SlideShare une entreprise Scribd logo
1  sur  39
www.GLOBALSKILLUP.com
PMP® Certification Training!
www.GLOBALSKILLUP.com
2
CONNECT WITH US
www.GLOBALSKILLUP.com
Risk Management
Chapter 11
www.GLOBALSKILLUP.com
Chapter 11
Objectives
Understand the different Risk Management
Processes
Their Inputs, Tools and Techniques,
Outputs
This chapter entails one to
understand the various Risk
Management aspects
required to identify, remove
and harness threats or
opportunities.
Driving the project towards
the desired outcome while
the project progresses with
minimal impact to the
project objectives being
accomplished to make the
project successful!
www.GLOBALSKILLUP.com
It includes the processes to ensure the project risks are
identified, analyzed, acted, planned with responses and
controlled for minimal impact on project objectives.
Project Risks can be broadly categorized based on the level of
knowledge we have upon them.
Known Risks. The risks which are identified and are
aware to the project management team.
Unknown Risks. The risks which are not yet identified &
might occur instantaneously without prior knowledge.
Risks should be perceived as:
Overall Project Risk. This is the holistic risk of the project
itself considering all individual project risks along with any
other unknown risks beyond the project control.
Individual Project Risks. Risks which can standalone or
in a category group well within reach of the project which
impact partially or a complete project objective set.
Knowledge Area: Risk Management
www.GLOBALSKILLUP.com
There are 6 Risk Management processes, namely:
1. Plan Risk Management
Process of ensuring the Risk management is
planned in detailed manner which can be applied
over the course of the project.
2. Identify Risks
Identification of Risks over the Course of the
Project and documentation of their
characteristics.
3. Perform Qualitative Risk Analysis
Performing a qualitative analysis of risks and
conditions to prioritize their effects on project
objectives.
4. Perform Quantitative Risk Analysis
Measuring the probability and consequences of
risks and estimating their implications for project
objectives.
5. Plan Risk Responses
Once Risks are prioritized and weighted, each of
risks are provided a response plan (Avoid,
Transfer, Mitigate, Accept for Negative Risks and
Exploit, Enhance, Share, Accept for Positive
Risks)
6. Control Risks
Controlling Risks over the duration of the project
to the benefit of the project objectives.
Knowledge Area: Risk Management
www.GLOBALSKILLUP.com
Risk responses by Stakeholders
/Organizations depend on:
 Risk Appetite. Degree of Risk which
will be taken up in order to gain a
reward. Variations are measured over
course of the project in LCL (Lower
Control Limit) & UCL(Upper Control
Limit) to understand the stakeholder
risk appetite levels.
 Risk Tolerance Levels. Degree of
Risk which will be entertained beyond
which the attention is required.
 Risk Threshold Levels. Extreme
Levels of Risk either on lower side or
upper side. Crossing the lower side,
the Risk is absolutely negligible and
crossing the upper side, the Risk will
not be tolerated any further.
Knowledge Area: Risk Management
Total Cost to
Sponsor/Stakeholder
{Project
Cost
{Contingency Reserve
Actual Work Cost
{
{
Management
Reserve
Tolerance Level
Threshold Level
Appetite
www.GLOBALSKILLUP.com
11.1 Plan Risk Management
Inputs
•Project Management Plan
•Project Charter
•Stakeholder Register
•Enterprise Environmental
Factors
•Organizational Process
Assets
Tools & Techniques
•Analytical Techniques
•Expert Judgment
•Meetings
Outputs
•Risk Management
Plan
•Integration
•Develop Project Management Plan
•Scope
•Plan Scope Management
•Collect Requirements
•Define Scope
•Create WBS
•Time
•Plan Schedule Management
•Define Activities
•Sequence Activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
•Cost
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Quality
•Plan Quality Management
•Human Resource
•Plan HR Management
•Communications
•Plan Communications Management
•Risk
•Plan Risk Management
•Identify Risks
•Perform Qualitative Risk Analysis
•Perform Quantitative Risk Analysis
•Plan Risk Responses
•Procurement
•Plan Procurement Management
•Stakeholder
•Plan Stakeholder Management
Planning Process
Risks are uncertain events which may trigger positive or negative impact
on the project outcome. Planning risk management involves end to end
management of risks involved in the project.
Key benefit of this process ensures the degree, type and visibility of risks
are given right and required risk ratings.
Risks in the project have to be dealt with due diligence and with
complete understanding of the same from all the stakeholders. Risk
management starts much before the project is actually conceived.
Identified risks are then in the later stages managed to be minimized,
exploited and if not planned for contingencies. Risks are regularly
revisited and reviewed over the duration of the project.
www.GLOBALSKILLUP.com
Analytical Techniques help understand the holistic view of the Risks on the
project.
One mechanism beneficial to diagnose and understand the tolerance and
risk appetite levels of the decision makers/stakeholders.
This definitely helps understand the amount of risks which can be handled
and which need to be pitched as immediate escalation points on the
project.
Analytical Techniques
www.GLOBALSKILLUP.com
This plan defines how the risk activities will be performed on the project.
It may include the following:
Methodology
Defined approach along with the tools to perform Risk management
Roles and responsibilities
Defines risk management resources roles & responsibilities
Budgeting
Helps estimate budget to ensure the required reserves are defined
Timing
Time when the information has to be conveyed
Risk categories
Risks may be categorized into multiple categories based on the
project being performed. They may be grouped based on various
approaches.
RBS(Risk Breakdown Structure) helps identify risks from multiple
sources identified in risk identification exercise and categorize them
in a structured manner for ease of addressing them.
Risk Management Plan
www.GLOBALSKILLUP.com
Definitions of Risk Probability and Impact: Define the probability and impact definitions that will be used in
the project. Sample Impact Definition Table is shown here.
Probability and Impact Matrix
Risk Management Plan
Very Low
0.10
Low
0.25
Moderate
0.50
High
0.75
Very High
0.90
Scope Insignificant Changes Changes Moderate Changes Major Changes
Major Significant
Changes
Time
<5% Increased
Timeline
<25% Increased
Timeline
25-50% Increased
Timeline
50-70% Increased
Timeline
>70% Increased
Timeline
Cost
<5% Increased Project
Cost
<25% Increased
Project Cost
25-50% Increased
Project Cost
50-70% Increased
Project Cost
>70% Increased
Project Cost
Quality
Quality Changes Not
Significant
Quality May Need To
Be Improved
Sponsor Needs To
Approve The Quality
Product Quality Is Not
Acceptable To
Sponsor
End Product Quality Is
Useless
Very Likely
Most Likely
Likely
Chance of
Likely
Unlikely
Probability
/Impact
Very Low Low Moderate High Very High
Revised Stakeholders’ Tolerances
Continuous revision of stakeholders
tolerances based on their risk appetite over
project duration.
Reporting Formats
Define the report formats which include the
manner, risks will be documented,
formatted, communicated to which
stakeholder group.
Tracking
Risk Tracking is very important as the risks
continuously evolve from one quadrant to
another. Recording of their risk movements
is equally important from the Risk Auditing
perspective.
www.GLOBALSKILLUP.com
11.2 Identify Risks
Inputs
•Risk, Cost, Schedule,
Quality, HR Management
Plan
•Scope Baseline
•Activity Cost Estimates
•Activity Duration
Estimates
•Stakeholder Register
•Project Documents
•Procurement Documents
•Enterprise Environmental
Factors
•Organizational Process
Assets
Tools & Techniques
•Documentation
Reviews
•Information Gathering
Techniques
•Checklist Analysis
•Assumptions Analysis
•Diagramming
Techniques
•SWOT Analysis
•Expert Judgment
Outputs
•Risk Register
•Integration
•Develop Project Management Plan
•Scope
•Plan Scope Management
•Collect Requirements
•Define Scope
•Create WBS
•Time
•Plan Schedule Management
•Define Activities
•Sequence Activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
•Cost
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Quality
•Plan Quality Management
•Human Resource
•Plan HR Management
•Communications
•Plan Communications Management
•Risk
•Plan Risk Management
•Identify Risks
•Perform Qualitative Risk Analysis
•Perform Quantitative Risk Analysis
•Plan Risk Responses
•Procurement
•Plan Procurement Management
•Stakeholder
•Plan Stakeholder Management
Planning Process
Risks are uncertain events and identification of them early leads us to
better preparation with suitable action plans.
Documentation of the identified risks with their characteristics helps us
be prepared in likely or unlikely situation of the Risk occurrence.
Documentation of the risks in a consistent manner will provide sufficient
detail so as to compare them with each other and suitable associated
action response plan be derived.
This process of identification of risks is iterative and has to be performed
across the intervals of the project duration.
www.GLOBALSKILLUP.com
Risk Register is a document which records the Risk Analysis and
Risk Response Planning. This document evolves as the project
progresses and is a live document.
Risk Register provides input about the Risk events to impact
resource selection and availability during the Estimate Activity
Resources leading to more finer estimates.
List of Identified Risks:
Identified risks are detailed as much possible including the
root cause.
