A reminder of the project components
Task A – Preparation of GDMP
• supply-demand scenarios
• identification and ranking of infrastructure projects
• economic benefits of gas
• investment requirements
Task B – Policy notes
• PNs 1-6 – Review of the existing framework
• PNs 7-10 – Recommendations on PSC provisions, incentives for
private investment, price regulation and the balance between
export and domestic consumption of gas
Task C – Training programme
This workshop forms part of Tasks A and C
3
What happens next?
We will now go away and update DASS-TIM with revised
assumptions
We will then use DASS-TIM to model the agreed policy
scenarios, plus other scenarios which illustrate matters of
interest
The results of the modelling will be used to
• complete the analysis under Task A
• inform the next set of Policy Notes (7-10) under Task B
4
Reporting schedule
Draft Technical Report
Draft Task A outputs
18 October 2013
Draft Policy Notes 7-10
(Draft Policy Notes 1-6 submitted with
Interim Report)
18 October 2013
Final Technical Report
Final Task A outputs after comments
15 November 2013
Final Policy Notes
Final Policy Notes 1-10 after comments
15 November 2013
5
Capacity-building and consultation
We expect to hold one or more further meetings during
August and September ahead of the submission of the
Draft Technical Report
These meetings will be used to
• present the results of modelling of the policy scenarios
• discuss our initial conclusions from this analysis
DASS-TIM will be transferred following a final workshop
• update users on any changes to the model since this
workshop
• provide the final assumptions and scenarios used
6
Contact details for the team
Team leader
• David Aron (davidaron@pdc.uk.com)
Modelling team
• Ray Tomkins (ray@eca-uk.com)
• William Derbyshire (william.derbyshire@eca-uk.com)
• Tatiana Tumenggung (tatiana.tumenggung@eca-uk.com)
Local advisor
• David Braithwaite (davidjb@cbn.net.id)
Or you can contact us through the PIU

Contenu connexe

En vedette (9)

Organisational and regulatory david braithwaite (formatted)
Organisational and regulatory   david braithwaite (formatted)Organisational and regulatory   david braithwaite (formatted)
Organisational and regulatory david braithwaite (formatted)
 
Road infrastructure safety in victoria greg chambers
Road infrastructure safety in victoria   greg chambersRoad infrastructure safety in victoria   greg chambers
Road infrastructure safety in victoria greg chambers
 
Roadside hazard management john coles
Roadside hazard management   john colesRoadside hazard management   john coles
Roadside hazard management john coles
 
3 vulnerable road users
3 vulnerable road users3 vulnerable road users
3 vulnerable road users
 
Steering committee draft policy note 3 revised (1)
Steering committee draft policy note 3 revised (1)Steering committee draft policy note 3 revised (1)
Steering committee draft policy note 3 revised (1)
 
Railway safety regulatory function ind ii
Railway safety regulatory function   ind iiRailway safety regulatory function   ind ii
Railway safety regulatory function ind ii
 
2008 pmk-168
 2008 pmk-168 2008 pmk-168
2008 pmk-168
 
2008 pmk-169
 2008 pmk-169 2008 pmk-169
2008 pmk-169
 
Esr 01 & esr-02 closing meeting
Esr 01 & esr-02 closing meetingEsr 01 & esr-02 closing meeting
Esr 01 & esr-02 closing meeting
 

Similaire à Gdmp model workshop 6 - next steps

August 2013 strategic projects monthly review
August 2013   strategic projects monthly reviewAugust 2013   strategic projects monthly review
August 2013 strategic projects monthly review647435
 
A Structured Approach to Estimating Software Intensive Projects - René Berghu...
A Structured Approach to Estimating Software Intensive Projects - René Berghu...A Structured Approach to Estimating Software Intensive Projects - René Berghu...
A Structured Approach to Estimating Software Intensive Projects - René Berghu...Nesma
 
2014_10 Overview Global Product Readiness
2014_10 Overview Global Product Readiness2014_10 Overview Global Product Readiness
2014_10 Overview Global Product ReadinessCatherine Wolf
 
Best practices for reconciling Architecture roadmaps across domains
Best practices for reconciling Architecture roadmaps across domainsBest practices for reconciling Architecture roadmaps across domains
Best practices for reconciling Architecture roadmaps across domainsMohan K.
 
