SlideShare une entreprise Scribd logo
1  sur  49
CONTRACT and
ARBITRATION
Jit Kumar Gupta
Chandigarh
CONTRACT
 Most construction carried through contract system-agreement
between owner and construction agency
 Construction a complex process involving both parties
 Owner’s team- architect, engineer and consultant
 both parties must pull in same direction & with same speed to
successfully complete project
 Word- Contract- drawn from latin word- contractor- drawing
together
 Contract-An agreement enforceable by law is a contract- Indian
Contract Act, 1872
 Contract—an agreement between two or more persons
 --intended to be enforceable by law
 --constituted by making offer by one and
 - Acceptance by other
OBJECT OF CONTRACT
 To complete work given to construction company :
 --without any complication
 - within specified time
 -- within specified cost
 -conforming to specified quality
 --without loss of harmony between key participants
------------------------------------------
 Completion of work
 Completion of work within time
 Completion of work within time and cost
 Completion of work within time and cost conforming to quality
 Completion of work within time and cost conforming to quality and without
sacrificing harmony
 -------------------------------------
 Owner desires– Best value for money spent
 Contractor wants – Maximum rate of return on investment
 Common objective–Completion of Work
PRE- REQUISITE OF VALID CONTRACT
 i.There must be two parties one making offer and other
accepting offer
 Ii. Agreement between contacting parties to terms& conditions
of contract
 iiiGenuine intention of parties to accept/fulfill their rights and
duties
 Iv Legal capacity of parties to make contract
 v Consideration of some value exchanged
 Vi Agreement enforceable by law--Agreement not enforceable
is a void contract
 Vii Agreement enforceable at option of one or more parties
but not enforceable at the options of other- void
 Viii Both parties must be major
 Ix Parties must be of sound mind
TYPES OF CONTRACTS
Types of contracts–
i. Based on purpose- full contract, labour
contract,/transport contracts/procurement
contracts /Turnkey contracts /consultancy/
Erection contracts
ii. Based on Economic conditions– lump sum
/cost+fee /item rate/ turnkey/ BOOT/ labour/
demolition/ day work
TYPES OF CONTRACTS
1 Measurement Contracts(Item rate & %age
contracts)
 2 Lump Sum Contracts
 3 Cost plus Fee Contracts
 4 Turnkey Contracts
 5 BOOT Contracts
 6 Labour Contracts
 7 Demolition Contracts
 8 Other Works
 9 Day Works
 10. Consultancy Contracts
TYPES OF CONTRACTS
1 Measurement Contracts
--Item rate –for large works- owner quotes quantity and
unit, Tenderer- Rate for each item- payment based on actual
measuremnt
-- % age contracts- for small/ repetitive/ repair/
maintenance works-owners gives, items, rate, quantities,
amount- Contractor –quotes-- % above, below, at par-
payment based on actual measurement
 2 Lump Sum Contracts-when cost of entire work
quoted based on scope of work, planning, designing, working
drawings all drawings, specifications frozen before inviting
tender—
 -- owners knows total cost of work in beginning,
 -- no change in scope can be made,
TYPES OF CONTRACTS
 3 Cost plus Fee Contracts- adopted for
emergency/miscellaneous/undefined scope of works–
 Contractor paid– actual cost+ fixed fee+ incentive
 - contractor risk minimum-owner cost uncertain- adopted in
government/private sector work
 4 Turnkey Contracts—
 contractor responsibility for defined scope of work--planning,
designing ,construction, commissioning
 - paid fixed lump sum amount
 - Risk for the contractor-- weather/ site/foundation/ unforeseen
problems
 -suitable for projects where all functional parameters are
defined
 - thermal plant- commercial/ defense /interior projects
 -eliminates co-ordination problems
TYPES OF CONTRACTS
 5 BOOT Contracts- Build, own, operate, Transfer
contracts
 —encouraging private sector-to fund- build- own-
operate
 --collect toll, for a fixed time and then hand back
projects to authority
 – suitable for highways, airports, power plant, waters
supply, bridges etc
 - govt. acts as facilitator- legal issues, land
acquisition,, enforcement
 - Government may also join – in a separate holding
company
 DFBOOT- Designing, financing, build, own, operate,
transfer
TYPES OF CONTRACTS
 6 Labour Contracts-
 -owner supplies all materials
 - contractor- labour/ equipment/plant/machinery
 - responsible for execution work
 - may lead to misuse/waste of material
 - popular for quality of material/construction
 - problems related to escalation of cost of material donot impact
project
 —need effective supervision for;
 -- quality
 --wastage
 --workmanship
 -suitable for all types of work
 - new/addition/alteration/repair etc
TYPES OF CONTRACTS
 7 Demolition Contracts-
 -involves demolition of existing building/removal of debris
 - contractor removes/salvage/ pay for material to owner
 - highest bidder given contract
 -entire bid money deposited by contractor
 - to forfeit incase of default/ non-compliance/non-removal of
debris,
 Contractor – take insurance of worker, compensate them for
accidents
 contract to define scope of work- part/whole demolition
 -incase of part- to make good any loss to remaining building
 - item to be retained by owner to be specified
 -Earnest money refunded to contractor after the work
TYPES OF CONTRACTS
 8 Other Works-
 -- splitting
 --large repetitive works
 --into smaller parts
 --- allotted through tendering
 --- canals/metros railway/road work/electrical/water
supply etc-
TYPES OF CONTRACTS
 9 Day Works
 -for specialized works of small nature
 - which cannot be measured in value terms
 -decorative/craft/artwork etc
 -payment include material cost+ hire
 - charges for machinery + labour charges +profit
 --- no security/tendering
 - clark of work to report to architect/engineer for
progress
 - wages paid to conform Government guidelines
 - uncertainty in cost
 - difficulty in measurement
TYPES OF CONTRACTS
 10. Consultancy Contracts-
 --Hiring of consultants for specialized projects
 -- paid on job basis/ lump sum basis/ call basis/
retainer ship basis
 -- depending on situation/ other factors
 Consultants selected on
 --Quality base selection- for specialised projects-
master plans/ finance
 --Best Expert Advise—Feasibility/structural
engineering/major projects-dam
 -- Selection under Fixed Budget– for simple/precisely
defined projects
Selection of
Contractors
SELECTION OF CONTRACTORS
 Selection of contractor- most important part of
contract management
 Critical Factors of construction depend on
selection of a suitable contractor to ensure—
 - Quality
 -- Speed
 --Economy
 -- Harmony
 - Selection of Contractor to be based on
principles of--equity and fair play
SELECTION OF CONTRACTOR
 Contractor is selected by owner by any of the
following process after negotiations, when
needed
 1. Public Tender
2. Pre- Qualification
 3. Post- Qualification
 4. Limited Tenders
 5. Single Tenders
 6. Nomination
SELECTION OF CONTRACTOR- PUBLIC TENDER
Tender– or quotation is a:
-- written offer
-- to execute a work or
-- supply of materials required
-- for construction of a facility
-- within a stipulated time
-- under specified conditions of tender/quotation
Public Tender
 For Government works
 - public tenders invited from registered contractors of appropriate
class
 - Tender notice explains
 -- conditions
 - work experience,
 financial solvency,
 annual turnover,
 registration as contractor.
PRE-QUALIFICATION OF CONTRACTORS
Contractors are pre-qualified to ensure:
--competition is among capable and qualified bidders
-- Selection of best contractor
- Elimination of incompetent/ insincere contractors
 Pre- qualification of contractor is based on—
 - work experience,
 - financial solvency,
 -- annual turnover, .
 - quality of work executed
 --Organisational structure
 --Board of Directors
 --Plant and Machinery available
 - Manpower available - technical/non-technical
 --General reputation
DELHI GOVERNMENT- REGISTRATION OF
CONTRACTORS
Tender documents is issued only to
those contractors, who are registered
in the
-- I&FC Deptt. ( Irrigation and Flood
control Deptt)
-- CPWD,
--PWD (NCT of Delhi),
--MES
-- duly got verified by I&FC Deptt.
DELHI GOVERNMENT- REGISTRATION OF
CONTRACTORS

