SlideShare une entreprise Scribd logo
1  sur  5
Télécharger pour lire hors ligne
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 9, Issue 2 (Sep. - Oct. 2013), PP 10-14
www.iosrjournals.org
www.iosrjournals.org 10 | Page
The Performance Analysis of a Fettling Shop Using Simulation
Mathew Thomas
Department of Mechanical Engineering, Viswajyothi College of Engineering and Technology, Vazhakulam,
Muvattupuzha, Kerala, India.
Abstract: Fettling shop is the product finishing shop of casting products.After the knockout, the casting is taken
to the fettling shop for doing the fettling work. The fettling process includes cutting, shot blasting, grinding and
painting. In all these process the sand and extra metal on the castings are removed. The project titled „The
performance analysis of a fettling shop using simulation‟ is based on a fettling shop of a casting industry. The
main aim of the project is the performance analysis of the fettling shop. This project is a simulation based
project and is done using a simulation tool called arena. The main concepts related with the performance
analysis are Bottleneck analysis, Productivity analysis and System improvement analysis.
Keywords: Performance analysis, Fettling shop, Bottleneck, Simulation.
I. Introduction
The performance analysis is mainly done with Bottleneck analysis, Productivity analysis and System
improvement analysis. Here, performance analysis of the fettling shop is done using a simulation tool called
arena.
A. PERFORMANCE ANALYSIS
Performance analysis is the process of analyzing the performance of a system or a process. Here,
performance analysis of a casting industry fettling shop is done. The different performance analysis tools are
Bottleneck analysis, Productivity analysis and System improvement analysis. The main aim of the project is the
performance analysis of the fettling shop. This is a simulation based project and is done using a simulation tool
called arena.
B. FETTLING SHOP
The fettling shop is the product finishing shop of casting products.After the knockout, the casting is
taken to the fettling shop for doing the fettling work. The fettling process includes cutting, shot blasting,
grinding and painting. In all these process the sand and extra metal on the castings are removed.
C. BOTTLENECK
In engineering, a bottleneck is a phenomenon by which the performance or capacity of an entire system
is severely limited by a single component. Formally, a bottleneck lies on a system's critical path and provides
the lowest throughput. As such, system designers will try to avoid bottlenecks and direct effort towards locating
and tuning existing bottlenecks.
D. PRODUCTIVITY
Productivity is an average measure of the efficiency of production. Productivity is a ratio of production
output to input (i.e, capital, labor, land, materials, etc.). It is a measure of how well the resources are utilized to
produce an output. i.e, Productivity=Output/Input. The measure of productivity is defined as a total output per
one unit of a total input.
E.SYSTEM IMPROVEMENT
System improvement is the process of improving the overall performance of the system. The results of
system improvement are output maximization, production capacity improvement of the system, reduction of
waiting times, reduction of number of products waiting at workstations etc.
F.SIMULATION MODELING
Simulation modeling is the process of creating and analyzing a digital prototype of a physical model to
predict its performance in the real world. Simulation modeling allows designers and engineers to avoid repeated
building of multiple physical prototypes to analyze designs for new or existing parts.
The Performance Analysis Of A Fettling Shop Using Simulation
www.iosrjournals.org 11 | Page
G. BASIC PROCESS ARENA MODULES
The main basic process arena modules are shown below in table 1.These basic process arena modules
are used for modeling purposes
Module Name Symbol Function
Create Used as a source to generates new entities.
Assign Used to assign values to variables
Process Used as the main processing method
Record Used to collect statistics in a particular location in the model
Dispose Used as the exit point of entities from a simulation model
Table 1-Basic process arena modules
H. ADVANCED TRANSFER MODULES
The advanced transfer modules used for modeling process are request, transport, station and free.
Symbols & functions of advanced transfer modules are shown in table 2
Module Name Symbol Function
Request Used to assign a transporter unit to an entity and then to move the
unit to the entity’s location
Transport Used to transfer an entity controlling a transporter unit to a
destination.
Station Used to define a station or a set of stations.
Free Used to release the entity’s most recently allocated transporter unit.
Table 2-Advanced transfer modules
II. Literature Review
