SlideShare une entreprise Scribd logo
1  sur  19
Virtual Commissioning + Real-Time Training =
Increased Performance & Profits
info@gses.com
2
Overview
• Gas conversion of existing coal power plant
• Project execution strategy for existing virtual simulator
• Benefits of having a simulator before plant gas startup
commissioning
3
Overview of Gas Conversion
• Increasingly stringent and uncertain regulatory environment
• Plus, falling natural gas prices
• These conditions have made converting existing coal-fired steam-
generating boilers to natural gas firing more and more attractive.
• Based on recent gas conversion announcements, existing coal units
generating a total of approximately 9,000 MW will be converted for
natural gas firing.
Source : Power Engineering Magazine (www.power-eng.com) – “Coal to Natural Gas Conversion – Drivers and Lessons”
4
Overview of Gas Conversion
The major drivers of this trend have been:
– Mercury and Air Toxics Standards (MATS) regulations
– New Source Review (NSR) settlements
– Natural Gas availability and pricing
– The uniqueness of each project to deliver electricity at the required
capacity to make it economically feasible to convert existing coal-fired
units to natural gas-firing capability.
Source : Power Engineering Magazine (www.power-eng.com) – “Coal to Natural Gas Conversion – Drivers and Lessons”
5
Simulator Considerations
• Using natural gas changes the heat absorption characteristics in the boiler
and convection pass. There are modifications that have to be made to
meet the designed steam temperatures and full boiler output.
• In addition, considerations have to be given to achieve low emission goals.
These modifications include:
– Gas Supply: Modifications to the gas supply and vent piping, installation of pressure-
reducing valve station.
– Boiler: Modifications to the radiation and/or convective area to help achieve original
steam temperatures, new burners and igniters, windbox modifications
– Flue Gas Recirculation (FGR): FGR to control NOX and steam temperatures by recycling a
portion of the flue gas from the economizer outlet back into the windbox
– Flue Gas System: Modifications to the Air & Gas System. Forced-draft/induced-draft fan
modifications and other control functions to maintain furnace pressure.
6
• From GSE: Two team members including an
engineering manager
• From DCS: One project engineer
• From plant: Energy production supervisor and two
shift supervisors
Resource Team
7
Overview of Project Execution Strategy
• Schedule
• DCS virtual configuration
• Project staging
• Discrepancy recording system
8
Schedule
Simulator Model Design Process
1. Conference call kickoff meeting
2. Model scope design review meeting
3. Model changes
4. FAT’ed DCS shipped to GSE
5. Integration & testing at GSE
9
Simulator Air & Gas Drawing
10
Simulator Fuel Gas Drawing
11
Simulator Boiler Drawing
12
DCS Virtual Configuration
• DCS was already converted to the DCS vendor’s
virtual controllers
• FAT’ed DCS shipped to GSE
• 3 Dual monitor operator stations
13
Plant Simulator Layout
14
Project Staging
Staged at GSE facility
1. Access to model engineer(s)
2. Plant operators
3. After initial integration, remote access provided to
DCS vendor for support
15
Discrepancy Recording System
GSE Mantis DR System
• An online system where users can be easily added
• Different sections available for different types of
discrepancies
• Severity of discrepancy can be assigned
• Discrepancy can be assigned to people, commented on,
and edited
16
Overall Benefits
Total DCS issues identified: 63
• Potentially costly items
• Drum level reference changed
• Boiler feed pump controls
• Trips were not connected
• Control schemes were changed
17
Overall Benefits Continued
• Plant trip conditions can be tested that require either
third party controls or DCS control logic modifications.
• Startup/shutdown procedures can be adjusted ahead of
time based on interaction with the simulator during
integration.
18
• Real-time training during the integration and FAT Phases
• Required graphics & logic tuning and modifications can be
sent to the plant for more efficient commissioning of the
new gas controls.
Conclusion
Thank you.
For more information, go to:
www.GSES.com
info@gses.com
Or call 800-638-7912

Contenu connexe

Tendances

Equipment sizing and costing using Petro-SIM
Equipment sizing and costing using Petro-SIMEquipment sizing and costing using Petro-SIM
Equipment sizing and costing using Petro-SIMKBC (A Yokogawa Company)
 
