SlideShare une entreprise Scribd logo
1  sur  8
Télécharger pour lire hors ligne
IOSR Journal of Electrical and Electronics Engineering (IOSR-JEEE)
e-ISSN: 2278-1676,p-ISSN: 2320-3331, Volume 10, Issue 4 Ver. III (July – Aug. 2015), PP 73-80
www.iosrjournals.org
DOI: 10.9790/1676-10437380 www.iosrjournals.org 73 | Page
Screening Power Plants for Green-Based Generation Expansion
Planning for Kenya
Patrobers Simiyu
Institute of Energy & Environmental Technology (IEET); Jomo Kenyatta University of Agriculture &
Technology; Kenya
Abstract: The main concern in the global generation sector was the huge CO2 emissions from the conventional
power generation. In Kenya, the sector prepares 20 year rolling least cost power development plan (LCPDP)
for expanding the power system to meet the current and future power demands. The 2011-2031 LCPDP
generation plan proposed a system expansion that would result in a 33% fossil fuel power generation posing a
huge CO2 emission dilemma. However, renewable energy integration in the least-cost generation expansion
planning (GEP) was considered key to energy security and emission reduction. During GEP, the screening
curves are useful preliminary tool in selecting candidate generation options. In this study the screening curves
were used in vetting the candidate plants for green-base GEP in Kenya. The findings showed that the green
base load candidate plants were namely; 140MW Geothermal, 140MW low grand falls hydro, 300MW Wind,
1000MW imports, 60MWMutonga hydro and 1000MW nuclear plants characterized by US$ 90-660/kW.yr fixed
cost, more than 40% capacity factor and US$cts 6-13/kWh levelized cost of electricity (LCOE). Suitable green
peaking plant were 180MW GT-Natural gas, 100MW Solar PV and imports depicted by US$ 100-700/kW.yr
fixed cost, less than 40% capacity factor and US$cts 15-30/kWh LCOE. These were a mix of green generation
plants for cost effective utilization and environmental sustainability in Kenya. Therefore, the research
recommended the selected candidate plants for simulation and optimization of a green-based generation
expansion plan for Kenya using relevant GEP models.
Key Words: annual generation cost curves; base load plants; generation expansion planning; levelized cost of
electricity; screening curves; peaking plants.
I. Introduction
The growing concerns for climate change mitigation in the generation sector have driven many
countries in the world towards environmentally-benign generation investments [1]; [2]. Renewable energy (RE)
is regarded as an appropriate clean power alternative to the conventional carbon intensive plants [3]; [4].
Consequently, RE integration in least-cost generation expansion planning (GEP) is considered key to energy
security and emission reduction [5]; [6].
In Kenya, the sector prepares 20 year rolling least cost power development plan (LCPDP) at the energy
regulatory commission (ERC) for expanding the power system to meet the current and future power demands.
The 2011-2031 LCPDP had significant RE composition [7]. However, there was room for more integration
because the planned large hydropower and heavy fuel oil (HFO) dominated power generation posed serious
challenges. According to [8], the large hydros were vulnerable to acute energy shortfalls due to the frequent
droughts. Conversely, the HFO and the planned conventional coal power plants posed the CO2 emissions
dilemma [9].
However, Kenya owns huge under-exploited RE resources yet for exploitation. Therefore this study
assessed the Kenya generation potential using the screening curves with the aim of identifying a portfolio of
sustainable RE candidate plants for green-based GEP. This would stimulate the Kenya generation sector in
adopting a more sustainable GEP towards security of power and CO2 emission reductions. In addition, as a
regional hub in social-economic development, Kenya will stand as a benchmark for many countries in Africa
and beyond. This paper is divided into seven sections. The section two gives an overview of the screening
curves. Section three presents the RE potential in Kenya. Section four outlines the study methodology. Section
five gives the results. Section six gives the discussion while the last section gives the conclusion and
recommendation for future research.
II. Screening Curves
The screening curve analysis (SCA) involves preliminary vetting of candidate generation sources to
establish the most economical supply option. In this approach, the total costs during the operating life of the
potential options are discounted and plotted against capacity factor values. The resulting screening curves
captures major trade-offs between capital and operating costs and the utilization levels of various generation
technologies allowing higher cost options to be excluded for further consideration [10].
Screening Power Plants for Green-Based Generation Expansion Planning for Kenya
DOI: 10.9790/1676-10437380 www.iosrjournals.org 74 | Page
In the SCA, the annual total generation cost (AGC) is represented as a function of variable fuel cost
(VFC) and variable operation and maintenance cost (VOMC). The annualized capital cost (ACC) and fixed
operation and maintenance cost (FOMC) are held constant. The linear equation (1) shows the screening curve
expression [11].
AGG = {ACC + FOMC + VFC + VOMC . T}…………………………..….……..……..……………………… (1)
Where: ACC; Annualized capital cost per MW, FOMC; Fixed operation and maintenance cost per MW per
year, VFC; Variable fuel cost per MWh, VOMC; Variable operation and maintenance cost per MWh and T; total
year operating hours for the given MW.
Additionally, the screening curves integrated with the load duration curve (LDC) can give an
appropriate mix of plants to minimize the total generation cost of a power system. In this way, the screening
curves are positioned on the upper half while the LDC placed on the lower half. By projecting the intersection
point from the screening curves onto the LDC, the portion of generation capacity that would be supplied from
the plants captured in the screening curves is yielded [10]; [12].
However, SCA is inadequate for GEP as it doesn’t capture the complex and diverse power generation
parameters such as system reliability, resource capacity constraints, related uncertainties as well as the existing
generation system [12]; [11]. For this reason, numerous and sophisticated GEP models extensive in literature are
available for effective simulation of the generating system’s operation and subsequently optimizing the
generation expansion plan [13]. Nevertheless, prior to the process, the screening curves are useful preliminary
screening tool in selecting candidate generation plants [12].
III. Renewable Energy Potential In Kenya
Kenya is well endowed with enormous RE resources. The hydropower potential in Kenya totals
1670MW but only 807MW of this capacity is installed. Detailed hydropower assessments revealed a 700MW
High Grand Falls potential project along the Tana River and a further 100MW at Karura. Additionally, Mutonga
(60MW) and low grand falls (LGF) (140MW) sites were found suitable for immediate development. Moreover
feasibility studies established Ewaso Ng’iro South River (220MW) and the North-Rift Valley basin at Arror
(70MW) [9].
The geothermal resources mainly situated within the Kenya’s East African Rift system are currently
installed at 250.4MW. Detailed exploration studies revealed that the potential geothermal sites have a total
generation of 5,000 – 10, 000 MWe. The prospects are clustered mainly into Central Rift (1,800MW), South
Rift (2,400MW) and North Rift (3,450MW) [9] [14].
Kenya’s strategic location along the equator offers great potential of about 4-6 KWh/m2
/day of daily
insolation for solar power. This potential is spread in many parts of the coast, north eastern, eastern amongst
other parts of the country [15]. The total area capable of delivering 6KWh/m2
per day is about 106, 000 km2
with a potential of 638, 790 TWh for solar photovoltaic (PV) and thermal though less than 1% is in use [16];
[17].
Additionally, a huge potential of about 346W/m2
and wind speeds of over 6m/s for wind power
generation exists. On average about 90,000 Km2
of area in the country have very excellent wind speeds of 6m/s
yet a meager 5.3MW is currently installed [9]. Nonetheless, the steady growing interest in wind power is
significantly increasing its role in the Kenya electricity mix for grid and off-grid power systems [15].
Moreover, there are commercially exploitable coal reserves discovered in the Mui basin in Kitui
County besides the RE potential. In the 2011-2031 LCPDP, conventional coal power generation was projected
to come on line in 2015 and by 2030 it would provide 4500MW of power. Nevertheless, the projected use of the
coal technology will increase the CO2 emissions to record levels contradicting the climate change mitigation
strategies [8].
Furthermore, there are other cost-effective energy resources within Kenya’s reach. There are at least
2000MW hydropower imports from Ethiopia. Secondly, about 2340MW Natural gas imports and local reserves