Timothy M. Elftman (1999) described about the examination of the effects of bottlenecks and
production control rules at assembly stations. In manufacturing centers, products manufactured at different
locations are often joined together at assembly stations. If not managed properly this common event can lead to
defective products, lost throughput, and increased WIP. All of which will result in lost capital for the
manufacturing center. Christoph Roser et.al (2002) suggested various techniques for shifting bottleneck
detection. This involves a novel method for detecting bottlenecks in manufacturing systems and the shifting of
these bottlenecks. All manufacturing systems are constrained by one or more bottlenecks. Improving the
bottleneck will improve the whole system.
Karthik Krishna et.al (2008) described the iterative use of simulation and scheduling methodologies to
improve productivity. It includes the integrated use of process simulation, production scheduling, and detailed
analysis of material-handling methods and their improvement. The study undertook the identification and
improvement of production and scheduling policies to the benefit of a manufacturing process whose original
throughput capacity fell significantly short of high and increasing demand. Prameth tantivanich et.al (2002)
suggested a simulation approach for productivity improvement of an IC factory. It is used to develop a
simulation model to intimate a real world IC assembly line in order to identify alternatives for productivity
improvement. Melaka (2009) described productivity analysis of table top fan assembly process using arena
simulation. The objectives of this study are mainly to investigate the problems and wastes in the assembly
process of table top fan and simulate the processes for higher productivity and efficiency. There are some
significant problems faced in the assembly processes such as bottleneck at some operation and low productivity
and efficiency.
Create
Assign
Process
Record
Dispose
Request
Transport
Station
Free
The Performance Analysis Of A Fettling Shop Using Simulation
www.iosrjournals.org 12 | Page
III. Methodology And Analysis
The main aim of the project is the performance analysis of the fettling shop. The fettling shop is the
product finishing shop of casting products. The methodology of the project is shown below.
ANALYSIS
The different cases in the analysis are described below.
1. Analysis of the system performance with respect to number of machines.
The overall performance of the system can be improved by increasing the number of machines in workstations.
2. Analysis of the system performance with respect to transporters.
The overall performance of the system can be improved by increasing the number of transporters in fettling
shop.
3. Analysis of the system performance with respect to distance between workstations.
Smaller distance helps for reducing material handling time and maximizing the products output. Distance
between workstations is an important variable which affects the overall performance.
4. Analysis of the system performance with respect to sequence.
Change the processing sequence of products for achieving more products output and maximum system
performance.
5. Analysis of the system performance with respect to product mix.
We can change the product mix by increasing the number of products from present condition. It helps to achieve
more product variety from the fettling shop.
IV. Results
The results of different simulation experiments are as follows.
A. Analysis Of The System Performance With Respect To Number Of Machines.
a) Output
Average number of casting products finished in a week (7
Days)
332
b) Delay Times in Fettling Shop
Average delay of products in a week 84.61 minutes (1.41 hours)
c) Utilization of Machines in Fettling Shop
Utilization of cutting machines 22 %
Utilization of grinding machines 58 %
Utilization of painting machine 37 %
Utilization of shot blasting machine 21 %
d) Flow Times of Products
Average cylinder frame flow time 296.36 minutes
Average fly wheel 1 flow time 243.86 minutes
Average fly wheel 2 flow time 135.05 minutes
Average fly wheel 3 flow time 119.21 minutes
Average gear case flow time 137.82 minutes
Average machine tool bed flow time 275.40 minutes
e) Total Time
Average total time of fettling shop is 218.54 minutes (3.642 hours)
The Performance Analysis Of A Fettling Shop Using Simulation
www.iosrjournals.org 13 | Page
B. ANALYSIS OF THE SYSTEM PERFORMANCE WITH RESPECT TO TRANSPORTERS
a) Output
Average number of casting products finished in a
week (7 Days)
329
b) Delay Times in Fettling Shop
Average delay of products in a week 154.83 minutes (2.58 hours)
c) Utilization of Machines in Fettling Shop
Utilization of cutting machines 30 %
Utilization of grinding machines 86 %
Utilization of painting machine 73 %
Utilization of shot blasting machine 28 %