Risk statements may be used in conjunction to triggers such
as Event->Impact and/or Event -> Effect.
List of Potential Responses:
During the identification of the risks, there may be situations
where in the risk response is readily known. These potential
responses should be recorded.
While the project progresses, the risks registered are
continuously reviewed for triggers and/or risk responses.
Risk Register
www.GLOBALSKILLUP.com
Documentation Reviews
A detailed study or review of the various
project documents may help indicate and
identify the risks in the project.
Various documents which may be
subjected to review, but not limited to:
Plan Documents
Assumptions
Previous Project Documents
Legal Documents
Compliance Considerations
Organizational Policies
Databases
Historical Plans
Information may be gathered in
various formats:
Brainstorming
Delphi Technique
Interviewing
Root Cause Analysis
Information Gathering Techniques
www.GLOBALSKILLUP.com
Checklist Analysis
Risk Identification Checklists may be evolved
over a period of time in any organization which
become a ready reckoner for identification of
risks.
However, proper care should be taken to explore
risks beyond the Checklist itself as this may not
be comprehensive to every project running in the
organization.
Every project is conceived based on certain
assumptions, scenarios and possible postulate.
Each one of these need to be evaluated and
understood in the context of the project in
progress.
AssumptionAnalysis
Certain
Un Certain
LeastImportant
MostImportant
Critical
Region
A AA
AA
A
A
A
A
A
A
A
A
www.GLOBALSKILLUP.com
Diagramming Techniques
Diagramming techniques involve the usage of the
diagramming methods based on which the risks
can be identified.
Such as:
Ishikawa’s Fish Bone Diagram
System or Process Flow Charts
Influence Diagrams – Helps to identify the
decision tree. As shown below.
Strengths, Weakness, Opportunities, Threats
Analysis in short is known as SWOT analysis.
Analysis of the Project is performed to diagnose
the Strengths, Weakness, Opportunities, Threats.
This is first done in a manner to identify
Strengths and Weakness. Then based on
Strengths, opportunities are further explored.
Similarly based on weakness, threats are further
explored.
SWOTAnalysis
Strengths
- Strong Brand
Awareness among
Customers
Weakness
- Low Funds for
Expansion
Opportunities
- Build Partnerships
- Increase
Investments
Threats
- Increased
Competition &
Marketing Spends
Fund
Research
Market
Value
Launch
Product
Research
Success
Market
Success
Influence Diagram
www.GLOBALSKILLUP.com
11.3 Perform Qualitative Risk Analysis
Inputs
•Risk Management Plan
•Scope Baseline
•Risk Register
•Enterprise Environmental
Factors
•Organizational Process
Assets
Tools & Techniques
•Risk Probability And
Impact Assessment
•Probability And Impact
Matrix
•Risk Data Quality
Assessment
•Risk Categorization
•Risk Urgency
Assessment
•Expert Judgment
Outputs
•Project Document
Updates
•Integration
•Develop Project Management Plan
•Scope
•Plan Scope Management
•Collect Requirements
•Define Scope
•Create WBS
•Time
•Plan Schedule Management
•Define Activities
•Sequence Activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
•Cost
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Quality
•Plan Quality Management
•Human Resource
•Plan HR Management
•Communications
•Plan Communications Management
•Risk
•Plan Risk Management
•Identify Risks
•Perform Qualitative Risk Analysis
•Perform Quantitative Risk Analysis
•Plan Risk Responses
•Procurement
•Plan Procurement Management
•Stakeholder
•Plan Stakeholder Management
Planning Process
Performing a qualitative analysis of risks and conditions to prioritize their
effects on project objectives.
Key benefit of this process is to ensure the specialized focus is on the
high quality risks.
This is done through out the project duration and will cause re-
assessment of certain risks as the project evolves.
In order to ensure there is no influence or bias on the assessment, the
probability and impact definitions are defined upfront.
This also helps in establishing “perform quantitative risk analysis”.
www.GLOBALSKILLUP.com
Risk Probability Assessment investigates the
likelihood that each specific risk will occur.
Risk Impact Assessment investigates the impact
on the outcome of the project on Scope, Time,
Cost, Quality parameters should the risk occur.
Each risk is analyzed for both probability and
impact assessment. Risk probabilities and
impacts are rated based on the definitions in the
Risk Management Plan.
All risks are rated based on their assessed
probability and impact as defined in the matrix.
Each of the risks are color coded and accordingly
paid attention. The Risks which are more darker
in color lead to more attention from the project
management team.
Probability ↓ Threats (Negative Risks) Opportunities (Positive Risks)
0.90 .0090 .2250 .4500 .6750 .8100 .8100 .6750 .4500 .2250 .0090
0.75 .0075 .1875 .3750 .5625 .6750 .6750 .5625 .3750 .1875 .0075
0.50 .0050 .1250 .2500 .3750 .4500 .4500 .3750 .2500 .1250 .0050
0.25 .0025 .0625 .1250 .1875 .2250 .2250 .1875 .1250 .0625 .0025
0.10 .0010 .0250 .0500 .0750 .0900 .0900 .0750 .0500 .0250 .0010
Impact
→
Very Low
0.10
Low
0.25
Moderate
0.50
High
0.75
Very High
0.90
Very High
0.90
High
0.75
Moderate
0.50
Low
0.25
Very Low
0.10
Risk Probability & Impact Assessment
www.GLOBALSKILLUP.com
A detailed study of the supplementary data
for each risk helps ensure each risk is paid
rightful attention.
This involves the degree of examination of
the data about the risk is known and
understood.
Parameters based on which the data
quality assessment is performed usually
involves accuracy, quality, reliability and
integrity of the data about the risk.
Risks may be categorized based on the:
Sources of Risk Identified
Which affect a particular project area
Common root causes
Common actions or solutions adopted for
risks and so on..
Risk Data Quality Assessment Risk Categorization
www.GLOBALSKILLUP.com
Risks which need immediate attention from the perspective of time criticality are
required to be acted upon quickly.
Based on the time criticality, the risk priorities define the Risk Rank Ratings.
Risk Urgency Assessment
www.GLOBALSKILLUP.com
11.4 Perform Quantitative Risk Analysis
Inputs
• Risk, Cost, Schedule
Management Plan
• Risk Register
• Enterprise
Environmental Factors
• Organizational Process
Assets
Tools &
Techniques
• Data Gathering and
Representation
Techniques
• Quantitative Risk
Analysis and
Modeling
Techniques
• Expert Judgment
Outputs
• Project
Document
Updates
•Integration
•Develop Project Management Plan
•Scope
•Plan Scope Management
•Collect Requirements
•Define Scope
•Create WBS
•Time
•Plan Schedule Management
•Define Activities
•Sequence Activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
•Cost
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Quality
•Plan Quality Management
•Human Resource
•Plan HR Management
•Communications
•Plan Communications Management
•Risk
•Plan Risk Management
•Identify Risks
•Perform Qualitative Risk Analysis
•Perform Quantitative Risk Analysis
•Plan Risk Responses
•Procurement
•Plan Procurement Management
•Stakeholder
•Plan Stakeholder Management
Planning Process
Key benefit is to measure the probability and consequences of
risks and estimating their implications for project objectives.
Helps in reducing the project uncertainty by performing the
quantitative risk analysis.
It is mostly used to evaluate the aggregate effect of all risks
affecting the project.
Performing this process requires budget and involves cost. This
Cost benefit should be evaluated before this process can be
exercised.
www.GLOBALSKILLUP.com
Commonly used approaches involve:
1. Sensitivity Analysis
2. Expected Monetary Value analysis
3. Modeling and Simulation
Quantitative RiskAnalysis and Modeling Techniques
1. Sensitivity Analysis
This analysis helps identify
the most potential impact on
the project. A sample Tornado
Diagram shows how it is
performed.
-3000 -2000 -1000 0 1000 2000 3000 4000 5000 6000
Risk 5
Risk 4
Risk 3
Risk 2
Risk 1
Inverted Tornado Diagram
Negative Impact Positive Impact
www.GLOBALSKILLUP.com
Quantitative RiskAnalysis and Modeling Techniques
2. Expected Monetary Value(EMV)
Highest EMV wins.
This type of analysis provides the future possible income or outgo values based on
the statistical probability and impact values.
Risk A
Risk C
80% likely
Risk B
20% likely
Outcome1
70% likely
Outcome2
10% likely
Outcome3
20% likely
INR 100 Lakh
Implication
INR 35 Lakh
Implication
INR 65 Lakh
Implication
INR 100 Lakh
Implication
INR 30 Lakh
Implication
www.GLOBALSKILLUP.com
What is your Investment decision based on Risk?
New Product
or
Maintain?
New Product
Development
Investment
$60M
Maintain
Product
Investment
$30M
Strong Sales
Revenue:
$150M
Weak Sales
Revenue :
$70M
Strong Sales
Revenue :
$80M
Weak Sales
Revenue :
$20M
www.GLOBALSKILLUP.com
What is your Investment decision based on Risk?
New Product
or
Maintain?
New Product
Development
Investment
$60M
Maintain
Product
Investment
$30M
Strong Sales
Revenue :
$150M
Weak Sales
Revenue :
$70M
Strong Sales
Revenue :
$80M
Weak Sales
Revenue :
$20M
150-60 =
$90M
70-60 =
$10M
80-30 =
$50M
20-30 =
-$10M
70% Chance
30% Chance
70% Chance
30% Chance
www.GLOBALSKILLUP.com
Investment decision is based on lowest risk
(eliminating -10M) as well as based on highest EMV(66M)
New Product
or
Maintain?
New Product
Development
Investment
$60M
Maintain
Product
Investment
$30M
Strong Sales
Revenue :
$150M
Weak Sales
Revenue :
$70M
Strong Sales
Revenue :
$80M
Weak Sales
Revenue :
$20M
150-60 =
$90M
70-60 =
$10M
80-30 =
$50M
20-30 =
-$10M
EMV of New Product =
70% * 90 + 30% * 10 =
63 + 3 = $66M
70% Chance
30% Chance
70% Chance
30% Chance
EMV of Maintain =
