Objectives
• Developing a long-term strategy for the future
development of Indonesia’s gas market (for up to 50
years)
• Identifying key transportation infrastructure required for
the gas market in the medium to long-term (20-25 years)
• Defining policy measures required to implement the
strategy
• Building the capacity for continual development and
improvement of the long-term strategy
while recognising the huge uncertainties around future
Indonesian and international energy markets
3. 3
Three inter-linked tasks
TASK A
GDMP Model
TASK B
Policy issues
TASK C
Capacity-building
Optimal uses of gas in the
long to very long-term
Medium-term infrastructure
development plan
Barriers to increasing gas
production
Promoting the domestic
gas market
Using the GDMP Model for
planning
Revising the regulatory
framework
4. 4
Task A components
• Task A1 Benchmarking - completed
• Task A2 Market Conditions – in progress
• Task A3 Demand Scenarios – in progress
• Task A4 Supply Situation – completed
• Task A5 Supply and Demand – in progress
• Task A6 Gas Infrastructure – data availability issues
• Task A7 Load Management - data availability issues
• Task A8 Gas Economic Benefits - later
• Task A9 Development of Uneconomic Fields – in progress
• Task A10 Economic Ranking - later
• Task A11 Investment and Financing - later
• Task A12 Manpower Requirements - later
5. 5
Task A activities
Scenarios
Task A5
GDMP
Model
Demand
Task A3
Market
Issues
Tasks A1 / A2
Supply
Task A4
Infrastructure
Options
Tasks A6 / A7
Economic
Ranking
Task A10
Infrastructure
Plan
Tasks A11 / A12
Gas Economic
Benefits
Task A8
Optimal Uses
of Gas
6. 6
Task B policy notes
B1 – Overview of gas resources and
development potential
B2 – Impediments to developing
resources
B7 – Review of PSC provisions
B4 – Policy support for developing
domestic gas markets
B5 – Framework for gas infrastructure
development
B6 – Permitting and approvals
processes
B8 – Regulation of consumer gas
prices
B9 – Private investment in gas
infrastructure
B3 – Identification of policy gaps and
recommendations for policy action
B10 – Gas export scenarios
Increasing gas production
Developing the domestic gas market
Improving the policy framework
As inputs to GDMP Model Using outputs from GDMP Model
7. 7
Deliverables
• Consensus-Building Workshop – June 2012
• Inception Report – August 2012
– issues and scope of work
• Interim Report – March 2013
– progress update on Task A / drafts of B1 to B6
• Draft Final Report – to be determined
– draft strategy and infrastructure plan / drafts of B7 to B9
• Final Report – to be determined
– revised strategy and infrastructure plan / draft of B10
• Final Policy Notes – to be determined
– revised B1 to B10
• Training Programme
– two-day GDMP Model Scenarios workshop proposed for May 2013
– other model training workshops to be arranged at a later date