SlideShare une entreprise Scribd logo
1  sur  42
Streamlining Earned Value Management Proprietary & Confidential Ron Babich, VP Hard Dollar  Ron.babich@harddollar.com 480-776-2934
Project COST Management 2 Proprietary & Confidential Design (Materials) Estimating (Budget) Scheduling (Time) Progress (Project Controls) Finance (Accounting)
Overview Building the Cost Model Developing EVM Measurements Case Study: Successful Process Readiness
Capital Planning Project Variance 4 Proprietary & Confidential Project Plan Costs 15% 50% Costs Plan
EVM Requirements Effort Required WBS Period of Time Schedule Progress Performance Measurement Baseline
Regulatory  Requirements 6 Proprietary & Confidential Regulatory Requirements
7 Proprietary & Confidential Regulatory Requirements
Characteristics of Credible Cost Estimates Clear Identification  of Task Provision for Program Uncertainties Broad Participation in Preparation Recognition of Inflation Availability of Valid Data Recognition of Excluded Costs Standardized Structure  For Estimate Independent Review  Of Estimates
Budget/Cost Estimate Challenges 9 Proprietary & Confidential Typical Challenges
Auditors should… 10 Proprietary & Confidential Cost Element  Valid and Applicable Labor Includes Time  Phase Break Down Calculations  on each element are correct Program is Accurate Total Of Sub-Elements Escalation was applied  Over time
Case Study - NASA 0 of 10 Projects followed  All  Basic Steps 3 of 10 Projects  included detailed WBS 2 of 10 Measure Cost/Performance Identify Risk
Case Study – US Customs $1.05 BilCommercial Environmental Life Cycle No Formal Cost Model Spreadsheet  No Structured Documented Process for Determining Size/Reuse Size No Relevant, Measured, Normalized Historical Cost Data  to Calibrate Models Measurement
What is Earned Value Management? Earned Value Management (EVM)… Project management process that combines schedule performance and cost performance  Answers:  What did we get for the money we spent? Used since the 1960’s by the Department of Defense Central part of CERT and C/SCSC (Cost/Schedule Control Systems Criteria) Was recently revised and adopted as ANSI/EIA 748 13 Proprietary & Confidential
Example: Rail Project 14 Proprietary & Confidential Scope 4 Miles  Time 4 Weeks  Cost $ 4 Mil Scope 4 Miles  Time 4 Weeks  Cost $ 4 Mil
What is Earned Value Management? The Essence of Earned Value Management (EVM)… 15 Proprietary & Confidential Budget    X   % Complete = Earned Value
What are the Benefits of EVM? ,[object Object]
Provides a true picture of a project’s value at any point in time
Ideal method of monitoring project status and likelihood of success16 Proprietary & Confidential
EVM Give us… 17 Proprietary & Confidential Operations Financial Gov Report Compliance Production Factors Predictive Profit/Loss Mitigate Risk Cash Flow Schedule Scope Cost
Driving Trends Affecting EVM Owner Budgets are Being Reduced Credit limitations Less capacity for risk …Leading to Greater Owner Scrutiny of Project Health Are we on track? Have we over-paid? What is the forecast? …Leading to Increased Adoption of EVM In traditional markets: Aerospace, Defense In new markets: Oil & Gas, Mining, Power, Civil, Commercial 18 Proprietary & Confidential
What are the Key Requirements of EVM? Step 1: Define the work 19 Proprietary & Confidential
What are the Key Requirements of EVM? Step 2: Assign budget (planned) values 20 Proprietary & Confidential
What are the Key Requirements of EVM? Step 3: Schedule the work 21 Proprietary & Confidential
What are the Key Requirements of EVM? Step 4: Cost-load the schedule 22 Proprietary & Confidential What does it tell the contractor? What are our expected costs over time What does it tell the owner? What is our expected spend level over time What do you need to track this value?  Estimate / budget Cost-loaded schedule Budgeted Cost of Work Scheduled (BCWS) $1,000,000 Cost $500,000 Time
What are the Key Requirements of EVM? Step 5: Track progress (% complete) 23 Proprietary & Confidential What does it tell the contractor? What should our costs have been based on the work we completed What does it tell the owner? What should our spend level have been based on the work completed What do you need to track this value?  Estimate / budget  Progress history (units completed)                  Budgeted Cost of Work Scheduled (BCWS) Budgeted Cost of Work Performed (BCWP) $1,000,000 Cost $500,000 $450,000 Earned Value Time
What are the Key Requirements of EVM? Step 6: Track actual costs (optional) 24 Proprietary & Confidential Budgeted Cost of Work Scheduled (BCWS) What does it tell the contractor? What have our costs actually been for the work we completed What does it tell the owner? What has our spend level actually been for the work completed What do you need to track this value?  Actual costs from accounting; or  “Accrued” costs Budgeted Cost of Work Performed (BCWP)                Actual Cost of Work Performed (ACWP) $1,000,000 Cost $500,000 $450,000 $400,000 Earned Value Time
Where is EVM trackedby: Owners, PMO’s, CM’s, Contractors Spreadsheets Finance-focused systems ERP Accounting Project-focused systems HD + Primavera HD + MS Project 25 Proprietary & Confidential
System Process Keys 26 Proprietary & Confidential Scope Schedule Cost
Level of Detail in Planning  Specifics during detailed estimating: ,[object Object]
Detail the work into small manageable steps
Rule of thumb:  No activities >1 shift,[object Object]
Based on activity progress
Information to forecast schedule and cost at completion
Evaluate Resource Needs and Deployment1 2 3
Case Study Operations: Audience – Who Owns Tracking ,[object Object]
General Foremen
Project Controls Group
Front-Line Supervisors (Foremen) are excluded  ,[object Object]
Earned Hours from Progress Budget Hours times % Complete = Earned Hours Progress from Field
Case Study: Cost Earned Hours  Progress From Schedule Timesheet Hours From Payroll Actual Hours divided by Earned Hours Billed Cost Discuss Forecast Calculations
Warning: Watch out for these common challenges ,[object Object]