70% * 50 + 30% * -10 =
35 + (-10) = $25M
www.GLOBALSKILLUP.com
Quantitative RiskAnalysis and Modeling Techniques
3. Modeling and Simulation
This type of analysis is performed when the actual
cost of performing activities may have multiple
variables and could cost immensely to actually
perform feasibility in reality.
Monte Carlo Simulation provides unique multiple
iterations of outcomes based on the predefined
trigger values and parameters using which these
simulations are performed statistically using a
computing machine.
Example: Simply treat it as a task repeated over
many times with different variables over a project
schedule network. What will be the output? Will it
vary every time? Yes. Though repetitions of the task
many times will give us a precise range of how many
days +/- it would take to accomplish that.
That is how the Simulations would help you come up
with almost certain range of all. This includes the
probability of the risks on the Project as well.
Benefits of such Monte Carlo or any other
simulation includes:
- Almost precise calculations considering many
parameters for Cost estimates, Schedule
estimates, Overall risk and so on.
- Since it includes path convergence for the
schedule network, the complexity of every task is
accounted, which brings more stability in
estimates.
www.GLOBALSKILLUP.com
Monte Carlo Simulation
Explained
Project
or
Investment
Decision
Risk of Investment 40,000 People, 2B$ Cost, 800 Machines 5 Years Project
Risk of Investment 20,000 People, 3B$ Cost, 600 Machines 10 Years Project
.
.
.
.
.
.
.
.
.
.
.
.
Definitive
Range of
Years
based on
Multiple
Risk
Based
Scenarios
.
.
.
.
.
.
.
.
www.GLOBALSKILLUP.com
11.5 Plan Risk Responses
Inputs
• Risk Management
Plan
• Risk Register
Tools &
Techniques
• Strategies For
Negative Risks Or
Threats
• Strategies For
Positive Risks Or
Opportunities
• Contingent
Response Strategies
• Expert Judgment
Outputs
• Project
Management
Plan Updates
• Project
Document
Updates
•Integration
•Develop Project Management Plan
•Scope
•Plan Scope Management
•Collect Requirements
•Define Scope
•Create WBS
•Time
•Plan Schedule Management
•Define Activities
•Sequence Activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
•Cost
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Quality
•Plan Quality Management
•Human Resource
•Plan HR Management
•Communications
•Plan Communications Management
•Risk
•Plan Risk Management
•Identify Risks
•Perform Qualitative Risk Analysis
•Perform Quantitative Risk Analysis
•Plan Risk Responses
•Procurement
•Plan Procurement Management
•Stakeholder
•Plan Stakeholder Management
Planning Process
This is one of the most important Risk Management processes as we
step into the effective actions and evaluate options of how to address
these prioritized risks.
Key benefits of this includes the allocation of budget, resources and
schedule for the identified and actionable risks.
From the multiple options available to response for each risk it is
imperative to understand which option/response will be most appropriate
in the context of the project limits.
Risks include both threats and opportunities for which the responses can
be developed and initiated for action.
www.GLOBALSKILLUP.com
Negative Risks or Threats can be acted with response
in following manner:
1. Avoid
2. Transfer
3. Mitigate
4. Accept (Applicable for both Negative Threat &
Positive Opportunity)
Avoid
Where possible it is always recommended to
ensure the critical risks are completely avoided
either by eliminating the threat or by ensuring the
project is shielded completely from the impact of
the threat.
Most radical extreme step to avoid risk would be
to shutdown the project itself.
Transfer
Transfer of risk to a third party for a price ensures
the risk even if it occurs minimizes the impact on
the project, since it is offset with the third party.
Risks which are transferred to a third party
involves risks with major cost implication to
project.
Transfer of the risk, does not eliminate risk itself, it
just transfers the ownership to a third party.
Mitigate
Project team acts to minimize the impact &
probability of the risk over a period of time to
ensure the risk is brought to minimal state or
completely eliminated.
Accept
Team acknowledges the risk and waits until the
risk occurs to respond on it.
Active Acceptance – Build a contingency reserve
to ensure when the risk occurs it is readily acted with
the contingency (time, cost, scope, quality).
Passive Acceptance – It is documented and then
awaited until risk occurs, so that further action can
be taken up.
Strategies For Negative Risks Or Threats
Critical Risks with
High Impact
Less Critical Risks with Low
Impact
Avoid Good Strategy
Mitigate Good Strategy
Transfer Good Strategy
Accept Good Strategy
www.GLOBALSKILLUP.com
Positive Risk Example: A potential delay in the
delivery of materials which happened to be
delivered ahead of time. This risk is now an
opportunity to check on the schedule what work
can be done already in advance given the
availability of materials.
Positive Risks or Opportunities can be acted with
response in following manner listed below.
1. Exploit
2. Enhance
3. Share
4. Accept (Passive Acceptance Only)
Exploit
When there are risks which can be beneficial to
the organization, it is natural that these risks are
driven towards ensuring Risk occurs.
Enhance
When you want to increase the probability or likely
chances to ensure the risk occurs by maximizing
the possibilities of risk occurrence.
Share
Sharing of the risk to third party for maximum
throughput when we make the risk occur to
maximize risk out come.
Accept
Accepting the risk to harness the opportunity
when the risk actually arises on its own and not
actively pursuing.
Strategies for Positive Risks or Opportunities
www.GLOBALSKILLUP.com
Some of the responses are planned only when the risks will occur such as in Accept – Active Acceptance.
In such a response planning, a contingent reserve or a fall back plan is established so as to respond
appropriately upon the occurrence of such a risk.
There is no substitute to experience when it comes to Contingent Response Strategies – Expert Judgment
stays on top of the list strategy.
While many project managers simply prefer to have a transfer of risks when they occur, rather than manage
in practice.
Contingent Response Strategies
www.GLOBALSKILLUP.com
11.6 Control Risks
Inputs
•Project Management Plan
•Risk Register
•Work Performance Data
•Work Performance Reports
Tools & Techniques
•Risk Reassessment
•Risk Audits
•Variance and Trend Analysis
•Technical Performance
Measurement
•Reserve Analysis
•Meetings
Outputs
•Work Performance
Information
•Change Requests
•Project Management Plan
Updates
•Project Document Updates
•Organizational Process Assets
Updates
•Integration
•Monitor and Control Project Work
•Perform Integrated Change Control
•Scope
•Validate Scope
•Control Scope
•Time
•Control Schedule
•Cost
•Control Costs
•Quality
•Control Quality
•Human Resource
•Communications
•Control Communications
•Risk
•Monitor & Control Risks
•Procurement
•Control Procurements
•Stakeholder
•Control Stakeholder Management
Monitoring & Controlling
Process
It is the process of controlling risks during the project by
monitoring existing risks, their response plans, risk movements,
identification of new risks, elimination of outdated risks to
ensure the project objectives are least harmed or nil impact due
to risks.
Key benefit includes the effective Risk management and its
minimized or nullified risk impact on the project objectives.
This process also ensure the planned risk management
processes are being followed during the course of the project
and any further improvements to the risk processes are
adopted.
www.GLOBALSKILLUP.com
Risk Reassessment
It is a continuous process through out Project life cycle and performed across all Process Groups.
Risk Reassessments should be carried out frequently to perform the new risk identification, re-planning the
risk responses, close the outdated risks.
Based on the project size and the organizational practice, the project management team and/or specialized
risk management team reassess the risks at frequent intervals.
Identify
Observe
RegulateClose
Re-Assess
www.GLOBALSKILLUP.com
More Tools & Techniques
Variance & Trend Analysis
Performance baselines defined in
the project should be constantly
monitored for any variances.
Also based on the trend analysis
of baseline performance, suitable
actions should be planned,
including further risk identification
and actions in the Project.
Technical Performance
Measurement
Technical performance of the Project is
usually measured based on the type of
project we execute.
Suppose in a software project, we would
be interested in the Technical
performance of Planned Flawless
Modules against Actual Modules with
Flaws.
Suppose in a construction project, we
would be interested in the Technical
performance based on planned bricks
with weight of 2 KG versus actual weight
being 2.4 KG.
Measuring such Technical performance
gives an indication of the success
chances of Project.
www.GLOBALSKILLUP.com
Chapter 11 - Debrief
www.GLOBALSKILLUP.com
THIS BRINGS TO “RISK MANAGEMENT” COMPLETION.
From what we have understood so far is:
 6 Risk Management Knowledge Area Processes
 Identified their Inputs, Tools & Techniques, Outputs
Chapter 11
www.GLOBALSKILLUP.com
PMP Group Trainings across India
Bangalore | Hyderabad | Pune | Delhi | Chennai | Mumbai | Noida | Gurgaon
Online Trainings Too
www.GLOBALSKILLUP.com
Acknowledgements & Disclaimer
PMI, PMBOK, PMP, CAPM, PgMP, PMI-
ACP, PMI-RMP, PMI-SP are registered
marks of Project Management Institute,
Inc.
All registered trademarks, symbols, names
are marks of their respective owners and
acknowledged.

