SlideShare une entreprise Scribd logo
1  sur  26
Page 1 
Modernization of Local Public 
Services in the Republic of 
Moldova 
Overview of the project
Modernization of Local Public Services 
in the Republic of Moldova 
• Based on bilateral government negotiations Moldova-Germany Nov 
Page 2 
2009 
• Duration 6 years: 1/2010 – 12/2015 
• Main Institutional Counterpart: Ministry of Regional Development 
and Construction and the Regional Development Agencies 
• German contribution: €17.9 million 
• Technical assistance – €10.6 million 
• German Investment Support – €7.3 million 
• Cofinancing by Romanian Government of €0.7 million 
• Cofinancing by Swedish Government of €5.5 million 
• Cofinancing by European Union €5.0 million
Page 3 
German contribution of €17.9 million 
• Overall: €17.9 million 
• Technical assistance – €10.6 million 
• 2010 – 2013: €5.1 Mio million 
• 2014: €2.0 million 
• Pilot Project Investments: €3.6 million 
• German Investment Support – €7.3 million 
• Investments 
• 12 RDA staff (4 North / 5 Centre / 3 South)
Cofinancing by Romanian Government of €0.7 million 
Page 4 
Pilot project - capital investment and procurement of equipment 
Improving water supply and sewerage in Rosu village, Cahul rayon
Cofinancing by Swedish Government of €5.5 million 
Page 5 
€3.3 million (2012 – 2014) 
• Regional Operational Plans on WSS, SWM and EE in public buildings 
developed (North, Centre and South RDAs). 
• Regional indicators on a. m. areas established and data-bases 
developed. 
• Models of transparent and participatory design processes for 
preparing Regional Operational Plans drafted, based on sector focus 
groups with participation of key stakeholders from the respective sectors, 
civil society and the private sector, as well as external specialists. 
• Formal mechanisms and procedures for coordination and 
collaboration with responsible sector ministries (Environment and 
Economy) established.
Cofinancing by Swedish Government of €5.5 million 
€2.2 million (2014) 
• Support to regional development institutions and local public 
authorities. 
> Implementation of investment projects to improve local public 
service delivery. 
Benchmarks: 
• Investment projects prepared for Regional Development to 
Page 6 
ready-for-procurement stage (volume €6 million). 
• Project implementation management by RDAs without major 
shortcomings (related investment funding provided by 
Germany). 
• Improved management of projects by LPAs, supported by 
certified energy auditors, financed by the National Fund for 
Energy Efficiency.
Page 7 
Cofinancing by European Union €5.0 million 
Overall 
objec-tive 
Support Moldova in advancing its economic, social and territorial cohesion with 
focus on development of policy, legal, institutional and developmental 
framework for an effective development policy for Moldova’s regions. 
Purpose • Facilitate a regional planning process leading to the development of a 
project pipeline relevant to specified areas and concerns of MD’s RD and 
EU Cohesion Policy. 
• Develop capacities essential to sustain the above objectives and support the 
wider regional development process. 
Expec-ted 
results 
• Detailed regional plans covering five thematic fields essential to the 
development of Moldova’s regions (WSS, SWM, local roads of key 
importance) from these updated regional operational plans for each 
region (N, S, C). 
• Updated regional operational plans for each region where RD institutions 
are in place. 
• Verified capacity among responsible bodies relevant to the above results, 
including capacity to continuously manage a project pipeline. 
• Pipeline of ready to go, ready to finance and ready to procure projects.
MLPS Project Objective 
Improved Local Public Serviсes in selected villages and towns in the 
Republic of Moldova 
Page 8 
• Intervention Area I 
• Investments in innovative technologies and infrastructure; 
• Increased capacities and modernised management of services; 
• Enhanced inter-municipal cooperation and local participation. 
• Intervention Area II 
• Enhanced coordination between institutions at local, regional and 
central levels through coherent planning and programming of 
investments; 
• Regional sector planning for WSS, SWM, EE in public buildings; 
• Projects Pipeline, prioritised and ready for implementation.
Basic Assumption 
• Planned activities lead to progress towards achieving 
Page 9 
the IA1 Objective: 
Local Public Authorities effectively 
cooperate and manage 
improvements of 
local public services 
in the selected 
communities in pilot rayons
Success Indicators 
• 25 planned pilot measures for improvement of local 
public services implemented in 3 project priority sectors 
(WSS, SWM, EE). 
• LPAs signed 70 formal agreements for joint delivery of 
Page 10 
local public services in 3 project priority sectors. 
• In 35 communities, 50% of implemented measures in 3 
project priority sectors have improved women’s access 
to local public services.
Page 11 
Energy Efficient Street Lighting in 
Soroca rayon 
Improvement of WSS services in 
Riscani rayon 
Improvement of Solid Waste 
Management Services in Soldanesti, 
Rezina and Floresti rayons 
Energy Efficiency in Public Buildings 
in Orhei rayon, Orhei Regional 
Hospital 
Energy Efficiency in Public Buildings 
in Nisporeni rayon, Nisporeni 
Regional Hospital 
Improvement of WSS services in 
Iargara, Leova rayon 
Improvement of WSS services in 
Cahul rayon 
Background Map Source: MRDC
Page 12 
1. 
Integrated 
local planning 
and 
programming 
Efficient 
Local 
Public 
Services 
2. 
Improvement of 
cooperation 
between 
LPAs 
3. 
Investments to 
optimise 
infrastructure 
to provide 
local public 
services 
4. 
Increased 
capacities of 
LPAs and 
service 
providers 
5. 
Mobilisation and 
awareness 
raising 
of the 
population 
Support Model 
Comprehensive 
Approach 
… for enhanced 
sustainability
Page 13 
Basic presumption 
• Planned activities lead to the Result 
Intervention Area 2: 
Regional and local public authorities effectively plan 
strategic investments in three priority sectors (water 
supply and sanitation, solid waste management and 
energy efficiency of public buildings).
Page 14 
Main success indicators 
• The three Regional Development Agencies have facilitated the 
development of viable project concepts in priority sectors, 
equivalent to the total amount of EUR 170 million. 
• 70% of stakeholders from 30 Local Public Authorities involved in the 
Local Planning and Programming expresses their satisfaction 
regarding the capabilities to facilitate/promote Regional 
Development Agencies. 
• 75% of the project concepts promoted by the Regional 
Development Agencies are examined in detail in terms of 
environmental impact, taking into account national regulations.
Scope of Work Regional Planning and Programming 
Page 15 
• Development of Regional Sector Programmes for: 
• Water Supply and Sanitation (WSS); 
• Solid Waste Management (SWM); 
• Energy Efficiency (EE) in Public Buildings ; 
• Regional and Local Roads. 
• Project pipeline of ‘ready to finance projects’ (including feasibility studies, 
environmental impact assessments, technical design documents, etc.) for 
investments in the above sectors. 
• Capacity development of local and regional development actors.
Page 16 
Regional Planning and Programming 
Activities (2012 – 2014): 
• Update Regional Development Strategies through inclusion of new 
priority area Energy Efficiency in Public Buildings. 
• Update Regional Operational Plans in Water and Sanitation, Solid 
Waste Management and Energy Efficiency in Public Buildings. 
• Capacity Development for Regional Development Agencies and Regional 
Development Councils. 
Partners and Mediators: 
• Financial support through Swedish Sida. 
• Three Regional Development Agencies. 
• Three Regional Development Councils. 
• MRDC, Ministry of Economy, Agency for Energy Efficiency, Ministry of 
Environment.
Page 17 
Intervention’s 
logics Regional 
Regional 
planning (A1) 
Planning (1) 
Project 
Project’s 
identification 
Identification 
(B1) 
Project 
Project’s 
development 
Development 
(A2) 
Targeted 
Sector 
Reform (3B) 
Reform in the 
concerned area 
Financing 
(3) 
(B2) 
Sustainable projects and services 
introduce sustainable changes
Page 18 
Stages of Progression in Project Development 
Swedish Contribution 
EU 
Possible 
Project 
Concept (PPC) 
Viable Project 
Concept 
(VPC) 
‘Ready -to –Go’ Project 
(RGP) (final project) 
proposed for funding 
EU Contribution 
Stages and donors
Key stages in project concepts identification and 
development, according to the RSP approach 
• PPC – project idea that is relevant to and consistent with the Regional 
Page 19 
Development Strategy 
• VPC – project idea which has been sufficiently developed to clearly 
identify key features; sound understanding of the results/positive 
change the project can bring; 
• RGP – final project proposal, not necessarily a full feasibility study, but 
has all the required documentation, tender books, local commitments, 
etc. 
• Project Pipeline – a mechanism whereby a series of projects is 
developed from conception towards readiness. Projects in the pipeline 
can have different degrees of readiness, qualities, and speeds, but it 
must be ensured that poor quality projects do not progress through the 
pipeline.
Regional Sector Working Groups with representatives of LPAs, public service providers, line 
ministries, and specialised decentralised nstitutions formed by the RDAs under the auspices of the 
MRDC in each sector, each region. 
Page 20 
Introduction: sector regional planning 
and programming as an instrument, 
participatory and integrated approach 
Current sector status, legal, institutional 
framework, 
development of the RD vision for 
improved services, 
The elaboration and discussion of 
scenarios, 
facilitating project concepts development 
Drafting of Regional Sector 
Programmes, consultation and 
approval, project concepts 
development 
Regional Sector Working Groups
Page 21 
Regional Sector Programmes 
The Regional Sector Programme is an operational tool which will be used to 
support the development of better investment projects in Moldova. 
• Align the respective Sector Policies, Regional Development Strategies and 
local priorities; 
• Facilitate sound decision-making based on transparent criteria; 
• Contribute to investment attraction in the covered sectors: 
• Solid Waste Management ; 
• Water Supply and Sanitation; 
• Energy Efficiency of Public Buildings; 
• Regional and Local Roads.
Next stages: 2014 – 2015 
Develop projects: 
• From concept to as ready to go as possible. 
• At least estimated €140 million for projects. 
• Likely investments of around €80 million in SWM, €30 million in WSS, 
Page 22 
€25 million in EE (PB), €40 million in roads. 
To complete this work. It is likely that at some stage: 
• Further assistance will be needed from other donors/IFIs (i.e. to take 
over some projects from us at an appropriate point). 
• There should be an alignment between the medium-term public 
investment programme and the developing pipeline of ‘real’ 
investments. 
• Substantial and prioritised sector reform needs to move in tandem (as 
already indicated in part in Regional Sector Planning documents). 
In short , we need ‘an agenda for change’ and for ‘gear shift” .
MLPS Project Pipeline 
Projections for project development volumes ready by end of 2015 
Page 23 
Requirements for 
implementation: 
Sector ~ No. of 
Projects 
>>> Capacitated implementing agencies > RDAs 
>>> Funding 
~ Million € 
(totals) 
EE (Jan 2014) 
EE (end 2015) 
9 
13-15 
9 
12 
SWM 3 30 
WSS 10 28 
Roads 10 30 
Total 47 109
Page 24 
Visualisation of a Project Pipeline 
15 concepts 
10 projects 
7 projects 
20 concepts 
Possible 
Project 
Concept 
Viable 
Project 
Concept 
‘Ready -to –Go’ Project 
(final project) proposed 
for funding
Page 25 
Capacity Development for Regional and Cross- 
Border Cooperation in the Republic of Moldova 
• Strengthening the capacity of the LPAs for identification and 
development of project proposals; 
• Training courses conducted by the RDAs, in cooperation with local 
NGOs; 
• Assistance in launch of project proposals for EU and National Fund for 
Regional Development programmes; 
• Medium-term collaboration with the Public Administration Academy by 
mainstreaming elements of training and lessons learnt in a national 
curriculum; 
• Support to the Antenna Office for implementation of EU Programs; 
• Support in implementation of the EU Strategy for the Danube region.
Page 26 
Welcome to invest. 
German Development Cooperation through GIZ 
Chișinău, 31a Bulgară str., 
T + 373 22 22-83-19 
F + 373 22 00-02-38 
Internet: www.giz.de, www.serviciilocale.md

