BUILDING CONSTRUCTION 1
CONSTRUCTION ACTIVITIES AND PROCESS
TUTORS: MR. LEE XIA SHENG AR. CHIN TUCK HING, MS. SUJA
LIM JIAN JUN 0316867
1 | P a g e
Site preparation
Survey work 1 week
setting out 1 week
Earthwork 1-2 weeks
Foundation
Pile 3 weeks
pile cap 2 weeks
Stump 2 weeks
Ground Beam 2 weeks
Ground Floor
Slab 2 weeks
Column 2 weeks
Beam 2 weeks
Staircase 2 weeks
wall 2 weeks
plastering 2 weeks
First Floor
Slab 2 weeks
Column 2 weeks
Beam 2 weeks
Staircase 2 weeks
wall 2 weeks
plastering 2 weeks
Second Floor
Slab 2 weeks
Column 2 weeks
Beam 2 weeks
Staircase 2 weeks
wall 2 weeks
plastering 2 weeks
Roof Slab
Utility
Electrical Supply 1 week
Water Supply 1 week
Door and Windows Total: 2 week
Finishes
1st floor Kitchen
Plumbing 1 week
Plastering interiors
1st floor 2 week
Plastering Interiors
2nd floor 1 week
Skidding floors
Painting - first coat 2 week
Painting - second
coat 2 week
Sanitary fitting of
bathroom and
kitchen 1 week
Electrical fitting 1 week
Total 57 week
2 | P a g e
WEEK 1
Activity 1: Site survey
Duration: 7 days
Materials: -
Equipment:-
Skilled Workers: Backhoe Loader Operator(1), General workers(4),
Lorry driver(1)
Technical Information: Analysis is done to the construction site by
surveyor and further planning and advices to the site for construction
preparation and development.
Activity 2: Mobilization
Duration: 2-3 days
Materials: Machineries
Equipment: Lorries(2), mobile crane(1), backhoe loaders(1), Hydraulic
Piling Hammer(1), excavator(1), compactor (1), boring machine(1)
Skilled Workers: lorry drivers(2), excavator operator(1), backhoe
loader operator(1), Hydraulic Piling Hammer operator(1), compactor
operators (1), boring machine operator(1)
Technical Information: Machineries required is delivered to the site
and wait for job to be executed.
Activity 3: Site Clearing
Duration: 7 days
Materials: -
Equipment: Backhoe Loader, chainsaw, lorry truck (carry earth &
plants away)
Skilled Workers: Backhoe Loader Operator(1), General workers(4),
Lorry driver(1)
Technical Information: Excavation of unfavorable soil and substances
such as stones and tree barks. Initial leveling is done for the
preparation of earthwork.
3 | P a g e
WEEK 2
Activity 1: Hoarding (setting out), staking (plan boundary)
Duration: 5 days
Materials: blue metal decks, nails, wooden pegs, planks, stakes,
Builder’s line
Equipment: hammer, measuring tape, theodolite, Dummy level,
construction sign board
Skilled Workers: quantity surveyor (2), general workers (4)
Technical Information: Boundary of the construction site is precisely
measured and borders the site where the construction takes place.
The site is marked with gridlines with a setback of 20 feet from the
road and 10 feet for the porch according to UBBL and the location of
the pile is marked.
Activity 2: Earthwork
Duration: 7 days
Materials: -
Equipment: excavator, compactor
Skilled Workers: Excavator Operator (1), Compactor Operator (1)
Technical Information: Removal of top soil and land leveling. The
land is excavated to around 300mm of the top soil. Keep away or
stored well for reuse due to its high water retentive characteristic.
4 | P a g e
WEEK 3
Activity 1: Earthwork (continued)
Duration: 7 days (continued from last week)
Materials: -
Equipment: excavator, compactor
Skilled Workers: Excavator Operator (1), Compactor Operator (1)
Technical information: Removal of top soil and land leveling. The
land is excavated to around 300mm of the top soil. Keep away or
stored well for reuse due to its high water retentive characteristic
Activity 2: Piling (Grid 13- Grid 15)
Duration: 10-14 days
Materials: Reinforced concrete piles, Concrete Grade 30,
Reinforcement, wooden formworks
Equipment: Hydraulic Piling Hammer(1), Rebar Bending machine(1),
Boring Machine(1), cement concrete mixer (1), hacker (1)
Skilled Workers: Hydraulic Piling Hammer Operator (1), Boring
Machine Operator (1), Rebar Bender (1), General construction
workers (6)
Technical Information: The depth/length of the piles is depending on
the soil condition based on the soil test, after that the engineers will
decide the pile length to fit the soil condition of the site, based on the
result of the test. Difference in height of the piles will be cut below
cap using hacker. The rebar connected to the piles are then removed
and left for the joining of capping reinforcement. Soil specimen is
taken for soil test experiment to determine the length of the pile. The
pile integrity test (Load test) is done to determine the strength to
support the load.
