] BEST of Carnaval 2010[EB1 da Estalagem] BEST of Carnaval 2010
[EB1 da Estalagem] BEST of Carnaval 2010
 
Thinking Highways - Distracted 12-09
Thinking Highways - Distracted 12-09Thinking Highways - Distracted 12-09
Thinking Highways - Distracted 12-09
 
Canva for iPad Tutorial
Canva for iPad TutorialCanva for iPad Tutorial
Canva for iPad Tutorial
 
Colores crivstiuyfg
Colores crivstiuyfgColores crivstiuyfg
Colores crivstiuyfg
 
MCPDA SDP CLE 2015
MCPDA SDP CLE 2015MCPDA SDP CLE 2015
MCPDA SDP CLE 2015
 
Unidad ii lectores rss
Unidad ii lectores rssUnidad ii lectores rss
Unidad ii lectores rss
 
Uneix-te! Voluntariat ambiental a les Terres de l'Ebre
Uneix-te! Voluntariat ambiental a les Terres de l'Ebre Uneix-te! Voluntariat ambiental a les Terres de l'Ebre
Uneix-te! Voluntariat ambiental a les Terres de l'Ebre
 
Employee Training on California Labor Law
Employee Training on California Labor LawEmployee Training on California Labor Law
Employee Training on California Labor Law
 
SB 1 Simple Present BE 1
SB 1 Simple Present BE 1SB 1 Simple Present BE 1
SB 1 Simple Present BE 1
 
IPC Research
IPC ResearchIPC Research
IPC Research
 
Music Video Pitch
Music Video PitchMusic Video Pitch
Music Video Pitch
 
Humasol info presentation 2015 2016
Humasol info presentation 2015 2016Humasol info presentation 2015 2016
Humasol info presentation 2015 2016
 
Comenzar
ComenzarComenzar
Comenzar
 
Holland Resume 9.8.15
Holland Resume 9.8.15Holland Resume 9.8.15
Holland Resume 9.8.15
 
SSTG: Consell de barri de Vallvidrera, el Tibidabo i les Planes
SSTG: Consell de barri de Vallvidrera, el Tibidabo i les PlanesSSTG: Consell de barri de Vallvidrera, el Tibidabo i les Planes
SSTG: Consell de barri de Vallvidrera, el Tibidabo i les Planes
 

Similaire à Project Milestones quotes from Project Director

Key to a successful EGTL Site
Key to a successful EGTL SiteKey to a successful EGTL Site
Key to a successful EGTL SiteNick Tasker
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docxhyacinthshackley2629
 
McConnell Dowell Mastermyne - Made to Mine
McConnell Dowell Mastermyne - Made to MineMcConnell Dowell Mastermyne - Made to Mine
McConnell Dowell Mastermyne - Made to MineChris Swaine
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E HeilandErik Heiland
 
DarlingtonRefurb_PerfomanceReport_July2014
DarlingtonRefurb_PerfomanceReport_July2014DarlingtonRefurb_PerfomanceReport_July2014
DarlingtonRefurb_PerfomanceReport_July2014Piyush Sharma
 
CV-English_Bartilotti-16-12-2014
CV-English_Bartilotti-16-12-2014CV-English_Bartilotti-16-12-2014
CV-English_Bartilotti-16-12-2014Manuel Bartilotti
 
EAE Newsletter - Nov - Issue #6
EAE Newsletter - Nov - Issue #6EAE Newsletter - Nov - Issue #6
EAE Newsletter - Nov - Issue #6Darcy Pearson
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129James Zhang (Chi, Zhang)
 
Lewis Chapman Resume
Lewis Chapman ResumeLewis Chapman Resume
Lewis Chapman ResumeLewis Chapman
 
SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover
SELA Region Q4-2013 Thru-tubing Recompletion  and Thru-tubing WorkoverSELA Region Q4-2013 Thru-tubing Recompletion  and Thru-tubing Workover
SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing WorkoverKevin Kelley
 
Current Public Resume
Current Public ResumeCurrent Public Resume
Current Public ResumeLee Riopel
 
dave resume sept 2015
dave resume sept 2015dave resume sept 2015
dave resume sept 2015Dave Hoover
 

Similaire à Project Milestones quotes from Project Director (20)

Oil Search Nius
Oil Search NiusOil Search Nius
Oil Search Nius
 
Key to a successful EGTL Site
Key to a successful EGTL SiteKey to a successful EGTL Site
Key to a successful EGTL Site
 
10-3 Term Paper Submission QSO-680 Seminar in.docx
10-3 Term Paper Submission                    QSO-680 Seminar in.docx10-3 Term Paper Submission                    QSO-680 Seminar in.docx
10-3 Term Paper Submission QSO-680 Seminar in.docx
 
McConnell Dowell Mastermyne - Made to Mine
McConnell Dowell Mastermyne - Made to MineMcConnell Dowell Mastermyne - Made to Mine
McConnell Dowell Mastermyne - Made to Mine
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland
 
CV PMG
CV PMGCV PMG
CV PMG
 
Project Analysis - PPT
Project Analysis - PPTProject Analysis - PPT
Project Analysis - PPT
 
DarlingtonRefurb_PerfomanceReport_July2014
DarlingtonRefurb_PerfomanceReport_July2014DarlingtonRefurb_PerfomanceReport_July2014
DarlingtonRefurb_PerfomanceReport_July2014
 
CV Latest Rosdi PL381
CV Latest Rosdi PL381CV Latest Rosdi PL381
CV Latest Rosdi PL381
 