Model based design-Hardware in loop-software in loop
Model based design-Hardware in loop-software in loopModel based design-Hardware in loop-software in loop
Model based design-Hardware in loop-software in loopMahmoud Hussein
 
Europe User Conference: BP - implementing and supporting a multi-model, multi...
Europe User Conference: BP - implementing and supporting a multi-model, multi...Europe User Conference: BP - implementing and supporting a multi-model, multi...
Europe User Conference: BP - implementing and supporting a multi-model, multi...KBC (A Yokogawa Company)
 
Building Grid Resilience
Building Grid ResilienceBuilding Grid Resilience
Building Grid ResilienceAdvisian
 
Europe User Conference: Galp refinery wide model - a real work example
Europe User Conference: Galp refinery wide model - a real work exampleEurope User Conference: Galp refinery wide model - a real work example
Europe User Conference: Galp refinery wide model - a real work exampleKBC (A Yokogawa Company)
 
Asphalt batch process with PLC & SCADA ppt
Asphalt batch process with PLC & SCADA pptAsphalt batch process with PLC & SCADA ppt
Asphalt batch process with PLC & SCADA pptjazz_306
 
Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWmelanie_bissonnette
 
Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7KBC (A Yokogawa Company)
 
Wind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioningWind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioningAdvisian
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Nicholas Naing
 
Mechanical Engineering Seminar 2017_1
Mechanical Engineering Seminar 2017_1Mechanical Engineering Seminar 2017_1
Mechanical Engineering Seminar 2017_1Nicholas Naing
 
Advisian dynamic process simulation capability june 2019
Advisian dynamic process simulation capability june 2019Advisian dynamic process simulation capability june 2019
Advisian dynamic process simulation capability june 2019Advisian
 

Tendances (20)

Sustaining energy performance
Sustaining energy performanceSustaining energy performance
Sustaining energy performance
 
Equipment sizing and costing using Petro-SIM
Equipment sizing and costing using Petro-SIMEquipment sizing and costing using Petro-SIM
Equipment sizing and costing using Petro-SIM
 
Besf building renewal_021815
Besf building renewal_021815Besf building renewal_021815
Besf building renewal_021815
 
Model based design-Hardware in loop-software in loop
Model based design-Hardware in loop-software in loopModel based design-Hardware in loop-software in loop
Model based design-Hardware in loop-software in loop
 
Europe User Conference: BP - implementing and supporting a multi-model, multi...
Europe User Conference: BP - implementing and supporting a multi-model, multi...Europe User Conference: BP - implementing and supporting a multi-model, multi...
Europe User Conference: BP - implementing and supporting a multi-model, multi...
 
Building Grid Resilience
Building Grid ResilienceBuilding Grid Resilience
Building Grid Resilience
 
Europe User Conference: Galp refinery wide model - a real work example
Europe User Conference: Galp refinery wide model - a real work exampleEurope User Conference: Galp refinery wide model - a real work example
Europe User Conference: Galp refinery wide model - a real work example
 
An introduction to energy management
An introduction to energy managementAn introduction to energy management
An introduction to energy management
 
Asphalt batch process with PLC & SCADA ppt
Asphalt batch process with PLC & SCADA pptAsphalt batch process with PLC & SCADA ppt
Asphalt batch process with PLC & SCADA ppt
 
Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NW
 
KBC unit monitoring Petro-SIM and PI-AF
KBC unit monitoring Petro-SIM and PI-AFKBC unit monitoring Petro-SIM and PI-AF
KBC unit monitoring Petro-SIM and PI-AF
 
Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7
 
11 pv o&m cost modeling for solar fleets
11   pv o&m cost modeling for solar fleets11   pv o&m cost modeling for solar fleets
11 pv o&m cost modeling for solar fleets
 
Wind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioningWind farm re-powering, life extension and decommissioning
Wind farm re-powering, life extension and decommissioning
 
AdamEshkanian_EngProjects
AdamEshkanian_EngProjectsAdamEshkanian_EngProjects
AdamEshkanian_EngProjects
 
Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2Mechanical Engineering Seminar 2017_2
Mechanical Engineering Seminar 2017_2
 
Mechanical Engineering Seminar 2017_1
Mechanical Engineering Seminar 2017_1Mechanical Engineering Seminar 2017_1
Mechanical Engineering Seminar 2017_1
 