 Contractors enlisted in various classes
are entitled to submit their tenders, as per
financial limits of estimated cost shown
below:
 Class I - upto Rs. 20.00 Crore
 Class II - upto Rs. 5.00 Crore
 Class III - upto Rs. 150.00 lac
 Class IV - upto Rs. 60.00 lac
ENLISTMENT PROCEDURE:
 Contractor to submit application in a prescribed form
complete with all documents
 Reports submitted verified / works done by contractor
inspected and/or to get such other reports as may be
considered necessary.
 If contractor found suitable for enlistment-- enlistment
order issued—otherwise rejection letter sent of to
contractor
 -- decision of enlistment authority final and binding on
contractor.
-- authority reserves right to limit number of contractor to be
enlisted in any class .
 Enlistment of contractors may be closed at any point of
time.
 While closing department may have a reserved list of eligible
contractors from pending applications.
 Out of this-- contractors enlisted depending on requirement
in a particular area/ NCT as a whole.
PERIOD OF ENLISTMENT
 Enlistment valid for a period of four years.
 Enlistment can, be revalidated .
 Each revalidation shall be for a period of three
years
 Enlistment shall be open to:
 -- review by the enlistment authority
 -- liable to termination,
 -- suspension
 - demotion to a lower class
 -- any other such action
 -- at any time if considered necessary
 -- by the enlistment authority,
 -- after issue of show cause notice
ARBITRATION
ARBITRATION
 Disputes are part of human living
 In ancient times disputes referred to Village
Panchayats for speedy settlements
 During British Rule, Arbitration was encouraged
 Arbitration Act, 1899 was the first Act
 Replaced by Arbitration Act, 1940 as full code
 The Arbitration and Reconciliation Act, 1996
based on the UN Model Act was passed in 1996
 Act provides for-
 Domestic Arbitration
 International commercial and
 Enforcement of foreign Arbitral awards
MODES OF SETTLEMENT OF DISPUTES
 1. Capitulation- weaker party give in -to retain
goodwill/ long term business relationship with stronger
party
 2. Negotiation--Both parties sink differences and try
to reach amicable settlement
 3. Arbitration- Disinterested/impartial third party
appointed to adjudicate
 4. Litigation- Disputes taken to court resulting in
abnormal delay and heavy expenditure
 5. Dispute Resolution Board- Board constituted on
award of contract to resolve disputes as and when
they arise
ARBITRATION
 --Settlement of a dispute (whether of fact, law, or
procedure)
 between parties to a contract
 -- by a neutral third party (the arbitrator)
 -- without resorting to court action.
 -- Arbitration is usually voluntary but
 -- sometimes it is required by law.
 -- If both sides agree to be bound by arbitrator's decision
 'award‘ becomes a binding arbitration.
 Exact procedure to be followed (if not included in the
contract under dispute)
 - governed usually by a country's arbitration laws, or
 --by arbitration rules prescribed by International
Chamber Of Commerce (ICC)
ARBITRATION
 Arbitration most popular mode of settling
disputes in building and construction disputes
 Most construction projects provide for
arbitration
 Helps in imparting justice in a:
 -- speedier and
 -- cost-effective manner
 Determining of disputes by the decision of one
or more – persons known as Arbitrator
 Every dispute – which can be settled by a civil
court can be settled under Arbitration
ARBITRATION- OBJECTIVES
 Make provision for arbitral procedure which is:
 -- fair,
 -- efficient
 -- capable of meeting needs of specific arbitration
 To Minimise supervisory role of Courts
 Arbitral tribunal to give reasons for the award
 To ensure Arbitral tribunal remains within its jurisdiction
 Permit Arbitral tribunal to use:
 -- mediation,
 -- conciliation or
 -- other procedures to settle disputes
 To make decisions of Tribunal enforceable as a degree
of court
DEFINITIONS
 Arbitrator- A person appointed to settle disputes
 Arbitration Agreement- A written agreement
between client and contractor to settle future
disputes
 Order of reference– Order containing names of
the arbitrator, specific dispute, nature, time limit
for award
 Presiding arbitrator-An umpire when each
party’s arbitrator or both parties arbitrator
choose one presiding arbitrator
 Award– Written decision of the arbitrator on
completion of the proceedings
ARBITRATION VS LITIGATION
 Advantage of Arbitration over litigation:
 More Speed
 Less Expensive
 More Privacy
 Informal Proceedings
 Expertise of the Arbitrators in the field
 Flexibility in choice of meeting place and
location
 finality of decision
 Continued good relations between parties-
owners and client
PROCEDURE FOR ARBITRATION
 Specific clause to be introduced in contract-
settling disputes by arbitration
 Aggrieved party to approach the designated
authority to appoint arbitrator with list of
all/selected disputes and amount involved for
each dispute-
 Arbitrator is then appointed with list and -- referred
with the papers submitted
 Few contracts provide for direct resolution of
disputes by parties- failure to do so can lead to
appointment of an Arbitrator
 Arbitration conducted under the provisions of
Arbitration and Conciliation Act, 1996
 Parties are to be treated on equality and given
full opportunity to present their case
PROCEDURE FOR ARBITRATION
 Parties are free to agree on the procedure for
Arbitral Tribunal
 Parties free to agree on the place and language for
arbitration
 Arbitration proceedings start from the date of
receipt of request for arbitration
 Claimant to state facts supporting the claim, issues
involved and remedy sought
 Respondent to give defence against these claims
 Tribunal to decide on oral/documentary evidence
 Experts appointed by Tribunal in case of specific
technical issues
 Assistance of court may be sought for taking
evidence
PROCEDURE FOR ARBITRATION
 Decision of the Tribunal to be by majority- being
in odd numbers
 Award to be in writing and signed by all
members
 It is to be reasoned award unless otherwise
agreed to by parties
 Award amount, if not paid, to carry interest
@18% per annum from date of award to date of