are available for 180MW combined cycle gas turbine (CCGT) plants. Finally, the country has adopted a
systematic international methodology of developing the nuclear infrastructure for commissioning its first ever
1000MW nuclear power plant by 2024 [7].
IV. Methodology
The candidate generation plants from the Kenya’s available energy resources for the study include;
140MW geothermal, 1000MW nuclear, 300MW coal, 180MW Gas Turbine (GT)-Kerosene, 180MW GT-
Natural gas, 160MW heavy fuel oil (HFO), 1000MW imports, 60MW Mutonga hydro, 140MW low grand falls
(LGF), 300MW wind and 100MW solar photovoltaic (PV). A generation cost model (GCM) was set up in the
Microsoft Excel encompassing each candidate plant. The GCM was mainly comprised of power generation
technical and economic power generation characteristics namely; fixed & variable generation costs, total outage
rate (TOR), outage adjustment factor (OAF), interim replacement (IR), interest during construction (IDC) and
Screening Power Plants for Green-Based Generation Expansion Planning for Kenya
DOI: 10.9790/1676-10437380 www.iosrjournals.org 75 | Page
capital recovery factor (CRF). Figure 1.0 shows the GCM outline for the candidate plants.
Figure 1.0: GCM Outline for the Candidate Generation Plants
The equations (2) to (10) were used to represent the power generation characteristics for all the
candidates in the GCM.
Capital ($X106
) =
Installed Capacity MW X Capital ($/kW )
(103)
………………………......………………...……...…....(2)
Fixed Annual Capital($/kW. yr) = {Capital($/kW) X(IDC Factor)X(CRF + IR)}...........................................(3)
Total Fixed Annual Cost($/kW. yr) = {Fixed Annual Capital($/kW. yr) + Fixed O&𝑀($/kW. yr)}….........(4)
OAF =
1
(1− TOR )
……………………………….…….…………………………….……..……...……………….(5)
Annual Fixed Cost($/kW. yr) = {Total Fixed Annual Cost($/kW. yr) X(OAF)}..............................................(6)
Annual Fixed Cost($/kWh) =
Annual Fixed Cost ($/kW .yr)
(8760)
…………………............…….….……...……………..(7)
Fuel Cost($/kWh) =
Fuel Price ($/Gj) X Heat Rate (kJ/kWh )
(106)
……………........................….………….……………..(8)
Total Variable Cost($/kWh) = {Fuel Cost($/kWh) + CO2 TaxCost($/kWh + Variable O&𝑀 𝐶𝑜𝑠𝑡($/
kWh)}………………………………………………...……………….................................................................(9)
Total Variable Cost($/kW. yr) = {Total Variable Cost($/kWh) X 8760}……..………………………...…..(10)
The GCM was used to evaluate the annual generation cost (AGC) for each candidate plant as a function
of the annual variable cost (AVC); the annualized fixed cost (AFC) held constant. These cost variables for the
candidates are shown in the AGC curve expression in equation (11). In this linear equation, the AFC is the
intercept while the AVC, the slope.
AGC($/kW. yr) = {AVC($/kW. yr). (% CapacityFactor) + AFC($/kW. yr)}…............................................(11)
Similarly, the levelized cost of electricity (LCOE) for each candidate plant was calculated. The total
variable cost (TVC), AFC and capacity factor were key LCOE components. The LCOE expression is
represented using equation (12).
LCOE($/kWh) = TVC ($/kWh) +
AFC ($/kW .yr)
(8760 X % Capacity Factor )
………………............…………….…………….(12)
The AGC and the LCOE screening curves were used in the selection of the base load and peaking RE
candidate plants for GEP.
V. Results
The generation cost model (GCM) was developed for screening the candidate generation plants. Table
1.1 presents the GCM for the candidate generation plants. From table 1.1, the capital costs widely varied across
the candidate plants. Solar PV had the highest capital cost of US$4450/kW.yr while the imports had the lowest
of about a tenth of the solar PV’s capital cost (US$455/kW.yr). On the other hand, the fuel cost was quite
Screening Power Plants for Green-Based Generation Expansion Planning for Kenya
DOI: 10.9790/1676-10437380 www.iosrjournals.org 76 | Page
significant in GT-kerosene had the highest fuel cost at U$cts 22.2/kWh while HFO the least at U$cts 9.1/kWh.
The RE such as solar PV, wind, low grand falls (LGF), Mutonga hydro, imports and geothermal had no fuel
costs.
Table 1.1: Candidate Generation Plants’ Generation Cost Model (GCM).
Geotherma
l
Nuclea
r Coal
GT-
KER
O
GT-
N.GA
S HFO
Impor
t
Mutong
a LGF Wind
Solar
PV
Configuration
(n x MW)
1 x 140
1 X
1000
1 X
300
1 x
180
1 x
180
1 x
160
1000 1x60 1x140 300 100
Total Capacity
(MW)
140 1000 300 180 180 160 1000 60 140 300 100
Fixed Cost
Capital ( $ x 106
) 511 4055 631 135 135 218 455 259 507 690 445
Capital
($/kW)
3650 4055 2104 750 750 1364 455 4314 3621 2300 4450
IDC Factor 1.1344 1.2605 1.1341 1.0725 1.0725
1.065
4
1.0654 1.3378
1.337
8
1.065
4
1.138
0
Annuity Factor
(or C.R.F.)
0.0937 0.0839 0.0937 0.1019 0.1019
0.101
9
0.0937 0.0817
0.081
7
0.093
7
0.111
4
Interim
Replacement
0.921% 0.68%
0.921
%
0.35% 0.35% 0.35% 0.35% 1.03% 0.87% 0.64% 0.63%
Fixed Annual
Capital
($/kW/yr)
426.0 463.6 245.5 84.7 84.7 153.1 47.1 531.4 438.2 245.3 596.1
Fixed O&M
Costs
($/kW/yr)
56.0 90.0 63 11.8 11.8 62.5 30.0 21.3 19.8 28.1 39.0
Total Fixed
Annual Cost
($/kW/yr)
482 554 309 97 97 216 15 553 458 273 635
Total Outage
Rate (TOR)
0.068 0.150 0.156 0.078 0.078 0.098 0.150 0.0969
0.096
9
0.100 0.091
Outage
Adjustment
Factor (OAF)
1.073 1.177 1.185 1.085 1.085 1.108 1.176 1.107 1.107 1.111 1.100
Annual Fixed
Cost
($/kW/yr)
517 652 366 105 105 239 91 612 507 304 699
Annual Fixed
Cost ($/kWh)
0.0590 0.0744 0.0417 0.0120 0.0120
0.027
3
0.0104 0.0699
0.057
9
0.034
7
0.079
8
Variable Cost
Fuel Price ($/GJ) - 4.557 19.37 9.11 11.08 - - - - -
Heat Rate
(kJ/kWh)
- 10900 11,440 11,447 8,197 - - - - -
FuelCost($/kWh) - 0.0087 0.0497 0.2216 0.1043
0.090
9
- - - - -
CO2 Tax Cost
($/kWh)
- 0.0221 0.0089 0.0066
0.008
9
- - - - -
Variable O&M
Cost ($/kWh)
0.00557 0.0049 0.0036 0.0120 0.0010
0.008
9
- 0.0053
0.005
3
0.001
0
0.001
0
Total Variable
Cost ($/kWh)
0.00557 0.0136 0.0754 0.2425 0.1119
0.108
7
0.0500 0.0053
0.005
3
0.001
0
0.001
0
Total Variable
Cost
($/kW/yr)
49 119 660 2124 980 952 438 47 47 9 9
Screening Power Plants for Green-Based Generation Expansion Planning for Kenya
DOI: 10.9790/1676-10437380 www.iosrjournals.org 77 | Page
The annualized fixed costs (AFC) & annualized variable costs (AVC) for the candidate plants at varied
capacity factors yielded the annual generation cost curves (AGC). Figure 1.1 shows AGC curves realized for the
candidate plants. Similarly, the unit cost or levelized costs of electricity (LCOE) for the candidate plants at
varied capacity factors generated the LCOE curves. Figure 1.2 shows the LCOE for candidate plants.
figure 1.1: AGC Curves for candidate plants
0
500
1000
1500
2000
2500
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Geothermal
Nuclear
Coal
GT-KERO
GT- N.GAS
HFO
Import
Mutonga
% Capacity Factor
AnnuallizedFixed&
VariableCost($/kW.yr)
Unit Cost
($/kW.yr)
Capacity
Factor
Geo Nucl Coal
GT-
KER
GT-
N.GA
HFO Impo Muto LGF Wind SoPV
0% 517 652 366 105 105 239 91 612 507 304 699
10% 522 663 432 317 203 334 135 617 512 305 700
20% 527 675 498 530 301 429 178 621 517 305 700
30% 532 687 564 742 399 525 222 626 521 306 701
40% 536 699 630 954 497 620 266 631 526 307 702
50% 541 711 696 1167 595 715 310 635 531 - -
60% 546 723 762 1379 693 810 354 640 535 - -
70% 551 735 828 1592 791 905 397 - - - -
80% 556 747 894 1804 889 1001 441 - - - -
90% 561 759 960 2017 987 1096 485 - - - -
100% 566 770 1026 2229 1085 1191 529 - - - -
Unit Cost
($/kWh)
Capacity
Factor
Geo Nucl Coal
GT-
KER
GT-
N.GA
HFO Impo Muto LGF Wind SoPV
10% 0.5957 0.757 0.493 0.362 0.231 0.382 0.154 0.704 0.584 0.348 0.799
20% 0.3006 0.385 0.284 0.302 0.172 0.245 0.102 0.355 0.295 0.174 0.400
30% 0.2023 0.262 0.215 0.282 0.152 0.200 0.085 0.238 0.198 0.117 0.267
40% 0.1531 0.200 0.180 0.272 0.142 0.177 0.076 0.180 0.150 0.088 0.200
50% 0.1236 0.162 0.159 0.266 0.136 0.163 0.071 0.145 0.121 - -
60% 0.1039 0.138 0.145 0.262 0.132 0.154 0.067 0.122 0.102 - -
70% 0.0899 0.120 0.135 0.260 0.129 0.148 0.065 - - - -
80% 0.0793 0.107 0.128 0.257 0.127 0.143 0.063 - - - -
90% 0.0711 0.096 0.122 0.256 0.125 0.139 0.062 - - - -
100% 0.0646 0.088 0.117 0.254 0.124 0.136 0.060 - - - -
Screening Power Plants for Green-Based Generation Expansion Planning for Kenya
DOI: 10.9790/1676-10437380 www.iosrjournals.org 78 | Page
The results in figure 1.1 show that solar PV had the highest AFC of US$ 699/kW.yr while the
Ethiopia’s hydropower imports the least at US$ 91/kW/yr. On the contrary, GT-kerosene incurred the highest
AVC of US$ 2124/kW.yr while wind and solar PV the least at US$ 9/kW.yr each. On the other hand, the results
in figure 1.2 show that solar PV at 30% capacity factor cost highest at US$cts 20/kWh while hydropower
imports from Ethiopia at 90% capacity factor cost the least at US$cts 6.2/kWh.
figure 1.2: LCOE curves for candidate plants
The results in figure 1.1 collaborated with figure 1.2 distinguished base loads from peaking power
plants. The base load and peaking candidate power plants are displayed in table 1.2. In table 1.2, it was observed