Econoseek
EconoseekEconoseek
Econoseek
 
KBC roadmap
KBC roadmapKBC roadmap
KBC roadmap
 
Advisian dynamic process simulation capability june 2019
Advisian dynamic process simulation capability june 2019Advisian dynamic process simulation capability june 2019
Advisian dynamic process simulation capability june 2019
 

En vedette

Human Performance improvement for the Turkish Energy Sector
Human Performance improvement for the Turkish Energy SectorHuman Performance improvement for the Turkish Energy Sector
Human Performance improvement for the Turkish Energy SectorGSE Systems, Inc.
 
Simulation Training Post Fukushima
Simulation Training Post FukushimaSimulation Training Post Fukushima
Simulation Training Post FukushimaGSE Systems, Inc.
 
Simulator Management: Ideas for Today and Tomorrow
Simulator Management: Ideas for Today and TomorrowSimulator Management: Ideas for Today and Tomorrow
Simulator Management: Ideas for Today and TomorrowGSE Systems, Inc.
 
Are Your Employees Playing Games?
Are Your Employees Playing Games?Are Your Employees Playing Games?
Are Your Employees Playing Games?GSE Systems, Inc.
 
Proposal For a Nuclear Reactor Operations Course at Purdue University
Proposal For a Nuclear Reactor Operations Course at Purdue UniversityProposal For a Nuclear Reactor Operations Course at Purdue University
Proposal For a Nuclear Reactor Operations Course at Purdue UniversityGSE Systems, Inc.
 
VIZRAD - Evolving Simulaton in Radiation Training
VIZRAD - Evolving Simulaton in Radiation TrainingVIZRAD - Evolving Simulaton in Radiation Training
VIZRAD - Evolving Simulaton in Radiation TrainingGSE Systems, Inc.
 
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...GSE Systems, Inc.
 
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...GSE Systems, Inc.
 
Total Training Solution - Entry2Expert
Total Training Solution - Entry2ExpertTotal Training Solution - Entry2Expert
Total Training Solution - Entry2ExpertGSE Systems, Inc.
 
How to Improve Operator Training Throughput Using Screening & Selection
How to Improve Operator Training Throughput Using Screening & SelectionHow to Improve Operator Training Throughput Using Screening & Selection
How to Improve Operator Training Throughput Using Screening & SelectionGSE Systems, Inc.
 
Improving Operational Performance With Smarter, Cost-Effective Training Programs
Improving Operational Performance With Smarter, Cost-Effective Training ProgramsImproving Operational Performance With Smarter, Cost-Effective Training Programs
Improving Operational Performance With Smarter, Cost-Effective Training ProgramsGSE Systems, Inc.
 
Applying Safety DNA Analytics to Enhance Your E2E Workforce Process
Applying Safety DNA Analytics to Enhance Your E2E Workforce ProcessApplying Safety DNA Analytics to Enhance Your E2E Workforce Process
Applying Safety DNA Analytics to Enhance Your E2E Workforce Process GSE Systems, Inc.
 
Innovation in Nuclear Simulation
Innovation in Nuclear SimulationInnovation in Nuclear Simulation
Innovation in Nuclear SimulationGSE Systems, Inc.
 
Implementation of Dynamic Simulation for Engineering and Human Factors
Implementation of Dynamic Simulation for Engineering and Human FactorsImplementation of Dynamic Simulation for Engineering and Human Factors
Implementation of Dynamic Simulation for Engineering and Human FactorsGSE Systems, Inc.
 
Real-Time Simulation for Design of New Nuclear Plants
Real-Time Simulation for Design of New Nuclear PlantsReal-Time Simulation for Design of New Nuclear Plants
Real-Time Simulation for Design of New Nuclear PlantsGSE Systems, Inc.
 
Investigating Ways to Prevent Electrical Arc Flash
Investigating Ways to Prevent Electrical Arc FlashInvestigating Ways to Prevent Electrical Arc Flash
Investigating Ways to Prevent Electrical Arc FlashGSE Systems, Inc.
 
Increasing ROI Through Simulation and the 'Digital Twin'
Increasing ROI Through Simulation and the 'Digital Twin'Increasing ROI Through Simulation and the 'Digital Twin'
Increasing ROI Through Simulation and the 'Digital Twin'GSE Systems, Inc.
 