payment
 Award to be final and binding
 Enforced as – decree of the Civil Court
CHARACTERISTICS OF GOOD AWARD
 Sticking to the scope of defined issues
 Stick to time limit
 Unambiguous, unconditional, complete and
clear decision
 Judgment and decision that of the Arbitrator
only and no one else
 Complete application of mind of Arbitrator’s
VALUATION
VALUATION
 Valuation was introduced due to
 -- Land Acquisition Act – for assessing value of land on
market value
 -- for levying property tax by municipalities based on
ratable value of property
 -- for buying/selling property
 -- Valuation necessity till property lives as a concept
 Valuation is a process by which value of an asset is
estimated
 - It is not an exact science with mathematical accuracy
 -It is an expert opinion – supported by relevant fact and
information impacting value of asset
 Duty of the valuer to avoid undervaluing/ over-valuing
property
VALUATION
 It is a guess based on certain objective factors
 -Valuation depends upon–
 -- location,
 -- quality of construction,
 -- life of building
 - current status of building
 -- type/nature of buildings- temporary/ permanent
 -- prevailing cost of land
 -- Cost of construction- plinth area rates
 -demand and supply
 - Purpose of valuation
 -cost indices
- --Available data
- —sound judgment, experience
- It is multi-disciplinary work involving knowledge of—Architecture,
engineering, mathematics, land, geography, materials etc
VALUE
 Value represent—
 -- worth, utility, attachment to a thing in the eyes of a
person
 - For a thing to have value it must possess
 - economic & Legal qualities--- utility, demand, scarcity,,
transferability of ownership
 --Value differs from person to person
 - hence different persons value differently same property
 -- Value is a relative concept
 - valuation is a function of:
 -- place,
 --purpose and
 -- time
METHOD OF VALUATION
1. Land and Building Method
2. Composite Rate Method
3. Development Potential Method
4. Rent Capitalization Method
5. Profit Capitalization Method
6. Cost Approach Method
LAND AND BUILDING METHOD
Land and Building Method involves a sum of ;
-- Fair Market Value of Land + Depreciated value of
building
- Depreciated value of building is worked out on the
basis of plinth area, plinth area rate of building
based on CPWD/PWD for the area based on cost
index, age of building, estimated total life of
building, savage value-
- Value of building= Value of building component+
services+ market value of land
- Valuation used for –
- --Residential/
- --self-occupied properties and
- -- certify the present worth of property
2. COMPOSITE RATE METHOD
 Method used for assessing value of Residential
apartment and commercial complexes
 Comprises of = Rate per unit area of building+
proportionate share of land
 Land component decided on- location, land
values, amenities provided by developer,
specification of land
 Building component depends on- cost of
construction, age, specification, finishes,
structure, materials, location, accessibility, quality
etc
 In case of old apartments- depreciated value is
worked out for the building
3 DEVELOPMENT POTENTIAL METHOD
 Based on the potential of land for immediate
future development- fair market value
 Used for assessing value of vacant
undeveloped/under-developed land parcels on
outskirts of city and for land within the city
based on the existing local bye-laws
 Used by developers for investment into land
and carving out smaller plots for sale
 Applied when demand for small plots exist and
land is sufficient to take up real estate
development involving residential/commercial
development with minimal cost
4 RENT CAPITALISATION METHOD
 Method used for valuation of rented properties, properties
under Rent Control Act
 Method considers- tenant right( not legally saleable) and
owners right to receive rent.
 This method has- Net Maintainable Rent- NMR for landlord
which is worked out by deducting outgoings from the Gross
Maintainable Rent- GMR
 - Net rent capitalised and depreciation is ignored
 Essentials for this valuation are–
 -- Gross rent,
 -- outgoing,
 --Capital employed,
 -- rate of return ,
 -- life of building,
 --unused portion of asset for future use,
 -- money required for repair
5 PROFIT CAPITALIZATION METHOD
 Used for single commercial properties like-
cinema, hotel, marriage halls etc
 Net profit is capitalised
 Based on Gross profit minus outgoings
 Method sensitive to market variations
 Method approximate- applied in the absence
of data by other methods
 Net profit obtained- helps to assess value of
property along with rate of return
 Net profit- average of last 3-5 years taken
 Part of profit is goodwill taken from the tenets
6. COST APPROACH METHOD
 Applied primarily to service properties-
which are
 -- not frequently exchanged in market
 -- donot generate revenue by themselves
 Useful on new or special purpose
properties
 -Logic is that prudent investor:
 -- should not pay more for property
 -- than cost of producing a substitute
property with the same utility
VALUATION PROCESS INBRIEF
 Appointment of valuer detailing property, purpose
and scale of fee charged
 Ascertain the purpose of valuation
 Visit the site of valuation
 Document the site with maps and photographs
 Study relevant Act, practices, approach to
valuation to suit the purpose
 Follow the set procedure to determine its value
 Where necessary check by other methods and
observe difference
 Based on experience/ wisdom form an opinion of
the realistic value of asset by appropriate method
PRECAUTIONS TO BE TAKEN WHILE VALUATION
 Ascertain all possible facts
 Identify the property
 Donot inflate the value
 Donot understate the value
 Donot value illegal properties
 Donot delegate valuation to incompetent colleague/assisttant
 Apply appropriate method of valuation
 Donot rely entirely on legal opinion
 Do not rely entirely on previous valuation report
 Take all possible precaution
 Remain objective- minimize subjectivity
 Donot yield to any pressure of offer
 Use all available legal documents- building plans, occupation
certificate, completion certificate etc
Thanks