d) Flow Times of Products
Average cylinder frame flow time 387.27 minutes
Average fly wheel 1 flow time 331.37 minutes
Average fly wheel 2 flow time 195.71 minutes
Average fly wheel 3 flow time 149.73 minutes
Average gear case flow time 168.45 minutes
Average machine tool bed flow time 359.24 minutes
e) Total Time
Average total time = 288.63 minutes (4.81 hours)
C. ANALYSIS OF THE SYSTEM PERFORMANCE WITH RESPECT TO DISTANCE BETWEEN
WORKSTATIONS.
a) Output
Average number of casting products finished in a
week (7 Days)
329
b) Delay Times in Fettling Shop
Average delay of products in a week 157.05 minutes (2.61 hours)
c) Utilization of Machines in Fettling Shop
Utilization of cutting machines 30 %
Utilization of grinding machines 86 %
Utilization of painting machine 73 %
Utilization of shot blasting machine 28 %
d) Flow Times of Products
Average cylinder frame flow time 390.10 minutes
Average fly wheel 1 flow time 329.41 minutes
Average fly wheel 2 flow time 195.51 minutes
Average fly wheel 3 flow time 149.17 minutes
Average gear case flow time 170.38 minutes
Average machine tool bed flow time 364.80 minutes
e) Total Time
Average total time = 289.58 minutes (4.82 hours)
D. ANALYSIS OF THE SYSTEM PERFORMANCE WITH RESPECT TO SEQUENCE.
a) Output
Average number of casting products finished in a
week (7 Days)
323
b) Delay Times in Fettling Shop
Average delay of products in a week 263.42 minutes (4.39 hours)
c) Utilization of Machines in Fettling Shop
Utilization of cutting machines 44 %
Utilization of grinding machines 96 %
Utilization of painting machine 64 %
Utilization of shot blasting machine 27 %
d) Flow Times of Products
Average cylinder frame flow time 433.10 minutes
Average fly wheel 1 flow time 400.24 minutes
The Performance Analysis Of A Fettling Shop Using Simulation
www.iosrjournals.org 14 | Page
Average fly wheel 2 flow time 423.63 minutes
Average fly wheel 3 flow time 412.70 minutes
Average gear case flow time 406.60 minutes
Average machine tool bed flow time 408.96 minutes
e) Total Time
Average total time = 415.30 minutes (6.92 hours)
E.ANALYSIS OF THE SYSTEM PERFORMANCE WITH RESPECT TO PRODUCT MIX.
a) Output
Average number of casting products finished in a
week (7 Days)
330
b) Delay Times in Fettling Shop
Average delay of products in a week 149.30 minutes (2.48 hours)
c) Utilization of Machines in Fettling Shop
Utilization of cutting machines 26 %
Utilization of grinding machines 85 %
Utilization of painting machine 71 %
Utilization of shot blasting machine 26 %
d) Flow Times of Products
Average cylinder frame flow time 153.99 minutes
Average fly wheel 1 flow time 341.66 minutes
Average fly wheel 2 flow time 349.01 minutes
Average fly wheel 3 flow time 181.47 minutes
Average gear case flow time 404.46 minutes
Average machine tool bed flow time 178.10 minutes
Average 7-th product flow time 366.94 minutes
e) Total Time
Average total time = 276.77 minutes (4.61hours)
V. Conclusion
The various satisfied results of the project are as follows. The project helped to understand the current
state and performance of the fettling shop. Arena modeling helped to understand critical areas like bottleneck.
Simulation study on the model helped to identify the improvement areas of the current system. ‘What if
analysis’ helped to forecast expected future results after new system improvement suggestions. Finally, the
performance improvement model is obtained.
References
[1] Al.Araidah, O.Boran (2012) -“Reducing delay in healthcare delivery at outpatients clinics using discrete event simulation”.
[2] Bronislav Chramcov, Petr beran (2005) -“A simulation approach to achieving more efficient production systems”.
[3] Chompoonoot kasemset,Voratas kachitvichyanukul (2008)- “Simulation-based procedure for implementing theory of constraints:
extension for cases with multiple bottlenecks”.
[4] Christoph Roser,Masaru Nakano ,Minoru Tanaka (2002) –“Shifting bottleneck detection”.
[5] Felipe f. Baesler,Milton Moraga,Francisco j. Ramis (2002) -“Productivity improvement in the wood industry using simulation and
artificial intelligence”.
[6] Galina Merkuryeva (2005) –“Metamodelling for simulation applications in production”.
[7] Julian h. Kang,Sung-mo ahn , Ji-hyun nam (2006)-“Productivity assessment of rock transportation trucks using simulation
technology”.
[8] Kidak Levent B,Aksarayli Mehmet (2011) -“Simulation modeling for process improvement in a general surgery service”.
[9] Melaka (2009)-“Productivity analysis of table top fan assembly process using arena simulation”.
[10] Navin Gupta, Edward j. Williams (2005) –“Simulation improves service and profitability of an automobile service garage”.
[11] Seraj yousef abed (2004) -”A simulation study to increase the capacity of a rusk production line “.
[12] Prameth tantivanich (2002), Prapaisrisudasna-“A simulation approach for productivity improvement of an ic factory”.