En vedette (19)

Human Performance improvement for the Turkish Energy Sector
Human Performance improvement for the Turkish Energy SectorHuman Performance improvement for the Turkish Energy Sector
Human Performance improvement for the Turkish Energy Sector
 
Simulation Training Post Fukushima
Simulation Training Post FukushimaSimulation Training Post Fukushima
Simulation Training Post Fukushima
 
Simulator Management: Ideas for Today and Tomorrow
Simulator Management: Ideas for Today and TomorrowSimulator Management: Ideas for Today and Tomorrow
Simulator Management: Ideas for Today and Tomorrow
 
Are Your Employees Playing Games?
Are Your Employees Playing Games?Are Your Employees Playing Games?
Are Your Employees Playing Games?
 
Proposal For a Nuclear Reactor Operations Course at Purdue University
Proposal For a Nuclear Reactor Operations Course at Purdue UniversityProposal For a Nuclear Reactor Operations Course at Purdue University
Proposal For a Nuclear Reactor Operations Course at Purdue University
 
VIZRAD - Evolving Simulaton in Radiation Training
VIZRAD - Evolving Simulaton in Radiation TrainingVIZRAD - Evolving Simulaton in Radiation Training
VIZRAD - Evolving Simulaton in Radiation Training
 
ANS-3.5 Overview
ANS-3.5 OverviewANS-3.5 Overview
ANS-3.5 Overview
 
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
Solving Refining & Petrochemicals Workforce Development Challenges with Perfo...
 
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
Designing a High-Fidelity Full-Scope Training Simulator for a Triple-Pressure...
 
Total Training Solution - Entry2Expert
Total Training Solution - Entry2ExpertTotal Training Solution - Entry2Expert
Total Training Solution - Entry2Expert
 
How to Improve Operator Training Throughput Using Screening & Selection
How to Improve Operator Training Throughput Using Screening & SelectionHow to Improve Operator Training Throughput Using Screening & Selection
How to Improve Operator Training Throughput Using Screening & Selection
 
Improving Operational Performance With Smarter, Cost-Effective Training Programs
Improving Operational Performance With Smarter, Cost-Effective Training ProgramsImproving Operational Performance With Smarter, Cost-Effective Training Programs
Improving Operational Performance With Smarter, Cost-Effective Training Programs
 
Applying Safety DNA Analytics to Enhance Your E2E Workforce Process
Applying Safety DNA Analytics to Enhance Your E2E Workforce ProcessApplying Safety DNA Analytics to Enhance Your E2E Workforce Process
Applying Safety DNA Analytics to Enhance Your E2E Workforce Process
 
Innovation in Nuclear Simulation
Innovation in Nuclear SimulationInnovation in Nuclear Simulation
Innovation in Nuclear Simulation
 
Implementation of Dynamic Simulation for Engineering and Human Factors
Implementation of Dynamic Simulation for Engineering and Human FactorsImplementation of Dynamic Simulation for Engineering and Human Factors
Implementation of Dynamic Simulation for Engineering and Human Factors
 
Process Modeling Simulation
Process Modeling SimulationProcess Modeling Simulation
Process Modeling Simulation
 
Real-Time Simulation for Design of New Nuclear Plants
Real-Time Simulation for Design of New Nuclear PlantsReal-Time Simulation for Design of New Nuclear Plants
Real-Time Simulation for Design of New Nuclear Plants
 
Investigating Ways to Prevent Electrical Arc Flash
Investigating Ways to Prevent Electrical Arc FlashInvestigating Ways to Prevent Electrical Arc Flash
Investigating Ways to Prevent Electrical Arc Flash
 
Increasing ROI Through Simulation and the 'Digital Twin'
Increasing ROI Through Simulation and the 'Digital Twin'Increasing ROI Through Simulation and the 'Digital Twin'
Increasing ROI Through Simulation and the 'Digital Twin'
 

Similaire à Virtual Commissioning and Real-Time Training for Increasing Performance

Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsGerard B. Hawkins
 
Case study -4 Mort Street
Case study -4 Mort StreetCase study -4 Mort Street
Case study -4 Mort StreetShamitha Reddy
 
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...GSE Systems, Inc.
 
Retrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsRetrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsWIGreenBuilding
 
Czero Engineering - Feb 2017
Czero Engineering  - Feb 2017Czero Engineering  - Feb 2017
Czero Engineering - Feb 2017Czero
 
EFEU / FLEXe Nurmoranta Maria advanced control as a key to flexibility capab...
EFEU / FLEXe Nurmoranta  Maria advanced control as a key to flexibility capab...EFEU / FLEXe Nurmoranta  Maria advanced control as a key to flexibility capab...
EFEU / FLEXe Nurmoranta Maria advanced control as a key to flexibility capab...CLIC Innovation Ltd
 
Gas Combustion Turbine System
Gas Combustion Turbine SystemGas Combustion Turbine System
Gas Combustion Turbine SystemPeter Bright
 
Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Shaun West
 
Kalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project PortfolioKalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project PortfolioKalpak Dhake
 
Thermal Power Library - Overview
Thermal Power Library - OverviewThermal Power Library - Overview
Thermal Power Library - OverviewModelon
 
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
353685130-CCGT-Combined-Cycle-Gas-Turbine.pptJiji118054
 
Chapter 5b -_cracking_ffcu
Chapter 5b -_cracking_ffcuChapter 5b -_cracking_ffcu
Chapter 5b -_cracking_ffcuHelena Francis
 
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and EngineersEnergy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and Engineersenergytrustor
 
Revamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen PlantsRevamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen PlantsGerard B. Hawkins
 
Ashrae 90.1 2004 appendix g - performance rating method
Ashrae 90.1   2004 appendix g - performance rating methodAshrae 90.1   2004 appendix g - performance rating method
Ashrae 90.1 2004 appendix g - performance rating methodEduardo Miranda Cáceres
 

Similaire à Virtual Commissioning and Real-Time Training for Increasing Performance (20)

Appsolu
AppsoluAppsolu
Appsolu
 
Revamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen PlantsRevamps for Modern Hydrogen Plants
Revamps for Modern Hydrogen Plants
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
 
Case study -4 Mort Street
Case study -4 Mort StreetCase study -4 Mort Street
Case study -4 Mort Street
 
Epa of cogen
Epa of cogenEpa of cogen
Epa of cogen
 
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
High-Fidelity Operator Training Simulator for CCGT Implemented Before Plant C...
 
Retrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsRetrocommissioning of Existing Buildings
Retrocommissioning of Existing Buildings
 
Czero Engineering - Feb 2017
Czero Engineering  - Feb 2017Czero Engineering  - Feb 2017
Czero Engineering - Feb 2017
 
EFEU / FLEXe Nurmoranta Maria advanced control as a key to flexibility capab...
EFEU / FLEXe Nurmoranta  Maria advanced control as a key to flexibility capab...EFEU / FLEXe Nurmoranta  Maria advanced control as a key to flexibility capab...
EFEU / FLEXe Nurmoranta Maria advanced control as a key to flexibility capab...
 
Gas Combustion Turbine System
Gas Combustion Turbine SystemGas Combustion Turbine System
Gas Combustion Turbine System
 
Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009Improved power plant performance, Sulzer Technical Review, 2009
Improved power plant performance, Sulzer Technical Review, 2009
 
Kalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project PortfolioKalpak Mechanical Engineering Project Portfolio
Kalpak Mechanical Engineering Project Portfolio
 
Thermal Power Library - Overview
Thermal Power Library - OverviewThermal Power Library - Overview
Thermal Power Library - Overview
 
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
353685130-CCGT-Combined-Cycle-Gas-Turbine.ppt
 
Chapter 5b -_cracking_ffcu
Chapter 5b -_cracking_ffcuChapter 5b -_cracking_ffcu
Chapter 5b -_cracking_ffcu
 
Condensing Boiler Optimization
Condensing Boiler OptimizationCondensing Boiler Optimization
Condensing Boiler Optimization
 
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and EngineersEnergy Trust New Buildings: Technical Updates for Modelers and Engineers
Energy Trust New Buildings: Technical Updates for Modelers and Engineers
 
Revamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen PlantsRevamps for Ageing Hydrogen Plants
Revamps for Ageing Hydrogen Plants
 
Ashrae 90.1 2004 appendix g - performance rating method
Ashrae 90.1   2004 appendix g - performance rating methodAshrae 90.1   2004 appendix g - performance rating method
Ashrae 90.1 2004 appendix g - performance rating method
 

Plus de GSE Systems, Inc.

Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019GSE Systems, Inc.
 
GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Second Simulator Address Plant Training Needs CONTE 2019GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Second Simulator Address Plant Training Needs CONTE 2019GSE Systems, Inc.
 
GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Gaining Value From Virtual Control Panels CONTE 2019GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Gaining Value From Virtual Control Panels CONTE 2019GSE Systems, Inc.
 
Onyx relap5 Presentation from SCS 2019
Onyx relap5 Presentation from SCS 2019Onyx relap5 Presentation from SCS 2019
Onyx relap5 Presentation from SCS 2019GSE Systems, Inc.
 
GSE Performance Improvement Solutions
GSE Performance Improvement SolutionsGSE Performance Improvement Solutions
GSE Performance Improvement SolutionsGSE Systems, Inc.
 
PSA-HD Simulator for Severe Accidents
PSA-HD Simulator for Severe AccidentsPSA-HD Simulator for Severe Accidents
PSA-HD Simulator for Severe AccidentsGSE Systems, Inc.
 
Potential Model Changes as a Result of Fukushima
Potential Model Changes as a Result of FukushimaPotential Model Changes as a Result of Fukushima
Potential Model Changes as a Result of FukushimaGSE Systems, Inc.
 
Dynamic Simulation for HFE & Control System Design Validation
Dynamic Simulation for HFE & Control System Design ValidationDynamic Simulation for HFE & Control System Design Validation
Dynamic Simulation for HFE & Control System Design ValidationGSE Systems, Inc.
 
Fossil Power Simulator Efficiencies When Using Automated Testing
Fossil Power Simulator Efficiencies When Using Automated TestingFossil Power Simulator Efficiencies When Using Automated Testing
Fossil Power Simulator Efficiencies When Using Automated TestingGSE Systems, Inc.
 
E-learning, 3D and Simulation for Competency Development
E-learning, 3D and Simulation for Competency DevelopmentE-learning, 3D and Simulation for Competency Development
E-learning, 3D and Simulation for Competency DevelopmentGSE Systems, Inc.
 

Plus de GSE Systems, Inc. (10)

Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019Hyperspring Implementation of BWROG EP/SAG CONTE 2019
Hyperspring Implementation of BWROG EP/SAG CONTE 2019
 
GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Second Simulator Address Plant Training Needs CONTE 2019GSE Second Simulator Address Plant Training Needs CONTE 2019
GSE Second Simulator Address Plant Training Needs CONTE 2019
 
GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Gaining Value From Virtual Control Panels CONTE 2019GSE Gaining Value From Virtual Control Panels CONTE 2019
GSE Gaining Value From Virtual Control Panels CONTE 2019
 
Onyx relap5 Presentation from SCS 2019
Onyx relap5 Presentation from SCS 2019Onyx relap5 Presentation from SCS 2019
Onyx relap5 Presentation from SCS 2019
 
GSE Performance Improvement Solutions
GSE Performance Improvement SolutionsGSE Performance Improvement Solutions
GSE Performance Improvement Solutions
 
PSA-HD Simulator for Severe Accidents
PSA-HD Simulator for Severe AccidentsPSA-HD Simulator for Severe Accidents
PSA-HD Simulator for Severe Accidents
 
Potential Model Changes as a Result of Fukushima
Potential Model Changes as a Result of FukushimaPotential Model Changes as a Result of Fukushima
Potential Model Changes as a Result of Fukushima
 
Dynamic Simulation for HFE & Control System Design Validation
Dynamic Simulation for HFE & Control System Design ValidationDynamic Simulation for HFE & Control System Design Validation
Dynamic Simulation for HFE & Control System Design Validation
 
Fossil Power Simulator Efficiencies When Using Automated Testing
Fossil Power Simulator Efficiencies When Using Automated TestingFossil Power Simulator Efficiencies When Using Automated Testing
Fossil Power Simulator Efficiencies When Using Automated Testing
 