Contenu connexe

Tendances

George Chabrzyk
George ChabrzykGeorge Chabrzyk
George ChabrzykPPF5Serbia
 
Bottom up Budgeting
Bottom up BudgetingBottom up Budgeting
Bottom up BudgetingAlvin Almo
 
Klaudija Lutovska- IPA CBC & IPARD 2
Klaudija Lutovska- IPA CBC & IPARD 2Klaudija Lutovska- IPA CBC & IPARD 2
Klaudija Lutovska- IPA CBC & IPARD 2Klaudija Lutovska
 
Broadway corridor-planning-program-presentation-may-2018
Broadway corridor-planning-program-presentation-may-2018Broadway corridor-planning-program-presentation-may-2018
Broadway corridor-planning-program-presentation-may-2018Kathryn Huang
 
Mukul Asher: Analysing the Bangalore Municipal Budget
Mukul Asher: Analysing the Bangalore Municipal BudgetMukul Asher: Analysing the Bangalore Municipal Budget
Mukul Asher: Analysing the Bangalore Municipal BudgetThe Takshashila Institution
 
Budget planning training 14022014
Budget planning training 14022014Budget planning training 14022014
Budget planning training 14022014PPF5Serbia
 
Chandigarh vipul mehta
Chandigarh vipul mehtaChandigarh vipul mehta
Chandigarh vipul mehtavipularch
 
Rural Planning Organizations: Rural Transportation Planning in Pennsylvania
Rural Planning Organizations: Rural Transportation Planning in PennsylvaniaRural Planning Organizations: Rural Transportation Planning in Pennsylvania
Rural Planning Organizations: Rural Transportation Planning in PennsylvaniaRPO America
 
Preparation of IPA II Action Documents
Preparation of IPA II Action DocumentsPreparation of IPA II Action Documents
Preparation of IPA II Action DocumentsPPF5Serbia
 
Day2 session1 costing and mtef
Day2 session1 costing and mtefDay2 session1 costing and mtef
Day2 session1 costing and mtefOECD Environment
 
Preparing IPA II Sector Planning Documents - Serbia
Preparing IPA II Sector Planning Documents - SerbiaPreparing IPA II Sector Planning Documents - Serbia
Preparing IPA II Sector Planning Documents - SerbiaPPF5Serbia
 
Davao bottom up budgeting
Davao bottom up budgetingDavao bottom up budgeting
Davao bottom up budgetingWBKDC
 
Twenty Years of Rural Transportation Planning: Revisiting and Renewing North ...
Twenty Years of Rural Transportation Planning: Revisiting and Renewing North ...Twenty Years of Rural Transportation Planning: Revisiting and Renewing North ...
Twenty Years of Rural Transportation Planning: Revisiting and Renewing North ...RPO America
 
Donor board digest - April-June 2019
Donor board digest - April-June 2019Donor board digest - April-June 2019
Donor board digest - April-June 2019Decentralizationgovua
 
2017 i 1_blaz_barboric_attractivedanube
2017 i 1_blaz_barboric_attractivedanube2017 i 1_blaz_barboric_attractivedanube
2017 i 1_blaz_barboric_attractivedanubeATTRACTIVE DANUBE
 