Contenu connexe

Tendances

OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
Idris Animasaun, PMP
 
Project Management Foundations Series Course 103 - Project Stakeholder Manage...
Project Management Foundations Series Course 103 - Project Stakeholder Manage...Project Management Foundations Series Course 103 - Project Stakeholder Manage...
Project Management Foundations Series Course 103 - Project Stakeholder Manage...
Think For A Change
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk management
s. Akhlaque
 
Project managemenet knowledge areas
Project managemenet knowledge areasProject managemenet knowledge areas
Project managemenet knowledge areas
linajarruti
 

Tendances (20)

Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
CCP_SEC5_ Project Management
CCP_SEC5_ Project ManagementCCP_SEC5_ Project Management
CCP_SEC5_ Project Management
 
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
OVERVIEW OF PROJECT MANAGEMENT KNOWLEDGE AREAS 2
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 
Project Management Foundations Series Course 103 - Project Stakeholder Manage...
Project Management Foundations Series Course 103 - Project Stakeholder Manage...Project Management Foundations Series Course 103 - Project Stakeholder Manage...
Project Management Foundations Series Course 103 - Project Stakeholder Manage...
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
project management essentials
project management essentialsproject management essentials
project management essentials
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk management
 
Project managemenet knowledge areas
Project managemenet knowledge areasProject managemenet knowledge areas
Project managemenet knowledge areas
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project Life Cycle and Phases with Risk Management discussion
Project Life Cycle and Phases with Risk Management discussionProject Life Cycle and Phases with Risk Management discussion
Project Life Cycle and Phases with Risk Management discussion
 