E-learning, 3D and Simulation for Competency Development
E-learning, 3D and Simulation for Competency DevelopmentE-learning, 3D and Simulation for Competency Development
E-learning, 3D and Simulation for Competency Development
 

Dernier

notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfsmsksolar
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 

Dernier (20)

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Rums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdfRums floating Omkareshwar FSPV IM_16112021.pdf
Rums floating Omkareshwar FSPV IM_16112021.pdf
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 

Virtual Commissioning and Real-Time Training for Increasing Performance

  • 1. Virtual Commissioning + Real-Time Training = Increased Performance & Profits info@gses.com
  • 2. 2 Overview • Gas conversion of existing coal power plant • Project execution strategy for existing virtual simulator • Benefits of having a simulator before plant gas startup commissioning
  • 3. 3 Overview of Gas Conversion • Increasingly stringent and uncertain regulatory environment • Plus, falling natural gas prices • These conditions have made converting existing coal-fired steam- generating boilers to natural gas firing more and more attractive. • Based on recent gas conversion announcements, existing coal units generating a total of approximately 9,000 MW will be converted for natural gas firing. Source : Power Engineering Magazine (www.power-eng.com) – “Coal to Natural Gas Conversion – Drivers and Lessons”
  • 4. 4 Overview of Gas Conversion The major drivers of this trend have been: – Mercury and Air Toxics Standards (MATS) regulations – New Source Review (NSR) settlements – Natural Gas availability and pricing – The uniqueness of each project to deliver electricity at the required capacity to make it economically feasible to convert existing coal-fired units to natural gas-firing capability. Source : Power Engineering Magazine (www.power-eng.com) – “Coal to Natural Gas Conversion – Drivers and Lessons”
  • 5. 5 Simulator Considerations • Using natural gas changes the heat absorption characteristics in the boiler and convection pass. There are modifications that have to be made to meet the designed steam temperatures and full boiler output. • In addition, considerations have to be given to achieve low emission goals. These modifications include: – Gas Supply: Modifications to the gas supply and vent piping, installation of pressure- reducing valve station. – Boiler: Modifications to the radiation and/or convective area to help achieve original steam temperatures, new burners and igniters, windbox modifications – Flue Gas Recirculation (FGR): FGR to control NOX and steam temperatures by recycling a portion of the flue gas from the economizer outlet back into the windbox – Flue Gas System: Modifications to the Air & Gas System. Forced-draft/induced-draft fan modifications and other control functions to maintain furnace pressure.
  • 6. 6 • From GSE: Two team members including an engineering manager • From DCS: One project engineer • From plant: Energy production supervisor and two shift supervisors Resource Team
  • 7. 7 Overview of Project Execution Strategy • Schedule • DCS virtual configuration • Project staging • Discrepancy recording system
  • 8. 8 Schedule Simulator Model Design Process 1. Conference call kickoff meeting 2. Model scope design review meeting 3. Model changes 4. FAT’ed DCS shipped to GSE 5. Integration & testing at GSE
  • 9. 9 Simulator Air & Gas Drawing
  • 12. 12 DCS Virtual Configuration • DCS was already converted to the DCS vendor’s virtual controllers • FAT’ed DCS shipped to GSE • 3 Dual monitor operator stations
  • 14. 14 Project Staging Staged at GSE facility 1. Access to model engineer(s) 2. Plant operators 3. After initial integration, remote access provided to DCS vendor for support
  • 15. 15 Discrepancy Recording System GSE Mantis DR System • An online system where users can be easily added • Different sections available for different types of discrepancies • Severity of discrepancy can be assigned • Discrepancy can be assigned to people, commented on, and edited
  • 16. 16 Overall Benefits Total DCS issues identified: 63 • Potentially costly items • Drum level reference changed • Boiler feed pump controls • Trips were not connected • Control schemes were changed
  • 17. 17 Overall Benefits Continued • Plant trip conditions can be tested that require either third party controls or DCS control logic modifications. • Startup/shutdown procedures can be adjusted ahead of time based on interaction with the simulator during integration.
  • 18. 18 • Real-time training during the integration and FAT Phases • Required graphics & logic tuning and modifications can be sent to the plant for more efficient commissioning of the new gas controls. Conclusion
  • 19. Thank you. For more information, go to: www.GSES.com info@gses.com Or call 800-638-7912