5 | P a g e
Week 4
Activity 1: Piling (Grid 8 - Grid 12)
Duration: 10-14 days
Materials: Reinforced concrete piles, Concrete Grade 30,
Reinforcement, wooden formworks
Equipment: Hydraulic Piling Hammer(1), Rebar Bending machine(1),
Boring Machine(1), cement concrete mixer (1)
Skilled Workers: Hydraulic Piling Hammer Operator (1), Boring
Machine Operator (1), Rebar Bender (1), General construction
workers (6)
Technical Information: The depth/length of the piles is depending on
the soil condition based on the soil test, after that the engineers will
decide the pile length to fit the soil condition of the site, based on the
result of the test. Difference in height of the piles will be cut below
cap using hacker. The rebar connected to the piles are then removed
and left for the joining of capping reinforcement. Soil specimen is
taken for soil test experiment to determine the length of the pile. The
pile integrity test (Load test) is done to determine the strength to
support the load.
6 | P a g e
Week 5
Activity 1: Leveling of Piles before capping
Duration: 3 days
Materials: Reinforced concrete piles, Concrete Grade 30,
Reinforcement, wooden formworks
Equipment: Hydraulic Piling Hammer(1), Rebar Bending machine(1),
Boring Machine(1), cement concrete mixer (1)
Skilled Workers: Hydraulic Piling Hammer Operator (1), Boring
Machine Operator (1), Rebar Bender (1), General construction
workers (6)
Technical Information: When the piling is penetrated into the soil,
the piles are in different height. The piles need to be cut before cap
by using hacker. The rebar are removed and then the capping
reinforcement are applied. Activity 2: Pile capping
Duration: 7 -14 days
Materials: Reinforced concrete piles, Concrete Grade 30,
Reinforcement, wooden formworks
Equipment: Hydraulic Piling Hammer(1), Rebar Bending machine(1),
Boring Machine(1), cement concrete mixer (1)
Skilled Workers: Hydraulic Piling Hammer Operator (1), Boring
Machine Operator (1), Rebar Bender (1), General construction
workers (6)
Technical Information: pile caps takes around 2 weeks to reach its
maximum strength, but usually it can be done after it is left curing for
about a week. Stumping can be constructed around that time.
7 | P a g e
Week 6
Activity 1: Stump from Pile caps
Duration:7 days-14 days
Materials: Concrete Grade 30, reinforcements, timber formworks.
Equipment: Concrete Vibrator(1), Rebar bending machine(1),
tablesaw(1)
Skilled Workers: Land Surveyor (1), Carpenter(2), Bar Bender (1),
General worker (2)
Technical Information: After pilings , the land surveyor will identity of
the height required of the stumps and thereafter construct the
stumps based on the data. Steel rebar are bent into cage form, with
starter bar protruding upward to connect for latter construction of
columns. Constructed the same way as the pile capping, the stumps
are left for curing in order to achieve its required structural strength
before the construction of the beams. It is left to cure for a week.
8 | P a g e
WEEK 7
Activity 1: Ground Beam (Grid 13-Grid 17)
Duration: 14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1),
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3)
Technical information: Formworks is constructed with steel rebar
reinforcement and starter bar. Thereafter a mixture of concrete with
aggregates and cement is then pour into the casting form and left for
curing around a week time.
9 | P a g e
WEEK 8
Activity 1: Ground Beam (Grid 8-Grid 13)
Duration: 14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1),
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3)
Technical information: Formworks is constructed with steel rebar
reinforcement and starter bar. Thereafter a mixture of concrete with
aggregates and cement is then pour into the casting form and left for
curing around a week time.