Contenu connexe

Tendances

Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
jagadish108
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
guestdb5e498
 
Architecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationArchitecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliation
Aditi Garg
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 

Tendances (20)

Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Valuation part of Building
Valuation part of Building Valuation part of Building
Valuation part of Building
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Valuation in Civil Engineering
Valuation in Civil EngineeringValuation in Civil Engineering
Valuation in Civil Engineering
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Tender
TenderTender
Tender
 
Valuation
ValuationValuation
Valuation
 
Architecture Professional practice
Architecture Professional  practice Architecture Professional  practice
Architecture Professional practice
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Architecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationArchitecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliation
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Job layout per
Job layout perJob layout per
Job layout per
 
Contracts
ContractsContracts
Contracts
 
Valuation - professional prractice and valuation
Valuation - professional prractice and valuationValuation - professional prractice and valuation
Valuation - professional prractice and valuation
 
Arbitration Of Construction Disputes
Arbitration Of Construction DisputesArbitration Of Construction Disputes
Arbitration Of Construction Disputes
 

Similaire à Contract and Arbitration

Similaire à Contract and Arbitration (20)

Mode of Tendering.pptx
 Mode of Tendering.pptx Mode of Tendering.pptx
Mode of Tendering.pptx
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tender
 
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Unit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & ByelawsUnit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & Byelaws
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
Tendering in the domain of construction industry
Tendering  in the domain of construction industryTendering  in the domain of construction industry
Tendering in the domain of construction industry
 
Tendering presenation
Tendering presenationTendering presenation
Tendering presenation
 
tendering
 tendering tendering
tendering
 
Contract closing ppt
Contract closing pptContract closing ppt
Contract closing ppt
 
Contracts & tenders
Contracts & tendersContracts & tenders
Contracts & tenders
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
contracts-unit 3.ppt
contracts-unit 3.pptcontracts-unit 3.ppt
contracts-unit 3.ppt
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
Arbitration Dispute Cross Arguments: Asia NGPipeline -Substance of EPC contra...
 
Construction practices
Construction practicesConstruction practices
Construction practices
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their types
 

Plus de JIT KUMAR GUPTA

Planning and Designing Green buildings-.issues, options and strategies
Planning and Designing Green buildings-.issues, options and strategiesPlanning and Designing Green buildings-.issues, options and strategies
Planning and Designing Green buildings-.issues, options and strategies
JIT KUMAR GUPTA
 
_Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy...
_Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy..._Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy...
_Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy...
JIT KUMAR GUPTA
 
Rationalizing the Planned Growth of Urban India- paper.docx
Rationalizing the Planned Growth of Urban India- paper.docxRationalizing the Planned Growth of Urban India- paper.docx
Rationalizing the Planned Growth of Urban India- paper.docx
JIT KUMAR GUPTA
 
Suggestion and Options for integrating villages. within the framework of the...
Suggestion and Options for  integrating villages. within the framework of the...Suggestion and Options for  integrating villages. within the framework of the...
Suggestion and Options for integrating villages. within the framework of the...
JIT KUMAR GUPTA
 
Making cities Climate Responsive and Sustainable
Making cities Climate Responsive and SustainableMaking cities Climate Responsive and Sustainable
Making cities Climate Responsive and Sustainable
JIT KUMAR GUPTA
 
-Redefining and Rationalising Development Controls - Copy.docx
-Redefining and Rationalising  Development Controls - Copy.docx-Redefining and Rationalising  Development Controls - Copy.docx
-Redefining and Rationalising Development Controls - Copy.docx
JIT KUMAR GUPTA
 

Plus de JIT KUMAR GUPTA (20)

COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Making Buildings cost-effective , Energy Efficient ptx
Making Buildings cost-effective , Energy Efficient  ptxMaking Buildings cost-effective , Energy Efficient  ptx
Making Buildings cost-effective , Energy Efficient ptx
 
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING  SYSTEMS- IGBC, GRIHA, LEED--.pptxRATING  SYSTEMS- IGBC, GRIHA, LEED--.pptx
RATING SYSTEMS- IGBC, GRIHA, LEED--.pptx
 
Factors Causing Urban Heat Island- 14.4,24.docx
Factors Causing Urban Heat Island- 14.4,24.docxFactors Causing Urban Heat Island- 14.4,24.docx
Factors Causing Urban Heat Island- 14.4,24.docx
 
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.pptMaking and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
Making and Unmaking of Chandigarh - A City of Two Plans2-4-24.ppt
 
Planning and Designing Green buildings-.issues, options and strategies
Planning and Designing Green buildings-.issues, options and strategiesPlanning and Designing Green buildings-.issues, options and strategies
Planning and Designing Green buildings-.issues, options and strategies
 
_Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy...
_Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy..._Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy...
_Neighborhood Planning in Capital City of Chandigarh- An Appraisal (2) - Copy...
 
Reviewing, Revising and Redefining Master Plans and Development Plans to Ma...
Reviewing, Revising and  Redefining Master Plans and Development Plans to  Ma...Reviewing, Revising and  Redefining Master Plans and Development Plans to  Ma...
Reviewing, Revising and Redefining Master Plans and Development Plans to Ma...
 
