Project design and management contributions to improve IITA’s Research for Development program
1. Project design and management
contributions to improve IITA’s
Research for Development program
Braima James
Candidate
Deputy Director
Project development and management
IITA
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
2. Outline
The job
R4D environment
Project planning
- Overview
- Specify problem Planning aims to coordinate decisions
- Agreeing objectives in an attempt to influence, direct and
- Analyze options control the future in order to achieve
- Plan of operations certain predetermined objectives
If IITA were a donor…
- Bank of CNs
- Control management
- MIS
Conclusions
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
3. 1. The job
7 key responsibility areas 26yrs post-PhD experience
Lead responses to funding opportunities Managed 10 projects of US9m, 38% of which
I led in proposal development
Facilitate project proposals development 25 projects: 11 successful, 9 pending, 6
unfunded or refused
Strengthen use of appropriate design for UNDP-ESCaPP; IFAD/CGM; CG-NGOIPM; SDC
proposal development cowpea & vegs; FAO cassava & Striga; ADA
vegs; NRC vegs; BI-WAFRINET; SPIPM
Develop/conduct training programs to Project planning/management, UK; IPM tools,
strengthen project management at IITA Australia; Corporate governance, FARA
Facilitate development of strategic IITA-Benin; HVP; PRSP-SL; initiatives with
initiatives/internal proposals CFC, UEMOA, UNIDO;3 partnership wshps pa;
Facilitate partnerships for smooth Inclusive partnerships through projects
implementation of projects development and coordination
Collaborate with CGO & DDG-RS: recruit MoU with host-countries, CIRAD, NRC-Norway
staff; establish sites; monitor progress
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
4. 2. R4D environment: MTP projects
MTP legacies on SC priorities CLS HVP AH RTS BPS AB OT
Gene conservation & use
Increased knowledge/tech
Improved/stabilized profitability
High food & nutritional quality
Efficient labour-use
Self reliant NARS/capacity dev
Markets/informed enterprises
Policy advice/ext environment
Suggestion
- Consider placing some the 3 thematic projects within commodity MTP projects
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
5. R4D environment: many special projects, one mission
Suggestions
- Coordinate results generation into common impact to achieve IITA mission
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
6. 3. Project planning: Overview
SPECIFY
Formulate strategy PROBLEM Implement strategy
- Leadership - Long-term
- Decision-making - Anticipate changes
- Communications - Proactive/ideas/vision
MONITOR ANALYSE
PROGRESS PLANNING CYCLE
OPTIONS
- Work culture Short-term
- Resources - Reactive/tactical
- Authority levels - Reverse losses
CONTROL
Strategy: STANDARDS Implementation:
Establish key targets in Forecast & correct changes
social, political, in target environment and
technology & economic justify ones position and
environment & show proposals to deliver the
means to fulfil them desired change
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
7. Specify problem/a good problem statement
Situation
- What situation needs change? Allocate $ to BC or
experiential learning or both?
- Who/what/region is affected?
- Magnitude of the problem?
Causes (not symptoms)
- Why does problem exists?
- Single or multiple causes? Functional Leaf loss in S. macrocarpon:
group Mite population density per leaf
- Are causes interdependent?
On-station On-farm
Consequences
8.6 5.5 159.8 52.9
- Population size affected? Pest mite
Predators 8.3 1.5 1.6 0.6
- Political, cultural, economic?
Suggestions
- Intensive problem analyses is pivotal to resource mobilization/allocation
- Learn PSW tools: Surveys; historical profiles; consultations, pinboarding
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
8. Agreeing objectives/the desired future
SMART Objectives
- State what will/should happen DD-Projects: Authority environment
- Specify project expectations
- Clarify how to influence future Negotiated
Agree, not set, objectives
- More motivated implementers
Existing
- Maximise chances of achievement
- Inputs of diverse expertise
- Realistic plans/complement capacity Imposed
- Confident decision-making: managers
Suggestions
- Invest in professionally facilitated project planning workshops
- Greater involvement of potential partners in a timely manner
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
9. Agreeing objectives: MTP project strategy
Diverse expertise: IITA, AVRDC, ARC, ICIPE, NARS Benin, Ghana, Nigeria, Togo
Suggestion
- Harmonize strategic planning approaches across MTP projects
- Specify research/thrusts (= central pillars/strategic objectives. HVP now has 4
research thrusts: a) Productivity growth; b) Market efficiency & enterprise; c)
Nutritional quality & product diversity; d) Policies & institutional arrangements
- Position component projects within strategic objectives per MTP projects
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
10. Agreeing objectives: Template to position projects
Equivalent objectives to propose
Hierarchy of Description
Strategic plan Component projects
expectations
Goal - Greater why Mission Problem statement in
- Summarise rationale executive summary
Purpose - Change/impact needed Vision/research thrusts Basis of goal statement
- Motivation for outputs
Output - Specific deliverables Strategic objective/RT Basis of purpose
- ToR for projects
Activities - How/action Responses/RT Basis of outputs
Output - What? Qty/quality N/A Output targets
target - Location, time
Activities - How/action N/A Activities & resources
Suggestions
- Hands on training/common understanding of hierarchy of objectives