10 | P a g e
Week 9
Activity 1: Ground floor slab (grid 12- grid 17)
Duration: 14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1),
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3)
Technical Information: The Ground slab is cast after beam, the
workers can proceed to next construction during curing time.
Formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pour into the casting form and left for curing around a week
time. DPM is laid on the concrete and screeded with long even plank.
11 | P a g e
Week 10
Activity 1: Ground floor slab (grid 8 - 12 ,continued from the first )
Duration: 14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1),
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3)
Technical Information: The Ground slab is cast after beam, the
workers can proceed to next construction during curing time.
Formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pour into the casting form and left for curing around a week
time. DPM is laid on the concrete and screeded with long even plank.
12 | P a g e
Week 11
Activity 1: Ground Floor Columns (Grid 12 – Grid 15)
Duration: 14 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending
machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (4)
Technical information: Same as the construction of beams, the
formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pouring into the casting form and left for curing around a week
time.
13 | P a g e
Week 12
Activity 1: Ground Floor Columns (Grid 8-Grid 11)
Duration: 14 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending
machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (4)
Technical information: Same as the construction of beams, the
formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pouring into the casting form and left for curing around a week
time.
Activity 2: First Floor Beam (Grid 12- Grid 17) , first half
Duration: 14 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending
machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (4)
Technical information: The formworks is constructed with steel rebar
reinforcement and starter bar. Thereafter a mixture of concrete with
aggregates and cement is then pouring into the casting form and left
for curing around a week time.
14 | P a g e
Week 13
Activity 2: First Floor Beam (Grid 8 - Grid 12) , second half
Duration: 14 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending
machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (4)
Technical information: The formworks is constructed with steel rebar
reinforcement and starter bar. Thereafter a mixture of concrete with
aggregates and cement is then pouring into the casting form and left
for curing around a week time.
15 | P a g e
Week 14
Activity 1: First Floor Slab (Grid 13-grid 17)
Duration: 14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1),
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3)
Technical Information: The Ground slab is cast after beams, the
workers can proceed to next construction during curing time.
Formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pour into the casting, screeded with plank and then left for
curing around a week time. A layer of protection is laid on top of the
concrete during curing.
16 | P a g e
Week 15
Activity 1: First Floor Slab ( second half floor)
Duration: 14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1),
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3)
Technical Information: The Ground slab is cast after beams, the
workers can proceed to next construction during curing time.
Formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pour into the casting, screeded with plank and then left for
curing around a week time. A layer of protection is laid on top of the
concrete during curing.
17 | P a g e
Week 16
Activity 1: first floor column (grid 12-grid 17), first half
Duration: 14 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending
machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (4)
Technical information: Same as the construction of beams, the
formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pouring into the casting form and left for curing around a week
time.
Activity 2: Ground Floor Staircase (to level 1)
Duration: 8-14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1), spirit level.
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)
Technical Information: The formworks of the stairs is constructed
with steel rebar reinforcement and starter bar. Thereafter a mixture
of concrete with aggregates and cement is then pouring into the
casting form and left for curing around a week time. A concrete test is
taken to check the strength of the casting after it was left to cure for
a week.
18 | P a g e
Week 17
Activity 1: first floor column (grid 8-grid 12), second half
Duration: 14 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending
machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (4)
Technical information: Same as the construction of beams, the
formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pouring into the casting form and left for curing around a week
time.
Activity 2: Second Floor Beam (Grid 12- Grid 17) , first half
Duration: 14 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending
machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (4)
Technical information: The formworks is constructed with steel rebar
reinforcement and starter bar. Thereafter a mixture of concrete with
aggregates and cement is then pouring into the casting form and left
for curing around a week time.
Activity 3: Ground Floor Staircase (to level 1, continued)
Duration: 8-14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1), spirit level.
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)
Technical Information: The formworks of the stairs is constructed
with steel rebar reinforcement and starter bar. Thereafter a mixture
of concrete with aggregates and cement is then pouring into the
casting form and left for curing around a week time. A concrete test is
taken to check the strength of the casting after it was left to cure for
a week.
19 | P a g e
Week 18
Activity 1: Second Floor Beam (Grid 8- Grid 12) , second half
Duration: 14 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending
machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (4)
Technical information: The formworks is constructed with steel rebar
reinforcement and starter bar. Thereafter a mixture of concrete with
aggregates and cement is then pouring into the casting form and left
for curing around a week time.