Contenu connexe

Tendances

Design of Virtual Cellular Manufacturing using Optimization Techniques
Design of Virtual Cellular Manufacturing using Optimization TechniquesDesign of Virtual Cellular Manufacturing using Optimization Techniques
Design of Virtual Cellular Manufacturing using Optimization Techniques
Praveen Kumar B
 
Ijmer 46064551
Ijmer 46064551Ijmer 46064551
Ijmer 46064551
IJMER
 
Optimization of surface roughness in high speed end milling operation using
Optimization of surface roughness in  high speed end milling operation usingOptimization of surface roughness in  high speed end milling operation using
Optimization of surface roughness in high speed end milling operation using
IAEME Publication
 

Tendances (15)

IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
 
Implementation and Selection of Optimum Layout Design in Cellular Manufacturi...
Implementation and Selection of Optimum Layout Design in Cellular Manufacturi...Implementation and Selection of Optimum Layout Design in Cellular Manufacturi...
Implementation and Selection of Optimum Layout Design in Cellular Manufacturi...
 
Facility layout ppt
Facility layout pptFacility layout ppt
Facility layout ppt
 
vignesh conference
vignesh conferencevignesh conference
vignesh conference
 
Ac04606177183
Ac04606177183Ac04606177183
Ac04606177183
 
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear box
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear boxDesign and Analysis of fluid flow in AISI 1008 Steel reduction gear box
Design and Analysis of fluid flow in AISI 1008 Steel reduction gear box
 
Design of Virtual Cellular Manufacturing using Optimization Techniques
Design of Virtual Cellular Manufacturing using Optimization TechniquesDesign of Virtual Cellular Manufacturing using Optimization Techniques
Design of Virtual Cellular Manufacturing using Optimization Techniques
 
IRJET - Optimization of Machining Parameters in a Turning Operation of Flyash...
IRJET - Optimization of Machining Parameters in a Turning Operation of Flyash...IRJET - Optimization of Machining Parameters in a Turning Operation of Flyash...
IRJET - Optimization of Machining Parameters in a Turning Operation of Flyash...
 
Ijmer 46064551
Ijmer 46064551Ijmer 46064551
Ijmer 46064551
 
IRJET- Artificial Intelligence ARM- Review
IRJET- Artificial Intelligence ARM- ReviewIRJET- Artificial Intelligence ARM- Review
IRJET- Artificial Intelligence ARM- Review
 
IRJET- Research Review on Multi-Objective Optimization of Machining Parameter...
IRJET- Research Review on Multi-Objective Optimization of Machining Parameter...IRJET- Research Review on Multi-Objective Optimization of Machining Parameter...
IRJET- Research Review on Multi-Objective Optimization of Machining Parameter...
 
Optimization of surface roughness in high speed end milling operation using
Optimization of surface roughness in  high speed end milling operation usingOptimization of surface roughness in  high speed end milling operation using
Optimization of surface roughness in high speed end milling operation using
 
Riv2
Riv2Riv2
Riv2
 
IRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection MoldingIRJET- Optimization of Plastic Injection Molding
IRJET- Optimization of Plastic Injection Molding
 
Chapter 4 product layout - 1st (3)
Chapter 4  product layout - 1st (3)Chapter 4  product layout - 1st (3)
Chapter 4 product layout - 1st (3)
 

En vedette

A Comparison between Natural and Synthetic Food Flavoring Extracts Using Infr...
A Comparison between Natural and Synthetic Food Flavoring Extracts Using Infr...A Comparison between Natural and Synthetic Food Flavoring Extracts Using Infr...
A Comparison between Natural and Synthetic Food Flavoring Extracts Using Infr...
IOSR Journals
 

En vedette (20)

J010337176
J010337176J010337176
J010337176
 
G017633943
G017633943G017633943
G017633943
 
Optical Studies on Eritrean Quartz
Optical Studies on Eritrean QuartzOptical Studies on Eritrean Quartz
Optical Studies on Eritrean Quartz
 
Corchorusolitoriuswaste(mulukiya) as a potential sorbent for the removal of c...
Corchorusolitoriuswaste(mulukiya) as a potential sorbent for the removal of c...Corchorusolitoriuswaste(mulukiya) as a potential sorbent for the removal of c...
Corchorusolitoriuswaste(mulukiya) as a potential sorbent for the removal of c...
 
A Comparison between Natural and Synthetic Food Flavoring Extracts Using Infr...
A Comparison between Natural and Synthetic Food Flavoring Extracts Using Infr...A Comparison between Natural and Synthetic Food Flavoring Extracts Using Infr...
A Comparison between Natural and Synthetic Food Flavoring Extracts Using Infr...
 
