SlideShare une entreprise Scribd logo
1  sur  12
ERJ DIVE
Company Private
ACCESSORIES SHOP
DEFINE
2
,Bill Borah
DEFINE CONT’D
3
0
5
10
15
20
25
Apr May
LaborHrs
Months
ERJ Average Labor Hrs
(Current)
EVENT PRE-WORK ACTIVITIES
Part Family A
Takt Time:
129
Part
Number Description
Monthly
Demand Pre Test Disassy Cleaning Inspect
Shimmin
g Assy Test F. Prep
Total Work
Content
ERJ 75.0 45.0 60 60 150 250 160 40 30 720
Slat "CRJ" 30.0 45.0 60 60 150 240 160 40 30 710
Variation
%
0 0 0 0 4 0 0 0 1.39
Avg C/T 45.00 60.00 60.00 150.00 245.00 160.00 40.00 30.00 119.17
INVESTIGATE
INVESTIGATE CONT’D
5
MaterialsROAActuationQuality
Receive
Unit
Shop
Incoming
Pre-
Checks
Dissy. Insp
Pull parts
Assy.
Functional
Test
Final
Inspection
Final
Prep
Ship Unit
Incoming
PO
Review
Physical movement (Unit/paperwork)
Electronic communication
Internal process
45 Min. 2 Hrs 2 Hrs 10 Hrs 1 Hr
0.5 Hr
INVESTIGATE CONT’D
6
Count of SO Average Sum of Hrs
12 Hrs Target
Cum Avg 23.2
VERIFY CONT’D
Count of SO Average Sum of Hrs
12 Hrs Target
Cum Avg 23.2
VERIFY CONT’D
Progression Timeline
Contact ASE for
recommendations of SB
& CMM revision. Assign
Action items and commit
dates. Enhance shimming
process through SB
change
Create Special Tooling for
shim stack up.
Complete time
observation study of
current state & cycle time
reduction plan.
Conduct standard work
Kaizen event.
Order cleaning tanks.
Obtain spring tester PO
approval.
Obtain shimming
software verification if
standard shimming
process is not adopted.
5/23/11 5/28/11 5/31/11 6/5/11 6/10/11 6/15/11 6/20/11 6/30/11
Implement process gates
on all benches to monitor
times.
11Hrs
by
Aug 1
Benefits = 6Hr reduction
3Hr reduction
0.5Hr reduction
10 Min reduction
2 Hr reduction
20 Min reduction
See standard work
Kaizen
VERIFY CONT’D
ENSURE
No. Activity Owner Due Date
1 Enhance shimming process SB & CMM rec. Bowman/ Borah/ Dobbs 5/31/2011
2 Time observation study (current & future) Bowman/ Morales 5/31/2011
3 Incorporation of Process Gates Bowman/ Morales 6/1/2011
4 Standard Work Kaizen Event Bowman/ Morales 6/5/2011
5 SB ENG action items closed Borah/Porsche 6/12/2011
6 Spring Tester Quote and PO approval Bowman/ Mclaughlin 6/15/2011
7 Shimming software if standard shim process NV Anwar/ Bowman/Lyn. 6/30/2011
8 Order cleaning tanks Bowman/ Benn 7/1/2011
9 SB action item approval for standard shimming Borah/ Porsche 8/15/2011
10 Solvent PD680 added to CMM as alternative Borah/ Porsche 8/15/2011
% Complete
Team: ERJ Kaizen team Date: 08/05/11
ENSURE CONT’D
11
17.4
13.53
11.66
0
5
10
15
20
May-11 Jun-11 Jul-11
AverageLaborHours
Months
ERJ Current Labor Hour Trend (Monthly)
Monthly Average Labor Hrs
Goal 12 Hours
28 Units
June
26 Units
May
34 Units
July
TOTAL TIME CURRENT STATE 12HRS
MaterialsROAActuationQuality
Receive
Unit
Shop
Incoming
Pre-
Checks
Dissy. Insp
Pull parts
Assy.
Functional
Test
Final
Inspection
Final
Prep
Ship Unit
Incoming
PO
Review
Physical movement (Unit/paperwork)
Electronic communication
Internal process
45 Min. 1 Hrs 2 Hrs 7 Hrs 1 Hr
0.5 Hr
Reduced Times
ENSURE CONT’D

Contenu connexe

Tendances

Quality Control & warehousing
Quality Control & warehousing Quality Control & warehousing
Quality Control & warehousing carlfglobal
 