Status of Transportation Priorities Plan Update
Status of Transportation Priorities Plan UpdateStatus of Transportation Priorities Plan Update
Status of Transportation Priorities Plan UpdateFairfax County
 

Tendances (20)

George Chabrzyk
George ChabrzykGeorge Chabrzyk
George Chabrzyk
 
Bottom up Budgeting
Bottom up BudgetingBottom up Budgeting
Bottom up Budgeting
 
Klaudija Lutovska- IPA CBC & IPARD 2
Klaudija Lutovska- IPA CBC & IPARD 2Klaudija Lutovska- IPA CBC & IPARD 2
Klaudija Lutovska- IPA CBC & IPARD 2
 
Broadway corridor-planning-program-presentation-may-2018
Broadway corridor-planning-program-presentation-may-2018Broadway corridor-planning-program-presentation-may-2018
Broadway corridor-planning-program-presentation-may-2018
 
Mukul Asher: Analysing the Bangalore Municipal Budget
Mukul Asher: Analysing the Bangalore Municipal BudgetMukul Asher: Analysing the Bangalore Municipal Budget
Mukul Asher: Analysing the Bangalore Municipal Budget
 
Budget planning training 14022014
Budget planning training 14022014Budget planning training 14022014
Budget planning training 14022014
 
Chandigarh vipul mehta
Chandigarh vipul mehtaChandigarh vipul mehta
Chandigarh vipul mehta
 
Rural Planning Organizations: Rural Transportation Planning in Pennsylvania
Rural Planning Organizations: Rural Transportation Planning in PennsylvaniaRural Planning Organizations: Rural Transportation Planning in Pennsylvania
Rural Planning Organizations: Rural Transportation Planning in Pennsylvania
 
Preparation of IPA II Action Documents
Preparation of IPA II Action DocumentsPreparation of IPA II Action Documents
Preparation of IPA II Action Documents
 
Day2 session1 costing and mtef
Day2 session1 costing and mtefDay2 session1 costing and mtef
Day2 session1 costing and mtef
 
Preparing IPA II Sector Planning Documents - Serbia
Preparing IPA II Sector Planning Documents - SerbiaPreparing IPA II Sector Planning Documents - Serbia
Preparing IPA II Sector Planning Documents - Serbia
 
Davao bottom up budgeting
Davao bottom up budgetingDavao bottom up budgeting
Davao bottom up budgeting
 
Twenty Years of Rural Transportation Planning: Revisiting and Renewing North ...
Twenty Years of Rural Transportation Planning: Revisiting and Renewing North ...Twenty Years of Rural Transportation Planning: Revisiting and Renewing North ...
Twenty Years of Rural Transportation Planning: Revisiting and Renewing North ...
 
Donor board digest - April-June 2019
Donor board digest - April-June 2019Donor board digest - April-June 2019
Donor board digest - April-June 2019
 
Presentation, ReSPA, 7th Regional Public Procurement Conference, Vlora, 9-10 ...
Presentation, ReSPA, 7th Regional Public Procurement Conference, Vlora, 9-10 ...Presentation, ReSPA, 7th Regional Public Procurement Conference, Vlora, 9-10 ...
Presentation, ReSPA, 7th Regional Public Procurement Conference, Vlora, 9-10 ...
 
2017 i 1_blaz_barboric_attractivedanube
2017 i 1_blaz_barboric_attractivedanube2017 i 1_blaz_barboric_attractivedanube
2017 i 1_blaz_barboric_attractivedanube
 
2015 bub
2015 bub2015 bub
2015 bub
 
Marina Ilic
Marina IlicMarina Ilic
Marina Ilic
 
Status of Transportation Priorities Plan Update
Status of Transportation Priorities Plan UpdateStatus of Transportation Priorities Plan Update
Status of Transportation Priorities Plan Update
 
Pc i social sector
Pc i social sectorPc i social sector
Pc i social sector
 

En vedette

Planificare strategică şi programare - Tudor Meşina, director, ADR Centru
Planificare strategică şi programare - Tudor Meşina, director, ADR Centru  Planificare strategică şi programare - Tudor Meşina, director, ADR Centru
Planificare strategică şi programare - Tudor Meşina, director, ADR Centru GIZ Moldova
 
Alexandr Muravschi, consultant senior GIZ - Planificarea sectorială regională...
Alexandr Muravschi, consultant senior GIZ - Planificarea sectorială regională...Alexandr Muravschi, consultant senior GIZ - Planificarea sectorială regională...
Alexandr Muravschi, consultant senior GIZ - Planificarea sectorială regională...GIZ Moldova
 
Rolul MDRC în diversificarea resurselor financiare ce contribuie la realizare...
Rolul MDRC în diversificarea resurselor financiare ce contribuie la realizare...Rolul MDRC în diversificarea resurselor financiare ce contribuie la realizare...
Rolul MDRC în diversificarea resurselor financiare ce contribuie la realizare...GIZ Moldova
 
Alexandr Muravschi, consultant senior GIZ - Prezentarea progreselor în cadrul...
Alexandr Muravschi, consultant senior GIZ - Prezentarea progreselor în cadrul...Alexandr Muravschi, consultant senior GIZ - Prezentarea progreselor în cadrul...
Alexandr Muravschi, consultant senior GIZ - Prezentarea progreselor în cadrul...GIZ Moldova
 
Prezentare MLPS Comitet Director din 12 martie 2013
Prezentare MLPS Comitet Director din 12 martie 2013Prezentare MLPS Comitet Director din 12 martie 2013
Prezentare MLPS Comitet Director din 12 martie 2013GIZ Moldova
 
De la idee la realizare – parcursul unui proiect de dezvoltare regională - Se...
De la idee la realizare – parcursul unui proiect de dezvoltare regională - Se...De la idee la realizare – parcursul unui proiect de dezvoltare regională - Se...
De la idee la realizare – parcursul unui proiect de dezvoltare regională - Se...GIZ Moldova
 
Iurii Socol, șef, Direcția reglementări tehnico-economice, MDRC - Performanța...
Iurii Socol, șef, Direcția reglementări tehnico-economice, MDRC - Performanța...Iurii Socol, șef, Direcția reglementări tehnico-economice, MDRC - Performanța...
Iurii Socol, șef, Direcția reglementări tehnico-economice, MDRC - Performanța...GIZ Moldova
 
Prezentarea proiectului "Modernizarea serviciilor publice locale în Republica...
Prezentarea proiectului "Modernizarea serviciilor publice locale în Republica...Prezentarea proiectului "Modernizarea serviciilor publice locale în Republica...
Prezentarea proiectului "Modernizarea serviciilor publice locale în Republica...GIZ Moldova
 
Tatiana Badan, Preşedintele Congresului Autorităţilor Locale din Moldova (CAL...
Tatiana Badan, Preşedintele Congresului Autorităţilor Locale din Moldova (CAL...Tatiana Badan, Preşedintele Congresului Autorităţilor Locale din Moldova (CAL...
Tatiana Badan, Preşedintele Congresului Autorităţilor Locale din Moldova (CAL...GIZ Moldova
 
Ghenadie Vîrtos, Cancelaria de Stat - Rolul Cooperării Intercomunitare în ca...
Ghenadie Vîrtos, Cancelaria de Stat  - Rolul Cooperării Intercomunitare în ca...Ghenadie Vîrtos, Cancelaria de Stat  - Rolul Cooperării Intercomunitare în ca...
Ghenadie Vîrtos, Cancelaria de Stat - Rolul Cooperării Intercomunitare în ca...GIZ Moldova
 
Igor Malai, Ministerul Dezvoltării Regionale şi Construcţiilor - Cooperarea i...
Igor Malai, Ministerul Dezvoltării Regionale şi Construcţiilor - Cooperarea i...Igor Malai, Ministerul Dezvoltării Regionale şi Construcţiilor - Cooperarea i...
Igor Malai, Ministerul Dezvoltării Regionale şi Construcţiilor - Cooperarea i...GIZ Moldova
 