20 | P a g e
Week 19
Activity 1: Second Floor Slab (first half)
Duration: 14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1),
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3)
Technical Information: The Ground slab is cast after beams, the
workers can proceed to next construction during curing time.
Formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pour into the casting, screeded with plank and then left for
curing around a week time. A layer of protection is laid on top of the
concrete during curing.
21 | P a g e
Week 20
Activity 1: Second Floor Slab (second half)
Duration: 14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1),
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3)
Technical Information: The Ground slab is cast after beams, the
workers can proceed to next construction during curing time.
Formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pour into the casting, screeded with plank and then left for
curing around a week time. A layer of protection is laid on top of the
concrete during curing.
22 | P a g e
Week 21
Activity 1: Second floor column (grid 8-grid 13)
Duration: 14 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending
machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (4)
Technical information: Same as the construction of beams, the
formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pouring into the casting form and left for curing around a week
time.
Activity 2: First Floor Staircase (to level 2)
Duration: 8-14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1), spirit level.
Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)
Technical Information: The formworks of the stairs is constructed
with steel rebar reinforcement and starter bar. Thereafter a mixture
of concrete with aggregates and cement is then pouring into the
casting form and left for curing around a week time. A concrete test is
taken to check the strength of the casting after it was left to cure for
a week.
23 | P a g e
Week 22
Activity 1: Roof floor Beams (Grid 8- Grid 13) , All floor
Duration: 14 Days
Materials: Concrete Grade 30, reinforcement, timber formwork
Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending
machine (1), table saw
Skilled worker: Carpenter (2) , bar bender (2), general worker (4)
Technical information: The formworks is constructed with steel rebar
reinforcement and starter bar. Thereafter a mixture of concrete with
aggregates and cement is then pouring into the casting form and left
for curing around a week time.
24 | P a g e
Week 23
Activity 1: third floor Slab (all floor)
Duration: 14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1),
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3)
Technical Information: The Ground slab is cast after beams, the
workers can proceed to next construction during curing time.
Formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pour into the casting, screeded with plank and then left for
curing around a week time. A layer of protection is laid on top of the
concrete during curing.
25 | P a g e
WEEK 24
Activity 1: brickwalls Ground Level (Grid 3- 4)
Duration: 15-20 days
Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar,
Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Builder’s line is used to alight the walls during
stacking of bricks and construction of the wall. The clay bricks are
bonded with mortar and stack together with specific bonding pattern.
Wire mesh is laid on the bricks in certain layer interval as
reinforcement and stiffer will be constructed between walls to
strengthen the walls.
26 | P a g e
WEEK 25
Activity 1: brickwalls Ground Level (Grid 4-5)
Duration: 15-20 days
Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar,
Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Builder’s line is used to alight the walls during
stacking of bricks and construction of the wall. The clay bricks are
bonded with mortar and stack together with specific bonding pattern.
Wire mesh is laid on the bricks in certain layer interval as
reinforcement and stiffer will be constructed between walls to
strengthen the walls.
27 | P a g e
Week 26
Activity 1: brickwalls Ground Level (Grid 5-6)
Duration: 15-20 days
Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar,
Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Builder’s line is used to alight the walls during
stacking of bricks and construction of the wall. The clay bricks are
bonded with mortar and stack together with specific bonding pattern.
Wire mesh is laid on the bricks in certain layer interval as
reinforcement and stiffer will be constructed between walls to
strengthen the walls.
28 | P a g e
Week 27
Activity 1: Brickwall First Level (Grid 3-4)
Duration: 15-20 days
Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar,
Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Builder’s line is used to alight the walls during
stacking of bricks and construction of the wall. The clay bricks are
bonded with mortar and stack together with specific bonding pattern.
Wire mesh is laid on the bricks in certain layer interval as
reinforcement and stiffer will be constructed between walls to
strengthen the walls.
29 | P a g e
Week 28
Activity 1: Brickwall First Level (Grid 4-5)
Duration: 15-20 days
Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar,
Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Builder’s line is used to alight the walls during
stacking of bricks and construction of the wall. The clay bricks are
bonded with mortar and stack together with specific bonding pattern.