CV-English_Bartilotti-16-12-2014
CV-English_Bartilotti-16-12-2014CV-English_Bartilotti-16-12-2014
CV-English_Bartilotti-16-12-2014
 
EAE Newsletter - Nov - Issue #6
EAE Newsletter - Nov - Issue #6EAE Newsletter - Nov - Issue #6
EAE Newsletter - Nov - Issue #6
 
CV Peter Heinzelmann
CV Peter HeinzelmannCV Peter Heinzelmann
CV Peter Heinzelmann
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
 
Lewis Chapman Resume
Lewis Chapman ResumeLewis Chapman Resume
Lewis Chapman Resume
 
SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover
SELA Region Q4-2013 Thru-tubing Recompletion  and Thru-tubing WorkoverSELA Region Q4-2013 Thru-tubing Recompletion  and Thru-tubing Workover
SELA Region Q4-2013 Thru-tubing Recompletion and Thru-tubing Workover
 
CV at 2015 Aug
CV at 2015 AugCV at 2015 Aug
CV at 2015 Aug
 
project management UOC-1
project management UOC-1project management UOC-1
project management UOC-1
 
Current Public Resume
Current Public ResumeCurrent Public Resume
Current Public Resume
 
dave resume sept 2015
dave resume sept 2015dave resume sept 2015
dave resume sept 2015
 
CV Bonnell - March 2015
CV Bonnell - March 2015CV Bonnell - March 2015
CV Bonnell - March 2015
 

Project Milestones quotes from Project Director

  • 1. Major milestones achieved at Tanjung Bin 4 11 Jun 2015 After several months of hard work, the team at Tanjung Bin 4 have overcome huge obstacles and are now celebrating two milestones that point the way to the plant’s completion.  Unforeseeable ground movements impacted progress at the Tanjung Bin site causing 10 months of delay to the project  The entire project has been re-thought to mitigate the effects of the delay  On 31 May and 03 June 2015, two pivotal milestones achieved – first fire on oil for the boiler, and turbine on turning gear For the last two years, we’ve heard little from the Alstom teams at Tanjung Bin, although they have been working around the clock. They have shown not just endurance, but exceptional skill and resilience in adapting to difficult conditions, after unforeseen physical conditions affected the Bunker Bay and Mill foundations. Now that these significant milestones – first fire on oil for the boiler, and turbine on turning gear – have been reached, the teams are ready to tell their story. “Normally, we would communicate regularly on the progress of a project,” says Marc Villemin, Project Director. “But with drastic changes and drawbacks taking place, we have been focussed on dealing with the adversity to minimise the overall impact on the project completion date.” Ground movement on the site – February 2013 The Tanjung Bin EPC project started on the 01 March 2012. The 1000MW ultra supercritical coal-fired power plant is a turnkey project, with Alstom as the leader of a Consortium with its partners, Mudajaya and Shin Eversendai, who collectively are supplying overall plant engineering, global procurement and logistics, civil, electrical and mechanical construction, plus comprehensive commissioning. The initial project plan put completion at 48 months, with an end-date of March 2016. All was progressing smoothly until February 2013, when the soil movement was discovered which affected the foundations of the bunker bay. This unforeseeable circumstance led to a complete demolition and reconstruction of the
  • 2. bunker bay area, adding an extra 5 months to the project timeline. Extra delays as more problems unfold As a knock-on effect of the reconstruction, erection of the turbine hall was consequently delayed due to the civil interface between the structures, and the main arterial routes for the electrical and piping links between each of the buildings needed to be reconsidered. The entire site plan was compromised. These issues added extra delay, putting the project 10 months behind schedule. As well as the lost time, the team had to contend with further soil movements as they worked to overcome the initial problem. “We have had to completely re-think the project,” says Marc. “We had to re-design the foundations, implement new technologies and completely re-sequence the erection of the whole plant. We had to invent new methodologies of construction and to think laterally to overcome the obstructions.” Teams worked harder, smarter and faster to make up lost time The Alstom teams rose to the challenge, putting in hours of extra labour and working 24/7 to regain lost time. They also stepped in where contractors and consortium partner teams were struggling, showing leadership and initiative.  The excavation plan for the entire site was revised due to the soil instability. Excavations were limited in depth as much as possible.  Critical areas were reprioritised, with some elements being descoped. The contractor workforce was reinforced, with expertise deployed where it was needed most and work accelerated so teams were operating 24 hours a day.  The construction sequence of the different parts of the site was changed, effectively re-drawing the
  • 3. entire plan for the project First fire and turbine on barring On May 31st, the teams celebrated the first fire on oil in Tanjung Bin’s boiler, and on June 3rd, the turbine was successfully rotated on turning gear. After so much anticipation, it was a great relief when both procedures went without a hitch. “This achievement is the result of everybody’s hard work,” says Marc, “and I congratulate the site teams who have been the ones implementing this success.” Delays reduced significantly There’s more good news for the team – the delay has now been reduced from 10 months to nearing 2 months. There is still some way to go, and staff will continue to work all-out to achieve the planned synchronisation date of September 2015. There is lots more commissioning work to be done and the team is focused on their next milestones – steam blow and firing the boiler on coal. “These milestones are major steps towards the completion of the project. The challenge is not over and the game far from being won, but with such a team and such motivation, I am confident we will make it,” says Marc. “Step by step, we are bringing the project back on course, despite the difficulties and challenges, and leaving behind the unexpected events we had to face.”