F1802052830
F1802052830F1802052830
F1802052830
 
E010123337
E010123337E010123337
E010123337
 
Pollution Due To Noise from Selected Places
Pollution Due To Noise from Selected PlacesPollution Due To Noise from Selected Places
Pollution Due To Noise from Selected Places
 
L016136369
L016136369L016136369
L016136369
 
Cloud Computing for E-Commerce
Cloud Computing for E-CommerceCloud Computing for E-Commerce
Cloud Computing for E-Commerce
 
E013152730
E013152730E013152730
E013152730
 
The Protective Role Of High Dietary Protein On Arsenic Induced Hepatotoxicity...
The Protective Role Of High Dietary Protein On Arsenic Induced Hepatotoxicity...The Protective Role Of High Dietary Protein On Arsenic Induced Hepatotoxicity...
The Protective Role Of High Dietary Protein On Arsenic Induced Hepatotoxicity...
 
The Effect Service Quality to Customer Satisfaction and Customer Loyalty of A...
The Effect Service Quality to Customer Satisfaction and Customer Loyalty of A...The Effect Service Quality to Customer Satisfaction and Customer Loyalty of A...
The Effect Service Quality to Customer Satisfaction and Customer Loyalty of A...
 
Network Lifetime Analysis of Routing Protocols of Short Network in Qualnet
Network Lifetime Analysis of Routing Protocols of Short Network in QualnetNetwork Lifetime Analysis of Routing Protocols of Short Network in Qualnet
Network Lifetime Analysis of Routing Protocols of Short Network in Qualnet
 
Intelligent Fault Identification System for Transmission Lines Using Artifici...
Intelligent Fault Identification System for Transmission Lines Using Artifici...Intelligent Fault Identification System for Transmission Lines Using Artifici...
Intelligent Fault Identification System for Transmission Lines Using Artifici...
 
Performance Analysis of OFDM in Combating Multipath Fading
Performance Analysis of OFDM in Combating Multipath FadingPerformance Analysis of OFDM in Combating Multipath Fading
Performance Analysis of OFDM in Combating Multipath Fading
 
Implementation of XOR Based Pad Generation Mutual Authentication Protocol for...
Implementation of XOR Based Pad Generation Mutual Authentication Protocol for...Implementation of XOR Based Pad Generation Mutual Authentication Protocol for...
Implementation of XOR Based Pad Generation Mutual Authentication Protocol for...
 
A01260104
A01260104A01260104
A01260104
 
H017124652
H017124652H017124652
H017124652
 
M017427985
M017427985M017427985
M017427985
 

Similaire à The Performance Analysis of a Fettling Shop Using Simulation

Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...
Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...
Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...
International Journal of Engineering Inventions www.ijeijournal.com
 
Literature-survey
Literature-surveyLiterature-survey
Literature-survey
Deepu Rajan
 
Optimization of Injection Molding Process-literature review
Optimization of Injection Molding Process-literature reviewOptimization of Injection Molding Process-literature review
Optimization of Injection Molding Process-literature review
Alex Larsh
 

Similaire à The Performance Analysis of a Fettling Shop Using Simulation (20)

Improving layout and workload of manufacturing system using Delmia Quest simu...
Improving layout and workload of manufacturing system using Delmia Quest simu...Improving layout and workload of manufacturing system using Delmia Quest simu...
Improving layout and workload of manufacturing system using Delmia Quest simu...
 
I012536474
I012536474I012536474
I012536474
 
“Development of automatic feeder system in cellular manufacturing to improve ...
“Development of automatic feeder system in cellular manufacturing to improve ...“Development of automatic feeder system in cellular manufacturing to improve ...
“Development of automatic feeder system in cellular manufacturing to improve ...
 
IRJET- Literature Review on Manufacturing System Performance Improvement ...
IRJET-  	  Literature Review on Manufacturing System Performance Improvement ...IRJET-  	  Literature Review on Manufacturing System Performance Improvement ...
IRJET- Literature Review on Manufacturing System Performance Improvement ...
 
Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...
Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...
Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...
 
Job shop
Job shopJob shop
Job shop
 
Review on GROUP TECHNOLOGY & it’s implementation
Review on GROUP TECHNOLOGY & it’s implementationReview on GROUP TECHNOLOGY & it’s implementation
Review on GROUP TECHNOLOGY & it’s implementation
 
Job Shop Layout Design Using Group Technology
Job Shop Layout Design Using Group TechnologyJob Shop Layout Design Using Group Technology
Job Shop Layout Design Using Group Technology
 
O0123190100
O0123190100O0123190100
O0123190100
 
IRJET- Improvement of Overall Equipment Effectiveness of Valve Stem Seal ...
IRJET-  	  Improvement of Overall Equipment Effectiveness of Valve Stem Seal ...IRJET-  	  Improvement of Overall Equipment Effectiveness of Valve Stem Seal ...
IRJET- Improvement of Overall Equipment Effectiveness of Valve Stem Seal ...
 
Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant Preliminary Study of an Assembling Plant
Preliminary Study of an Assembling Plant
 
Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...Line Balancing and facility optimization of Machine Shop with Work Study and ...
Line Balancing and facility optimization of Machine Shop with Work Study and ...
 