that at high capacity factor of above 40%, the base load candidates incurred at higher AFC than AVC and low
LCOE. However, the case for the 300MW coal was rather incomparable with all the other base load plants. The
Coal plant had an AFC of US$ 366 per kW.yr lower than the AVC of US$ 660 per kW.yr. Besides, its LCOE
was the highest in relation to all the other base load candidate plants.
On the contrary, at low capacity factor of 30% and 40%, the peaking candidate plants had higher AVC
than AFC and high LCOE. However, this was exceptional for 100MW solar PV which had a lower AVC of US$
9 per kW.yr than AFC of US$ 699 per kW.yr. Although, solar PV and 160MW HFO had the same LCOE of
US$cts 20/kWh; the HFO’s relatively higher AVC of US$ 952 per kW.yr gave solar PV the comparative
advantage as a better peaking plant. Similarly, the 180MW GT-kerosene was as unfavorable peaking plant as
HFO on account of its highest AVC.
Table 1.2: Base Load and Peaking Candidate Plants
SNo.
Candidate Generation
Plants
Annual Fixed
Cost
($/kW/yr)
Annual
Variable Cost
($/kW/yr)
LCOE
($cts/kWh)
% Capacity
Factors
Plant
Type
1 140MW Geothermal 517 49 7.1 90
BaseLoads
2 300MW Wind 304 9 8.8 40
3 140MW LGF 507 47 10.2 60
4 1000MW Nuclear 652 119 10.7 80
5 60MW Mutonga hydro 612 47 12.2 60
6 300MW Coal 366 660 14.5 60
7 1000MW Imports 91 438 6.2 90 Both
8 180MW GT-Nat Gas 105 980 15.2 30
PeakLoads
9 160MW HFO 239 952 20.0 30
10 100MW Solar PV 699 9 20.0 40
11 180MW GT-Kero 105 2124 28.2 30
Consequently, 140MW geothermal, 140MW LGF hydro, 300MW wind, 1000MW imports, 60MW
mutonga hydro and 1000MW nuclear plants were selected as suitable green base load plants while coal was
excluded. On the other hand, 180MW GT-natural gas and 100MW solar PV plants were suitable green peaking
Screening Power Plants for Green-Based Generation Expansion Planning for Kenya
DOI: 10.9790/1676-10437380 www.iosrjournals.org 79 | Page
plants while 160MW HFO and 180MW GT-kerosene were barred. The abundant hydropower imports from
Ethiopia served both as a base and peaking power plant.
VI. Discussion
The results from the annual generation cost (AGC) and the levelized cost of electricity (LCOE) curves
were used to select suitable base load and peaking plants for GEP. According to [12]; [11], the AGC and LCOE
curves are used during preliminary screening of generation plants. An appropriate mix of candidate plants
minimizes the total generation cost. Therefore, green base load plants were identified as those with high fixed
costs (US$ 90-660/kW.yr), high capacity factor (more than 40%) and low LCOE (US$cts 6-13/kWh) namely;
140MW Geothermal, 140MW LGF hydro, 300MW Wind, 1000MW imports, 60MW Mutonga hydro and
1000MW nuclear plants.
Additionally, suitable green peaking plants were recognized as those with low fixed costs (US$ 100-
250/kW.yr), low capacity factor (less than 40%) and high LCOE (US$cts 15-30/kWh). The 180MW GT-Natural
gas was the main peaking option. Although 100MW Solar PV had the highest fixed cost (US$660/kW.yr), low
capacity factor (40%) and high LCOE (US$cts 20/kWh); it was classified as a peaking plant on account of its
intermittent nature. Additionally, the imports were considered partly as a peaking plant on account of it
abundance and relatively low cost. The characteristics for the base load and peaking plants and related energy
technologies were extensive in literature as cited by [10]; [13]; [11]. In addition, the selected power plants were
majorly clean and RE in accordance to the classification by [5]; [13]; [4].
As a matter of fact, Kenya was well placed to plan for exploitation of these enormous candidate energy
resources for the following reasons. The 60MW Mutonga and 140MW LGF hydropower sites were due for
immediate development [9]. Besides; the abundant unexploited feasible geothermal totaling to 7600MW existed
[14] for shifting the base load generation from the vulnerable hydropower [9]. Moreover, the Kenya’s strategic
location along the equator offered about 638, 790 TWh potential for solar PV as a potential peaking substitute
for the expensive HFO power [16]; [17]. Furthermore, a huge potential of about 346W/m2
for wind base load
power generation exists [15]. Moreover, an effective green generation portfolio required a proportion of other
resources for higher generation system’s reliability and stability [5]. Subsequently, there were at least 2000MW
hydropower imports from Ethiopia, about 2340MW natural gas and about 4000MW nuclear potential [7]. This
was a secure and reliable green-based generation portfolio for security of power and CO2 emission reduction.
VII. Conclusion And Recommendation
The selected green base load candidate plants for GEP were those with US$ 90-660/kW.yr fixed costs,
more than 40% capacity factor and US$cts 6-13/kWh LCOE namely; 140MW Geothermal, 140MW LGF hydro,
300MW Wind, 1000MW imports, 60MW Mutonga hydro and 1000MW nuclear plants. Additionally, suitable
green peaking plants were those with US$ 100-250/kW.yr fixed costs, less than 40% capacity factor and US$cts
15-30/kWh LCOE namely 180MW GT-Natural gas and 100MW Solar PV. Additionally, the plentiful imports
served as a peaking plant. This was a mix of green generation plants for cost effective utilization and
environmental sustainability in Kenya. Therefore, the research recommended the selected candidates for
simulation and optimization of a green-based generation expansion plan for Kenya using relevant GEP models.
Acknowledgement
I would like to thank Dr. Oliver Johnson of the Stockholm Environmental Institute (SEI); Nairobi for
his mentorship during the preparation of this paper. I also acknowledge the assistance provided by the SEI
Write-shop to Support Developing of Country Publications on Transitions to Modern Energy Systems in which
this paper was chosen. I declare that there was not conflict of interest in this research.
References
[1] IPCC. (2011). Renewable Energy Sources and Climate Change Mitigation; Summary for Policy Makers and Technical Summary.
Online at:http://www.ipcc.ch/pdf/special-reports/srren/SRREN_FD_SPM_final.pdf
[2] IPCC. (2013). Working Group I Contribution to the IPCC Fifth Assessment Report, Climate Change 2013: Physical Science Basis,
Summary for Policy Makers. Online at: http://www.ipcc.ch/
[3] Mejía Giraldo, Diego Adolfo, López Lezama, Jesús María, Gallego Pareja, Luis Alfonso. (2012). Power System Capacity
Expansion Planning Model Considering Carbon Emissions Constraints; Revista Facultad de Ingeniería Universidad de Antioquia.
Online at: http://www.redalyc.org/articulo.oa?id=43025115012 ISSN 0120-6230
[4] REN21. (2014). Renewables 2014 Global Status Report. Renewable Energy Policy Network for the 21st
Century. Online at:
http://www.ren21.net/Portals/o/documents/
[5] Kathib, H. (2003). Economic Evaluation of Projects in Electricity Supply Industry. The Institution of Electrical Engineers, London,
UK.
[6] Maslyuk, S and Dharmaratna. (2013). Renewable Electricity Generation, CO2 Emissions and Economic Growth: Evidence from
Middle-Income Countries in Asia. Estudios De Economia Aplicada. Vol. 31 – 1 pp. 217 – 244.
[7] MOE. (2011). Updated Least Cost Power Development Plan. Nairobi: Ministry of Energy.
[8] MEWNR. (2014). National Climate Change Framework Policy. Nairobi: Ministry of Environment, Water & Natural Resources.
[9] MOE. (2013). National Energy Policy. Nairobi: Ministry of Energy.
Screening Power Plants for Green-Based Generation Expansion Planning for Kenya
DOI: 10.9790/1676-10437380 www.iosrjournals.org 80 | Page
[10] IAEA. (1984). Technical Reports Series No. 241; Expansion Planning for Electrical Generating Systems: A Guidebook,
International Atomic energy Agency. Online at: http://www.energycommunity.org/documents/IAEATRS241.pdf
[11] Zhang, Tong. (2013). Generation Capacity Planning Using Screening Curves Method. Master of Science in Engineering Thesis.
University of Texa; Austrin. Online at: http://repositories.lib.utexas.edu/bitstream/handle/2152/21763/ZHANG-THESIS-
2013.pdf?sequence=1
[12] Bhattacharyya, S.C. (2011). Energy Economics Concepts Issues, Market & Governance. Springer Verlag London Ltd. UK (e-ISBN
978-0-85729-268-1)
[13] Elkarmi, F. and Abu-Shikhah, N. (2012). Power System Planning Technologies & Applications: Concepts, Solutions and
Management. Engineering Science Reference (IGI Global). ISBN 978-1-4666-0174-1 (ebook). Online athttp://www.igi-global.com
[14] Kengen. (2013). 61st
Annual Report & Financial Statements; Financial Year Ended 30th
June 2013, Nairobi: Kenya Generation
Company.
[15] SWERA. (2008). Kenya Country Report; Solar and Wind Energy Resource Assessment. Nairobi. Online at:
http://www.unep.org/eou/Portals/52/Reports/SWERA_ TE_Final Report.pdf
[16] Bazilian, M., Onyeji, I., Liebreich, M., MacGill, I., Chase, J. (2013). Reconsidering the Economics of PV Power. Renewable
Energy, 53:329 - 328.
[17] Ondracnek, J. (2014). Are we there yet? Improving Solar PV Economics and Power Planning in Developing Countries: A Case-
Study of Kenya. Renewable & Sustainable Energy Reviews 30: 604 – 615.