Wire mesh is laid on the bricks in certain layer interval as
reinforcement and stiffer will be constructed between walls to
strengthen the walls.
30 | P a g e
Week 29
Activity 1: Brickwall First Level (Grid 4-5)
Duration: 15-20 days
Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar,
Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Builder’s line is used to alight the walls during
stacking of bricks and construction of the wall. The clay bricks are
bonded with mortar and stack together with specific bonding pattern.
Wire mesh is laid on the bricks in certain layer interval as
reinforcement and stiffer will be constructed between walls to
strengthen the walls.
31 | P a g e
Week 30
Activity 1: Brickwall Second Level (Grid 3-4a)
Duration: 15-20 days
Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar,
Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Builder’s line is used to alight the walls during
stacking of bricks and construction of the wall. The clay bricks are
bonded with mortar and stack together with specific bonding pattern.
Wire mesh is laid on the bricks in certain layer interval as
reinforcement and stiffer will be constructed between walls to
strengthen the walls.
32 | P a g e
Week 31
Activity 1: Brickwall Second Level (Grid 4a-5)
Duration: 15-20 days
Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar,
Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Builder’s line is used to alight the walls during
stacking of bricks and construction of the wall. The clay bricks are
bonded with mortar and stack together with specific bonding pattern.
Wire mesh is laid on the bricks in certain layer interval as
reinforcement and stiffer will be constructed between walls to
strengthen the walls.
33 | P a g e
Week 32
Activity 1: Brickwall Second Level (Grid 13 -17)
Duration: 15-20 days
Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar,
Builder’s line, Wire mesh reinforcement
Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)
Skilled Workers: General Workers (6)
Technical Information: Builder’s line is used to alight the walls during
stacking of bricks and construction of the wall. The clay bricks are
bonded with mortar and stack together with specific bonding pattern.
Wire mesh is laid on the bricks in certain layer interval as
reinforcement and stiffer will be constructed between walls to
strengthen the walls.
Activitity 2: Façade roof slab
Duration: 14 days
Materials: Concrete Grade 30, reinforcements, timber formworks,
Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank
Equipment: Concrete Vibrator(1), Rebar bending machine(1), table
saw(1), concrete mixer(1),
Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3)
Technical Information: The Ground slab is cast after beam, the
workers can proceed to next construction during curing time.
Formworks is constructed with steel rebar reinforcement and starter
bar. Thereafter a mixture of concrete with aggregates and cement is
then pour into the casting form and left for curing around a week
time. DPM is laid on the concrete and screeded with long even plank.
34 | P a g e
Week 33
Activity 1: Framing (ground floor)
Durations: 7 days
Materials: Openings wooden frame (for door and windows)
Equipment: Spirit level, Measuring tape
Skilled Workers: General Workers (4)
Technical Information: The opening frames are constructed in
position and align after the brick wall is done. Architrave is added
after the door/window frame is added.
Activity 2: Incoming Electrical Circuit Supply Installation
Duration: 10-14 days
Materials: Copper Cables (different sizes), Kilowatt hour meter
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts,
Skilled Workers: Electric Technician (2), Plumbers (2)
Technical Information: Incoming electricity cables are brought into
the house and connected to a circuit box in the house to facilitate the
plumbing works later on.
Week 34
Activity 1: Framing (First floor)
Durations: 7 days
Materials: Openings wooden frame (for door and windows)
Equipment: Spirit level, Measuring tape
Skilled Workers: General Workers (4)
Technical Information: The opening frames are constructed in
position and align after the brick wall is done. Architrave is added
after the door/window frame is added.
Activity 2: Incoming Electrical Circuit Supply Installation
Duration: 10-14 days (continued)
Materials: Copper Cables (different sizes), Kilowatt hour meter
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts,
Skilled Workers: Electric Technician (2), Plumbers (2)
Technical Information: Incoming electricity cables are brought into
the house and connected to a circuit box in the house to facilitate the
plumbing works later on.
35 | P a g e
Week 35
Activity 1: Framing (Second floor)
Durations: 7 days
Materials: Openings wooden frame (for door and windows)
Equipment: Spirit level, Measuring tape
Skilled Workers: General Workers (4)
Technical Information: The opening frames are constructed in
position and align after the brick wall is done. Architrave is added
after the door/window frame is added.