K012556370
K012556370K012556370
K012556370
 
K012556370
K012556370K012556370
K012556370
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
IRJET- Use of Simulation in Different Phases of Manufacturing System Life Cycle
IRJET- Use of Simulation in Different Phases of Manufacturing System Life CycleIRJET- Use of Simulation in Different Phases of Manufacturing System Life Cycle
IRJET- Use of Simulation in Different Phases of Manufacturing System Life Cycle
 
Literature-survey
Literature-surveyLiterature-survey
Literature-survey
 
Production process
Production processProduction process
Production process
 
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean PrinciplesIRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
IRJET-Productivity Improvement in a Pressure Vessel using Lean Principles
 
Optimization of Injection Molding Process-literature review
Optimization of Injection Molding Process-literature reviewOptimization of Injection Molding Process-literature review
Optimization of Injection Molding Process-literature review
 

Plus de IOSR Journals

Plus de IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Dernier

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 

Dernier (20)

22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 

The Performance Analysis of a Fettling Shop Using Simulation

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 9, Issue 2 (Sep. - Oct. 2013), PP 10-14 www.iosrjournals.org www.iosrjournals.org 10 | Page The Performance Analysis of a Fettling Shop Using Simulation Mathew Thomas Department of Mechanical Engineering, Viswajyothi College of Engineering and Technology, Vazhakulam, Muvattupuzha, Kerala, India. Abstract: Fettling shop is the product finishing shop of casting products.After the knockout, the casting is taken to the fettling shop for doing the fettling work. The fettling process includes cutting, shot blasting, grinding and painting. In all these process the sand and extra metal on the castings are removed. The project titled „The performance analysis of a fettling shop using simulation‟ is based on a fettling shop of a casting industry. The main aim of the project is the performance analysis of the fettling shop. This project is a simulation based project and is done using a simulation tool called arena. The main concepts related with the performance analysis are Bottleneck analysis, Productivity analysis and System improvement analysis. Keywords: Performance analysis, Fettling shop, Bottleneck, Simulation. I. Introduction The performance analysis is mainly done with Bottleneck analysis, Productivity analysis and System improvement analysis. Here, performance analysis of the fettling shop is done using a simulation tool called arena. A. PERFORMANCE ANALYSIS Performance analysis is the process of analyzing the performance of a system or a process. Here, performance analysis of a casting industry fettling shop is done. The different performance analysis tools are Bottleneck analysis, Productivity analysis and System improvement analysis. The main aim of the project is the performance analysis of the fettling shop. This is a simulation based project and is done using a simulation tool called arena. B. FETTLING SHOP The fettling shop is the product finishing shop of casting products.After the knockout, the casting is taken to the fettling shop for doing the fettling work. The fettling process includes cutting, shot blasting, grinding and painting. In all these process the sand and extra metal on the castings are removed. C. BOTTLENECK In engineering, a bottleneck is a phenomenon by which the performance or capacity of an entire system is severely limited by a single component. Formally, a bottleneck lies on a system's critical path and provides the lowest throughput. As such, system designers will try to avoid bottlenecks and direct effort towards locating and tuning existing bottlenecks. D. PRODUCTIVITY Productivity is an average measure of the efficiency of production. Productivity is a ratio of production output to input (i.e, capital, labor, land, materials, etc.). It is a measure of how well the resources are utilized to produce an output. i.e, Productivity=Output/Input. The measure of productivity is defined as a total output per one unit of a total input. E.SYSTEM IMPROVEMENT System improvement is the process of improving the overall performance of the system. The results of system improvement are output maximization, production capacity improvement of the system, reduction of waiting times, reduction of number of products waiting at workstations etc. F.SIMULATION MODELING Simulation modeling is the process of creating and analyzing a digital prototype of a physical model to predict its performance in the real world. Simulation modeling allows designers and engineers to avoid repeated building of multiple physical prototypes to analyze designs for new or existing parts.