Contenu connexe

Tendances

Massachusetts policies for combined heat & power
Massachusetts policies for combined heat & powerMassachusetts policies for combined heat & power
Massachusetts policies for combined heat & power
TNenergy
 
The Value of Diversifying Uncertain Renewable Generation through the Transmis...
The Value of Diversifying Uncertain Renewable Generation through the Transmis...The Value of Diversifying Uncertain Renewable Generation through the Transmis...
The Value of Diversifying Uncertain Renewable Generation through the Transmis...
Power System Operation
 

Tendances (20)

IRENA GPCA presentation 2015 1012
IRENA GPCA presentation 2015 1012IRENA GPCA presentation 2015 1012
IRENA GPCA presentation 2015 1012
 
Evaluation of the role of energy storages in Europe with TIMES PanEU
Evaluation of the role of energy storages in Europe with TIMES PanEUEvaluation of the role of energy storages in Europe with TIMES PanEU
Evaluation of the role of energy storages in Europe with TIMES PanEU
 
Analysis of the required global energy system transformations and the associa...
Analysis of the required global energy system transformations and the associa...Analysis of the required global energy system transformations and the associa...
Analysis of the required global energy system transformations and the associa...
 
Analysis of the relative roles of supply-side and demand-side measures in tac...
Analysis of the relative roles of supply-side and demand-side measures in tac...Analysis of the relative roles of supply-side and demand-side measures in tac...
Analysis of the relative roles of supply-side and demand-side measures in tac...
 
Mitigation Pathways to well below 2C in ETSAP-TIAM
Mitigation Pathways to well below 2C in ETSAP-TIAMMitigation Pathways to well below 2C in ETSAP-TIAM
Mitigation Pathways to well below 2C in ETSAP-TIAM
 
IRENA - Remap 2030 - Cost and Benefits...
IRENA - Remap 2030 - Cost and Benefits...IRENA - Remap 2030 - Cost and Benefits...
IRENA - Remap 2030 - Cost and Benefits...
 
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
Addressing RE Intermittency and Operation Aspects of Generating Units in Long...
 
IRENA - Renewable Energy and Jobs Annual Review 2015
IRENA - Renewable Energy and Jobs Annual Review 2015IRENA - Renewable Energy and Jobs Annual Review 2015
IRENA - Renewable Energy and Jobs Annual Review 2015
 
Assessment of renewable energy in nation-wide power grid in Japan by optimal ...
Assessment of renewable energy in nation-wide power grid in Japan by optimal ...Assessment of renewable energy in nation-wide power grid in Japan by optimal ...
Assessment of renewable energy in nation-wide power grid in Japan by optimal ...
 
Capacity Building on Modeling the Ethiopian Energy System: Final Workshop
Capacity Building on Modeling the Ethiopian Energy System: Final WorkshopCapacity Building on Modeling the Ethiopian Energy System: Final Workshop
Capacity Building on Modeling the Ethiopian Energy System: Final Workshop
 
Pushing the limits of TIAM - Achieving well-below 2 degrees scenarios
Pushing the limits of TIAM - Achieving well-below 2 degrees scenariosPushing the limits of TIAM - Achieving well-below 2 degrees scenarios
Pushing the limits of TIAM - Achieving well-below 2 degrees scenarios
 
Status ETSAP_TIAM Git project and starting up ETSAP-TIAM update
Status ETSAP_TIAM Git project and starting up ETSAP-TIAM updateStatus ETSAP_TIAM Git project and starting up ETSAP-TIAM update
Status ETSAP_TIAM Git project and starting up ETSAP-TIAM update
 
Status of US CCS projects and data available
Status of US CCS projects and data availableStatus of US CCS projects and data available
Status of US CCS projects and data available
 
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
Enhancement to the TIMES Source Code: Enabling REGIONS and TIME-SLICES to be ...
 
Economic Assessment of Low-Emission Development Scenarios for Ukraine
Economic Assessment of Low-Emission Development Scenarios for UkraineEconomic Assessment of Low-Emission Development Scenarios for Ukraine
Economic Assessment of Low-Emission Development Scenarios for Ukraine
 
Massachusetts policies for combined heat & power
Massachusetts policies for combined heat & powerMassachusetts policies for combined heat & power
Massachusetts policies for combined heat & power
 
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
Overview of Hydrogen TCP, Task 41. Introduce discussion points from the hydro...
 
Sustainable energy and climate mitigation pathways in the Republic of Mauritius
Sustainable energy and climate mitigation pathways in the Republic of MauritiusSustainable energy and climate mitigation pathways in the Republic of Mauritius
Sustainable energy and climate mitigation pathways in the Republic of Mauritius
 
Addressing flexibility and decarbonization of energy systems through TIMES mo...
Addressing flexibility and decarbonization of energy systems through TIMES mo...Addressing flexibility and decarbonization of energy systems through TIMES mo...
Addressing flexibility and decarbonization of energy systems through TIMES mo...
 
The Value of Diversifying Uncertain Renewable Generation through the Transmis...
The Value of Diversifying Uncertain Renewable Generation through the Transmis...The Value of Diversifying Uncertain Renewable Generation through the Transmis...
The Value of Diversifying Uncertain Renewable Generation through the Transmis...
 

