1. Internship in Nestle Pakistan-SKP Factory
Supervisor: Miss Iqra Ashraf & Mr. Mohsin
Area: Engineering Utilities
Assistance: Plant Managers/Team Leaders of different Plants.
Area: MRU&STD, D&J, Chilled Dairy, Water
Intern: Hafiz Muhammad Bilal (Mechatronics Engineer) from University of Engineering &
Technology, Lahore
1
2. Safety Training:
Safety is not a slogan, it’s a way of Life
Plant Safety requirement during visit.
LOTO Procedure
Danger Alarms
Nestle guidelines for plants visit
Introduction to 5S
Introduction to PPE’s
2
3. Projects:
Single Line Diagram
P&ID of Compressors
Raw water pumps automation
Boiler’s instruments calibration
Online data receiving of flow meters
3
4. Project1:
Single Line Diagram (SLD):
Assigned proper tag to each breaker
Format of tag: Output of breaker-Transformer-Panel Building-Panel #.Lock #
Re-numbering of panels of all Control Rooms
Updated Excel Sheet
Updated SLD on AutoCAD
Format on AutoCAD:
Made a detailed REPORT describing each step of project and learning outcomes.
Learnt about power distribution and made a report on it.
4
ACB or MCCB
Current Rating
Make
Model
Tag
5. Project2:
Piping & Instrumentation Diagram (P&ID):
Updated P&ID of SABROE, ATLAS & GEA Compressors.
Line tracing & proper tagging for identification.
Updated Excel sheets of all pipes, instruments and valves etc.
Made a detailed REPORT describing each step of project and learning outcomes.
5
6. Project3:
WWRO Pumps Control:
Cable Sizing calculation
Contact with Nestle vendor (Nafees Cables) and received Cable Charts.
Suggested proper LT Room for supply considering cost optimization and efficiency.
Suggested proper room for VFD panel.
Made a detailed REPORT describing each step of project and learning outcomes.
6
7. Project4:
Boilers Instruments Calibration:
Learnt about calibration of instruments.
Calibrated Boiler instruments i.e. Pressure transmitters, pressure gauges &
temperature transmitters etc.
Made a detailed REPORT describing each step of project and learning outcomes.
7
8. Project5:
Online data receiving of Flow Meters:
Inspected flow meters of Raw Water, Steam and Compressed Air by tracing
Profibus.
Suggested place of new installed flow meters in Profibus.
Differentiated between DP & PA Profibus.
Checked Profibus termination.
Updated excel sheet by including new installed flow meters.
Made a detailed REPORT describing each step of project and learning outcomes.
8
9. Utilities Area Visit:
Compressors
SABROE Compressors
ATLAS COPCO Compressors
GEA Compressors
Prepare a detailed REPORT on the working of all compressors and made Process
Flow Diagrams of each.
All Control Rooms (HT & LT) and learnt about control panels, circuit breakers and
their technical terminologies.
Transformer Room
Developed a Power Distribution Flow Diagram.
9
10. PLC:
Basic components of PLC
Types of PLC
PLC Programming Software's
HMI Software's
Studied some Ladder Logic codes on RS Logix500.
10
11. Plant Orientation:
Visited all plants:
MRU&STD
Water
Dairy & Juice
Tetra Hall
Chilled Dairy
PLE Hall
Developed Process Flow Diagrams of each plant.
Made a detailed REPORT describing each process and Working Principles of all
machines.
11
14. Water Treatment Plant:14
Deep Well Cartridge Filter UV Sand Filtration
FDP Mix Proof Valves Cartridge Filter UV
RO Mix Proof Valves Permeate Tank Re-Mineralization
Balance Tank Ozonation Filling
16. 16
Bermatic Tank Filter Feeding Pump Balance Tank
Pre Heater1
(55-60°C)
De-aerator
(50-55°C)
Pre-Heater2
(65°C)
22sec Holding
(98-101°C)
Pasteurizer
Pre-Heater2
(Cooling)
Pre-Heater1
(20-25°C)
Booster Pump
Acceptic TankFilling Machines
17. Tetra Hall:17
Peper Roll ASU ASSU H2O2 Bar
Squeezy
Roller
Heater
Aseptic
Chamber
Tube
Formation
Bending of
Packet
Filling Product
in Tube
Head Space
Injuction
Jaw System
Infeed
Conveyer
Flaps Presser
Out feed
Conveyer
PLE Hall