Ariana Fuerst, junior advisor of GIZ - Intermunicipal cooperation. Internatio...
Ariana Fuerst, junior advisor of GIZ - Intermunicipal cooperation. Internatio...Ariana Fuerst, junior advisor of GIZ - Intermunicipal cooperation. Internatio...
Ariana Fuerst, junior advisor of GIZ - Intermunicipal cooperation. Internatio...GIZ Moldova
 
Veaceslav Bălănel, vicepreşedintele raionul Cahul - Cooperarea intercomunitar...
Veaceslav Bălănel, vicepreşedintele raionul Cahul - Cooperarea intercomunitar...Veaceslav Bălănel, vicepreşedintele raionul Cahul - Cooperarea intercomunitar...
Veaceslav Bălănel, vicepreşedintele raionul Cahul - Cooperarea intercomunitar...GIZ Moldova
 
Ioan Leitner, Director General - Prezentarea experienţei S.C. APASERV Satu Ma...
Ioan Leitner, Director General - Prezentarea experienţei S.C. APASERV Satu Ma...Ioan Leitner, Director General - Prezentarea experienţei S.C. APASERV Satu Ma...
Ioan Leitner, Director General - Prezentarea experienţei S.C. APASERV Satu Ma...GIZ Moldova
 
Rafal Andrzej Stanek, OCDE - “INTER-MUNICIPAL COOPERATION: concept and forms...
Rafal Andrzej Stanek, OCDE -  “INTER-MUNICIPAL COOPERATION: concept and forms...Rafal Andrzej Stanek, OCDE -  “INTER-MUNICIPAL COOPERATION: concept and forms...
Rafal Andrzej Stanek, OCDE - “INTER-MUNICIPAL COOPERATION: concept and forms...GIZ Moldova
 
Krzysztof Kolanowski, Director - Launching of Information Center for Local Au...
Krzysztof Kolanowski, Director - Launching of Information Center for Local Au...Krzysztof Kolanowski, Director - Launching of Information Center for Local Au...
Krzysztof Kolanowski, Director - Launching of Information Center for Local Au...GIZ Moldova
 

En vedette (16)

Planificare strategică şi programare - Tudor Meşina, director, ADR Centru
Planificare strategică şi programare - Tudor Meşina, director, ADR Centru  Planificare strategică şi programare - Tudor Meşina, director, ADR Centru
Planificare strategică şi programare - Tudor Meşina, director, ADR Centru
 
Alexandr Muravschi, consultant senior GIZ - Planificarea sectorială regională...
Alexandr Muravschi, consultant senior GIZ - Planificarea sectorială regională...Alexandr Muravschi, consultant senior GIZ - Planificarea sectorială regională...
Alexandr Muravschi, consultant senior GIZ - Planificarea sectorială regională...
 
Rolul MDRC în diversificarea resurselor financiare ce contribuie la realizare...
Rolul MDRC în diversificarea resurselor financiare ce contribuie la realizare...Rolul MDRC în diversificarea resurselor financiare ce contribuie la realizare...
Rolul MDRC în diversificarea resurselor financiare ce contribuie la realizare...
 
Alexandr Muravschi, consultant senior GIZ - Prezentarea progreselor în cadrul...
Alexandr Muravschi, consultant senior GIZ - Prezentarea progreselor în cadrul...Alexandr Muravschi, consultant senior GIZ - Prezentarea progreselor în cadrul...
Alexandr Muravschi, consultant senior GIZ - Prezentarea progreselor în cadrul...
 
Prezentare MLPS Comitet Director din 12 martie 2013
Prezentare MLPS Comitet Director din 12 martie 2013Prezentare MLPS Comitet Director din 12 martie 2013
Prezentare MLPS Comitet Director din 12 martie 2013
 
De la idee la realizare – parcursul unui proiect de dezvoltare regională - Se...
De la idee la realizare – parcursul unui proiect de dezvoltare regională - Se...De la idee la realizare – parcursul unui proiect de dezvoltare regională - Se...
De la idee la realizare – parcursul unui proiect de dezvoltare regională - Se...
 
Iurii Socol, șef, Direcția reglementări tehnico-economice, MDRC - Performanța...
Iurii Socol, șef, Direcția reglementări tehnico-economice, MDRC - Performanța...Iurii Socol, șef, Direcția reglementări tehnico-economice, MDRC - Performanța...
Iurii Socol, șef, Direcția reglementări tehnico-economice, MDRC - Performanța...
 
Prezentarea proiectului "Modernizarea serviciilor publice locale în Republica...
Prezentarea proiectului "Modernizarea serviciilor publice locale în Republica...Prezentarea proiectului "Modernizarea serviciilor publice locale în Republica...
Prezentarea proiectului "Modernizarea serviciilor publice locale în Republica...
 
Tatiana Badan, Preşedintele Congresului Autorităţilor Locale din Moldova (CAL...
Tatiana Badan, Preşedintele Congresului Autorităţilor Locale din Moldova (CAL...Tatiana Badan, Preşedintele Congresului Autorităţilor Locale din Moldova (CAL...
Tatiana Badan, Preşedintele Congresului Autorităţilor Locale din Moldova (CAL...
 
Ghenadie Vîrtos, Cancelaria de Stat - Rolul Cooperării Intercomunitare în ca...
Ghenadie Vîrtos, Cancelaria de Stat  - Rolul Cooperării Intercomunitare în ca...Ghenadie Vîrtos, Cancelaria de Stat  - Rolul Cooperării Intercomunitare în ca...
Ghenadie Vîrtos, Cancelaria de Stat - Rolul Cooperării Intercomunitare în ca...
 
Igor Malai, Ministerul Dezvoltării Regionale şi Construcţiilor - Cooperarea i...
Igor Malai, Ministerul Dezvoltării Regionale şi Construcţiilor - Cooperarea i...Igor Malai, Ministerul Dezvoltării Regionale şi Construcţiilor - Cooperarea i...
Igor Malai, Ministerul Dezvoltării Regionale şi Construcţiilor - Cooperarea i...
 
Ariana Fuerst, junior advisor of GIZ - Intermunicipal cooperation. Internatio...
Ariana Fuerst, junior advisor of GIZ - Intermunicipal cooperation. Internatio...Ariana Fuerst, junior advisor of GIZ - Intermunicipal cooperation. Internatio...
Ariana Fuerst, junior advisor of GIZ - Intermunicipal cooperation. Internatio...
 
Veaceslav Bălănel, vicepreşedintele raionul Cahul - Cooperarea intercomunitar...
Veaceslav Bălănel, vicepreşedintele raionul Cahul - Cooperarea intercomunitar...Veaceslav Bălănel, vicepreşedintele raionul Cahul - Cooperarea intercomunitar...
Veaceslav Bălănel, vicepreşedintele raionul Cahul - Cooperarea intercomunitar...
 
Ioan Leitner, Director General - Prezentarea experienţei S.C. APASERV Satu Ma...
Ioan Leitner, Director General - Prezentarea experienţei S.C. APASERV Satu Ma...Ioan Leitner, Director General - Prezentarea experienţei S.C. APASERV Satu Ma...
Ioan Leitner, Director General - Prezentarea experienţei S.C. APASERV Satu Ma...
 
Rafal Andrzej Stanek, OCDE - “INTER-MUNICIPAL COOPERATION: concept and forms...
Rafal Andrzej Stanek, OCDE -  “INTER-MUNICIPAL COOPERATION: concept and forms...Rafal Andrzej Stanek, OCDE -  “INTER-MUNICIPAL COOPERATION: concept and forms...
Rafal Andrzej Stanek, OCDE - “INTER-MUNICIPAL COOPERATION: concept and forms...
 