Engine 15W40 CI-4 = 15345Km
Engine 15W40 CI-4 = 15345KmEngine 15W40 CI-4 = 15345Km
Engine 15W40 CI-4 = 15345KmRichie R Gultom
 
50338447 checklist-concrete-works
50338447 checklist-concrete-works50338447 checklist-concrete-works
50338447 checklist-concrete-worksimaduddin91
 
Inspection Report during Plant Outage @ NA Plant
Inspection Report during Plant Outage @ NA PlantInspection Report during Plant Outage @ NA Plant
Inspection Report during Plant Outage @ NA PlantAnas Asad
 
50727481 checklist-for-site-works
50727481 checklist-for-site-works50727481 checklist-for-site-works
50727481 checklist-for-site-worksimaduddin91
 
Quality Assurance in PEB - Pre Engineered steel buildings
Quality Assurance in PEB - Pre Engineered steel buildingsQuality Assurance in PEB - Pre Engineered steel buildings
Quality Assurance in PEB - Pre Engineered steel buildingsmbphenix
 
20170922231916 120
20170922231916 12020170922231916 120
20170922231916 120qczoomen
 
SPD12 Pipeline Dynamic Simulation
SPD12 Pipeline Dynamic SimulationSPD12 Pipeline Dynamic Simulation
SPD12 Pipeline Dynamic SimulationSaleh Lari Mojarrad
 
Water Treatment System Mf
Water Treatment System MfWater Treatment System Mf
Water Treatment System MfAyham Awad
 
Nambiraj K_Resume_New
Nambiraj K_Resume_NewNambiraj K_Resume_New
Nambiraj K_Resume_NewNambiraj K
 
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineQa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineJOBY Joby.Stephan
 
Industrial Inspection | SCI, Control & Inspection
Industrial Inspection | SCI, Control & InspectionIndustrial Inspection | SCI, Control & Inspection
Industrial Inspection | SCI, Control & InspectionSCI Control & Inspección
 

Tendances (20)

CV. P.S.MANJUNATHAN
CV. P.S.MANJUNATHANCV. P.S.MANJUNATHAN
CV. P.S.MANJUNATHAN
 
haitham abdelaal CV
haitham abdelaal CVhaitham abdelaal CV
haitham abdelaal CV
 
Resume
ResumeResume
Resume
 
Quality Control & warehousing
Quality Control & warehousing Quality Control & warehousing
Quality Control & warehousing
 
Engine 15W40 CI-4 = 15345Km
Engine 15W40 CI-4 = 15345KmEngine 15W40 CI-4 = 15345Km
Engine 15W40 CI-4 = 15345Km
 
50338447 checklist-concrete-works
50338447 checklist-concrete-works50338447 checklist-concrete-works
50338447 checklist-concrete-works
 
Inspection Report during Plant Outage @ NA Plant
Inspection Report during Plant Outage @ NA PlantInspection Report during Plant Outage @ NA Plant
Inspection Report during Plant Outage @ NA Plant
 
50727481 checklist-for-site-works
50727481 checklist-for-site-works50727481 checklist-for-site-works
50727481 checklist-for-site-works
 
Drone quality control airplane inspection
Drone quality control airplane inspectionDrone quality control airplane inspection
Drone quality control airplane inspection
 
Quality Assurance in PEB - Pre Engineered steel buildings
Quality Assurance in PEB - Pre Engineered steel buildingsQuality Assurance in PEB - Pre Engineered steel buildings
Quality Assurance in PEB - Pre Engineered steel buildings
 
20170922231916 120
20170922231916 12020170922231916 120
20170922231916 120
 
Omega profile
Omega profileOmega profile
Omega profile
 
Cryogenic testing system
Cryogenic testing systemCryogenic testing system
Cryogenic testing system
 
SPD12 Pipeline Dynamic Simulation
SPD12 Pipeline Dynamic SimulationSPD12 Pipeline Dynamic Simulation
SPD12 Pipeline Dynamic Simulation
 
Water Treatment System Mf
Water Treatment System MfWater Treatment System Mf
Water Treatment System Mf
 
Nambiraj K_Resume_New
Nambiraj K_Resume_NewNambiraj K_Resume_New
Nambiraj K_Resume_New
 
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineQa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
 
Resume - Metallurgy latest
Resume - Metallurgy latestResume - Metallurgy latest
Resume - Metallurgy latest
 
Michael CV.
Michael CV.Michael CV.
Michael CV.
 