Activity 2: Ground Floor Plumbing (First Fix)
Duration: 14 days
Materials: Copper Cables (different sizes), PVC pipes, socket box
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking
machine
Skilled Workers: Electricians(2), Plumbers (2)
Technical Information: Technicians will determine the location of the
sockets according to the engineering blue print. The brick wall is
hacked to accommodate the wiring pipe from the top to the ground
according UBBL requirements. The wall sockets will be installed after
the wiring is done.
36 | P a g e
Week 36
Activity 1: First Floor Plumbing (First Fix)
Duration: 14 days
Materials: Copper Cables (different sizes), PVC pipes, socket box
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking
machine
Skilled Workers: Electricians(2), Plumbers (2)
Technical Information: Technicians will determine the location of the
sockets according to the engineering blue print. The brick wall is
hacked to accommodate the wiring pipe from the top to the ground
according UBBL requirements. The wall sockets will be installed after
the wiring is done.
Week 37
Activity 1: First Floor Plumbing (First Fix)
Duration: 14 days
Materials: Copper Cables (different sizes), PVC pipes, socket box
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking
machine
Skilled Workers: Electricians(2), Plumbers (2)
Technical Information: Technicians will determine the location of the
sockets according to the engineering blue print. The brick wall is
hacked to accommodate the wiring pipe from the top to the ground
according UBBL requirements. The wall sockets will be installed after
the wiring is done.
Activity 2: Second Floor Plumbing (First Fix)
Duration: 14 days
Materials: Copper Cables (different sizes), PVC pipes, socket box
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking
machine
Skilled Workers: Electricians(2), Plumbers (2)
Technical Information: Technicians will determine the location of the
sockets according to the engineering blue print. The brick wall is
hacked to accommodate the wiring pipe from the top to the ground
according UBBL requirements. The wall sockets will be installed after
the wiring is done.
Activity 3: Plumbing (Sanitary and Kitchen)
Duration: 14 days
Materials: Copper Cables (different sizes), PVC pipes, socket box
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking
machine
Skilled Workers: Electricians(2), Plumbers (2)
Technical Information: Technicians will determine the location of the
sockets according to the engineering blue print. The brick wall is
hacked to accommodate the wiring pipe from the top to the ground
according UBBL requirements. The wall sockets will be installed after
the wiring is done.
37 | P a g e
Week 38
Activity 1: Plumbing (Sanitary and Kitchen)
Duration: 14 days
Materials: Copper Cables (different sizes), PVC pipes, socket box
Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking
machine
Skilled Workers: Electricians(2), Plumbers (2)
Technical Information: Technicians will determine the location of the
sockets according to the engineering blue print. The brick wall is
hacked to accommodate the wiring pipe from the top to the ground
according UBBL requirements. The wall sockets will be installed after
the wiring is done.
Week 39
Activity 1: Ground floor Wall Plastering (Grid 1-Grid 3)
Duration: 14-21 days (interior and exterior)
Materials: cement plaster, skim coat
Equipment: buckets, cement spatula trowels, groovers, edgers,
planks, sponges, scaffolding, plaster spray
Skilled Workers: general workers (2), plasterers(3)
Technical information: The plaster layer is not more than half inches,
and left for drying about 7 days before the finishing is applied. The
first coating thickness is around 1/2 to 3/4 inches while the finishing
coat will be around 3/16 inches thick. The surface of the rendering
preferably wetted before application of plastering. Rough surface
plastering is usually used outdoor to resist harsh weathering. Smooth
surface plastering with pores and easily defected characteristic is
preferably used indoor.
38 | P a g e
Week 40
Activity 1: Ground floor wall plastering (Grid 4-4a)
Duration: 14-21 days (interior and exterior)
Materials: cement plaster, skim coat
Equipment: buckets, cement spatula trowels, groovers, edgers,
planks, sponges, scaffolding, plaster spray
Skilled Workers: general workers (2), plasterers(3)
Technical information: The plaster layer is not more than half inches,
and left for drying about 7 days before the finishing is applied. The
first coating thickness is around 1/2 to 3/4 inches while the finishing
coat will be around 3/16 inches thick. The surface of the rendering
preferably wetted before application of plastering. Rough surface
plastering is usually used outdoor to resist harsh weathering. Smooth
surface plastering with pores and easily defected characteristic is
preferably used indoor.