UNIT 1
UNIT 1UNIT 1
UNIT 1
 
1_PMI-RMP_Project Risk Management Plan
1_PMI-RMP_Project Risk Management Plan1_PMI-RMP_Project Risk Management Plan
1_PMI-RMP_Project Risk Management Plan
 
PMI Project Management Principles
PMI Project Management PrinciplesPMI Project Management Principles
PMI Project Management Principles
 
Project management processes Groups
Project management processes GroupsProject management processes Groups
Project management processes Groups
 
11 project risk management
11 project risk management11 project risk management
11 project risk management
 
Project Management
Project ManagementProject Management
Project Management
 
Project management
Project managementProject management
Project management
 
Online PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsOnline PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groups
 

En vedette

Procurment Management
Procurment ManagementProcurment Management
Procurment Management
wellanet
 

En vedette (13)

Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
 
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
 
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for ExamEasy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
 
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
 
PMP CAPM Study Guide Procurement Management
PMP CAPM Study Guide Procurement ManagementPMP CAPM Study Guide Procurement Management
PMP CAPM Study Guide Procurement Management
 
Procurment Management
Procurment ManagementProcurment Management
Procurment Management
 
12 pmp procurement management exam
12 pmp procurement management exam12 pmp procurement management exam
12 pmp procurement management exam
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
Project Procurment Management
Project Procurment ManagementProject Procurment Management
Project Procurment Management
 
1
11
1
 
Pmp6
Pmp6Pmp6
Pmp6
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
2
22
2
 

Similaire à Online PMP Training Material for PMP Exam - Risk Management Knowledge Area

2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1
reddvise
 
Project Risk Management_intro
Project Risk Management_introProject Risk Management_intro
Project Risk Management_intro
Alex Iskandar
 

Similaire à Online PMP Training Material for PMP Exam - Risk Management Knowledge Area (20)

Projectriskmanagement pmbok5
Projectriskmanagement pmbok5Projectriskmanagement pmbok5
Projectriskmanagement pmbok5
 
Critical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_enCritical role of_risk_assessment_in_international_projects_en
Critical role of_risk_assessment_in_international_projects_en
 
2.11 risk management 1
2.11 risk management 12.11 risk management 1
2.11 risk management 1
 
Project mngmnt risks3.2
Project mngmnt risks3.2Project mngmnt risks3.2
Project mngmnt risks3.2
 
Risk Management Best Practices
Risk Management Best PracticesRisk Management Best Practices
Risk Management Best Practices
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
 
Managing risk as Opportunity
Managing risk as OpportunityManaging risk as Opportunity
Managing risk as Opportunity
 
16 Risk-final- V Imp.ppt
16 Risk-final- V Imp.ppt16 Risk-final- V Imp.ppt
16 Risk-final- V Imp.ppt
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
Planning risk responses and Risk Controlling
Planning risk responses and Risk ControllingPlanning risk responses and Risk Controlling
Planning risk responses and Risk Controlling
 
Presentation Project managment
Presentation Project managmentPresentation Project managment
Presentation Project managment
 
Risk Management Assignment
Risk Management AssignmentRisk Management Assignment
Risk Management Assignment
 
Project Risk management
Project Risk managementProject Risk management
Project Risk management
 
Control only.pdf
Control only.pdfControl only.pdf
Control only.pdf
 
bpm-risk-analysis
bpm-risk-analysisbpm-risk-analysis
bpm-risk-analysis
 
Project Risk Management_intro
Project Risk Management_introProject Risk Management_intro
Project Risk Management_intro
 

Dernier

internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
AllTops
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
Nimot Muili
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
SandaliGurusinghe2
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 

Dernier (14)

W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docx
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 