- Incorporate AU projected 6% annual productivity gain into planning process
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
11. Analyse options: Feasibility of tasks
Decision Tree Analysis
- Conceptual map of potential decisions/outcomes on activities to produce OTs
Start task: step 1 Step 1 succeeds Step 2 succeeds Continue
Step 1 fails Step 2 fails
1
= Decide
= Continue or exit/hand over
= Abandon task
Suggestions
- Test consequences of tasks prior to implementation
- Review/merge or develop alternative tasks based on possible consequences
- Visualize contingences, exit/handover of tasks (link to stakeholder analysis)
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
12. Analyse options: Relative feasibility of output targets
Force Field Analysis, e.g. IITA biopesticides
10
Learning
Specificity Durability
Demand Average
5 Production
Expertise
+ve forces
0
-ve forces
Application
-5
Average
2nd/other Toxicology
-10 pests Markets Registration Recruitment
Suggestions
- Assess/compare practicality of solutions (fertilisers, GMOs, biopesticides etc)
- Identify clear action points/inventory driving & restraining factors on OTs
- Minimize risks, amend/improve chances of success
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
13. Analyse options: Skills profiling
Confident HR decision making
- Identify skills required to deliver OT
- Analyse internal skills/within the group
- Negotiate synergies/linkages & cross functions
- Inventory of external skills
- Identify potential consultancy areas
Suggestions
- Stakeholder analysis helps place objectives within IITA control
- MTP projects may require pillar champions/coordinators
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
14. Plan of operations/writing
By this stage information is available to prepare a winning project proposal
- A strategy framework approved by RDC
- CNs approved by RDC to operationize the strategy
- Proposal writing includes PoP to indicate time, staff & $ resource allocation
Output 1: Collective action on MTP projects documented and lessons shared
Output target Activity 2007 timeframe Performance Responsible $
indicator
J F M A M J J A S O N D
MTP action Identify & prioritize RDC report DD-R & 000
initiatives emerging new themes on decisions Coordinator
published on
web Organize internal M&E/CCER DDG-R & 000
review report Coordinator
Facilitate strategic MTP strategy Consultant & 000
planning workshop document DD-R, DD-Proj
Recruit project Strategy DDG-R, CGO, 000
leadership operational HR
Convene symposium. 15 papers DD-R; 000
Coordinator
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
15. 4. If IITA were a donor: Bank of CNs
By end year 1 Benefits
Problem specification Coalition of interests in CNs
- Criteria to prioritize problem areas - Transparent decision making on CNs
- Justify technical, social, economic & - Ensure objectives are under IITA
environmental viability of CNs control
Which projects? Advocacy on donor policies
- SWOT CNs for robustness - Proactive donor intelligence
- Intranet-publicize database of CNs - Info support for investment
- Specify CNs which IITA would invest - Timely response to funding calls
in if it were a donor agency
- Basis of R4D $ mobilization/allocation
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
16. Control management: a control system
A good plan is achieved only if it is subjected to good system of control
- Output targets = control standards
- Monitor progress towards standards
- Compare results with standards
- Adjust objectives/flexibility
Suggestions
- Agree financial resource management tools with CGO, CFO and DD-R
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
17. Design a management information systems
Category Type of info required Source of the info Use of the info
Deliverables - What has been done? - Activity records - Plan future/year’s work
- Not done but planned? - Supervision reports - Identify successes
- Problems encountered? - Periodic reports - Identify strengths
- How problems solved? - Staff reviews - Identify weaknesses
- Change in ext situation? - Clients - Plan to overcome them
- How staff work as team? - Surveys - Review and evaluation
Suggestions
- Agree on categories of info and other MIS elements
- Agree on type of MIS required: formal, informal, extensive or limited
- Keep MIS simple, efficient and useful (advisory; not a spy in the cab!)
- Train/supervise project team in use of MIS
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
18. 5. Conclusion: I am suitable
IITA research results are the only tools we have to impact on national
(e.g., PRSP), regional (e.g. with SROs) and continental (e.g. CAADP)
agricultural development plans
I have summarized project planning & management tools & processes as
I know and apply in my work, and suggest each of us IRS learns such tools
for planning to improve effectiveness and usefulness of our research results
I have also suggested action areas to guide R4D decisions on projects &
increase IRS understanding & collective ownership of those decisions
I have drawn on 26yrs post-PhD experiences in education, partnership
building, project development, implementation/management & informal
discussions with colleagues to arrive at the summary I have provided
I believe I have clearly demonstrated that I am suitable for the
advertised position of DD-Project planning and management at IITA
International Institute of Tropical Agriculture – Institut international d’agriculture tropicale – www.iita.org
19. Thank you
I look forward to
working with you,
various authority
levels, SROs/NARS so
that together we help
improve IITA’s R4D
impact in the fight
against declining
livelihoods in SSA