GIS_Office_Project_Management_Framework_Presentation
GIS_Office_Project_Management_Framework_PresentationGIS_Office_Project_Management_Framework_Presentation
GIS_Office_Project_Management_Framework_PresentationBert Bruijn
 
Foundation works norwich - 15th october 2012
Foundation works   norwich - 15th october 2012Foundation works   norwich - 15th october 2012
Foundation works norwich - 15th october 2012carolmcnulty
 
AYESA Presentation - GC East Coast Railway_12th January.pdf
AYESA Presentation - GC East Coast Railway_12th January.pdfAYESA Presentation - GC East Coast Railway_12th January.pdf
AYESA Presentation - GC East Coast Railway_12th January.pdfrinkumandaljis
 
CIL: Project planning and infrastructure with notes
CIL: Project planning and infrastructure with notesCIL: Project planning and infrastructure with notes
CIL: Project planning and infrastructure with notesPAS_Team
 
205360 integration with peoplesoft
205360 integration with peoplesoft205360 integration with peoplesoft
205360 integration with peoplesoftp6academy
 
2017 iii 2_robert_tomas_inspire_miwp
2017 iii 2_robert_tomas_inspire_miwp2017 iii 2_robert_tomas_inspire_miwp
2017 iii 2_robert_tomas_inspire_miwpATTRACTIVE DANUBE
 
SUCCESS STORY: Streamlining the Architectural, Engineering and Professional (...
SUCCESS STORY: Streamlining the Architectural, Engineering and Professional (...SUCCESS STORY: Streamlining the Architectural, Engineering and Professional (...
SUCCESS STORY: Streamlining the Architectural, Engineering and Professional (...GoLeanSixSigma.com
 
Corporate Governance of ICT in the Public Sector
Corporate Governance of ICT in the Public SectorCorporate Governance of ICT in the Public Sector
Corporate Governance of ICT in the Public SectorThe Open Group SA
 
The Exceptions Based Annual Plan – Some Stakes in the Ground
The Exceptions Based Annual Plan – Some Stakes in the GroundThe Exceptions Based Annual Plan – Some Stakes in the Ground
The Exceptions Based Annual Plan – Some Stakes in the GroundSOLGMNZ
 
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdfPlan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdfmhutttch
 
QuEST Forum TL 9000 R6.0 Requirements & ISO 9001:2015
QuEST Forum TL 9000 R6.0 Requirements & ISO 9001:2015QuEST Forum TL 9000 R6.0 Requirements & ISO 9001:2015
QuEST Forum TL 9000 R6.0 Requirements & ISO 9001:2015QuEST Forum
 

Similaire à Gdmp model workshop 6 - next steps (20)

Gdmp model workshop 1 - introduction
Gdmp model workshop   1 - introductionGdmp model workshop   1 - introduction
Gdmp model workshop 1 - introduction
 
Information Management and Model Checking
Information Management and Model CheckingInformation Management and Model Checking
Information Management and Model Checking
 
August 2013 strategic projects monthly review
August 2013   strategic projects monthly reviewAugust 2013   strategic projects monthly review
August 2013 strategic projects monthly review
 
A Structured Approach to Estimating Software Intensive Projects - René Berghu...
A Structured Approach to Estimating Software Intensive Projects - René Berghu...A Structured Approach to Estimating Software Intensive Projects - René Berghu...
A Structured Approach to Estimating Software Intensive Projects - René Berghu...
 