Contenu connexe

Tendances

Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniquesWissem Amara
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsEssam Lotffy, PMP®, CCP®
 
Quality Assurance and Cost Control for Construction
Quality Assurance and Cost Control for ConstructionQuality Assurance and Cost Control for Construction
Quality Assurance and Cost Control for ConstructionRich Purtell
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJTapesh Ajmera
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
Chapter 07 project cost management
Chapter 07 project cost managementChapter 07 project cost management
Chapter 07 project cost managementghizlanejabri
 
Project Management 5 Cost Management
Project Management 5 Cost ManagementProject Management 5 Cost Management
Project Management 5 Cost Managementgrmkslideshare
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systemsLibra chudry
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examManish Purwar
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 

Tendances (20)

Project cost control techniques
Project cost control techniquesProject cost control techniques
Project cost control techniques
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Project cost control
Project cost controlProject cost control
Project cost control
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Quality Assurance and Cost Control for Construction
Quality Assurance and Cost Control for ConstructionQuality Assurance and Cost Control for Construction
Quality Assurance and Cost Control for Construction
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Chapter 07 project cost management
Chapter 07 project cost managementChapter 07 project cost management
Chapter 07 project cost management
 
Project Management 5 Cost Management
Project Management 5 Cost ManagementProject Management 5 Cost Management
Project Management 5 Cost Management
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systems
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Cost management
Cost managementCost management
Cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 

Similaire à Melbourne streamlining earned value with hd published

Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfHuyNguyen657394
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxARIV4
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxstilliegeorgiana
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptxYogesh Singh
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceLewisFowlerLLC
 
L03 integration management
L03 integration managementL03 integration management
L03 integration managementAsa Chan
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
Resource Management Maturity - Does Your Resource Management Practice Work Fo...
Resource Management Maturity - Does Your Resource Management Practice Work Fo...Resource Management Maturity - Does Your Resource Management Practice Work Fo...
Resource Management Maturity - Does Your Resource Management Practice Work Fo...Unanet
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptsheryl90
 