Rationalizing the Planned Growth of Urban India- paper.docx
Rationalizing the Planned Growth of Urban India- paper.docxRationalizing the Planned Growth of Urban India- paper.docx
Rationalizing the Planned Growth of Urban India- paper.docx
 
Suggestion and Options for integrating villages. within the framework of the...
Suggestion and Options for  integrating villages. within the framework of the...Suggestion and Options for  integrating villages. within the framework of the...
Suggestion and Options for integrating villages. within the framework of the...
 
Making cities Climate Responsive and Sustainable
Making cities Climate Responsive and SustainableMaking cities Climate Responsive and Sustainable
Making cities Climate Responsive and Sustainable
 
Managing Planning and Development of Citie- 26-2-24.docx
Managing Planning and  Development of  Citie-  26-2-24.docxManaging Planning and  Development of  Citie-  26-2-24.docx
Managing Planning and Development of Citie- 26-2-24.docx
 
Agenda, Approach and Options for Rationalising and Redefining Future Indian ...
Agenda, Approach and Options for Rationalising and Redefining Future  Indian ...Agenda, Approach and Options for Rationalising and Redefining Future  Indian ...
Agenda, Approach and Options for Rationalising and Redefining Future Indian ...
 
-Redefining and Rationalising Development Controls - Copy.docx
-Redefining and Rationalising  Development Controls - Copy.docx-Redefining and Rationalising  Development Controls - Copy.docx
-Redefining and Rationalising Development Controls - Copy.docx
 
Redefining and Rationalising Development Controls -Issues and Options
Redefining and Rationalising Development Controls -Issues and OptionsRedefining and Rationalising Development Controls -Issues and Options
Redefining and Rationalising Development Controls -Issues and Options
 
Book on-Identifying, Analysing and Planning sites for Architectural Projects
Book on-Identifying, Analysing and Planning sites for Architectural ProjectsBook on-Identifying, Analysing and Planning sites for Architectural Projects
Book on-Identifying, Analysing and Planning sites for Architectural Projects
 
7 Leveraging Tourism for Promoting Sustainable Development of Hill States.pdf
7 Leveraging  Tourism for Promoting Sustainable Development of Hill States.pdf7 Leveraging  Tourism for Promoting Sustainable Development of Hill States.pdf
7 Leveraging Tourism for Promoting Sustainable Development of Hill States.pdf
 
Strategies and Options For Making India Zero Waste Water-26-2-24.pptx
Strategies and Options For Making India Zero Waste Water-26-2-24.pptxStrategies and Options For Making India Zero Waste Water-26-2-24.pptx
Strategies and Options For Making India Zero Waste Water-26-2-24.pptx
 
SECMOL School In Leh- A Role Model of Vernacular , Passive and Sustainable H...
SECMOL School In Leh- A  Role Model of Vernacular , Passive and Sustainable H...SECMOL School In Leh- A  Role Model of Vernacular , Passive and Sustainable H...
SECMOL School In Leh- A Role Model of Vernacular , Passive and Sustainable H...
 
Hill Area development- Issues and Options
Hill Area development- Issues and OptionsHill Area development- Issues and Options
Hill Area development- Issues and Options
 

Dernier

一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
e9733fc35af6
 
一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理
Airst S
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
Airst S
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
Airst S
 
一比一原版(Essex毕业证书)埃塞克斯大学毕业证学位证书
一比一原版(Essex毕业证书)埃塞克斯大学毕业证学位证书一比一原版(Essex毕业证书)埃塞克斯大学毕业证学位证书
一比一原版(Essex毕业证书)埃塞克斯大学毕业证学位证书
F La
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
Airst S
 
一比一原版悉尼大学毕业证如何办理
一比一原版悉尼大学毕业证如何办理一比一原版悉尼大学毕业证如何办理
一比一原版悉尼大学毕业证如何办理
Airst S
 
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
e9733fc35af6
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
Airst S
 

Dernier (20)

一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
 
Human Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxHuman Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptx
 
Understanding the Role of Labor Unions and Collective Bargaining
Understanding the Role of Labor Unions and Collective BargainingUnderstanding the Role of Labor Unions and Collective Bargaining
Understanding the Role of Labor Unions and Collective Bargaining
 
一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理一比一原版伦敦南岸大学毕业证如何办理
一比一原版伦敦南岸大学毕业证如何办理
 
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation StrategySmarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
 
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
 
It’s Not Easy Being Green: Ethical Pitfalls for Bankruptcy Novices
It’s Not Easy Being Green: Ethical Pitfalls for Bankruptcy NovicesIt’s Not Easy Being Green: Ethical Pitfalls for Bankruptcy Novices
It’s Not Easy Being Green: Ethical Pitfalls for Bankruptcy Novices
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
 
3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt3 Formation of Company.www.seribangash.com.ppt
3 Formation of Company.www.seribangash.com.ppt
 
一比一原版(Essex毕业证书)埃塞克斯大学毕业证学位证书
一比一原版(Essex毕业证书)埃塞克斯大学毕业证学位证书一比一原版(Essex毕业证书)埃塞克斯大学毕业证学位证书
一比一原版(Essex毕业证书)埃塞克斯大学毕业证学位证书
 
ARTICLE 370 PDF about the indian constitution.
ARTICLE 370 PDF about the  indian constitution.ARTICLE 370 PDF about the  indian constitution.
ARTICLE 370 PDF about the indian constitution.
 
Shubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptxShubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptx
 
Navigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptxNavigating Employment Law - Term Project.pptx
Navigating Employment Law - Term Project.pptx
 
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptxAnalysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
Analysis of R V Kelkar's Criminal Procedure Code ppt- chapter 1 .pptx
 
The doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statuteThe doctrine of harmonious construction under Interpretation of statute
The doctrine of harmonious construction under Interpretation of statute
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
 
一比一原版悉尼大学毕业证如何办理
一比一原版悉尼大学毕业证如何办理一比一原版悉尼大学毕业证如何办理
一比一原版悉尼大学毕业证如何办理
 
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
 

Contract and Arbitration

  • 2. CONTRACT  Most construction carried through contract system-agreement between owner and construction agency  Construction a complex process involving both parties  Owner’s team- architect, engineer and consultant  both parties must pull in same direction & with same speed to successfully complete project  Word- Contract- drawn from latin word- contractor- drawing together  Contract-An agreement enforceable by law is a contract- Indian Contract Act, 1872  Contract—an agreement between two or more persons  --intended to be enforceable by law  --constituted by making offer by one and  - Acceptance by other
  • 3. OBJECT OF CONTRACT  To complete work given to construction company :  --without any complication  - within specified time  -- within specified cost  -conforming to specified quality  --without loss of harmony between key participants ------------------------------------------  Completion of work  Completion of work within time  Completion of work within time and cost  Completion of work within time and cost conforming to quality  Completion of work within time and cost conforming to quality and without sacrificing harmony  -------------------------------------  Owner desires– Best value for money spent  Contractor wants – Maximum rate of return on investment  Common objective–Completion of Work
  • 4. PRE- REQUISITE OF VALID CONTRACT  i.There must be two parties one making offer and other accepting offer  Ii. Agreement between contacting parties to terms& conditions of contract  iiiGenuine intention of parties to accept/fulfill their rights and duties  Iv Legal capacity of parties to make contract  v Consideration of some value exchanged  Vi Agreement enforceable by law--Agreement not enforceable is a void contract  Vii Agreement enforceable at option of one or more parties but not enforceable at the options of other- void  Viii Both parties must be major  Ix Parties must be of sound mind
  • 5. TYPES OF CONTRACTS Types of contracts– i. Based on purpose- full contract, labour contract,/transport contracts/procurement contracts /Turnkey contracts /consultancy/ Erection contracts ii. Based on Economic conditions– lump sum /cost+fee /item rate/ turnkey/ BOOT/ labour/ demolition/ day work
  • 6. TYPES OF CONTRACTS 1 Measurement Contracts(Item rate & %age contracts)  2 Lump Sum Contracts  3 Cost plus Fee Contracts  4 Turnkey Contracts  5 BOOT Contracts  6 Labour Contracts  7 Demolition Contracts  8 Other Works  9 Day Works  10. Consultancy Contracts
  • 7. TYPES OF CONTRACTS 1 Measurement Contracts --Item rate –for large works- owner quotes quantity and unit, Tenderer- Rate for each item- payment based on actual measuremnt -- % age contracts- for small/ repetitive/ repair/ maintenance works-owners gives, items, rate, quantities, amount- Contractor –quotes-- % above, below, at par- payment based on actual measurement  2 Lump Sum Contracts-when cost of entire work quoted based on scope of work, planning, designing, working drawings all drawings, specifications frozen before inviting tender—  -- owners knows total cost of work in beginning,  -- no change in scope can be made,
  • 8. TYPES OF CONTRACTS  3 Cost plus Fee Contracts- adopted for emergency/miscellaneous/undefined scope of works–  Contractor paid– actual cost+ fixed fee+ incentive  - contractor risk minimum-owner cost uncertain- adopted in government/private sector work  4 Turnkey Contracts—  contractor responsibility for defined scope of work--planning, designing ,construction, commissioning  - paid fixed lump sum amount  - Risk for the contractor-- weather/ site/foundation/ unforeseen problems  -suitable for projects where all functional parameters are defined  - thermal plant- commercial/ defense /interior projects  -eliminates co-ordination problems
  • 9. TYPES OF CONTRACTS  5 BOOT Contracts- Build, own, operate, Transfer contracts  —encouraging private sector-to fund- build- own- operate  --collect toll, for a fixed time and then hand back projects to authority  – suitable for highways, airports, power plant, waters supply, bridges etc  - govt. acts as facilitator- legal issues, land acquisition,, enforcement  - Government may also join – in a separate holding company  DFBOOT- Designing, financing, build, own, operate, transfer
  • 10. TYPES OF CONTRACTS  6 Labour Contracts-  -owner supplies all materials  - contractor- labour/ equipment/plant/machinery  - responsible for execution work  - may lead to misuse/waste of material  - popular for quality of material/construction  - problems related to escalation of cost of material donot impact project  —need effective supervision for;  -- quality  --wastage  --workmanship  -suitable for all types of work  - new/addition/alteration/repair etc
  • 11. TYPES OF CONTRACTS  7 Demolition Contracts-  -involves demolition of existing building/removal of debris  - contractor removes/salvage/ pay for material to owner  - highest bidder given contract  -entire bid money deposited by contractor  - to forfeit incase of default/ non-compliance/non-removal of debris,  Contractor – take insurance of worker, compensate them for accidents  contract to define scope of work- part/whole demolition  -incase of part- to make good any loss to remaining building  - item to be retained by owner to be specified  -Earnest money refunded to contractor after the work
  • 12. TYPES OF CONTRACTS  8 Other Works-  -- splitting  --large repetitive works  --into smaller parts  --- allotted through tendering  --- canals/metros railway/road work/electrical/water supply etc-
  • 13. TYPES OF CONTRACTS  9 Day Works  -for specialized works of small nature  - which cannot be measured in value terms  -decorative/craft/artwork etc  -payment include material cost+ hire  - charges for machinery + labour charges +profit  --- no security/tendering  - clark of work to report to architect/engineer for progress  - wages paid to conform Government guidelines  - uncertainty in cost  - difficulty in measurement
  • 14. TYPES OF CONTRACTS  10. Consultancy Contracts-  --Hiring of consultants for specialized projects  -- paid on job basis/ lump sum basis/ call basis/ retainer ship basis  -- depending on situation/ other factors  Consultants selected on  --Quality base selection- for specialised projects- master plans/ finance  --Best Expert Advise—Feasibility/structural engineering/major projects-dam  -- Selection under Fixed Budget– for simple/precisely defined projects