Industrial Inspection | SCI, Control & Inspection
Industrial Inspection | SCI, Control & InspectionIndustrial Inspection | SCI, Control & Inspection
Industrial Inspection | SCI, Control & Inspection
 

Similaire à ERJ DIVE

SMED - 6.pptx.pptx
SMED - 6.pptx.pptxSMED - 6.pptx.pptx
SMED - 6.pptx.pptxssuser820b7a
 
Single Minute Exchange of Die
Single Minute Exchange of DieSingle Minute Exchange of Die
Single Minute Exchange of DieManish Patil
 
Elimination of Rejection due to Journal Unclean at OP140 in Camshaft Line
Elimination of Rejection due to Journal Unclean at OP140 in Camshaft LineElimination of Rejection due to Journal Unclean at OP140 in Camshaft Line
Elimination of Rejection due to Journal Unclean at OP140 in Camshaft Linekamlashish Goswami
 
# 3 PPT - Expose Your Hidden Problems Using Visual Management
# 3 PPT - Expose Your Hidden Problems Using Visual Management# 3 PPT - Expose Your Hidden Problems Using Visual Management
# 3 PPT - Expose Your Hidden Problems Using Visual ManagementRhonda Kovera
 
Rencana kerja dan pemeliharaan peralatan
Rencana kerja dan pemeliharaan peralatan Rencana kerja dan pemeliharaan peralatan
Rencana kerja dan pemeliharaan peralatan hero1964
 
Pt hpm half yearly presentation on may
Pt hpm half yearly presentation on mayPt hpm half yearly presentation on may
Pt hpm half yearly presentation on mayaristomy
 
Scrum and Lean : Multiply the Powers by Om Band
Scrum and Lean : Multiply the Powers by Om BandScrum and Lean : Multiply the Powers by Om Band
Scrum and Lean : Multiply the Powers by Om Bandagilencr
 
Case Studies it is sbout honfs dfsdfsdjlfksldkfj
Case Studies it is sbout honfs dfsdfsdjlfksldkfjCase Studies it is sbout honfs dfsdfsdjlfksldkfj
Case Studies it is sbout honfs dfsdfsdjlfksldkfjTeproQC
 
Lincolnton Kaizen Event Final Pitch - Infographics
Lincolnton Kaizen Event Final Pitch - InfographicsLincolnton Kaizen Event Final Pitch - Infographics
Lincolnton Kaizen Event Final Pitch - InfographicsDerek Baker
 
8D 210801728
8D 2108017288D 210801728
8D 210801728辉 康
 
Accomplishments take out STD TIS
Accomplishments take out STD TISAccomplishments take out STD TIS
Accomplishments take out STD TISVictoria Blackmer
 
QIP-ASR166061
QIP-ASR166061QIP-ASR166061
QIP-ASR166061Tim Yao
 
Lean Management
Lean ManagementLean Management
Lean ManagementAshish Dev
 
QIC-Summit_ITP-Presentation_Rev-1.0.pptx
QIC-Summit_ITP-Presentation_Rev-1.0.pptxQIC-Summit_ITP-Presentation_Rev-1.0.pptx
QIC-Summit_ITP-Presentation_Rev-1.0.pptxShubhamShukla221709
 
Lean 101 2 Hour 2011
Lean 101 2 Hour 2011Lean 101 2 Hour 2011
Lean 101 2 Hour 2011LCI1998
 
Training ppt for control plan
Training ppt for control plan   Training ppt for control plan
Training ppt for control plan Jitesh Gaurav
 

Similaire à ERJ DIVE (20)

SMED - 6.pptx.pptx
SMED - 6.pptx.pptxSMED - 6.pptx.pptx
SMED - 6.pptx.pptx
 
Single Minute Exchange of Die
Single Minute Exchange of DieSingle Minute Exchange of Die
Single Minute Exchange of Die
 
Elimination of Rejection due to Journal Unclean at OP140 in Camshaft Line
Elimination of Rejection due to Journal Unclean at OP140 in Camshaft LineElimination of Rejection due to Journal Unclean at OP140 in Camshaft Line
Elimination of Rejection due to Journal Unclean at OP140 in Camshaft Line
 