271710575-Lecture-14-Project-Monitoring.ppt
271710575-Lecture-14-Project-Monitoring.ppt271710575-Lecture-14-Project-Monitoring.ppt
271710575-Lecture-14-Project-Monitoring.pptMohd Zulhairi Mohd Noor
 
Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason Uyder
 
The project plan
The project planThe project plan
The project planVatsalaPG
 
Effective Cost Measurement through DMAIC.
Effective Cost Measurement through DMAIC.Effective Cost Measurement through DMAIC.
Effective Cost Measurement through DMAIC.Kaustav Lahiri
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
Intro to Project Management
Intro to Project ManagementIntro to Project Management
Intro to Project ManagementNoman Aftab
 
0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdf0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdfRahulSamadhiya2
 
Introduction To Project Management
Introduction To Project ManagementIntroduction To Project Management
Introduction To Project ManagementTrue Corporation
 

Similaire à Melbourne streamlining earned value with hd published (20)

Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
 
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docxPJM6000Project Management PracticesWeek 5Deb Cote,.docx
PJM6000Project Management PracticesWeek 5Deb Cote,.docx
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance
 
L03 integration management
L03 integration managementL03 integration management
L03 integration management
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
Resource Management Maturity - Does Your Resource Management Practice Work Fo...
Resource Management Maturity - Does Your Resource Management Practice Work Fo...Resource Management Maturity - Does Your Resource Management Practice Work Fo...
Resource Management Maturity - Does Your Resource Management Practice Work Fo...
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
con_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.pptcon_mangt-lec4-project_costppt.ppt
con_mangt-lec4-project_costppt.ppt
 
Session 22 4th edition PMP
Session 22 4th edition PMPSession 22 4th edition PMP
Session 22 4th edition PMP
 
271710575-Lecture-14-Project-Monitoring.ppt
271710575-Lecture-14-Project-Monitoring.ppt271710575-Lecture-14-Project-Monitoring.ppt
271710575-Lecture-14-Project-Monitoring.ppt
 
Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12
 
The project plan
The project planThe project plan
The project plan
 
Chap005
Chap005Chap005
Chap005
 
Effective Cost Measurement through DMAIC.
Effective Cost Measurement through DMAIC.Effective Cost Measurement through DMAIC.
Effective Cost Measurement through DMAIC.
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
Intro to Project Management
Intro to Project ManagementIntro to Project Management
Intro to Project Management
 
0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdf0.Commercial Management slides _Lvl3.pdf
0.Commercial Management slides _Lvl3.pdf
 
Introduction To Project Management
Introduction To Project ManagementIntroduction To Project Management
Introduction To Project Management
 

Plus de InSync Conference

Frank munz oracle fusion middleware and aws cloud services in sync11
Frank munz oracle fusion middleware and aws cloud services in sync11Frank munz oracle fusion middleware and aws cloud services in sync11
Frank munz oracle fusion middleware and aws cloud services in sync11InSync Conference
 
Pythian MySQL - database for the web based economy
Pythian   MySQL - database for the web based economyPythian   MySQL - database for the web based economy
Pythian MySQL - database for the web based economyInSync Conference
 
IBM and Oracle Joint Solution Centre
IBM and Oracle Joint Solution CentreIBM and Oracle Joint Solution Centre
IBM and Oracle Joint Solution CentreInSync Conference
 
In Sync Running Apps On Oracle
In Sync  Running Apps On OracleIn Sync  Running Apps On Oracle
In Sync Running Apps On OracleInSync Conference
 
Oracle Fusion Middleware for JD Edwards
Oracle Fusion Middleware for JD EdwardsOracle Fusion Middleware for JD Edwards
Oracle Fusion Middleware for JD EdwardsInSync Conference
 
In sync10 cliffgodwin-ebs-final
In sync10 cliffgodwin-ebs-finalIn sync10 cliffgodwin-ebs-final
In sync10 cliffgodwin-ebs-finalInSync Conference
 
In sync10 cliffgodwin-appskeynote-final
In sync10 cliffgodwin-appskeynote-finalIn sync10 cliffgodwin-appskeynote-final
In sync10 cliffgodwin-appskeynote-finalInSync Conference
 