RIBAPlanofWork2013Template
RIBAPlanofWork2013TemplateRIBAPlanofWork2013Template
RIBAPlanofWork2013Template
 
2014_10 Overview Global Product Readiness
2014_10 Overview Global Product Readiness2014_10 Overview Global Product Readiness
2014_10 Overview Global Product Readiness
 
Best practices for reconciling Architecture roadmaps across domains
Best practices for reconciling Architecture roadmaps across domainsBest practices for reconciling Architecture roadmaps across domains
Best practices for reconciling Architecture roadmaps across domains
 
Practical experiences of portfolio management
Practical experiences of portfolio managementPractical experiences of portfolio management
Practical experiences of portfolio management
 
GIS_Office_Project_Management_Framework_Presentation
GIS_Office_Project_Management_Framework_PresentationGIS_Office_Project_Management_Framework_Presentation
GIS_Office_Project_Management_Framework_Presentation
 
Foundation works norwich - 15th october 2012
Foundation works   norwich - 15th october 2012Foundation works   norwich - 15th october 2012
Foundation works norwich - 15th october 2012
 
AYESA Presentation - GC East Coast Railway_12th January.pdf
AYESA Presentation - GC East Coast Railway_12th January.pdfAYESA Presentation - GC East Coast Railway_12th January.pdf
AYESA Presentation - GC East Coast Railway_12th January.pdf
 
CIL: Project planning and infrastructure with notes
CIL: Project planning and infrastructure with notesCIL: Project planning and infrastructure with notes
CIL: Project planning and infrastructure with notes
 
205360 integration with peoplesoft
205360 integration with peoplesoft205360 integration with peoplesoft
205360 integration with peoplesoft
 
2017 iii 2_robert_tomas_inspire_miwp
2017 iii 2_robert_tomas_inspire_miwp2017 iii 2_robert_tomas_inspire_miwp
2017 iii 2_robert_tomas_inspire_miwp
 
SUCCESS STORY: Streamlining the Architectural, Engineering and Professional (...
SUCCESS STORY: Streamlining the Architectural, Engineering and Professional (...SUCCESS STORY: Streamlining the Architectural, Engineering and Professional (...
SUCCESS STORY: Streamlining the Architectural, Engineering and Professional (...
 
Corporate Governance of ICT in the Public Sector
Corporate Governance of ICT in the Public SectorCorporate Governance of ICT in the Public Sector
Corporate Governance of ICT in the Public Sector
 
The Exceptions Based Annual Plan – Some Stakes in the Ground
The Exceptions Based Annual Plan – Some Stakes in the GroundThe Exceptions Based Annual Plan – Some Stakes in the Ground
The Exceptions Based Annual Plan – Some Stakes in the Ground
 
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdfPlan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
Plan Making Reforms Consultation - September 2023 Event Series - Publish.pdf
 
QuEST Forum TL 9000 R6.0 Requirements & ISO 9001:2015
QuEST Forum TL 9000 R6.0 Requirements & ISO 9001:2015QuEST Forum TL 9000 R6.0 Requirements & ISO 9001:2015
QuEST Forum TL 9000 R6.0 Requirements & ISO 9001:2015
 
6 sept project fiche
6 sept project fiche6 sept project fiche
6 sept project fiche
 

Plus de Indonesia Infrastructure Initiative

Indonesian railways revitalisation bambang susantono, vice minister for tra...
Indonesian railways revitalisation   bambang susantono, vice minister for tra...Indonesian railways revitalisation   bambang susantono, vice minister for tra...
Indonesian railways revitalisation bambang susantono, vice minister for tra...Indonesia Infrastructure Initiative
 
Railway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in javaRailway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in javaIndonesia Infrastructure Initiative
 
Development of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiyDevelopment of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiyIndonesia Infrastructure Initiative
 

Plus de Indonesia Infrastructure Initiative (20)

Presentasi Sanitasi INDII
Presentasi Sanitasi INDIIPresentasi Sanitasi INDII
Presentasi Sanitasi INDII
 
Balikpapan Public Diplomacy 25 May 2015
Balikpapan  Public Diplomacy 25 May 2015Balikpapan  Public Diplomacy 25 May 2015
Balikpapan Public Diplomacy 25 May 2015
 
World experience-in-railway-restructuring
World experience-in-railway-restructuringWorld experience-in-railway-restructuring
World experience-in-railway-restructuring
 
Indonesian railways revitalisation bambang susantono, vice minister for tra...
Indonesian railways revitalisation   bambang susantono, vice minister for tra...Indonesian railways revitalisation   bambang susantono, vice minister for tra...
Indonesian railways revitalisation bambang susantono, vice minister for tra...
 