  • 16. SELECTION OF CONTRACTORS  Selection of contractor- most important part of contract management  Critical Factors of construction depend on selection of a suitable contractor to ensure—  - Quality  -- Speed  --Economy  -- Harmony  - Selection of Contractor to be based on principles of--equity and fair play
  • 17. SELECTION OF CONTRACTOR  Contractor is selected by owner by any of the following process after negotiations, when needed  1. Public Tender 2. Pre- Qualification  3. Post- Qualification  4. Limited Tenders  5. Single Tenders  6. Nomination
  • 18. SELECTION OF CONTRACTOR- PUBLIC TENDER Tender– or quotation is a: -- written offer -- to execute a work or -- supply of materials required -- for construction of a facility -- within a stipulated time -- under specified conditions of tender/quotation Public Tender  For Government works  - public tenders invited from registered contractors of appropriate class  - Tender notice explains  -- conditions  - work experience,  financial solvency,  annual turnover,  registration as contractor.
  • 19. PRE-QUALIFICATION OF CONTRACTORS Contractors are pre-qualified to ensure: --competition is among capable and qualified bidders -- Selection of best contractor - Elimination of incompetent/ insincere contractors  Pre- qualification of contractor is based on—  - work experience,  - financial solvency,  -- annual turnover, .  - quality of work executed  --Organisational structure  --Board of Directors  --Plant and Machinery available  - Manpower available - technical/non-technical  --General reputation
  • 20. DELHI GOVERNMENT- REGISTRATION OF CONTRACTORS Tender documents is issued only to those contractors, who are registered in the -- I&FC Deptt. ( Irrigation and Flood control Deptt) -- CPWD, --PWD (NCT of Delhi), --MES -- duly got verified by I&FC Deptt.
  • 21. DELHI GOVERNMENT- REGISTRATION OF CONTRACTORS   Contractors enlisted in various classes are entitled to submit their tenders, as per financial limits of estimated cost shown below:  Class I - upto Rs. 20.00 Crore  Class II - upto Rs. 5.00 Crore  Class III - upto Rs. 150.00 lac  Class IV - upto Rs. 60.00 lac
  • 22. ENLISTMENT PROCEDURE:  Contractor to submit application in a prescribed form complete with all documents  Reports submitted verified / works done by contractor inspected and/or to get such other reports as may be considered necessary.  If contractor found suitable for enlistment-- enlistment order issued—otherwise rejection letter sent of to contractor  -- decision of enlistment authority final and binding on contractor. -- authority reserves right to limit number of contractor to be enlisted in any class .  Enlistment of contractors may be closed at any point of time.  While closing department may have a reserved list of eligible contractors from pending applications.  Out of this-- contractors enlisted depending on requirement in a particular area/ NCT as a whole.
  • 23. PERIOD OF ENLISTMENT  Enlistment valid for a period of four years.  Enlistment can, be revalidated .  Each revalidation shall be for a period of three years  Enlistment shall be open to:  -- review by the enlistment authority  -- liable to termination,  -- suspension  - demotion to a lower class  -- any other such action  -- at any time if considered necessary  -- by the enlistment authority,  -- after issue of show cause notice
  • 25. ARBITRATION  Disputes are part of human living  In ancient times disputes referred to Village Panchayats for speedy settlements  During British Rule, Arbitration was encouraged  Arbitration Act, 1899 was the first Act  Replaced by Arbitration Act, 1940 as full code  The Arbitration and Reconciliation Act, 1996 based on the UN Model Act was passed in 1996  Act provides for-  Domestic Arbitration  International commercial and  Enforcement of foreign Arbitral awards
  • 26. MODES OF SETTLEMENT OF DISPUTES  1. Capitulation- weaker party give in -to retain goodwill/ long term business relationship with stronger party  2. Negotiation--Both parties sink differences and try to reach amicable settlement  3. Arbitration- Disinterested/impartial third party appointed to adjudicate  4. Litigation- Disputes taken to court resulting in abnormal delay and heavy expenditure  5. Dispute Resolution Board- Board constituted on award of contract to resolve disputes as and when they arise
  • 27. ARBITRATION  --Settlement of a dispute (whether of fact, law, or procedure)  between parties to a contract  -- by a neutral third party (the arbitrator)  -- without resorting to court action.  -- Arbitration is usually voluntary but  -- sometimes it is required by law.  -- If both sides agree to be bound by arbitrator's decision  'award‘ becomes a binding arbitration.  Exact procedure to be followed (if not included in the contract under dispute)  - governed usually by a country's arbitration laws, or  --by arbitration rules prescribed by International Chamber Of Commerce (ICC)
  • 28. ARBITRATION  Arbitration most popular mode of settling disputes in building and construction disputes  Most construction projects provide for arbitration  Helps in imparting justice in a:  -- speedier and  -- cost-effective manner  Determining of disputes by the decision of one or more – persons known as Arbitrator  Every dispute – which can be settled by a civil court can be settled under Arbitration
  • 29. ARBITRATION- OBJECTIVES  Make provision for arbitral procedure which is:  -- fair,  -- efficient  -- capable of meeting needs of specific arbitration  To Minimise supervisory role of Courts  Arbitral tribunal to give reasons for the award  To ensure Arbitral tribunal remains within its jurisdiction  Permit Arbitral tribunal to use:  -- mediation,  -- conciliation or  -- other procedures to settle disputes  To make decisions of Tribunal enforceable as a degree of court
  • 30. DEFINITIONS  Arbitrator- A person appointed to settle disputes  Arbitration Agreement- A written agreement between client and contractor to settle future disputes  Order of reference– Order containing names of the arbitrator, specific dispute, nature, time limit for award  Presiding arbitrator-An umpire when each party’s arbitrator or both parties arbitrator choose one presiding arbitrator  Award– Written decision of the arbitrator on completion of the proceedings
  • 31. ARBITRATION VS LITIGATION  Advantage of Arbitration over litigation:  More Speed  Less Expensive  More Privacy  Informal Proceedings  Expertise of the Arbitrators in the field  Flexibility in choice of meeting place and location  finality of decision  Continued good relations between parties- owners and client
  • 32. PROCEDURE FOR ARBITRATION  Specific clause to be introduced in contract- settling disputes by arbitration  Aggrieved party to approach the designated authority to appoint arbitrator with list of all/selected disputes and amount involved for each dispute-  Arbitrator is then appointed with list and -- referred with the papers submitted  Few contracts provide for direct resolution of disputes by parties- failure to do so can lead to appointment of an Arbitrator  Arbitration conducted under the provisions of Arbitration and Conciliation Act, 1996  Parties are to be treated on equality and given full opportunity to present their case