Krzysztof Kolanowski, Director - Launching of Information Center for Local Au...
Krzysztof Kolanowski, Director - Launching of Information Center for Local Au...Krzysztof Kolanowski, Director - Launching of Information Center for Local Au...
Krzysztof Kolanowski, Director - Launching of Information Center for Local Au...
 

Similaire à Prezentare MLPS Comitet Director din 19 noiembrie 2012

MLPS Presentation for the Steering Committee Session from February 21, 2014
MLPS Presentation for the Steering Committee Session from February 21, 2014MLPS Presentation for the Steering Committee Session from February 21, 2014
MLPS Presentation for the Steering Committee Session from February 21, 2014GIZ Moldova
 
MLPS Presentation of the Steering Committee Session of 8 May 2015
MLPS Presentation of the Steering Committee Session of 8 May 2015MLPS Presentation of the Steering Committee Session of 8 May 2015
MLPS Presentation of the Steering Committee Session of 8 May 2015GIZ Moldova
 
MSPL presentation of the steering committee session of 8 october 2015
MSPL presentation of the steering committee session of 8 october 2015MSPL presentation of the steering committee session of 8 october 2015
MSPL presentation of the steering committee session of 8 october 2015GIZ Moldova
 
Presentation of the Steering Committee Session from 22 October 2014
Presentation of the Steering Committee Session from 22 October 2014Presentation of the Steering Committee Session from 22 October 2014
Presentation of the Steering Committee Session from 22 October 2014GIZ Moldova
 
Monitoring Committee Meeting, Q1, 2017
Monitoring Committee Meeting, Q1, 2017Monitoring Committee Meeting, Q1, 2017
Monitoring Committee Meeting, Q1, 2017GIZ Moldova
 
day2_10program_indicators_serbia_eng_1.pptx
day2_10program_indicators_serbia_eng_1.pptxday2_10program_indicators_serbia_eng_1.pptx
day2_10program_indicators_serbia_eng_1.pptxmilenastokanovic
 
MSPL presentation of the operational steering committee session of 21 septemb...
MSPL presentation of the operational steering committee session of 21 septemb...MSPL presentation of the operational steering committee session of 21 septemb...
MSPL presentation of the operational steering committee session of 21 septemb...GIZ Moldova
 
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...FIREMED project
 
Communication Strategy - Eng
Communication Strategy - EngCommunication Strategy - Eng
Communication Strategy - EngOleksandr Virnyk
 
Topics of the future programme public consultation
Topics of the future programme public consultationTopics of the future programme public consultation
Topics of the future programme public consultationInterreg Baltic Sea Region
 
Smart cities project guide Union Europea
Smart cities project guide Union EuropeaSmart cities project guide Union Europea
Smart cities project guide Union EuropeaSmart City
 
Presentation - Workshop on Scaling-up the implementation of nature-based solu...
Presentation - Workshop on Scaling-up the implementation of nature-based solu...Presentation - Workshop on Scaling-up the implementation of nature-based solu...
Presentation - Workshop on Scaling-up the implementation of nature-based solu...OECD Environment
 
1st issue of LiCEA newsletter
1st issue of LiCEA newsletter1st issue of LiCEA newsletter
1st issue of LiCEA newsletterJan Šašek
 
2011 report project supporting rbec transition 1
2011 report project supporting rbec transition 12011 report project supporting rbec transition 1
2011 report project supporting rbec transition 1Marcela Villanueva
 
Financing regional and local government investments: Case examples on ways to...
Financing regional and local government investments: Case examples on ways to...Financing regional and local government investments: Case examples on ways to...
Financing regional and local government investments: Case examples on ways to...OECD CFE
 
URABCT InfoDay Spain, 25 November 2014
URABCT InfoDay Spain, 25 November 2014URABCT InfoDay Spain, 25 November 2014
URABCT InfoDay Spain, 25 November 2014stasafranko
 

Similaire à Prezentare MLPS Comitet Director din 19 noiembrie 2012 (20)

MLPS Presentation for the Steering Committee Session from February 21, 2014
MLPS Presentation for the Steering Committee Session from February 21, 2014MLPS Presentation for the Steering Committee Session from February 21, 2014
MLPS Presentation for the Steering Committee Session from February 21, 2014
 
MLPS Presentation of the Steering Committee Session of 8 May 2015
MLPS Presentation of the Steering Committee Session of 8 May 2015MLPS Presentation of the Steering Committee Session of 8 May 2015
MLPS Presentation of the Steering Committee Session of 8 May 2015
 
MSPL presentation of the steering committee session of 8 october 2015
MSPL presentation of the steering committee session of 8 october 2015MSPL presentation of the steering committee session of 8 october 2015
MSPL presentation of the steering committee session of 8 october 2015
 
Presentation of the Steering Committee Session from 22 October 2014
Presentation of the Steering Committee Session from 22 October 2014Presentation of the Steering Committee Session from 22 October 2014
Presentation of the Steering Committee Session from 22 October 2014
 
Monitoring Committee Meeting, Q1, 2017
Monitoring Committee Meeting, Q1, 2017Monitoring Committee Meeting, Q1, 2017
Monitoring Committee Meeting, Q1, 2017
 
day2_10program_indicators_serbia_eng_1.pptx
day2_10program_indicators_serbia_eng_1.pptxday2_10program_indicators_serbia_eng_1.pptx
day2_10program_indicators_serbia_eng_1.pptx
 
MSPL presentation of the operational steering committee session of 21 septemb...
MSPL presentation of the operational steering committee session of 21 septemb...MSPL presentation of the operational steering committee session of 21 septemb...
MSPL presentation of the operational steering committee session of 21 septemb...
 
European Structural and Investment Funds: Delivery of the Programmes, Dr Caro...
European Structural and Investment Funds: Delivery of the Programmes, Dr Caro...European Structural and Investment Funds: Delivery of the Programmes, Dr Caro...
European Structural and Investment Funds: Delivery of the Programmes, Dr Caro...
 
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
Presentation of Mr. José Manuel Fernández Riveiro - Secretariat of the Union ...
 
Communication Strategy - Eng
Communication Strategy - EngCommunication Strategy - Eng
Communication Strategy - Eng
 
Topics of the future programme public consultation
Topics of the future programme public consultationTopics of the future programme public consultation
Topics of the future programme public consultation
 
Smart cities project guide Union Europea
Smart cities project guide Union EuropeaSmart cities project guide Union Europea
Smart cities project guide Union Europea
 
04.karelina
04.karelina04.karelina
04.karelina
 
Oulu: The implementation of the climate change programme as a cross administr...
Oulu: The implementation of the climate change programme as a cross administr...Oulu: The implementation of the climate change programme as a cross administr...
Oulu: The implementation of the climate change programme as a cross administr...
 
Presentation - Workshop on Scaling-up the implementation of nature-based solu...
Presentation - Workshop on Scaling-up the implementation of nature-based solu...Presentation - Workshop on Scaling-up the implementation of nature-based solu...
Presentation - Workshop on Scaling-up the implementation of nature-based solu...
 
1st issue of LiCEA newsletter
1st issue of LiCEA newsletter1st issue of LiCEA newsletter
1st issue of LiCEA newsletter
 
2011 report project supporting rbec transition 1
2011 report project supporting rbec transition 12011 report project supporting rbec transition 1
2011 report project supporting rbec transition 1
 
Financing regional and local government investments: Case examples on ways to...
Financing regional and local government investments: Case examples on ways to...Financing regional and local government investments: Case examples on ways to...
Financing regional and local government investments: Case examples on ways to...
 