En vedette

En vedette (20)

F017163443
F017163443F017163443
F017163443
 
D012622129
D012622129D012622129
D012622129
 
E017263040
E017263040E017263040
E017263040
 
A018140107
A018140107A018140107
A018140107
 
F1803023843
F1803023843F1803023843
F1803023843
 
J011138795
J011138795J011138795
J011138795
 
L1303046572
L1303046572L1303046572
L1303046572
 
A011210108
A011210108A011210108
A011210108
 
F1803053945
F1803053945F1803053945
F1803053945
 
K012447075
K012447075K012447075
K012447075
 
E012423034
E012423034E012423034
E012423034
 
An Assessment on Food Security in Developing Economies-Problems and Policy In...
An Assessment on Food Security in Developing Economies-Problems and Policy In...An Assessment on Food Security in Developing Economies-Problems and Policy In...
An Assessment on Food Security in Developing Economies-Problems and Policy In...
 
C010241521
C010241521C010241521
C010241521
 
K017426872
K017426872K017426872
K017426872
 
B010320815
B010320815B010320815
B010320815
 
Numerical Solution for the Design of a Traditional Aerospike Nozzle using Met...
Numerical Solution for the Design of a Traditional Aerospike Nozzle using Met...Numerical Solution for the Design of a Traditional Aerospike Nozzle using Met...
Numerical Solution for the Design of a Traditional Aerospike Nozzle using Met...
 
I010425559
I010425559I010425559
I010425559
 
O017328693
O017328693O017328693
O017328693
 
Q180305116119
Q180305116119Q180305116119
Q180305116119
 
D1103042431
D1103042431D1103042431
D1103042431
 

Similaire à L010437380

Iceland Capstone Project
Iceland Capstone ProjectIceland Capstone Project
Iceland Capstone Project
Daniel Liu
 
Research Paper - Final Year Project
Research Paper - Final Year ProjectResearch Paper - Final Year Project
Research Paper - Final Year Project
Ishan Rathnayake
 
Techno-Economic Analysis of Biomass Integrated Electricity Generation System
Techno-Economic Analysis of Biomass Integrated Electricity Generation SystemTechno-Economic Analysis of Biomass Integrated Electricity Generation System
Techno-Economic Analysis of Biomass Integrated Electricity Generation System
theijes
 
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
aeijjournal
 

Similaire à L010437380 (20)

Iceland Capstone Project
Iceland Capstone ProjectIceland Capstone Project
Iceland Capstone Project
 
Bankability of clean energy projects - South Africa case
Bankability of clean energy projects - South Africa caseBankability of clean energy projects - South Africa case
Bankability of clean energy projects - South Africa case
 
Bankability of Clean Energy Projects: the case of South Africa - 6 GW
Bankability of Clean Energy Projects: the case of South Africa - 6 GWBankability of Clean Energy Projects: the case of South Africa - 6 GW
Bankability of Clean Energy Projects: the case of South Africa - 6 GW
 
A Case Study Of An Educational Building Transformation To Renewable Energy
A Case Study Of An Educational Building Transformation To Renewable EnergyA Case Study Of An Educational Building Transformation To Renewable Energy
A Case Study Of An Educational Building Transformation To Renewable Energy
 
I010326469
I010326469I010326469
I010326469
 
Power energy generation report
Power energy generation reportPower energy generation report
Power energy generation report
 
Accelerated Development of Renewable Energy Irrigation System in Nigeria
Accelerated Development of Renewable Energy Irrigation System in NigeriaAccelerated Development of Renewable Energy Irrigation System in Nigeria
Accelerated Development of Renewable Energy Irrigation System in Nigeria
 
Captive Power Plants
Captive Power PlantsCaptive Power Plants
Captive Power Plants
 
SMALL HYDROPOWER RELEVANCE FOR BASIC ENERGY NEED IN AFRICA
SMALL HYDROPOWER RELEVANCE FOR BASIC ENERGY NEED IN AFRICASMALL HYDROPOWER RELEVANCE FOR BASIC ENERGY NEED IN AFRICA
SMALL HYDROPOWER RELEVANCE FOR BASIC ENERGY NEED IN AFRICA
 
Research Paper - Final Year Project
Research Paper - Final Year ProjectResearch Paper - Final Year Project
Research Paper - Final Year Project
 
23PESGM4066.pptx
23PESGM4066.pptx23PESGM4066.pptx
23PESGM4066.pptx
 
Energy Transition and Net Zero initiative
Energy Transition and Net Zero initiativeEnergy Transition and Net Zero initiative
Energy Transition and Net Zero initiative
 
Peak Shaving Using Grid-Connected Solar Panels Case Study: Ministry of Islami...
Peak Shaving Using Grid-Connected Solar Panels Case Study: Ministry of Islami...Peak Shaving Using Grid-Connected Solar Panels Case Study: Ministry of Islami...
Peak Shaving Using Grid-Connected Solar Panels Case Study: Ministry of Islami...
 
Developing Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in IndiaDeveloping Solar Projects under REC Mechanism in India
Developing Solar Projects under REC Mechanism in India
 
Techno-Economic Analysis of Biomass Integrated Electricity Generation System
Techno-Economic Analysis of Biomass Integrated Electricity Generation SystemTechno-Economic Analysis of Biomass Integrated Electricity Generation System
Techno-Economic Analysis of Biomass Integrated Electricity Generation System
 
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR ...
FEASIBILITY STUDY OF ORKNEY’S WINDFARM  DEVELOPMENT FOR SELF-SUFFICIENT FOR  ...FEASIBILITY STUDY OF ORKNEY’S WINDFARM  DEVELOPMENT FOR SELF-SUFFICIENT FOR  ...
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR ...
 
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
 
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
 
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
 
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
FEASIBILITY STUDY OF ORKNEY’S WINDFARM DEVELOPMENT FOR SELF-SUFFICIENT FOR EN...
 

Plus de IOSR Journals

Plus de IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Dernier

Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
panagenda
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Victor Rentea
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Victor Rentea
 

Dernier (20)

Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​Elevate Developer Efficiency & build GenAI Application with Amazon Q​
Elevate Developer Efficiency & build GenAI Application with Amazon Q​
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Vector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptxVector Search -An Introduction in Oracle Database 23ai.pptx
Vector Search -An Introduction in Oracle Database 23ai.pptx
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Platformless Horizons for Digital Adaptability
Platformless Horizons for Digital AdaptabilityPlatformless Horizons for Digital Adaptability
Platformless Horizons for Digital Adaptability
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
Modular Monolith - a Practical Alternative to Microservices @ Devoxx UK 2024
 