Optim Insync10 Paul Griffin presentation
Optim Insync10 Paul Griffin presentationOptim Insync10 Paul Griffin presentation
Optim Insync10 Paul Griffin presentationInSync Conference
 
Nswh Insync 2010 Ammar Customer Presentation
Nswh Insync 2010 Ammar Customer PresentationNswh Insync 2010 Ammar Customer Presentation
Nswh Insync 2010 Ammar Customer PresentationInSync Conference
 
Insync10 IBM JDE Sol Ed Announcement
Insync10 IBM JDE Sol Ed AnnouncementInsync10 IBM JDE Sol Ed Announcement
Insync10 IBM JDE Sol Ed AnnouncementInSync Conference
 
InSync10 Implement JDE Financial Analytics and Make Better Decisions
InSync10  Implement JDE Financial Analytics and Make Better DecisionsInSync10  Implement JDE Financial Analytics and Make Better Decisions
InSync10 Implement JDE Financial Analytics and Make Better DecisionsInSync Conference
 
Ebs operational reporting at santos evaluation, selection & implementation
Ebs operational reporting at santos evaluation, selection & implementationEbs operational reporting at santos evaluation, selection & implementation
Ebs operational reporting at santos evaluation, selection & implementationInSync Conference
 

Plus de InSync Conference (20)

Frank munz oracle fusion middleware and aws cloud services in sync11
Frank munz oracle fusion middleware and aws cloud services in sync11Frank munz oracle fusion middleware and aws cloud services in sync11
Frank munz oracle fusion middleware and aws cloud services in sync11
 
Pythian MySQL - database for the web based economy
Pythian   MySQL - database for the web based economyPythian   MySQL - database for the web based economy
Pythian MySQL - database for the web based economy
 
IBM and Oracle Joint Solution Centre
IBM and Oracle Joint Solution CentreIBM and Oracle Joint Solution Centre
IBM and Oracle Joint Solution Centre
 
In Sync Running Apps On Oracle
In Sync  Running Apps On OracleIn Sync  Running Apps On Oracle
In Sync Running Apps On Oracle
 
P6 r8
P6 r8P6 r8
P6 r8
 
P6 analytics
P6 analyticsP6 analytics
P6 analytics
 
Upk presentation insync
Upk presentation insync Upk presentation insync
Upk presentation insync
 
Oracle Fusion Middleware for JD Edwards
Oracle Fusion Middleware for JD EdwardsOracle Fusion Middleware for JD Edwards
Oracle Fusion Middleware for JD Edwards
 
In sync10 grc_suite
In sync10 grc_suiteIn sync10 grc_suite
In sync10 grc_suite
 
In sync10 cliffgodwin-ebs-final
In sync10 cliffgodwin-ebs-finalIn sync10 cliffgodwin-ebs-final
In sync10 cliffgodwin-ebs-final
 
In sync10 cliffgodwin-appskeynote-final
In sync10 cliffgodwin-appskeynote-finalIn sync10 cliffgodwin-appskeynote-final
In sync10 cliffgodwin-appskeynote-final
 
Mnod linsync10 oba
Mnod linsync10 obaMnod linsync10 oba
Mnod linsync10 oba
 
D linsync10 ofa5yrs
D linsync10 ofa5yrsD linsync10 ofa5yrs
D linsync10 ofa5yrs
 
D linsync10 fusaapps
D linsync10 fusaappsD linsync10 fusaapps
D linsync10 fusaapps
 
Optim Insync10 Paul Griffin presentation
Optim Insync10 Paul Griffin presentationOptim Insync10 Paul Griffin presentation
Optim Insync10 Paul Griffin presentation
 
Nswh Insync 2010 Ammar Customer Presentation
Nswh Insync 2010 Ammar Customer PresentationNswh Insync 2010 Ammar Customer Presentation
Nswh Insync 2010 Ammar Customer Presentation
 
Insync10 IBM JDE Sol Ed Announcement
Insync10 IBM JDE Sol Ed AnnouncementInsync10 IBM JDE Sol Ed Announcement
Insync10 IBM JDE Sol Ed Announcement
 