WS2 Infrastructure Issues
WS2 Infrastructure IssuesWS2 Infrastructure Issues
WS2 Infrastructure Issues
 
Development of multimodal transport in north java corridor
Development of multimodal transport in north java corridorDevelopment of multimodal transport in north java corridor
Development of multimodal transport in north java corridor
 
Railway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in javaRailway function in developing multimodal transportation in java
Railway function in developing multimodal transportation in java
 
The role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in javaThe role of ipc in developing multimodal transportation in java
The role of ipc in developing multimodal transportation in java
 
Government strategy in developing multimodal transportation
Government strategy in developing multimodal transportationGovernment strategy in developing multimodal transportation
Government strategy in developing multimodal transportation
 
The role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportationThe role of ferry in developing multimodal transportation
The role of ferry in developing multimodal transportation
 
Development of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiyDevelopment of multimodal transportation and inter regional connectivitiy
Development of multimodal transportation and inter regional connectivitiy
 
Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)Ws3 safe system approach (bahasa version)
Ws3 safe system approach (bahasa version)
 
Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)Ws3 safe system supporting vru (english version)
Ws3 safe system supporting vru (english version)
 
Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)Ws3 safe system supporting vru (bahasa version)
Ws3 safe system supporting vru (bahasa version)
 
Ws3 presentation
Ws3 presentationWs3 presentation
Ws3 presentation
 
Ws3 me
Ws3 meWs3 me
Ws3 me
 
Ws3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safetyWs3 infrastructure related to pedestrian safety
Ws3 infrastructure related to pedestrian safety
 
Ws3 gender and disability presentation
Ws3 gender and disability presentationWs3 gender and disability presentation
Ws3 gender and disability presentation
 
Ws2 introduction
Ws2 introductionWs2 introduction
Ws2 introduction
 
Workshop #2 safe system approach
Workshop #2 safe system approachWorkshop #2 safe system approach
Workshop #2 safe system approach
 

Dernier

Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsMiki Katsuragi
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningLars Bell
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo DayH2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo DaySri Ambati
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostZilliz
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 

Dernier (20)

Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering Tips
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine Tuning
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo DayH2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
H2O.ai CEO/Founder: Sri Ambati Keynote at Wells Fargo Day
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 

Gdmp model workshop 6 - next steps

  • 1. Gas Development Master Plan Next Steps Capacity Building Workshop Bali, 1-2 July 2013
  • 2. 2 A reminder of the project components Task A – Preparation of GDMP • supply-demand scenarios • identification and ranking of infrastructure projects • economic benefits of gas • investment requirements Task B – Policy notes • PNs 1-6 – Review of the existing framework • PNs 7-10 – Recommendations on PSC provisions, incentives for private investment, price regulation and the balance between export and domestic consumption of gas Task C – Training programme This workshop forms part of Tasks A and C
  • 3. 3 What happens next? We will now go away and update DASS-TIM with revised assumptions We will then use DASS-TIM to model the agreed policy scenarios, plus other scenarios which illustrate matters of interest The results of the modelling will be used to • complete the analysis under Task A • inform the next set of Policy Notes (7-10) under Task B
  • 4. 4 Reporting schedule Draft Technical Report Draft Task A outputs 18 October 2013 Draft Policy Notes 7-10 (Draft Policy Notes 1-6 submitted with Interim Report) 18 October 2013 Final Technical Report Final Task A outputs after comments 15 November 2013 Final Policy Notes Final Policy Notes 1-10 after comments 15 November 2013
  • 5. 5 Capacity-building and consultation We expect to hold one or more further meetings during August and September ahead of the submission of the Draft Technical Report These meetings will be used to • present the results of modelling of the policy scenarios • discuss our initial conclusions from this analysis DASS-TIM will be transferred following a final workshop • update users on any changes to the model since this workshop • provide the final assumptions and scenarios used
  • 6. 6 Contact details for the team Team leader • David Aron (davidaron@pdc.uk.com) Modelling team • Ray Tomkins (ray@eca-uk.com) • William Derbyshire (william.derbyshire@eca-uk.com) • Tatiana Tumenggung (tatiana.tumenggung@eca-uk.com) Local advisor • David Braithwaite (davidjb@cbn.net.id) Or you can contact us through the PIU