SCTM Projects
SCTM ProjectsSCTM Projects
SCTM Projects
 
URABCT InfoDay Spain, 25 November 2014
URABCT InfoDay Spain, 25 November 2014URABCT InfoDay Spain, 25 November 2014
URABCT InfoDay Spain, 25 November 2014
 

Plus de GIZ Moldova

Steering Committee Meeting from 23 June, 2017
Steering Committee Meeting from 23 June, 2017Steering Committee Meeting from 23 June, 2017
Steering Committee Meeting from 23 June, 2017GIZ Moldova
 
Ședința Comitetului Director MSPL din 23 iunie 2017
Ședința Comitetului Director MSPL din 23 iunie 2017Ședința Comitetului Director MSPL din 23 iunie 2017
Ședința Comitetului Director MSPL din 23 iunie 2017GIZ Moldova
 
Ședința Comitetului de Monitorizare
Ședința Comitetului de MonitorizareȘedința Comitetului de Monitorizare
Ședința Comitetului de MonitorizareGIZ Moldova
 
Prezentarea MSPL pentru ședința comitetului director din 21 septembrie 2016
Prezentarea MSPL pentru ședința comitetului director din 21 septembrie 2016Prezentarea MSPL pentru ședința comitetului director din 21 septembrie 2016
Prezentarea MSPL pentru ședința comitetului director din 21 septembrie 2016GIZ Moldova
 
Eficientizarea energetică a clădirilor publice. Modulul 3: Sistemele tehnice ...
Eficientizarea energetică a clădirilor publice. Modulul 3: Sistemele tehnice ...Eficientizarea energetică a clădirilor publice. Modulul 3: Sistemele tehnice ...
Eficientizarea energetică a clădirilor publice. Modulul 3: Sistemele tehnice ...GIZ Moldova
 
Eficientizarea energetică a clădirilor publice. Modulul 2: Modernizarea energ...
Eficientizarea energetică a clădirilor publice. Modulul 2: Modernizarea energ...Eficientizarea energetică a clădirilor publice. Modulul 2: Modernizarea energ...
Eficientizarea energetică a clădirilor publice. Modulul 2: Modernizarea energ...GIZ Moldova
 
Eficientizarea energetică a clădirilor publice. Modulul 1: Energia și necesit...
Eficientizarea energetică a clădirilor publice. Modulul 1: Energia și necesit...Eficientizarea energetică a clădirilor publice. Modulul 1: Energia și necesit...
Eficientizarea energetică a clădirilor publice. Modulul 1: Energia și necesit...GIZ Moldova
 
Prezentarea MSPL pentru ședința comitetului director din 8 octombrie 2015
Prezentarea MSPL pentru ședința comitetului director din 8 octombrie 2015Prezentarea MSPL pentru ședința comitetului director din 8 octombrie 2015
Prezentarea MSPL pentru ședința comitetului director din 8 octombrie 2015GIZ Moldova
 
Prezentarea MSPL pentru Ședința Comitetului Director din 8 mai 2015
Prezentarea MSPL pentru Ședința Comitetului Director din 8 mai 2015Prezentarea MSPL pentru Ședința Comitetului Director din 8 mai 2015
Prezentarea MSPL pentru Ședința Comitetului Director din 8 mai 2015GIZ Moldova
 
Nota de proiect MSPL
Nota de proiect MSPLNota de proiect MSPL
Nota de proiect MSPLGIZ Moldova
 
Angela Dumitrasco - Satisfaction degree of stakeholders regarding the Regiona...
Angela Dumitrasco - Satisfaction degree of stakeholders regarding the Regiona...Angela Dumitrasco - Satisfaction degree of stakeholders regarding the Regiona...
Angela Dumitrasco - Satisfaction degree of stakeholders regarding the Regiona...GIZ Moldova
 
CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...
CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...
CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...GIZ Moldova
 
CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...
CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...
CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...GIZ Moldova
 
Angela Dumitrașco - Gradul de satisfacție al părților interesate față de capa...
Angela Dumitrașco - Gradul de satisfacție al părților interesate față de capa...Angela Dumitrașco - Gradul de satisfacție al părților interesate față de capa...
Angela Dumitrașco - Gradul de satisfacție al părților interesate față de capa...GIZ Moldova
 
Petru Veverița - Rezultatele sondajului privind nivelul de satisfacție al păr...
Petru Veverița - Rezultatele sondajului privind nivelul de satisfacție al păr...Petru Veverița - Rezultatele sondajului privind nivelul de satisfacție al păr...
Petru Veverița - Rezultatele sondajului privind nivelul de satisfacție al păr...GIZ Moldova
 
Prezentarea sumară a Planului de activități pentru 2015 - Servicii publice lo...
Prezentarea sumară a Planului de activități pentru 2015 - Servicii publice lo...Prezentarea sumară a Planului de activități pentru 2015 - Servicii publice lo...
Prezentarea sumară a Planului de activități pentru 2015 - Servicii publice lo...GIZ Moldova
 
Prezentarea rezultatelor preliminare din 2014 - Servicii publice locale
Prezentarea rezultatelor preliminare din 2014 - Servicii publice localePrezentarea rezultatelor preliminare din 2014 - Servicii publice locale
Prezentarea rezultatelor preliminare din 2014 - Servicii publice localeGIZ Moldova
 
Cancelaria de Stat - Monitorizarea și evaluarea politicilor publice
Cancelaria de Stat - Monitorizarea și evaluarea politicilor publiceCancelaria de Stat - Monitorizarea și evaluarea politicilor publice
Cancelaria de Stat - Monitorizarea și evaluarea politicilor publice GIZ Moldova
 
Dezvoltarea Regională și Monitorizarea și Evaluarea bazată pe Rezultate: Prop...
Dezvoltarea Regională și Monitorizarea și Evaluarea bazată pe Rezultate: Prop...Dezvoltarea Regională și Monitorizarea și Evaluarea bazată pe Rezultate: Prop...
Dezvoltarea Regională și Monitorizarea și Evaluarea bazată pe Rezultate: Prop...GIZ Moldova
 
Prezentarea rezultatelor preliminare din 2014 - Planificarea și programarea r...
Prezentarea rezultatelor preliminare din 2014 - Planificarea și programarea r...Prezentarea rezultatelor preliminare din 2014 - Planificarea și programarea r...
Prezentarea rezultatelor preliminare din 2014 - Planificarea și programarea r...GIZ Moldova
 

Plus de GIZ Moldova (20)

Steering Committee Meeting from 23 June, 2017
Steering Committee Meeting from 23 June, 2017Steering Committee Meeting from 23 June, 2017
Steering Committee Meeting from 23 June, 2017
 
Ședința Comitetului Director MSPL din 23 iunie 2017
Ședința Comitetului Director MSPL din 23 iunie 2017Ședința Comitetului Director MSPL din 23 iunie 2017
Ședința Comitetului Director MSPL din 23 iunie 2017
 
Ședința Comitetului de Monitorizare
Ședința Comitetului de MonitorizareȘedința Comitetului de Monitorizare
Ședința Comitetului de Monitorizare
 
Prezentarea MSPL pentru ședința comitetului director din 21 septembrie 2016
Prezentarea MSPL pentru ședința comitetului director din 21 septembrie 2016Prezentarea MSPL pentru ședința comitetului director din 21 septembrie 2016
Prezentarea MSPL pentru ședința comitetului director din 21 septembrie 2016
 
Eficientizarea energetică a clădirilor publice. Modulul 3: Sistemele tehnice ...
Eficientizarea energetică a clădirilor publice. Modulul 3: Sistemele tehnice ...Eficientizarea energetică a clădirilor publice. Modulul 3: Sistemele tehnice ...
Eficientizarea energetică a clădirilor publice. Modulul 3: Sistemele tehnice ...
 