InSync10 Implement JDE Financial Analytics and Make Better Decisions
InSync10  Implement JDE Financial Analytics and Make Better DecisionsInSync10  Implement JDE Financial Analytics and Make Better Decisions
InSync10 Implement JDE Financial Analytics and Make Better Decisions
 
Life after upgrading to r12
Life after upgrading to r12Life after upgrading to r12
Life after upgrading to r12
 
Ebs operational reporting at santos evaluation, selection & implementation
Ebs operational reporting at santos evaluation, selection & implementationEbs operational reporting at santos evaluation, selection & implementation
Ebs operational reporting at santos evaluation, selection & implementation
 

Melbourne streamlining earned value with hd published

  • 1. Streamlining Earned Value Management Proprietary & Confidential Ron Babich, VP Hard Dollar Ron.babich@harddollar.com 480-776-2934
  • 2. Project COST Management 2 Proprietary & Confidential Design (Materials) Estimating (Budget) Scheduling (Time) Progress (Project Controls) Finance (Accounting)
  • 3. Overview Building the Cost Model Developing EVM Measurements Case Study: Successful Process Readiness
  • 4. Capital Planning Project Variance 4 Proprietary & Confidential Project Plan Costs 15% 50% Costs Plan
  • 5. EVM Requirements Effort Required WBS Period of Time Schedule Progress Performance Measurement Baseline
  • 6. Regulatory Requirements 6 Proprietary & Confidential Regulatory Requirements
  • 7. 7 Proprietary & Confidential Regulatory Requirements
  • 8. Characteristics of Credible Cost Estimates Clear Identification of Task Provision for Program Uncertainties Broad Participation in Preparation Recognition of Inflation Availability of Valid Data Recognition of Excluded Costs Standardized Structure For Estimate Independent Review Of Estimates
  • 9. Budget/Cost Estimate Challenges 9 Proprietary & Confidential Typical Challenges
  • 10. Auditors should… 10 Proprietary & Confidential Cost Element Valid and Applicable Labor Includes Time Phase Break Down Calculations on each element are correct Program is Accurate Total Of Sub-Elements Escalation was applied Over time
  • 11. Case Study - NASA 0 of 10 Projects followed All Basic Steps 3 of 10 Projects included detailed WBS 2 of 10 Measure Cost/Performance Identify Risk
  • 12. Case Study – US Customs $1.05 BilCommercial Environmental Life Cycle No Formal Cost Model Spreadsheet No Structured Documented Process for Determining Size/Reuse Size No Relevant, Measured, Normalized Historical Cost Data to Calibrate Models Measurement
  • 13. What is Earned Value Management? Earned Value Management (EVM)… Project management process that combines schedule performance and cost performance Answers: What did we get for the money we spent? Used since the 1960’s by the Department of Defense Central part of CERT and C/SCSC (Cost/Schedule Control Systems Criteria) Was recently revised and adopted as ANSI/EIA 748 13 Proprietary & Confidential
  • 14. Example: Rail Project 14 Proprietary & Confidential Scope 4 Miles Time 4 Weeks Cost $ 4 Mil Scope 4 Miles Time 4 Weeks Cost $ 4 Mil
  • 15. What is Earned Value Management? The Essence of Earned Value Management (EVM)… 15 Proprietary & Confidential Budget X % Complete = Earned Value
  • 16.
  • 17. Provides a true picture of a project’s value at any point in time
  • 18. Ideal method of monitoring project status and likelihood of success16 Proprietary & Confidential
  • 19. EVM Give us… 17 Proprietary & Confidential Operations Financial Gov Report Compliance Production Factors Predictive Profit/Loss Mitigate Risk Cash Flow Schedule Scope Cost
  • 20. Driving Trends Affecting EVM Owner Budgets are Being Reduced Credit limitations Less capacity for risk …Leading to Greater Owner Scrutiny of Project Health Are we on track? Have we over-paid? What is the forecast? …Leading to Increased Adoption of EVM In traditional markets: Aerospace, Defense In new markets: Oil & Gas, Mining, Power, Civil, Commercial 18 Proprietary & Confidential
  • 21. What are the Key Requirements of EVM? Step 1: Define the work 19 Proprietary & Confidential