Online PMP Training Material for PMP Exam - Risk Management Knowledge Area

  • 4. www.GLOBALSKILLUP.com Chapter 11 Objectives Understand the different Risk Management Processes Their Inputs, Tools and Techniques, Outputs This chapter entails one to understand the various Risk Management aspects required to identify, remove and harness threats or opportunities. Driving the project towards the desired outcome while the project progresses with minimal impact to the project objectives being accomplished to make the project successful!
  • 5. www.GLOBALSKILLUP.com It includes the processes to ensure the project risks are identified, analyzed, acted, planned with responses and controlled for minimal impact on project objectives. Project Risks can be broadly categorized based on the level of knowledge we have upon them. Known Risks. The risks which are identified and are aware to the project management team. Unknown Risks. The risks which are not yet identified & might occur instantaneously without prior knowledge. Risks should be perceived as: Overall Project Risk. This is the holistic risk of the project itself considering all individual project risks along with any other unknown risks beyond the project control. Individual Project Risks. Risks which can standalone or in a category group well within reach of the project which impact partially or a complete project objective set. Knowledge Area: Risk Management
  • 6. www.GLOBALSKILLUP.com There are 6 Risk Management processes, namely: 1. Plan Risk Management Process of ensuring the Risk management is planned in detailed manner which can be applied over the course of the project. 2. Identify Risks Identification of Risks over the Course of the Project and documentation of their characteristics. 3. Perform Qualitative Risk Analysis Performing a qualitative analysis of risks and conditions to prioritize their effects on project objectives. 4. Perform Quantitative Risk Analysis Measuring the probability and consequences of risks and estimating their implications for project objectives. 5. Plan Risk Responses Once Risks are prioritized and weighted, each of risks are provided a response plan (Avoid, Transfer, Mitigate, Accept for Negative Risks and Exploit, Enhance, Share, Accept for Positive Risks) 6. Control Risks Controlling Risks over the duration of the project to the benefit of the project objectives. Knowledge Area: Risk Management
  • 7. www.GLOBALSKILLUP.com Risk responses by Stakeholders /Organizations depend on:  Risk Appetite. Degree of Risk which will be taken up in order to gain a reward. Variations are measured over course of the project in LCL (Lower Control Limit) & UCL(Upper Control Limit) to understand the stakeholder risk appetite levels.  Risk Tolerance Levels. Degree of Risk which will be entertained beyond which the attention is required.  Risk Threshold Levels. Extreme Levels of Risk either on lower side or upper side. Crossing the lower side, the Risk is absolutely negligible and crossing the upper side, the Risk will not be tolerated any further. Knowledge Area: Risk Management Total Cost to Sponsor/Stakeholder {Project Cost {Contingency Reserve Actual Work Cost { { Management Reserve Tolerance Level Threshold Level Appetite
  • 8. www.GLOBALSKILLUP.com 11.1 Plan Risk Management Inputs •Project Management Plan •Project Charter •Stakeholder Register •Enterprise Environmental Factors •Organizational Process Assets Tools & Techniques •Analytical Techniques •Expert Judgment •Meetings Outputs •Risk Management Plan •Integration •Develop Project Management Plan •Scope •Plan Scope Management •Collect Requirements •Define Scope •Create WBS •Time •Plan Schedule Management •Define Activities •Sequence Activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule •Cost •Plan Cost Management •Estimate Costs •Determine Budget •Quality •Plan Quality Management •Human Resource •Plan HR Management •Communications •Plan Communications Management •Risk •Plan Risk Management •Identify Risks •Perform Qualitative Risk Analysis •Perform Quantitative Risk Analysis •Plan Risk Responses •Procurement •Plan Procurement Management •Stakeholder •Plan Stakeholder Management Planning Process Risks are uncertain events which may trigger positive or negative impact on the project outcome. Planning risk management involves end to end management of risks involved in the project. Key benefit of this process ensures the degree, type and visibility of risks are given right and required risk ratings. Risks in the project have to be dealt with due diligence and with complete understanding of the same from all the stakeholders. Risk management starts much before the project is actually conceived. Identified risks are then in the later stages managed to be minimized, exploited and if not planned for contingencies. Risks are regularly revisited and reviewed over the duration of the project.
  • 9. www.GLOBALSKILLUP.com Analytical Techniques help understand the holistic view of the Risks on the project. One mechanism beneficial to diagnose and understand the tolerance and risk appetite levels of the decision makers/stakeholders. This definitely helps understand the amount of risks which can be handled and which need to be pitched as immediate escalation points on the project. Analytical Techniques
  • 10. www.GLOBALSKILLUP.com This plan defines how the risk activities will be performed on the project. It may include the following: Methodology Defined approach along with the tools to perform Risk management Roles and responsibilities Defines risk management resources roles & responsibilities Budgeting Helps estimate budget to ensure the required reserves are defined Timing Time when the information has to be conveyed Risk categories Risks may be categorized into multiple categories based on the project being performed. They may be grouped based on various approaches. RBS(Risk Breakdown Structure) helps identify risks from multiple sources identified in risk identification exercise and categorize them in a structured manner for ease of addressing them. Risk Management Plan
  • 11. www.GLOBALSKILLUP.com Definitions of Risk Probability and Impact: Define the probability and impact definitions that will be used in the project. Sample Impact Definition Table is shown here. Probability and Impact Matrix Risk Management Plan Very Low 0.10 Low 0.25 Moderate 0.50 High 0.75 Very High 0.90 Scope Insignificant Changes Changes Moderate Changes Major Changes Major Significant Changes Time <5% Increased Timeline <25% Increased Timeline 25-50% Increased Timeline 50-70% Increased Timeline >70% Increased Timeline Cost <5% Increased Project Cost <25% Increased Project Cost 25-50% Increased Project Cost 50-70% Increased Project Cost >70% Increased Project Cost Quality Quality Changes Not Significant Quality May Need To Be Improved Sponsor Needs To Approve The Quality Product Quality Is Not Acceptable To Sponsor End Product Quality Is Useless Very Likely Most Likely Likely Chance of Likely Unlikely Probability /Impact Very Low Low Moderate High Very High Revised Stakeholders’ Tolerances Continuous revision of stakeholders tolerances based on their risk appetite over project duration. Reporting Formats Define the report formats which include the manner, risks will be documented, formatted, communicated to which stakeholder group. Tracking Risk Tracking is very important as the risks continuously evolve from one quadrant to another. Recording of their risk movements is equally important from the Risk Auditing perspective.
  • 12. www.GLOBALSKILLUP.com 11.2 Identify Risks Inputs •Risk, Cost, Schedule, Quality, HR Management Plan •Scope Baseline •Activity Cost Estimates •Activity Duration Estimates •Stakeholder Register •Project Documents •Procurement Documents •Enterprise Environmental Factors •Organizational Process Assets Tools & Techniques •Documentation Reviews •Information Gathering Techniques •Checklist Analysis •Assumptions Analysis •Diagramming Techniques •SWOT Analysis •Expert Judgment Outputs •Risk Register •Integration •Develop Project Management Plan •Scope •Plan Scope Management •Collect Requirements •Define Scope •Create WBS •Time •Plan Schedule Management •Define Activities •Sequence Activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule •Cost •Plan Cost Management •Estimate Costs •Determine Budget •Quality •Plan Quality Management •Human Resource •Plan HR Management •Communications •Plan Communications Management •Risk •Plan Risk Management •Identify Risks •Perform Qualitative Risk Analysis •Perform Quantitative Risk Analysis •Plan Risk Responses •Procurement •Plan Procurement Management •Stakeholder •Plan Stakeholder Management Planning Process Risks are uncertain events and identification of them early leads us to better preparation with suitable action plans. Documentation of the identified risks with their characteristics helps us be prepared in likely or unlikely situation of the Risk occurrence. Documentation of the risks in a consistent manner will provide sufficient detail so as to compare them with each other and suitable associated action response plan be derived. This process of identification of risks is iterative and has to be performed across the intervals of the project duration.
  • 13. www.GLOBALSKILLUP.com Risk Register is a document which records the Risk Analysis and Risk Response Planning. This document evolves as the project progresses and is a live document. Risk Register provides input about the Risk events to impact resource selection and availability during the Estimate Activity Resources leading to more finer estimates. List of Identified Risks: Identified risks are detailed as much possible including the root cause. Risk statements may be used in conjunction to triggers such as Event->Impact and/or Event -> Effect. List of Potential Responses: During the identification of the risks, there may be situations where in the risk response is readily known. These potential responses should be recorded. While the project progresses, the risks registered are continuously reviewed for triggers and/or risk responses. Risk Register