# 3 PPT - Expose Your Hidden Problems Using Visual Management
# 3 PPT - Expose Your Hidden Problems Using Visual Management# 3 PPT - Expose Your Hidden Problems Using Visual Management
# 3 PPT - Expose Your Hidden Problems Using Visual Management
 
Rencana kerja dan pemeliharaan peralatan
Rencana kerja dan pemeliharaan peralatan Rencana kerja dan pemeliharaan peralatan
Rencana kerja dan pemeliharaan peralatan
 
Audited Supplier Approval Report issued by SGS
Audited Supplier  Approval Report issued by SGSAudited Supplier  Approval Report issued by SGS
Audited Supplier Approval Report issued by SGS
 
Pt hpm half yearly presentation on may
Pt hpm half yearly presentation on mayPt hpm half yearly presentation on may
Pt hpm half yearly presentation on may
 
Work measurement
Work measurementWork measurement
Work measurement
 
Scrum and Lean : Multiply the Powers by Om Band
Scrum and Lean : Multiply the Powers by Om BandScrum and Lean : Multiply the Powers by Om Band
Scrum and Lean : Multiply the Powers by Om Band
 
Line balancing
Line balancingLine balancing
Line balancing
 
Case Studies it is sbout honfs dfsdfsdjlfksldkfj
Case Studies it is sbout honfs dfsdfsdjlfksldkfjCase Studies it is sbout honfs dfsdfsdjlfksldkfj
Case Studies it is sbout honfs dfsdfsdjlfksldkfj
 
Lincolnton Kaizen Event Final Pitch - Infographics
Lincolnton Kaizen Event Final Pitch - InfographicsLincolnton Kaizen Event Final Pitch - Infographics
Lincolnton Kaizen Event Final Pitch - Infographics
 
8D 210801728
8D 2108017288D 210801728
8D 210801728
 
Accomplishments take out STD TIS
Accomplishments take out STD TISAccomplishments take out STD TIS
Accomplishments take out STD TIS
 
QIP-ASR166061
QIP-ASR166061QIP-ASR166061
QIP-ASR166061
 
Lean Management
Lean ManagementLean Management
Lean Management
 
QIC-Summit_ITP-Presentation_Rev-1.0.pptx
QIC-Summit_ITP-Presentation_Rev-1.0.pptxQIC-Summit_ITP-Presentation_Rev-1.0.pptx
QIC-Summit_ITP-Presentation_Rev-1.0.pptx
 
Lean 101 2 Hour 2011
Lean 101 2 Hour 2011Lean 101 2 Hour 2011
Lean 101 2 Hour 2011
 
Training ppt for control plan
Training ppt for control plan   Training ppt for control plan
Training ppt for control plan
 
Line balance
Line balanceLine balance
Line balance
 

Plus de George Bowman

LEAN TRANSFORMATION Final 1
LEAN TRANSFORMATION Final 1LEAN TRANSFORMATION Final 1
LEAN TRANSFORMATION Final 1George Bowman
 
Lean Transformation_Insurance
Lean Transformation_InsuranceLean Transformation_Insurance
Lean Transformation_InsuranceGeorge Bowman
 
Out-Brief Presentation CH148 Pos 3 kaizen
Out-Brief Presentation CH148 Pos 3 kaizenOut-Brief Presentation CH148 Pos 3 kaizen
Out-Brief Presentation CH148 Pos 3 kaizenGeorge Bowman
 
CH-148 Shake Crab Reduction revised
CH-148 Shake Crab Reduction revisedCH-148 Shake Crab Reduction revised
CH-148 Shake Crab Reduction revisedGeorge Bowman
 
FMC modular flow guidelines 08-03-13
FMC modular flow guidelines 08-03-13FMC modular flow guidelines 08-03-13
FMC modular flow guidelines 08-03-13George Bowman
 
Source_EarlyFall_2010
Source_EarlyFall_2010Source_EarlyFall_2010
Source_EarlyFall_2010George Bowman
 

Plus de George Bowman (6)

LEAN TRANSFORMATION Final 1
LEAN TRANSFORMATION Final 1LEAN TRANSFORMATION Final 1
LEAN TRANSFORMATION Final 1
 
Lean Transformation_Insurance
Lean Transformation_InsuranceLean Transformation_Insurance
Lean Transformation_Insurance
 
Out-Brief Presentation CH148 Pos 3 kaizen
Out-Brief Presentation CH148 Pos 3 kaizenOut-Brief Presentation CH148 Pos 3 kaizen
Out-Brief Presentation CH148 Pos 3 kaizen
 