  • 22. What are the Key Requirements of EVM? Step 2: Assign budget (planned) values 20 Proprietary & Confidential
  • 23. What are the Key Requirements of EVM? Step 3: Schedule the work 21 Proprietary & Confidential
  • 24. What are the Key Requirements of EVM? Step 4: Cost-load the schedule 22 Proprietary & Confidential What does it tell the contractor? What are our expected costs over time What does it tell the owner? What is our expected spend level over time What do you need to track this value?  Estimate / budget Cost-loaded schedule Budgeted Cost of Work Scheduled (BCWS) $1,000,000 Cost $500,000 Time
  • 25. What are the Key Requirements of EVM? Step 5: Track progress (% complete) 23 Proprietary & Confidential What does it tell the contractor? What should our costs have been based on the work we completed What does it tell the owner? What should our spend level have been based on the work completed What do you need to track this value?  Estimate / budget  Progress history (units completed) Budgeted Cost of Work Scheduled (BCWS) Budgeted Cost of Work Performed (BCWP) $1,000,000 Cost $500,000 $450,000 Earned Value Time
  • 26. What are the Key Requirements of EVM? Step 6: Track actual costs (optional) 24 Proprietary & Confidential Budgeted Cost of Work Scheduled (BCWS) What does it tell the contractor? What have our costs actually been for the work we completed What does it tell the owner? What has our spend level actually been for the work completed What do you need to track this value?  Actual costs from accounting; or  “Accrued” costs Budgeted Cost of Work Performed (BCWP) Actual Cost of Work Performed (ACWP) $1,000,000 Cost $500,000 $450,000 $400,000 Earned Value Time
  • 27. Where is EVM trackedby: Owners, PMO’s, CM’s, Contractors Spreadsheets Finance-focused systems ERP Accounting Project-focused systems HD + Primavera HD + MS Project 25 Proprietary & Confidential
  • 28. System Process Keys 26 Proprietary & Confidential Scope Schedule Cost
  • 29.
  • 30. Detail the work into small manageable steps
  • 31.
  • 32. Based on activity progress
  • 33. Information to forecast schedule and cost at completion
  • 34. Evaluate Resource Needs and Deployment1 2 3
  • 35.
  • 38.
  • 39. Earned Hours from Progress Budget Hours times % Complete = Earned Hours Progress from Field
  • 40.
  • 41. Case Study: Cost Earned Hours Progress From Schedule Timesheet Hours From Payroll Actual Hours divided by Earned Hours Billed Cost Discuss Forecast Calculations
  • 42.
  • 43. Sand bagging of progress
  • 46.
  • 47. When monitoring work in the field, take the current schedule with you to verify
  • 48. If you have a supervisor that struggles with any part of the schedule, get the Project Controls group to help
  • 49.
  • 50. When PF’s are above 1.1 or below .80, go to the field, find out why and communicate that to management and project controls
  • 51. Monitor & Manage Material Movement
  • 53. Monitor & Manage Equipment Utilization
  • 54.
  • 55. Continuous Communication with Management on Schedule Status
  • 56. Make time at least once a day to verify accuracy of current schedule and communicate findings to Project Controls
  • 57.
  • 58. Monitor and Manage Non-Working Times
  • 59. Hold your supervisors accountable for assuring that their progress is accurate
  • 60.
  • 61. What is affected by incorrect Progress?
  • 62. Explain the flow process for calculating Productivity (draw flow on board)
  • 63.
  • 66. Enables the Owner to make sound Business Decisions (Minimize Unit Down Time)
  • 67.
  • 68. Questions? 42 Proprietary & Confidential Thank You! Contact Ron Babich ron.babich@harddollar.com 480-776-2934

Notes de l'éditeur

  1. Drive for Change
  2. Drivers
  3. Ultimately it is your responsibility to assure that the progress that is turned in is as accurate as possibleWhen monitoring work in the field, take the current schedule with you to verifyIf you have a supervisor that struggles with any part of the schedule, get the Project Controls group to helpClearly communicate the expectations to your supervisors