Eficientizarea energetică a clădirilor publice. Modulul 2: Modernizarea energ...
Eficientizarea energetică a clădirilor publice. Modulul 2: Modernizarea energ...Eficientizarea energetică a clădirilor publice. Modulul 2: Modernizarea energ...
Eficientizarea energetică a clădirilor publice. Modulul 2: Modernizarea energ...
 
Eficientizarea energetică a clădirilor publice. Modulul 1: Energia și necesit...
Eficientizarea energetică a clădirilor publice. Modulul 1: Energia și necesit...Eficientizarea energetică a clădirilor publice. Modulul 1: Energia și necesit...
Eficientizarea energetică a clădirilor publice. Modulul 1: Energia și necesit...
 
Prezentarea MSPL pentru ședința comitetului director din 8 octombrie 2015
Prezentarea MSPL pentru ședința comitetului director din 8 octombrie 2015Prezentarea MSPL pentru ședința comitetului director din 8 octombrie 2015
Prezentarea MSPL pentru ședința comitetului director din 8 octombrie 2015
 
Prezentarea MSPL pentru Ședința Comitetului Director din 8 mai 2015
Prezentarea MSPL pentru Ședința Comitetului Director din 8 mai 2015Prezentarea MSPL pentru Ședința Comitetului Director din 8 mai 2015
Prezentarea MSPL pentru Ședința Comitetului Director din 8 mai 2015
 
Nota de proiect MSPL
Nota de proiect MSPLNota de proiect MSPL
Nota de proiect MSPL
 
Angela Dumitrasco - Satisfaction degree of stakeholders regarding the Regiona...
Angela Dumitrasco - Satisfaction degree of stakeholders regarding the Regiona...Angela Dumitrasco - Satisfaction degree of stakeholders regarding the Regiona...
Angela Dumitrasco - Satisfaction degree of stakeholders regarding the Regiona...
 
CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...
CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...
CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...
 
CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...
CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...
CIVIS - Gradul de satisfacție al părților interesate față de capacitățile Age...
 
Angela Dumitrașco - Gradul de satisfacție al părților interesate față de capa...
Angela Dumitrașco - Gradul de satisfacție al părților interesate față de capa...Angela Dumitrașco - Gradul de satisfacție al părților interesate față de capa...
Angela Dumitrașco - Gradul de satisfacție al părților interesate față de capa...
 
Petru Veverița - Rezultatele sondajului privind nivelul de satisfacție al păr...
Petru Veverița - Rezultatele sondajului privind nivelul de satisfacție al păr...Petru Veverița - Rezultatele sondajului privind nivelul de satisfacție al păr...
Petru Veverița - Rezultatele sondajului privind nivelul de satisfacție al păr...
 
Prezentarea sumară a Planului de activități pentru 2015 - Servicii publice lo...
Prezentarea sumară a Planului de activități pentru 2015 - Servicii publice lo...Prezentarea sumară a Planului de activități pentru 2015 - Servicii publice lo...
Prezentarea sumară a Planului de activități pentru 2015 - Servicii publice lo...
 
Prezentarea rezultatelor preliminare din 2014 - Servicii publice locale
Prezentarea rezultatelor preliminare din 2014 - Servicii publice localePrezentarea rezultatelor preliminare din 2014 - Servicii publice locale
Prezentarea rezultatelor preliminare din 2014 - Servicii publice locale
 
Cancelaria de Stat - Monitorizarea și evaluarea politicilor publice
Cancelaria de Stat - Monitorizarea și evaluarea politicilor publiceCancelaria de Stat - Monitorizarea și evaluarea politicilor publice
Cancelaria de Stat - Monitorizarea și evaluarea politicilor publice
 
Dezvoltarea Regională și Monitorizarea și Evaluarea bazată pe Rezultate: Prop...
Dezvoltarea Regională și Monitorizarea și Evaluarea bazată pe Rezultate: Prop...Dezvoltarea Regională și Monitorizarea și Evaluarea bazată pe Rezultate: Prop...
Dezvoltarea Regională și Monitorizarea și Evaluarea bazată pe Rezultate: Prop...
 
Prezentarea rezultatelor preliminare din 2014 - Planificarea și programarea r...
Prezentarea rezultatelor preliminare din 2014 - Planificarea și programarea r...Prezentarea rezultatelor preliminare din 2014 - Planificarea și programarea r...
Prezentarea rezultatelor preliminare din 2014 - Planificarea și programarea r...
 