L010437380

  • 1. IOSR Journal of Electrical and Electronics Engineering (IOSR-JEEE) e-ISSN: 2278-1676,p-ISSN: 2320-3331, Volume 10, Issue 4 Ver. III (July – Aug. 2015), PP 73-80 www.iosrjournals.org DOI: 10.9790/1676-10437380 www.iosrjournals.org 73 | Page Screening Power Plants for Green-Based Generation Expansion Planning for Kenya Patrobers Simiyu Institute of Energy & Environmental Technology (IEET); Jomo Kenyatta University of Agriculture & Technology; Kenya Abstract: The main concern in the global generation sector was the huge CO2 emissions from the conventional power generation. In Kenya, the sector prepares 20 year rolling least cost power development plan (LCPDP) for expanding the power system to meet the current and future power demands. The 2011-2031 LCPDP generation plan proposed a system expansion that would result in a 33% fossil fuel power generation posing a huge CO2 emission dilemma. However, renewable energy integration in the least-cost generation expansion planning (GEP) was considered key to energy security and emission reduction. During GEP, the screening curves are useful preliminary tool in selecting candidate generation options. In this study the screening curves were used in vetting the candidate plants for green-base GEP in Kenya. The findings showed that the green base load candidate plants were namely; 140MW Geothermal, 140MW low grand falls hydro, 300MW Wind, 1000MW imports, 60MWMutonga hydro and 1000MW nuclear plants characterized by US$ 90-660/kW.yr fixed cost, more than 40% capacity factor and US$cts 6-13/kWh levelized cost of electricity (LCOE). Suitable green peaking plant were 180MW GT-Natural gas, 100MW Solar PV and imports depicted by US$ 100-700/kW.yr fixed cost, less than 40% capacity factor and US$cts 15-30/kWh LCOE. These were a mix of green generation plants for cost effective utilization and environmental sustainability in Kenya. Therefore, the research recommended the selected candidate plants for simulation and optimization of a green-based generation expansion plan for Kenya using relevant GEP models. Key Words: annual generation cost curves; base load plants; generation expansion planning; levelized cost of electricity; screening curves; peaking plants. I. Introduction The growing concerns for climate change mitigation in the generation sector have driven many countries in the world towards environmentally-benign generation investments [1]; [2]. Renewable energy (RE) is regarded as an appropriate clean power alternative to the conventional carbon intensive plants [3]; [4]. Consequently, RE integration in least-cost generation expansion planning (GEP) is considered key to energy security and emission reduction [5]; [6]. In Kenya, the sector prepares 20 year rolling least cost power development plan (LCPDP) at the energy regulatory commission (ERC) for expanding the power system to meet the current and future power demands. The 2011-2031 LCPDP had significant RE composition [7]. However, there was room for more integration because the planned large hydropower and heavy fuel oil (HFO) dominated power generation posed serious challenges. According to [8], the large hydros were vulnerable to acute energy shortfalls due to the frequent droughts. Conversely, the HFO and the planned conventional coal power plants posed the CO2 emissions dilemma [9]. However, Kenya owns huge under-exploited RE resources yet for exploitation. Therefore this study assessed the Kenya generation potential using the screening curves with the aim of identifying a portfolio of sustainable RE candidate plants for green-based GEP. This would stimulate the Kenya generation sector in adopting a more sustainable GEP towards security of power and CO2 emission reductions. In addition, as a regional hub in social-economic development, Kenya will stand as a benchmark for many countries in Africa and beyond. This paper is divided into seven sections. The section two gives an overview of the screening curves. Section three presents the RE potential in Kenya. Section four outlines the study methodology. Section five gives the results. Section six gives the discussion while the last section gives the conclusion and recommendation for future research. II. Screening Curves The screening curve analysis (SCA) involves preliminary vetting of candidate generation sources to establish the most economical supply option. In this approach, the total costs during the operating life of the potential options are discounted and plotted against capacity factor values. The resulting screening curves captures major trade-offs between capital and operating costs and the utilization levels of various generation technologies allowing higher cost options to be excluded for further consideration [10].
  • 2. Screening Power Plants for Green-Based Generation Expansion Planning for Kenya DOI: 10.9790/1676-10437380 www.iosrjournals.org 74 | Page In the SCA, the annual total generation cost (AGC) is represented as a function of variable fuel cost (VFC) and variable operation and maintenance cost (VOMC). The annualized capital cost (ACC) and fixed operation and maintenance cost (FOMC) are held constant. The linear equation (1) shows the screening curve expression [11]. AGG = {ACC + FOMC + VFC + VOMC . T}…………………………..….……..……..……………………… (1) Where: ACC; Annualized capital cost per MW, FOMC; Fixed operation and maintenance cost per MW per year, VFC; Variable fuel cost per MWh, VOMC; Variable operation and maintenance cost per MWh and T; total year operating hours for the given MW. Additionally, the screening curves integrated with the load duration curve (LDC) can give an appropriate mix of plants to minimize the total generation cost of a power system. In this way, the screening curves are positioned on the upper half while the LDC placed on the lower half. By projecting the intersection point from the screening curves onto the LDC, the portion of generation capacity that would be supplied from the plants captured in the screening curves is yielded [10]; [12]. However, SCA is inadequate for GEP as it doesn’t capture the complex and diverse power generation parameters such as system reliability, resource capacity constraints, related uncertainties as well as the existing generation system [12]; [11]. For this reason, numerous and sophisticated GEP models extensive in literature are available for effective simulation of the generating system’s operation and subsequently optimizing the generation expansion plan [13]. Nevertheless, prior to the process, the screening curves are useful preliminary screening tool in selecting candidate generation plants [12]. III. Renewable Energy Potential In Kenya Kenya is well endowed with enormous RE resources. The hydropower potential in Kenya totals 1670MW but only 807MW of this capacity is installed. Detailed hydropower assessments revealed a 700MW High Grand Falls potential project along the Tana River and a further 100MW at Karura. Additionally, Mutonga (60MW) and low grand falls (LGF) (140MW) sites were found suitable for immediate development. Moreover feasibility studies established Ewaso Ng’iro South River (220MW) and the North-Rift Valley basin at Arror (70MW) [9]. The geothermal resources mainly situated within the Kenya’s East African Rift system are currently installed at 250.4MW. Detailed exploration studies revealed that the potential geothermal sites have a total generation of 5,000 – 10, 000 MWe. The prospects are clustered mainly into Central Rift (1,800MW), South Rift (2,400MW) and North Rift (3,450MW) [9] [14]. Kenya’s strategic location along the equator offers great potential of about 4-6 KWh/m2 /day of daily insolation for solar power. This potential is spread in many parts of the coast, north eastern, eastern amongst other parts of the country [15]. The total area capable of delivering 6KWh/m2 per day is about 106, 000 km2 with a potential of 638, 790 TWh for solar photovoltaic (PV) and thermal though less than 1% is in use [16]; [17]. Additionally, a huge potential of about 346W/m2 and wind speeds of over 6m/s for wind power generation exists. On average about 90,000 Km2 of area in the country have very excellent wind speeds of 6m/s yet a meager 5.3MW is currently installed [9]. Nonetheless, the steady growing interest in wind power is significantly increasing its role in the Kenya electricity mix for grid and off-grid power systems [15]. Moreover, there are commercially exploitable coal reserves discovered in the Mui basin in Kitui County besides the RE potential. In the 2011-2031 LCPDP, conventional coal power generation was projected to come on line in 2015 and by 2030 it would provide 4500MW of power. Nevertheless, the projected use of the coal technology will increase the CO2 emissions to record levels contradicting the climate change mitigation strategies [8]. Furthermore, there are other cost-effective energy resources within Kenya’s reach. There are at least 2000MW hydropower imports from Ethiopia. Secondly, about 2340MW Natural gas imports and local reserves are available for 180MW combined cycle gas turbine (CCGT) plants. Finally, the country has adopted a systematic international methodology of developing the nuclear infrastructure for commissioning its first ever 1000MW nuclear power plant by 2024 [7]. IV. Methodology The candidate generation plants from the Kenya’s available energy resources for the study include; 140MW geothermal, 1000MW nuclear, 300MW coal, 180MW Gas Turbine (GT)-Kerosene, 180MW GT- Natural gas, 160MW heavy fuel oil (HFO), 1000MW imports, 60MW Mutonga hydro, 140MW low grand falls (LGF), 300MW wind and 100MW solar photovoltaic (PV). A generation cost model (GCM) was set up in the Microsoft Excel encompassing each candidate plant. The GCM was mainly comprised of power generation technical and economic power generation characteristics namely; fixed & variable generation costs, total outage rate (TOR), outage adjustment factor (OAF), interim replacement (IR), interest during construction (IDC) and