  • 14. www.GLOBALSKILLUP.com Documentation Reviews A detailed study or review of the various project documents may help indicate and identify the risks in the project. Various documents which may be subjected to review, but not limited to: Plan Documents Assumptions Previous Project Documents Legal Documents Compliance Considerations Organizational Policies Databases Historical Plans Information may be gathered in various formats: Brainstorming Delphi Technique Interviewing Root Cause Analysis Information Gathering Techniques
  • 15. www.GLOBALSKILLUP.com Checklist Analysis Risk Identification Checklists may be evolved over a period of time in any organization which become a ready reckoner for identification of risks. However, proper care should be taken to explore risks beyond the Checklist itself as this may not be comprehensive to every project running in the organization. Every project is conceived based on certain assumptions, scenarios and possible postulate. Each one of these need to be evaluated and understood in the context of the project in progress. AssumptionAnalysis Certain Un Certain LeastImportant MostImportant Critical Region A AA AA A A A A A A A A
  • 16. www.GLOBALSKILLUP.com Diagramming Techniques Diagramming techniques involve the usage of the diagramming methods based on which the risks can be identified. Such as: Ishikawa’s Fish Bone Diagram System or Process Flow Charts Influence Diagrams – Helps to identify the decision tree. As shown below. Strengths, Weakness, Opportunities, Threats Analysis in short is known as SWOT analysis. Analysis of the Project is performed to diagnose the Strengths, Weakness, Opportunities, Threats. This is first done in a manner to identify Strengths and Weakness. Then based on Strengths, opportunities are further explored. Similarly based on weakness, threats are further explored. SWOTAnalysis Strengths - Strong Brand Awareness among Customers Weakness - Low Funds for Expansion Opportunities - Build Partnerships - Increase Investments Threats - Increased Competition & Marketing Spends Fund Research Market Value Launch Product Research Success Market Success Influence Diagram
  • 17. www.GLOBALSKILLUP.com 11.3 Perform Qualitative Risk Analysis Inputs •Risk Management Plan •Scope Baseline •Risk Register •Enterprise Environmental Factors •Organizational Process Assets Tools & Techniques •Risk Probability And Impact Assessment •Probability And Impact Matrix •Risk Data Quality Assessment •Risk Categorization •Risk Urgency Assessment •Expert Judgment Outputs •Project Document Updates •Integration •Develop Project Management Plan •Scope •Plan Scope Management •Collect Requirements •Define Scope •Create WBS •Time •Plan Schedule Management •Define Activities •Sequence Activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule •Cost •Plan Cost Management •Estimate Costs •Determine Budget •Quality •Plan Quality Management •Human Resource •Plan HR Management •Communications •Plan Communications Management •Risk •Plan Risk Management •Identify Risks •Perform Qualitative Risk Analysis •Perform Quantitative Risk Analysis •Plan Risk Responses •Procurement •Plan Procurement Management •Stakeholder •Plan Stakeholder Management Planning Process Performing a qualitative analysis of risks and conditions to prioritize their effects on project objectives. Key benefit of this process is to ensure the specialized focus is on the high quality risks. This is done through out the project duration and will cause re- assessment of certain risks as the project evolves. In order to ensure there is no influence or bias on the assessment, the probability and impact definitions are defined upfront. This also helps in establishing “perform quantitative risk analysis”.
  • 18. www.GLOBALSKILLUP.com Risk Probability Assessment investigates the likelihood that each specific risk will occur. Risk Impact Assessment investigates the impact on the outcome of the project on Scope, Time, Cost, Quality parameters should the risk occur. Each risk is analyzed for both probability and impact assessment. Risk probabilities and impacts are rated based on the definitions in the Risk Management Plan. All risks are rated based on their assessed probability and impact as defined in the matrix. Each of the risks are color coded and accordingly paid attention. The Risks which are more darker in color lead to more attention from the project management team. Probability ↓ Threats (Negative Risks) Opportunities (Positive Risks) 0.90 .0090 .2250 .4500 .6750 .8100 .8100 .6750 .4500 .2250 .0090 0.75 .0075 .1875 .3750 .5625 .6750 .6750 .5625 .3750 .1875 .0075 0.50 .0050 .1250 .2500 .3750 .4500 .4500 .3750 .2500 .1250 .0050 0.25 .0025 .0625 .1250 .1875 .2250 .2250 .1875 .1250 .0625 .0025 0.10 .0010 .0250 .0500 .0750 .0900 .0900 .0750 .0500 .0250 .0010 Impact → Very Low 0.10 Low 0.25 Moderate 0.50 High 0.75 Very High 0.90 Very High 0.90 High 0.75 Moderate 0.50 Low 0.25 Very Low 0.10 Risk Probability & Impact Assessment
  • 19. www.GLOBALSKILLUP.com A detailed study of the supplementary data for each risk helps ensure each risk is paid rightful attention. This involves the degree of examination of the data about the risk is known and understood. Parameters based on which the data quality assessment is performed usually involves accuracy, quality, reliability and integrity of the data about the risk. Risks may be categorized based on the: Sources of Risk Identified Which affect a particular project area Common root causes Common actions or solutions adopted for risks and so on.. Risk Data Quality Assessment Risk Categorization
  • 20. www.GLOBALSKILLUP.com Risks which need immediate attention from the perspective of time criticality are required to be acted upon quickly. Based on the time criticality, the risk priorities define the Risk Rank Ratings. Risk Urgency Assessment
  • 21. www.GLOBALSKILLUP.com 11.4 Perform Quantitative Risk Analysis Inputs • Risk, Cost, Schedule Management Plan • Risk Register • Enterprise Environmental Factors • Organizational Process Assets Tools & Techniques • Data Gathering and Representation Techniques • Quantitative Risk Analysis and Modeling Techniques • Expert Judgment Outputs • Project Document Updates •Integration •Develop Project Management Plan •Scope •Plan Scope Management •Collect Requirements •Define Scope •Create WBS •Time •Plan Schedule Management •Define Activities •Sequence Activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule •Cost •Plan Cost Management •Estimate Costs •Determine Budget •Quality •Plan Quality Management •Human Resource •Plan HR Management •Communications •Plan Communications Management •Risk •Plan Risk Management •Identify Risks •Perform Qualitative Risk Analysis •Perform Quantitative Risk Analysis •Plan Risk Responses •Procurement •Plan Procurement Management •Stakeholder •Plan Stakeholder Management Planning Process Key benefit is to measure the probability and consequences of risks and estimating their implications for project objectives. Helps in reducing the project uncertainty by performing the quantitative risk analysis. It is mostly used to evaluate the aggregate effect of all risks affecting the project. Performing this process requires budget and involves cost. This Cost benefit should be evaluated before this process can be exercised.
  • 22. www.GLOBALSKILLUP.com Commonly used approaches involve: 1. Sensitivity Analysis 2. Expected Monetary Value analysis 3. Modeling and Simulation Quantitative RiskAnalysis and Modeling Techniques 1. Sensitivity Analysis This analysis helps identify the most potential impact on the project. A sample Tornado Diagram shows how it is performed. -3000 -2000 -1000 0 1000 2000 3000 4000 5000 6000 Risk 5 Risk 4 Risk 3 Risk 2 Risk 1 Inverted Tornado Diagram Negative Impact Positive Impact
  • 23. www.GLOBALSKILLUP.com Quantitative RiskAnalysis and Modeling Techniques 2. Expected Monetary Value(EMV) Highest EMV wins. This type of analysis provides the future possible income or outgo values based on the statistical probability and impact values. Risk A Risk C 80% likely Risk B 20% likely Outcome1 70% likely Outcome2 10% likely Outcome3 20% likely INR 100 Lakh Implication INR 35 Lakh Implication INR 65 Lakh Implication INR 100 Lakh Implication INR 30 Lakh Implication
  • 24. www.GLOBALSKILLUP.com What is your Investment decision based on Risk? New Product or Maintain? New Product Development Investment $60M Maintain Product Investment $30M Strong Sales Revenue: $150M Weak Sales Revenue : $70M Strong Sales Revenue : $80M Weak Sales Revenue : $20M
  • 25. www.GLOBALSKILLUP.com What is your Investment decision based on Risk? New Product or Maintain? New Product Development Investment $60M Maintain Product Investment $30M Strong Sales Revenue : $150M Weak Sales Revenue : $70M Strong Sales Revenue : $80M Weak Sales Revenue : $20M 150-60 = $90M 70-60 = $10M 80-30 = $50M 20-30 = -$10M 70% Chance 30% Chance 70% Chance 30% Chance
  • 26. www.GLOBALSKILLUP.com Investment decision is based on lowest risk (eliminating -10M) as well as based on highest EMV(66M) New Product or Maintain? New Product Development Investment $60M Maintain Product Investment $30M Strong Sales Revenue : $150M Weak Sales Revenue : $70M Strong Sales Revenue : $80M Weak Sales Revenue : $20M 150-60 = $90M 70-60 = $10M 80-30 = $50M 20-30 = -$10M EMV of New Product = 70% * 90 + 30% * 10 = 63 + 3 = $66M 70% Chance 30% Chance 70% Chance 30% Chance EMV of Maintain = 70% * 50 + 30% * -10 = 35 + (-10) = $25M