  • 33. PROCEDURE FOR ARBITRATION  Parties are free to agree on the procedure for Arbitral Tribunal  Parties free to agree on the place and language for arbitration  Arbitration proceedings start from the date of receipt of request for arbitration  Claimant to state facts supporting the claim, issues involved and remedy sought  Respondent to give defence against these claims  Tribunal to decide on oral/documentary evidence  Experts appointed by Tribunal in case of specific technical issues  Assistance of court may be sought for taking evidence
  • 34. PROCEDURE FOR ARBITRATION  Decision of the Tribunal to be by majority- being in odd numbers  Award to be in writing and signed by all members  It is to be reasoned award unless otherwise agreed to by parties  Award amount, if not paid, to carry interest @18% per annum from date of award to date of payment  Award to be final and binding  Enforced as – decree of the Civil Court
  • 35. CHARACTERISTICS OF GOOD AWARD  Sticking to the scope of defined issues  Stick to time limit  Unambiguous, unconditional, complete and clear decision  Judgment and decision that of the Arbitrator only and no one else  Complete application of mind of Arbitrator’s
  • 37. VALUATION  Valuation was introduced due to  -- Land Acquisition Act – for assessing value of land on market value  -- for levying property tax by municipalities based on ratable value of property  -- for buying/selling property  -- Valuation necessity till property lives as a concept  Valuation is a process by which value of an asset is estimated  - It is not an exact science with mathematical accuracy  -It is an expert opinion – supported by relevant fact and information impacting value of asset  Duty of the valuer to avoid undervaluing/ over-valuing property
  • 38. VALUATION  It is a guess based on certain objective factors  -Valuation depends upon–  -- location,  -- quality of construction,  -- life of building  - current status of building  -- type/nature of buildings- temporary/ permanent  -- prevailing cost of land  -- Cost of construction- plinth area rates  -demand and supply  - Purpose of valuation  -cost indices - --Available data - —sound judgment, experience - It is multi-disciplinary work involving knowledge of—Architecture, engineering, mathematics, land, geography, materials etc
  • 39. VALUE  Value represent—  -- worth, utility, attachment to a thing in the eyes of a person  - For a thing to have value it must possess  - economic & Legal qualities--- utility, demand, scarcity,, transferability of ownership  --Value differs from person to person  - hence different persons value differently same property  -- Value is a relative concept  - valuation is a function of:  -- place,  --purpose and  -- time
  • 40. METHOD OF VALUATION 1. Land and Building Method 2. Composite Rate Method 3. Development Potential Method 4. Rent Capitalization Method 5. Profit Capitalization Method 6. Cost Approach Method
  • 41. LAND AND BUILDING METHOD Land and Building Method involves a sum of ; -- Fair Market Value of Land + Depreciated value of building - Depreciated value of building is worked out on the basis of plinth area, plinth area rate of building based on CPWD/PWD for the area based on cost index, age of building, estimated total life of building, savage value- - Value of building= Value of building component+ services+ market value of land - Valuation used for – - --Residential/ - --self-occupied properties and - -- certify the present worth of property
  • 42. 2. COMPOSITE RATE METHOD  Method used for assessing value of Residential apartment and commercial complexes  Comprises of = Rate per unit area of building+ proportionate share of land  Land component decided on- location, land values, amenities provided by developer, specification of land  Building component depends on- cost of construction, age, specification, finishes, structure, materials, location, accessibility, quality etc  In case of old apartments- depreciated value is worked out for the building
  • 43. 3 DEVELOPMENT POTENTIAL METHOD  Based on the potential of land for immediate future development- fair market value  Used for assessing value of vacant undeveloped/under-developed land parcels on outskirts of city and for land within the city based on the existing local bye-laws  Used by developers for investment into land and carving out smaller plots for sale  Applied when demand for small plots exist and land is sufficient to take up real estate development involving residential/commercial development with minimal cost
  • 44. 4 RENT CAPITALISATION METHOD  Method used for valuation of rented properties, properties under Rent Control Act  Method considers- tenant right( not legally saleable) and owners right to receive rent.  This method has- Net Maintainable Rent- NMR for landlord which is worked out by deducting outgoings from the Gross Maintainable Rent- GMR  - Net rent capitalised and depreciation is ignored  Essentials for this valuation are–  -- Gross rent,  -- outgoing,  --Capital employed,  -- rate of return ,  -- life of building,  --unused portion of asset for future use,  -- money required for repair
  • 45. 5 PROFIT CAPITALIZATION METHOD  Used for single commercial properties like- cinema, hotel, marriage halls etc  Net profit is capitalised  Based on Gross profit minus outgoings  Method sensitive to market variations  Method approximate- applied in the absence of data by other methods  Net profit obtained- helps to assess value of property along with rate of return  Net profit- average of last 3-5 years taken  Part of profit is goodwill taken from the tenets
  • 46. 6. COST APPROACH METHOD  Applied primarily to service properties- which are  -- not frequently exchanged in market  -- donot generate revenue by themselves  Useful on new or special purpose properties  -Logic is that prudent investor:  -- should not pay more for property  -- than cost of producing a substitute property with the same utility
  • 47. VALUATION PROCESS INBRIEF  Appointment of valuer detailing property, purpose and scale of fee charged  Ascertain the purpose of valuation  Visit the site of valuation  Document the site with maps and photographs  Study relevant Act, practices, approach to valuation to suit the purpose  Follow the set procedure to determine its value  Where necessary check by other methods and observe difference  Based on experience/ wisdom form an opinion of the realistic value of asset by appropriate method
  • 48. PRECAUTIONS TO BE TAKEN WHILE VALUATION  Ascertain all possible facts  Identify the property  Donot inflate the value  Donot understate the value  Donot value illegal properties  Donot delegate valuation to incompetent colleague/assisttant  Apply appropriate method of valuation  Donot rely entirely on legal opinion  Do not rely entirely on previous valuation report  Take all possible precaution  Remain objective- minimize subjectivity  Donot yield to any pressure of offer  Use all available legal documents- building plans, occupation certificate, completion certificate etc