  • 3. Screening Power Plants for Green-Based Generation Expansion Planning for Kenya DOI: 10.9790/1676-10437380 www.iosrjournals.org 75 | Page capital recovery factor (CRF). Figure 1.0 shows the GCM outline for the candidate plants. Figure 1.0: GCM Outline for the Candidate Generation Plants The equations (2) to (10) were used to represent the power generation characteristics for all the candidates in the GCM. Capital ($X106 ) = Installed Capacity MW X Capital ($/kW ) (103) ………………………......………………...……...…....(2) Fixed Annual Capital($/kW. yr) = {Capital($/kW) X(IDC Factor)X(CRF + IR)}...........................................(3) Total Fixed Annual Cost($/kW. yr) = {Fixed Annual Capital($/kW. yr) + Fixed O&𝑀($/kW. yr)}….........(4) OAF = 1 (1− TOR ) ……………………………….…….…………………………….……..……...……………….(5) Annual Fixed Cost($/kW. yr) = {Total Fixed Annual Cost($/kW. yr) X(OAF)}..............................................(6) Annual Fixed Cost($/kWh) = Annual Fixed Cost ($/kW .yr) (8760) …………………............…….….……...……………..(7) Fuel Cost($/kWh) = Fuel Price ($/Gj) X Heat Rate (kJ/kWh ) (106) ……………........................….………….……………..(8) Total Variable Cost($/kWh) = {Fuel Cost($/kWh) + CO2 TaxCost($/kWh + Variable O&𝑀 𝐶𝑜𝑠𝑡($/ kWh)}………………………………………………...……………….................................................................(9) Total Variable Cost($/kW. yr) = {Total Variable Cost($/kWh) X 8760}……..………………………...…..(10) The GCM was used to evaluate the annual generation cost (AGC) for each candidate plant as a function of the annual variable cost (AVC); the annualized fixed cost (AFC) held constant. These cost variables for the candidates are shown in the AGC curve expression in equation (11). In this linear equation, the AFC is the intercept while the AVC, the slope. AGC($/kW. yr) = {AVC($/kW. yr). (% CapacityFactor) + AFC($/kW. yr)}…............................................(11) Similarly, the levelized cost of electricity (LCOE) for each candidate plant was calculated. The total variable cost (TVC), AFC and capacity factor were key LCOE components. The LCOE expression is represented using equation (12). LCOE($/kWh) = TVC ($/kWh) + AFC ($/kW .yr) (8760 X % Capacity Factor ) ………………............…………….…………….(12) The AGC and the LCOE screening curves were used in the selection of the base load and peaking RE candidate plants for GEP. V. Results The generation cost model (GCM) was developed for screening the candidate generation plants. Table 1.1 presents the GCM for the candidate generation plants. From table 1.1, the capital costs widely varied across the candidate plants. Solar PV had the highest capital cost of US$4450/kW.yr while the imports had the lowest of about a tenth of the solar PV’s capital cost (US$455/kW.yr). On the other hand, the fuel cost was quite
  • 4. Screening Power Plants for Green-Based Generation Expansion Planning for Kenya DOI: 10.9790/1676-10437380 www.iosrjournals.org 76 | Page significant in GT-kerosene had the highest fuel cost at U$cts 22.2/kWh while HFO the least at U$cts 9.1/kWh. The RE such as solar PV, wind, low grand falls (LGF), Mutonga hydro, imports and geothermal had no fuel costs. Table 1.1: Candidate Generation Plants’ Generation Cost Model (GCM). Geotherma l Nuclea r Coal GT- KER O GT- N.GA S HFO Impor t Mutong a LGF Wind Solar PV Configuration (n x MW) 1 x 140 1 X 1000 1 X 300 1 x 180 1 x 180 1 x 160 1000 1x60 1x140 300 100 Total Capacity (MW) 140 1000 300 180 180 160 1000 60 140 300 100 Fixed Cost Capital ( $ x 106 ) 511 4055 631 135 135 218 455 259 507 690 445 Capital ($/kW) 3650 4055 2104 750 750 1364 455 4314 3621 2300 4450 IDC Factor 1.1344 1.2605 1.1341 1.0725 1.0725 1.065 4 1.0654 1.3378 1.337 8 1.065 4 1.138 0 Annuity Factor (or C.R.F.) 0.0937 0.0839 0.0937 0.1019 0.1019 0.101 9 0.0937 0.0817 0.081 7 0.093 7 0.111 4 Interim Replacement 0.921% 0.68% 0.921 % 0.35% 0.35% 0.35% 0.35% 1.03% 0.87% 0.64% 0.63% Fixed Annual Capital ($/kW/yr) 426.0 463.6 245.5 84.7 84.7 153.1 47.1 531.4 438.2 245.3 596.1 Fixed O&M Costs ($/kW/yr) 56.0 90.0 63 11.8 11.8 62.5 30.0 21.3 19.8 28.1 39.0 Total Fixed Annual Cost ($/kW/yr) 482 554 309 97 97 216 15 553 458 273 635 Total Outage Rate (TOR) 0.068 0.150 0.156 0.078 0.078 0.098 0.150 0.0969 0.096 9 0.100 0.091 Outage Adjustment Factor (OAF) 1.073 1.177 1.185 1.085 1.085 1.108 1.176 1.107 1.107 1.111 1.100 Annual Fixed Cost ($/kW/yr) 517 652 366 105 105 239 91 612 507 304 699 Annual Fixed Cost ($/kWh) 0.0590 0.0744 0.0417 0.0120 0.0120 0.027 3 0.0104 0.0699 0.057 9 0.034 7 0.079 8 Variable Cost Fuel Price ($/GJ) - 4.557 19.37 9.11 11.08 - - - - - Heat Rate (kJ/kWh) - 10900 11,440 11,447 8,197 - - - - - FuelCost($/kWh) - 0.0087 0.0497 0.2216 0.1043 0.090 9 - - - - - CO2 Tax Cost ($/kWh) - 0.0221 0.0089 0.0066 0.008 9 - - - - - Variable O&M Cost ($/kWh) 0.00557 0.0049 0.0036 0.0120 0.0010 0.008 9 - 0.0053 0.005 3 0.001 0 0.001 0 Total Variable Cost ($/kWh) 0.00557 0.0136 0.0754 0.2425 0.1119 0.108 7 0.0500 0.0053 0.005 3 0.001 0 0.001 0 Total Variable Cost ($/kW/yr) 49 119 660 2124 980 952 438 47 47 9 9
  • 5. Screening Power Plants for Green-Based Generation Expansion Planning for Kenya DOI: 10.9790/1676-10437380 www.iosrjournals.org 77 | Page The annualized fixed costs (AFC) & annualized variable costs (AVC) for the candidate plants at varied capacity factors yielded the annual generation cost curves (AGC). Figure 1.1 shows AGC curves realized for the candidate plants. Similarly, the unit cost or levelized costs of electricity (LCOE) for the candidate plants at varied capacity factors generated the LCOE curves. Figure 1.2 shows the LCOE for candidate plants. figure 1.1: AGC Curves for candidate plants 0 500 1000 1500 2000 2500 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Geothermal Nuclear Coal GT-KERO GT- N.GAS HFO Import Mutonga % Capacity Factor AnnuallizedFixed& VariableCost($/kW.yr) Unit Cost ($/kW.yr) Capacity Factor Geo Nucl Coal GT- KER GT- N.GA HFO Impo Muto LGF Wind SoPV 0% 517 652 366 105 105 239 91 612 507 304 699 10% 522 663 432 317 203 334 135 617 512 305 700 20% 527 675 498 530 301 429 178 621 517 305 700 30% 532 687 564 742 399 525 222 626 521 306 701 40% 536 699 630 954 497 620 266 631 526 307 702 50% 541 711 696 1167 595 715 310 635 531 - - 60% 546 723 762 1379 693 810 354 640 535 - - 70% 551 735 828 1592 791 905 397 - - - - 80% 556 747 894 1804 889 1001 441 - - - - 90% 561 759 960 2017 987 1096 485 - - - - 100% 566 770 1026 2229 1085 1191 529 - - - - Unit Cost ($/kWh) Capacity Factor Geo Nucl Coal GT- KER GT- N.GA HFO Impo Muto LGF Wind SoPV 10% 0.5957 0.757 0.493 0.362 0.231 0.382 0.154 0.704 0.584 0.348 0.799 20% 0.3006 0.385 0.284 0.302 0.172 0.245 0.102 0.355 0.295 0.174 0.400 30% 0.2023 0.262 0.215 0.282 0.152 0.200 0.085 0.238 0.198 0.117 0.267 40% 0.1531 0.200 0.180 0.272 0.142 0.177 0.076 0.180 0.150 0.088 0.200 50% 0.1236 0.162 0.159 0.266 0.136 0.163 0.071 0.145 0.121 - - 60% 0.1039 0.138 0.145 0.262 0.132 0.154 0.067 0.122 0.102 - - 70% 0.0899 0.120 0.135 0.260 0.129 0.148 0.065 - - - - 80% 0.0793 0.107 0.128 0.257 0.127 0.143 0.063 - - - - 90% 0.0711 0.096 0.122 0.256 0.125 0.139 0.062 - - - - 100% 0.0646 0.088 0.117 0.254 0.124 0.136 0.060 - - - -