CH-148 Shake Crab Reduction revised
CH-148 Shake Crab Reduction revisedCH-148 Shake Crab Reduction revised
CH-148 Shake Crab Reduction revised
 
FMC modular flow guidelines 08-03-13
FMC modular flow guidelines 08-03-13FMC modular flow guidelines 08-03-13
FMC modular flow guidelines 08-03-13
 
Source_EarlyFall_2010
Source_EarlyFall_2010Source_EarlyFall_2010
Source_EarlyFall_2010
 

ERJ DIVE

  • 4. EVENT PRE-WORK ACTIVITIES Part Family A Takt Time: 129 Part Number Description Monthly Demand Pre Test Disassy Cleaning Inspect Shimmin g Assy Test F. Prep Total Work Content ERJ 75.0 45.0 60 60 150 250 160 40 30 720 Slat "CRJ" 30.0 45.0 60 60 150 240 160 40 30 710 Variation % 0 0 0 0 4 0 0 0 1.39 Avg C/T 45.00 60.00 60.00 150.00 245.00 160.00 40.00 30.00 119.17 INVESTIGATE
  • 5. INVESTIGATE CONT’D 5 MaterialsROAActuationQuality Receive Unit Shop Incoming Pre- Checks Dissy. Insp Pull parts Assy. Functional Test Final Inspection Final Prep Ship Unit Incoming PO Review Physical movement (Unit/paperwork) Electronic communication Internal process 45 Min. 2 Hrs 2 Hrs 10 Hrs 1 Hr 0.5 Hr
  • 7. Count of SO Average Sum of Hrs 12 Hrs Target Cum Avg 23.2 VERIFY CONT’D
  • 8. Count of SO Average Sum of Hrs 12 Hrs Target Cum Avg 23.2 VERIFY CONT’D
  • 9. Progression Timeline Contact ASE for recommendations of SB & CMM revision. Assign Action items and commit dates. Enhance shimming process through SB change Create Special Tooling for shim stack up. Complete time observation study of current state & cycle time reduction plan. Conduct standard work Kaizen event. Order cleaning tanks. Obtain spring tester PO approval. Obtain shimming software verification if standard shimming process is not adopted. 5/23/11 5/28/11 5/31/11 6/5/11 6/10/11 6/15/11 6/20/11 6/30/11 Implement process gates on all benches to monitor times. 11Hrs by Aug 1 Benefits = 6Hr reduction 3Hr reduction 0.5Hr reduction 10 Min reduction 2 Hr reduction 20 Min reduction See standard work Kaizen VERIFY CONT’D
  • 10. ENSURE No. Activity Owner Due Date 1 Enhance shimming process SB & CMM rec. Bowman/ Borah/ Dobbs 5/31/2011 2 Time observation study (current & future) Bowman/ Morales 5/31/2011 3 Incorporation of Process Gates Bowman/ Morales 6/1/2011 4 Standard Work Kaizen Event Bowman/ Morales 6/5/2011 5 SB ENG action items closed Borah/Porsche 6/12/2011 6 Spring Tester Quote and PO approval Bowman/ Mclaughlin 6/15/2011 7 Shimming software if standard shim process NV Anwar/ Bowman/Lyn. 6/30/2011 8 Order cleaning tanks Bowman/ Benn 7/1/2011 9 SB action item approval for standard shimming Borah/ Porsche 8/15/2011 10 Solvent PD680 added to CMM as alternative Borah/ Porsche 8/15/2011 % Complete Team: ERJ Kaizen team Date: 08/05/11
  • 11. ENSURE CONT’D 11 17.4 13.53 11.66 0 5 10 15 20 May-11 Jun-11 Jul-11 AverageLaborHours Months ERJ Current Labor Hour Trend (Monthly) Monthly Average Labor Hrs Goal 12 Hours 28 Units June 26 Units May 34 Units July
  • 12. TOTAL TIME CURRENT STATE 12HRS MaterialsROAActuationQuality Receive Unit Shop Incoming Pre- Checks Dissy. Insp Pull parts Assy. Functional Test Final Inspection Final Prep Ship Unit Incoming PO Review Physical movement (Unit/paperwork) Electronic communication Internal process 45 Min. 1 Hrs 2 Hrs 7 Hrs 1 Hr 0.5 Hr Reduced Times ENSURE CONT’D