  • 27. www.GLOBALSKILLUP.com Quantitative RiskAnalysis and Modeling Techniques 3. Modeling and Simulation This type of analysis is performed when the actual cost of performing activities may have multiple variables and could cost immensely to actually perform feasibility in reality. Monte Carlo Simulation provides unique multiple iterations of outcomes based on the predefined trigger values and parameters using which these simulations are performed statistically using a computing machine. Example: Simply treat it as a task repeated over many times with different variables over a project schedule network. What will be the output? Will it vary every time? Yes. Though repetitions of the task many times will give us a precise range of how many days +/- it would take to accomplish that. That is how the Simulations would help you come up with almost certain range of all. This includes the probability of the risks on the Project as well. Benefits of such Monte Carlo or any other simulation includes: - Almost precise calculations considering many parameters for Cost estimates, Schedule estimates, Overall risk and so on. - Since it includes path convergence for the schedule network, the complexity of every task is accounted, which brings more stability in estimates.
  • 28. www.GLOBALSKILLUP.com Monte Carlo Simulation Explained Project or Investment Decision Risk of Investment 40,000 People, 2B$ Cost, 800 Machines 5 Years Project Risk of Investment 20,000 People, 3B$ Cost, 600 Machines 10 Years Project . . . . . . . . . . . . Definitive Range of Years based on Multiple Risk Based Scenarios . . . . . . . .
  • 29. www.GLOBALSKILLUP.com 11.5 Plan Risk Responses Inputs • Risk Management Plan • Risk Register Tools & Techniques • Strategies For Negative Risks Or Threats • Strategies For Positive Risks Or Opportunities • Contingent Response Strategies • Expert Judgment Outputs • Project Management Plan Updates • Project Document Updates •Integration •Develop Project Management Plan •Scope •Plan Scope Management •Collect Requirements •Define Scope •Create WBS •Time •Plan Schedule Management •Define Activities •Sequence Activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule •Cost •Plan Cost Management •Estimate Costs •Determine Budget •Quality •Plan Quality Management •Human Resource •Plan HR Management •Communications •Plan Communications Management •Risk •Plan Risk Management •Identify Risks •Perform Qualitative Risk Analysis •Perform Quantitative Risk Analysis •Plan Risk Responses •Procurement •Plan Procurement Management •Stakeholder •Plan Stakeholder Management Planning Process This is one of the most important Risk Management processes as we step into the effective actions and evaluate options of how to address these prioritized risks. Key benefits of this includes the allocation of budget, resources and schedule for the identified and actionable risks. From the multiple options available to response for each risk it is imperative to understand which option/response will be most appropriate in the context of the project limits. Risks include both threats and opportunities for which the responses can be developed and initiated for action.
  • 30. www.GLOBALSKILLUP.com Negative Risks or Threats can be acted with response in following manner: 1. Avoid 2. Transfer 3. Mitigate 4. Accept (Applicable for both Negative Threat & Positive Opportunity) Avoid Where possible it is always recommended to ensure the critical risks are completely avoided either by eliminating the threat or by ensuring the project is shielded completely from the impact of the threat. Most radical extreme step to avoid risk would be to shutdown the project itself. Transfer Transfer of risk to a third party for a price ensures the risk even if it occurs minimizes the impact on the project, since it is offset with the third party. Risks which are transferred to a third party involves risks with major cost implication to project. Transfer of the risk, does not eliminate risk itself, it just transfers the ownership to a third party. Mitigate Project team acts to minimize the impact & probability of the risk over a period of time to ensure the risk is brought to minimal state or completely eliminated. Accept Team acknowledges the risk and waits until the risk occurs to respond on it. Active Acceptance – Build a contingency reserve to ensure when the risk occurs it is readily acted with the contingency (time, cost, scope, quality). Passive Acceptance – It is documented and then awaited until risk occurs, so that further action can be taken up. Strategies For Negative Risks Or Threats Critical Risks with High Impact Less Critical Risks with Low Impact Avoid Good Strategy Mitigate Good Strategy Transfer Good Strategy Accept Good Strategy
  • 31. www.GLOBALSKILLUP.com Positive Risk Example: A potential delay in the delivery of materials which happened to be delivered ahead of time. This risk is now an opportunity to check on the schedule what work can be done already in advance given the availability of materials. Positive Risks or Opportunities can be acted with response in following manner listed below. 1. Exploit 2. Enhance 3. Share 4. Accept (Passive Acceptance Only) Exploit When there are risks which can be beneficial to the organization, it is natural that these risks are driven towards ensuring Risk occurs. Enhance When you want to increase the probability or likely chances to ensure the risk occurs by maximizing the possibilities of risk occurrence. Share Sharing of the risk to third party for maximum throughput when we make the risk occur to maximize risk out come. Accept Accepting the risk to harness the opportunity when the risk actually arises on its own and not actively pursuing. Strategies for Positive Risks or Opportunities
  • 32. www.GLOBALSKILLUP.com Some of the responses are planned only when the risks will occur such as in Accept – Active Acceptance. In such a response planning, a contingent reserve or a fall back plan is established so as to respond appropriately upon the occurrence of such a risk. There is no substitute to experience when it comes to Contingent Response Strategies – Expert Judgment stays on top of the list strategy. While many project managers simply prefer to have a transfer of risks when they occur, rather than manage in practice. Contingent Response Strategies
  • 33. www.GLOBALSKILLUP.com 11.6 Control Risks Inputs •Project Management Plan •Risk Register •Work Performance Data •Work Performance Reports Tools & Techniques •Risk Reassessment •Risk Audits •Variance and Trend Analysis •Technical Performance Measurement •Reserve Analysis •Meetings Outputs •Work Performance Information •Change Requests •Project Management Plan Updates •Project Document Updates •Organizational Process Assets Updates •Integration •Monitor and Control Project Work •Perform Integrated Change Control •Scope •Validate Scope •Control Scope •Time •Control Schedule •Cost •Control Costs •Quality •Control Quality •Human Resource •Communications •Control Communications •Risk •Monitor & Control Risks •Procurement •Control Procurements •Stakeholder •Control Stakeholder Management Monitoring & Controlling Process It is the process of controlling risks during the project by monitoring existing risks, their response plans, risk movements, identification of new risks, elimination of outdated risks to ensure the project objectives are least harmed or nil impact due to risks. Key benefit includes the effective Risk management and its minimized or nullified risk impact on the project objectives. This process also ensure the planned risk management processes are being followed during the course of the project and any further improvements to the risk processes are adopted.
  • 34. www.GLOBALSKILLUP.com Risk Reassessment It is a continuous process through out Project life cycle and performed across all Process Groups. Risk Reassessments should be carried out frequently to perform the new risk identification, re-planning the risk responses, close the outdated risks. Based on the project size and the organizational practice, the project management team and/or specialized risk management team reassess the risks at frequent intervals. Identify Observe RegulateClose Re-Assess
  • 35. www.GLOBALSKILLUP.com More Tools & Techniques Variance & Trend Analysis Performance baselines defined in the project should be constantly monitored for any variances. Also based on the trend analysis of baseline performance, suitable actions should be planned, including further risk identification and actions in the Project. Technical Performance Measurement Technical performance of the Project is usually measured based on the type of project we execute. Suppose in a software project, we would be interested in the Technical performance of Planned Flawless Modules against Actual Modules with Flaws. Suppose in a construction project, we would be interested in the Technical performance based on planned bricks with weight of 2 KG versus actual weight being 2.4 KG. Measuring such Technical performance gives an indication of the success chances of Project.
  • 37. www.GLOBALSKILLUP.com THIS BRINGS TO “RISK MANAGEMENT” COMPLETION. From what we have understood so far is:  6 Risk Management Knowledge Area Processes  Identified their Inputs, Tools & Techniques, Outputs Chapter 11
  • 38. www.GLOBALSKILLUP.com PMP Group Trainings across India Bangalore | Hyderabad | Pune | Delhi | Chennai | Mumbai | Noida | Gurgaon Online Trainings Too
  • 39. www.GLOBALSKILLUP.com Acknowledgements & Disclaimer PMI, PMBOK, PMP, CAPM, PgMP, PMI- ACP, PMI-RMP, PMI-SP are registered marks of Project Management Institute, Inc. All registered trademarks, symbols, names are marks of their respective owners and acknowledged.