  • 2. The Performance Analysis Of A Fettling Shop Using Simulation www.iosrjournals.org 11 | Page G. BASIC PROCESS ARENA MODULES The main basic process arena modules are shown below in table 1.These basic process arena modules are used for modeling purposes Module Name Symbol Function Create Used as a source to generates new entities. Assign Used to assign values to variables Process Used as the main processing method Record Used to collect statistics in a particular location in the model Dispose Used as the exit point of entities from a simulation model Table 1-Basic process arena modules H. ADVANCED TRANSFER MODULES The advanced transfer modules used for modeling process are request, transport, station and free. Symbols & functions of advanced transfer modules are shown in table 2 Module Name Symbol Function Request Used to assign a transporter unit to an entity and then to move the unit to the entity’s location Transport Used to transfer an entity controlling a transporter unit to a destination. Station Used to define a station or a set of stations. Free Used to release the entity’s most recently allocated transporter unit. Table 2-Advanced transfer modules II. Literature Review Timothy M. Elftman (1999) described about the examination of the effects of bottlenecks and production control rules at assembly stations. In manufacturing centers, products manufactured at different locations are often joined together at assembly stations. If not managed properly this common event can lead to defective products, lost throughput, and increased WIP. All of which will result in lost capital for the manufacturing center. Christoph Roser et.al (2002) suggested various techniques for shifting bottleneck detection. This involves a novel method for detecting bottlenecks in manufacturing systems and the shifting of these bottlenecks. All manufacturing systems are constrained by one or more bottlenecks. Improving the bottleneck will improve the whole system. Karthik Krishna et.al (2008) described the iterative use of simulation and scheduling methodologies to improve productivity. It includes the integrated use of process simulation, production scheduling, and detailed analysis of material-handling methods and their improvement. The study undertook the identification and improvement of production and scheduling policies to the benefit of a manufacturing process whose original throughput capacity fell significantly short of high and increasing demand. Prameth tantivanich et.al (2002) suggested a simulation approach for productivity improvement of an IC factory. It is used to develop a simulation model to intimate a real world IC assembly line in order to identify alternatives for productivity improvement. Melaka (2009) described productivity analysis of table top fan assembly process using arena simulation. The objectives of this study are mainly to investigate the problems and wastes in the assembly process of table top fan and simulate the processes for higher productivity and efficiency. There are some significant problems faced in the assembly processes such as bottleneck at some operation and low productivity and efficiency. Create Assign Process Record Dispose Request Transport Station Free
  • 3. The Performance Analysis Of A Fettling Shop Using Simulation www.iosrjournals.org 12 | Page III. Methodology And Analysis The main aim of the project is the performance analysis of the fettling shop. The fettling shop is the product finishing shop of casting products. The methodology of the project is shown below. ANALYSIS The different cases in the analysis are described below. 1. Analysis of the system performance with respect to number of machines. The overall performance of the system can be improved by increasing the number of machines in workstations. 2. Analysis of the system performance with respect to transporters. The overall performance of the system can be improved by increasing the number of transporters in fettling shop. 3. Analysis of the system performance with respect to distance between workstations. Smaller distance helps for reducing material handling time and maximizing the products output. Distance between workstations is an important variable which affects the overall performance. 4. Analysis of the system performance with respect to sequence. Change the processing sequence of products for achieving more products output and maximum system performance. 5. Analysis of the system performance with respect to product mix. We can change the product mix by increasing the number of products from present condition. It helps to achieve more product variety from the fettling shop. IV. Results The results of different simulation experiments are as follows. A. Analysis Of The System Performance With Respect To Number Of Machines. a) Output Average number of casting products finished in a week (7 Days) 332 b) Delay Times in Fettling Shop Average delay of products in a week 84.61 minutes (1.41 hours) c) Utilization of Machines in Fettling Shop Utilization of cutting machines 22 % Utilization of grinding machines 58 % Utilization of painting machine 37 % Utilization of shot blasting machine 21 % d) Flow Times of Products Average cylinder frame flow time 296.36 minutes Average fly wheel 1 flow time 243.86 minutes Average fly wheel 2 flow time 135.05 minutes Average fly wheel 3 flow time 119.21 minutes Average gear case flow time 137.82 minutes Average machine tool bed flow time 275.40 minutes e) Total Time Average total time of fettling shop is 218.54 minutes (3.642 hours)