  • 6. Screening Power Plants for Green-Based Generation Expansion Planning for Kenya DOI: 10.9790/1676-10437380 www.iosrjournals.org 78 | Page The results in figure 1.1 show that solar PV had the highest AFC of US$ 699/kW.yr while the Ethiopia’s hydropower imports the least at US$ 91/kW/yr. On the contrary, GT-kerosene incurred the highest AVC of US$ 2124/kW.yr while wind and solar PV the least at US$ 9/kW.yr each. On the other hand, the results in figure 1.2 show that solar PV at 30% capacity factor cost highest at US$cts 20/kWh while hydropower imports from Ethiopia at 90% capacity factor cost the least at US$cts 6.2/kWh. figure 1.2: LCOE curves for candidate plants The results in figure 1.1 collaborated with figure 1.2 distinguished base loads from peaking power plants. The base load and peaking candidate power plants are displayed in table 1.2. In table 1.2, it was observed that at high capacity factor of above 40%, the base load candidates incurred at higher AFC than AVC and low LCOE. However, the case for the 300MW coal was rather incomparable with all the other base load plants. The Coal plant had an AFC of US$ 366 per kW.yr lower than the AVC of US$ 660 per kW.yr. Besides, its LCOE was the highest in relation to all the other base load candidate plants. On the contrary, at low capacity factor of 30% and 40%, the peaking candidate plants had higher AVC than AFC and high LCOE. However, this was exceptional for 100MW solar PV which had a lower AVC of US$ 9 per kW.yr than AFC of US$ 699 per kW.yr. Although, solar PV and 160MW HFO had the same LCOE of US$cts 20/kWh; the HFO’s relatively higher AVC of US$ 952 per kW.yr gave solar PV the comparative advantage as a better peaking plant. Similarly, the 180MW GT-kerosene was as unfavorable peaking plant as HFO on account of its highest AVC. Table 1.2: Base Load and Peaking Candidate Plants SNo. Candidate Generation Plants Annual Fixed Cost ($/kW/yr) Annual Variable Cost ($/kW/yr) LCOE ($cts/kWh) % Capacity Factors Plant Type 1 140MW Geothermal 517 49 7.1 90 BaseLoads 2 300MW Wind 304 9 8.8 40 3 140MW LGF 507 47 10.2 60 4 1000MW Nuclear 652 119 10.7 80 5 60MW Mutonga hydro 612 47 12.2 60 6 300MW Coal 366 660 14.5 60 7 1000MW Imports 91 438 6.2 90 Both 8 180MW GT-Nat Gas 105 980 15.2 30 PeakLoads 9 160MW HFO 239 952 20.0 30 10 100MW Solar PV 699 9 20.0 40 11 180MW GT-Kero 105 2124 28.2 30 Consequently, 140MW geothermal, 140MW LGF hydro, 300MW wind, 1000MW imports, 60MW mutonga hydro and 1000MW nuclear plants were selected as suitable green base load plants while coal was excluded. On the other hand, 180MW GT-natural gas and 100MW solar PV plants were suitable green peaking
  • 7. Screening Power Plants for Green-Based Generation Expansion Planning for Kenya DOI: 10.9790/1676-10437380 www.iosrjournals.org 79 | Page plants while 160MW HFO and 180MW GT-kerosene were barred. The abundant hydropower imports from Ethiopia served both as a base and peaking power plant. VI. Discussion The results from the annual generation cost (AGC) and the levelized cost of electricity (LCOE) curves were used to select suitable base load and peaking plants for GEP. According to [12]; [11], the AGC and LCOE curves are used during preliminary screening of generation plants. An appropriate mix of candidate plants minimizes the total generation cost. Therefore, green base load plants were identified as those with high fixed costs (US$ 90-660/kW.yr), high capacity factor (more than 40%) and low LCOE (US$cts 6-13/kWh) namely; 140MW Geothermal, 140MW LGF hydro, 300MW Wind, 1000MW imports, 60MW Mutonga hydro and 1000MW nuclear plants. Additionally, suitable green peaking plants were recognized as those with low fixed costs (US$ 100- 250/kW.yr), low capacity factor (less than 40%) and high LCOE (US$cts 15-30/kWh). The 180MW GT-Natural gas was the main peaking option. Although 100MW Solar PV had the highest fixed cost (US$660/kW.yr), low capacity factor (40%) and high LCOE (US$cts 20/kWh); it was classified as a peaking plant on account of its intermittent nature. Additionally, the imports were considered partly as a peaking plant on account of it abundance and relatively low cost. The characteristics for the base load and peaking plants and related energy technologies were extensive in literature as cited by [10]; [13]; [11]. In addition, the selected power plants were majorly clean and RE in accordance to the classification by [5]; [13]; [4]. As a matter of fact, Kenya was well placed to plan for exploitation of these enormous candidate energy resources for the following reasons. The 60MW Mutonga and 140MW LGF hydropower sites were due for immediate development [9]. Besides; the abundant unexploited feasible geothermal totaling to 7600MW existed [14] for shifting the base load generation from the vulnerable hydropower [9]. Moreover, the Kenya’s strategic location along the equator offered about 638, 790 TWh potential for solar PV as a potential peaking substitute for the expensive HFO power [16]; [17]. Furthermore, a huge potential of about 346W/m2 for wind base load power generation exists [15]. Moreover, an effective green generation portfolio required a proportion of other resources for higher generation system’s reliability and stability [5]. Subsequently, there were at least 2000MW hydropower imports from Ethiopia, about 2340MW natural gas and about 4000MW nuclear potential [7]. This was a secure and reliable green-based generation portfolio for security of power and CO2 emission reduction. VII. Conclusion And Recommendation The selected green base load candidate plants for GEP were those with US$ 90-660/kW.yr fixed costs, more than 40% capacity factor and US$cts 6-13/kWh LCOE namely; 140MW Geothermal, 140MW LGF hydro, 300MW Wind, 1000MW imports, 60MW Mutonga hydro and 1000MW nuclear plants. Additionally, suitable green peaking plants were those with US$ 100-250/kW.yr fixed costs, less than 40% capacity factor and US$cts 15-30/kWh LCOE namely 180MW GT-Natural gas and 100MW Solar PV. Additionally, the plentiful imports served as a peaking plant. This was a mix of green generation plants for cost effective utilization and environmental sustainability in Kenya. Therefore, the research recommended the selected candidates for simulation and optimization of a green-based generation expansion plan for Kenya using relevant GEP models. Acknowledgement I would like to thank Dr. Oliver Johnson of the Stockholm Environmental Institute (SEI); Nairobi for his mentorship during the preparation of this paper. I also acknowledge the assistance provided by the SEI Write-shop to Support Developing of Country Publications on Transitions to Modern Energy Systems in which this paper was chosen. I declare that there was not conflict of interest in this research. References [1] IPCC. (2011). Renewable Energy Sources and Climate Change Mitigation; Summary for Policy Makers and Technical Summary. Online at:http://www.ipcc.ch/pdf/special-reports/srren/SRREN_FD_SPM_final.pdf [2] IPCC. (2013). Working Group I Contribution to the IPCC Fifth Assessment Report, Climate Change 2013: Physical Science Basis, Summary for Policy Makers. Online at: http://www.ipcc.ch/ [3] Mejía Giraldo, Diego Adolfo, López Lezama, Jesús María, Gallego Pareja, Luis Alfonso. (2012). Power System Capacity Expansion Planning Model Considering Carbon Emissions Constraints; Revista Facultad de Ingeniería Universidad de Antioquia. Online at: http://www.redalyc.org/articulo.oa?id=43025115012 ISSN 0120-6230 [4] REN21. (2014). Renewables 2014 Global Status Report. Renewable Energy Policy Network for the 21st Century. Online at: http://www.ren21.net/Portals/o/documents/ [5] Kathib, H. (2003). Economic Evaluation of Projects in Electricity Supply Industry. The Institution of Electrical Engineers, London, UK. [6] Maslyuk, S and Dharmaratna. (2013). Renewable Electricity Generation, CO2 Emissions and Economic Growth: Evidence from Middle-Income Countries in Asia. Estudios De Economia Aplicada. Vol. 31 – 1 pp. 217 – 244. [7] MOE. (2011). Updated Least Cost Power Development Plan. Nairobi: Ministry of Energy. [8] MEWNR. (2014). National Climate Change Framework Policy. Nairobi: Ministry of Environment, Water & Natural Resources. [9] MOE. (2013). National Energy Policy. Nairobi: Ministry of Energy.
  • 8. Screening Power Plants for Green-Based Generation Expansion Planning for Kenya DOI: 10.9790/1676-10437380 www.iosrjournals.org 80 | Page [10] IAEA. (1984). Technical Reports Series No. 241; Expansion Planning for Electrical Generating Systems: A Guidebook, International Atomic energy Agency. Online at: http://www.energycommunity.org/documents/IAEATRS241.pdf [11] Zhang, Tong. (2013). Generation Capacity Planning Using Screening Curves Method. Master of Science in Engineering Thesis. University of Texa; Austrin. Online at: http://repositories.lib.utexas.edu/bitstream/handle/2152/21763/ZHANG-THESIS- 2013.pdf?sequence=1 [12] Bhattacharyya, S.C. (2011). Energy Economics Concepts Issues, Market & Governance. Springer Verlag London Ltd. UK (e-ISBN 978-0-85729-268-1) [13] Elkarmi, F. and Abu-Shikhah, N. (2012). Power System Planning Technologies & Applications: Concepts, Solutions and Management. Engineering Science Reference (IGI Global). ISBN 978-1-4666-0174-1 (ebook). Online athttp://www.igi-global.com [14] Kengen. (2013). 61st Annual Report & Financial Statements; Financial Year Ended 30th June 2013, Nairobi: Kenya Generation Company. [15] SWERA. (2008). Kenya Country Report; Solar and Wind Energy Resource Assessment. Nairobi. Online at: http://www.unep.org/eou/Portals/52/Reports/SWERA_ TE_Final Report.pdf [16] Bazilian, M., Onyeji, I., Liebreich, M., MacGill, I., Chase, J. (2013). Reconsidering the Economics of PV Power. Renewable Energy, 53:329 - 328. [17] Ondracnek, J. (2014). Are we there yet? Improving Solar PV Economics and Power Planning in Developing Countries: A Case- Study of Kenya. Renewable & Sustainable Energy Reviews 30: 604 – 615.