Prezentare MLPS Comitet Director din 19 noiembrie 2012

  • 1. Page 1 Modernization of Local Public Services in the Republic of Moldova Overview of the project
  • 2. Modernization of Local Public Services in the Republic of Moldova • Based on bilateral government negotiations Moldova-Germany Nov Page 2 2009 • Duration 6 years: 1/2010 – 12/2015 • Main Institutional Counterpart: Ministry of Regional Development and Construction and the Regional Development Agencies • German contribution: €17.9 million • Technical assistance – €10.6 million • German Investment Support – €7.3 million • Cofinancing by Romanian Government of €0.7 million • Cofinancing by Swedish Government of €5.5 million • Cofinancing by European Union €5.0 million
  • 3. Page 3 German contribution of €17.9 million • Overall: €17.9 million • Technical assistance – €10.6 million • 2010 – 2013: €5.1 Mio million • 2014: €2.0 million • Pilot Project Investments: €3.6 million • German Investment Support – €7.3 million • Investments • 12 RDA staff (4 North / 5 Centre / 3 South)
  • 4. Cofinancing by Romanian Government of €0.7 million Page 4 Pilot project - capital investment and procurement of equipment Improving water supply and sewerage in Rosu village, Cahul rayon
  • 5. Cofinancing by Swedish Government of €5.5 million Page 5 €3.3 million (2012 – 2014) • Regional Operational Plans on WSS, SWM and EE in public buildings developed (North, Centre and South RDAs). • Regional indicators on a. m. areas established and data-bases developed. • Models of transparent and participatory design processes for preparing Regional Operational Plans drafted, based on sector focus groups with participation of key stakeholders from the respective sectors, civil society and the private sector, as well as external specialists. • Formal mechanisms and procedures for coordination and collaboration with responsible sector ministries (Environment and Economy) established.
  • 6. Cofinancing by Swedish Government of €5.5 million €2.2 million (2014) • Support to regional development institutions and local public authorities. > Implementation of investment projects to improve local public service delivery. Benchmarks: • Investment projects prepared for Regional Development to Page 6 ready-for-procurement stage (volume €6 million). • Project implementation management by RDAs without major shortcomings (related investment funding provided by Germany). • Improved management of projects by LPAs, supported by certified energy auditors, financed by the National Fund for Energy Efficiency.
  • 7. Page 7 Cofinancing by European Union €5.0 million Overall objec-tive Support Moldova in advancing its economic, social and territorial cohesion with focus on development of policy, legal, institutional and developmental framework for an effective development policy for Moldova’s regions. Purpose • Facilitate a regional planning process leading to the development of a project pipeline relevant to specified areas and concerns of MD’s RD and EU Cohesion Policy. • Develop capacities essential to sustain the above objectives and support the wider regional development process. Expec-ted results • Detailed regional plans covering five thematic fields essential to the development of Moldova’s regions (WSS, SWM, local roads of key importance) from these updated regional operational plans for each region (N, S, C). • Updated regional operational plans for each region where RD institutions are in place. • Verified capacity among responsible bodies relevant to the above results, including capacity to continuously manage a project pipeline. • Pipeline of ready to go, ready to finance and ready to procure projects.
  • 8. MLPS Project Objective Improved Local Public Serviсes in selected villages and towns in the Republic of Moldova Page 8 • Intervention Area I • Investments in innovative technologies and infrastructure; • Increased capacities and modernised management of services; • Enhanced inter-municipal cooperation and local participation. • Intervention Area II • Enhanced coordination between institutions at local, regional and central levels through coherent planning and programming of investments; • Regional sector planning for WSS, SWM, EE in public buildings; • Projects Pipeline, prioritised and ready for implementation.
  • 9. Basic Assumption • Planned activities lead to progress towards achieving Page 9 the IA1 Objective: Local Public Authorities effectively cooperate and manage improvements of local public services in the selected communities in pilot rayons
  • 10. Success Indicators • 25 planned pilot measures for improvement of local public services implemented in 3 project priority sectors (WSS, SWM, EE). • LPAs signed 70 formal agreements for joint delivery of Page 10 local public services in 3 project priority sectors. • In 35 communities, 50% of implemented measures in 3 project priority sectors have improved women’s access to local public services.
  • 11. Page 11 Energy Efficient Street Lighting in Soroca rayon Improvement of WSS services in Riscani rayon Improvement of Solid Waste Management Services in Soldanesti, Rezina and Floresti rayons Energy Efficiency in Public Buildings in Orhei rayon, Orhei Regional Hospital Energy Efficiency in Public Buildings in Nisporeni rayon, Nisporeni Regional Hospital Improvement of WSS services in Iargara, Leova rayon Improvement of WSS services in Cahul rayon Background Map Source: MRDC
  • 12. Page 12 1. Integrated local planning and programming Efficient Local Public Services 2. Improvement of cooperation between LPAs 3. Investments to optimise infrastructure to provide local public services 4. Increased capacities of LPAs and service providers 5. Mobilisation and awareness raising of the population Support Model Comprehensive Approach … for enhanced sustainability
  • 13. Page 13 Basic presumption • Planned activities lead to the Result Intervention Area 2: Regional and local public authorities effectively plan strategic investments in three priority sectors (water supply and sanitation, solid waste management and energy efficiency of public buildings).
  • 14. Page 14 Main success indicators • The three Regional Development Agencies have facilitated the development of viable project concepts in priority sectors, equivalent to the total amount of EUR 170 million. • 70% of stakeholders from 30 Local Public Authorities involved in the Local Planning and Programming expresses their satisfaction regarding the capabilities to facilitate/promote Regional Development Agencies. • 75% of the project concepts promoted by the Regional Development Agencies are examined in detail in terms of environmental impact, taking into account national regulations.
  • 15. Scope of Work Regional Planning and Programming Page 15 • Development of Regional Sector Programmes for: • Water Supply and Sanitation (WSS); • Solid Waste Management (SWM); • Energy Efficiency (EE) in Public Buildings ; • Regional and Local Roads. • Project pipeline of ‘ready to finance projects’ (including feasibility studies, environmental impact assessments, technical design documents, etc.) for investments in the above sectors. • Capacity development of local and regional development actors.
  • 16. Page 16 Regional Planning and Programming Activities (2012 – 2014): • Update Regional Development Strategies through inclusion of new priority area Energy Efficiency in Public Buildings. • Update Regional Operational Plans in Water and Sanitation, Solid Waste Management and Energy Efficiency in Public Buildings. • Capacity Development for Regional Development Agencies and Regional Development Councils. Partners and Mediators: • Financial support through Swedish Sida. • Three Regional Development Agencies. • Three Regional Development Councils. • MRDC, Ministry of Economy, Agency for Energy Efficiency, Ministry of Environment.
  • 17. Page 17 Intervention’s logics Regional Regional planning (A1) Planning (1) Project Project’s identification Identification (B1) Project Project’s development Development (A2) Targeted Sector Reform (3B) Reform in the concerned area Financing (3) (B2) Sustainable projects and services introduce sustainable changes
  • 18. Page 18 Stages of Progression in Project Development Swedish Contribution EU Possible Project Concept (PPC) Viable Project Concept (VPC) ‘Ready -to –Go’ Project (RGP) (final project) proposed for funding EU Contribution Stages and donors
  • 19. Key stages in project concepts identification and development, according to the RSP approach • PPC – project idea that is relevant to and consistent with the Regional Page 19 Development Strategy • VPC – project idea which has been sufficiently developed to clearly identify key features; sound understanding of the results/positive change the project can bring; • RGP – final project proposal, not necessarily a full feasibility study, but has all the required documentation, tender books, local commitments, etc. • Project Pipeline – a mechanism whereby a series of projects is developed from conception towards readiness. Projects in the pipeline can have different degrees of readiness, qualities, and speeds, but it must be ensured that poor quality projects do not progress through the pipeline.
  • 20. Regional Sector Working Groups with representatives of LPAs, public service providers, line ministries, and specialised decentralised nstitutions formed by the RDAs under the auspices of the MRDC in each sector, each region. Page 20 Introduction: sector regional planning and programming as an instrument, participatory and integrated approach Current sector status, legal, institutional framework, development of the RD vision for improved services, The elaboration and discussion of scenarios, facilitating project concepts development Drafting of Regional Sector Programmes, consultation and approval, project concepts development Regional Sector Working Groups
  • 21. Page 21 Regional Sector Programmes The Regional Sector Programme is an operational tool which will be used to support the development of better investment projects in Moldova. • Align the respective Sector Policies, Regional Development Strategies and local priorities; • Facilitate sound decision-making based on transparent criteria; • Contribute to investment attraction in the covered sectors: • Solid Waste Management ; • Water Supply and Sanitation; • Energy Efficiency of Public Buildings; • Regional and Local Roads.
  • 22. Next stages: 2014 – 2015 Develop projects: • From concept to as ready to go as possible. • At least estimated €140 million for projects. • Likely investments of around €80 million in SWM, €30 million in WSS, Page 22 €25 million in EE (PB), €40 million in roads. To complete this work. It is likely that at some stage: • Further assistance will be needed from other donors/IFIs (i.e. to take over some projects from us at an appropriate point). • There should be an alignment between the medium-term public investment programme and the developing pipeline of ‘real’ investments. • Substantial and prioritised sector reform needs to move in tandem (as already indicated in part in Regional Sector Planning documents). In short , we need ‘an agenda for change’ and for ‘gear shift” .
  • 23. MLPS Project Pipeline Projections for project development volumes ready by end of 2015 Page 23 Requirements for implementation: Sector ~ No. of Projects >>> Capacitated implementing agencies > RDAs >>> Funding ~ Million € (totals) EE (Jan 2014) EE (end 2015) 9 13-15 9 12 SWM 3 30 WSS 10 28 Roads 10 30 Total 47 109
  • 24. Page 24 Visualisation of a Project Pipeline 15 concepts 10 projects 7 projects 20 concepts Possible Project Concept Viable Project Concept ‘Ready -to –Go’ Project (final project) proposed for funding
  • 25. Page 25 Capacity Development for Regional and Cross- Border Cooperation in the Republic of Moldova • Strengthening the capacity of the LPAs for identification and development of project proposals; • Training courses conducted by the RDAs, in cooperation with local NGOs; • Assistance in launch of project proposals for EU and National Fund for Regional Development programmes; • Medium-term collaboration with the Public Administration Academy by mainstreaming elements of training and lessons learnt in a national curriculum; • Support to the Antenna Office for implementation of EU Programs; • Support in implementation of the EU Strategy for the Danube region.
  • 26. Page 26 Welcome to invest. German Development Cooperation through GIZ Chișinău, 31a Bulgară str., T + 373 22 22-83-19 F + 373 22 00-02-38 Internet: www.giz.de, www.serviciilocale.md