  • 4. The Performance Analysis Of A Fettling Shop Using Simulation www.iosrjournals.org 13 | Page B. ANALYSIS OF THE SYSTEM PERFORMANCE WITH RESPECT TO TRANSPORTERS a) Output Average number of casting products finished in a week (7 Days) 329 b) Delay Times in Fettling Shop Average delay of products in a week 154.83 minutes (2.58 hours) c) Utilization of Machines in Fettling Shop Utilization of cutting machines 30 % Utilization of grinding machines 86 % Utilization of painting machine 73 % Utilization of shot blasting machine 28 % d) Flow Times of Products Average cylinder frame flow time 387.27 minutes Average fly wheel 1 flow time 331.37 minutes Average fly wheel 2 flow time 195.71 minutes Average fly wheel 3 flow time 149.73 minutes Average gear case flow time 168.45 minutes Average machine tool bed flow time 359.24 minutes e) Total Time Average total time = 288.63 minutes (4.81 hours) C. ANALYSIS OF THE SYSTEM PERFORMANCE WITH RESPECT TO DISTANCE BETWEEN WORKSTATIONS. a) Output Average number of casting products finished in a week (7 Days) 329 b) Delay Times in Fettling Shop Average delay of products in a week 157.05 minutes (2.61 hours) c) Utilization of Machines in Fettling Shop Utilization of cutting machines 30 % Utilization of grinding machines 86 % Utilization of painting machine 73 % Utilization of shot blasting machine 28 % d) Flow Times of Products Average cylinder frame flow time 390.10 minutes Average fly wheel 1 flow time 329.41 minutes Average fly wheel 2 flow time 195.51 minutes Average fly wheel 3 flow time 149.17 minutes Average gear case flow time 170.38 minutes Average machine tool bed flow time 364.80 minutes e) Total Time Average total time = 289.58 minutes (4.82 hours) D. ANALYSIS OF THE SYSTEM PERFORMANCE WITH RESPECT TO SEQUENCE. a) Output Average number of casting products finished in a week (7 Days) 323 b) Delay Times in Fettling Shop Average delay of products in a week 263.42 minutes (4.39 hours) c) Utilization of Machines in Fettling Shop Utilization of cutting machines 44 % Utilization of grinding machines 96 % Utilization of painting machine 64 % Utilization of shot blasting machine 27 % d) Flow Times of Products Average cylinder frame flow time 433.10 minutes Average fly wheel 1 flow time 400.24 minutes
  • 5. The Performance Analysis Of A Fettling Shop Using Simulation www.iosrjournals.org 14 | Page Average fly wheel 2 flow time 423.63 minutes Average fly wheel 3 flow time 412.70 minutes Average gear case flow time 406.60 minutes Average machine tool bed flow time 408.96 minutes e) Total Time Average total time = 415.30 minutes (6.92 hours) E.ANALYSIS OF THE SYSTEM PERFORMANCE WITH RESPECT TO PRODUCT MIX. a) Output Average number of casting products finished in a week (7 Days) 330 b) Delay Times in Fettling Shop Average delay of products in a week 149.30 minutes (2.48 hours) c) Utilization of Machines in Fettling Shop Utilization of cutting machines 26 % Utilization of grinding machines 85 % Utilization of painting machine 71 % Utilization of shot blasting machine 26 % d) Flow Times of Products Average cylinder frame flow time 153.99 minutes Average fly wheel 1 flow time 341.66 minutes Average fly wheel 2 flow time 349.01 minutes Average fly wheel 3 flow time 181.47 minutes Average gear case flow time 404.46 minutes Average machine tool bed flow time 178.10 minutes Average 7-th product flow time 366.94 minutes e) Total Time Average total time = 276.77 minutes (4.61hours) V. Conclusion The various satisfied results of the project are as follows. The project helped to understand the current state and performance of the fettling shop. Arena modeling helped to understand critical areas like bottleneck. Simulation study on the model helped to identify the improvement areas of the current system. ‘What if analysis’ helped to forecast expected future results after new system improvement suggestions. Finally, the performance improvement model is obtained. References [1] Al.Araidah, O.Boran (2012) -“Reducing delay in healthcare delivery at outpatients clinics using discrete event simulation”. [2] Bronislav Chramcov, Petr beran (2005) -“A simulation approach to achieving more efficient production systems”. [3] Chompoonoot kasemset,Voratas kachitvichyanukul (2008)- “Simulation-based procedure for implementing theory of constraints: extension for cases with multiple bottlenecks”. [4] Christoph Roser,Masaru Nakano ,Minoru Tanaka (2002) –“Shifting bottleneck detection”. [5] Felipe f. Baesler,Milton Moraga,Francisco j. Ramis (2002) -“Productivity improvement in the wood industry using simulation and artificial intelligence”. [6] Galina Merkuryeva (2005) –“Metamodelling for simulation applications in production”. [7] Julian h. Kang,Sung-mo ahn , Ji-hyun nam (2006)-“Productivity assessment of rock transportation trucks using simulation technology”. [8] Kidak Levent B,Aksarayli Mehmet (2011) -“Simulation modeling for process improvement in a general surgery service”. [9] Melaka (2009)-“Productivity analysis of table top fan assembly process using arena simulation”. [10] Navin Gupta, Edward j. Williams (2005) –“Simulation improves service and profitability of an automobile service garage”. [11] Seraj yousef abed (2004) -”A simulation study to increase the capacity of a rusk production line “. [12] Prameth tantivanich (2002), Prapaisrisudasna-“A simulation approach for productivity improvement of an ic factory”.