39 | P a g e
Week 41
Activity 1: Ground floor plastering (Grid 4a-6)
Duration: 14-21 days (interior and exterior)
Materials: cement plaster, skim coat
Equipment: buckets, cement spatula trowels, groovers, edgers,
planks, sponges, scaffolding, plaster spray
Skilled Workers: general workers (2), plasterers(3)
Technical information: The plaster layer is not more than half inches,
and left for drying about 7 days before the finishing is applied. The
first coating thickness is around 1/2 to 3/4 inches while the finishing
coat will be around 3/16 inches thick. The surface of the rendering
preferably wetted before application of plastering. Rough surface
plastering is usually used outdoor to resist harsh weathering. Smooth
surface plastering with pores and easily defected characteristic is
preferably used indoor.
Activity 2: First floor plastering (Grid 1- Grid 4)
Duration: 14-21 days (interior and exterior)
Materials: cement plaster, skim coat
Equipment: buckets, cement spatula trowels, groovers, edgers,
planks, sponges, scaffolding, plaster spray
Skilled Workers: general workers (2), plasterers(3)
Technical information: The plaster layer is not more than half inches,
and left for drying about 7 days before the finishing is applied. The
surface of the rendering preferably wetted before application of
plastering. Rough surface plastering is usually used outdoor to resist
harsh weathering. Smooth surface plastering with pores and easily
defected characteristic is preferably used indoor.
40 | P a g e
Week 42
Activity 1: First floor plastering (Grid 4- Grid 4a)
Duration: 14-21 days (interior and exterior)
Materials: cement plaster, skim coat
Equipment: buckets, cement spatula trowels, groovers, edgers,
planks, sponges, scaffolding, plaster spray
Skilled Workers: general workers (2), plasterers(3)
Technical information: The plaster layer is not more than half inches,
and left for drying about 7 days before the finishing is applied. The
first coating thickness is around 1/2 to 3/4 inches while the finishing
coat will be around 3/16 inches thick. The surface of the rendering
preferably wetted before application of plastering. Rough surface
plastering is usually used outdoor to resist harsh weathering. Smooth
surface plastering with pores and easily defected characteristic is
preferably used indoor.
41 | P a g e
Week 43
Activity 1: First floor plastering (Grid 4a-6)
Duration: 14-21 days (interior and exterior)
Materials: cement plaster, skim coat
Equipment: buckets, cement spatula trowels, groovers, edgers,
planks, sponges, scaffolding, plaster spray
Skilled Workers: general workers (2), plasterers(3)
Technical information: The plaster layer is not more than half inches,
and left for drying about 7 days before the finishing is applied. The
surface of the rendering preferably wetted before application of
plastering. Rough surface plastering is usually used outdoor to resist
harsh weathering. Smooth surface plastering with pores and easily
defected characteristic is preferably used indoor.
Activity 2: Second floor plastering (Grid 1-Grid 4)
Duration: 14-21 days (interior and exterior)
Materials: cement plaster, skim coat
Equipment: buckets, cement spatula trowels, groovers, edgers,
planks, sponges, scaffolding, plaster spray
Skilled Workers: general workers (2), plasterers(3)
Technical information: The plaster layer is not more than half inches,
and left for drying about 7 days before the finishing is applied. The
surface of the rendering preferably wetted before application of
plastering. Rough surface plastering is usually used outdoor to resist
harsh weathering. Smooth surface plastering with pores and easily
defected characteristic is preferably used indoor.
42 | P a g e
Activity 3: Ground Floor Tiling (Grid 13- Grid 17)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s
square (1)
Skilled Worker: General worker (2)
Technical Information: Tiles are precisely measured according to the
application area of the building. This can help to save number of tiles
and as well able to maximize the applying area. The tile will be cut
into varies sizes and shapes to fit those with smaller surface area.
43 | P a g e
Week 44
Activity 1: second floor plastering (Grid 4-4b)
Duration: 14-21 days (interior and exterior)
Materials: cement plaster, skim coat
Equipment: buckets, cement spatula trowels, groovers, edgers,
planks, sponges, scaffolding, plaster spray
Skilled Workers: general workers (2), plasterers(3)
Technical information: The plaster layer is not more than half inches,
and left for drying about 7 days before the finishing is applied. The
first coating thickness is around 1/2 to 3/4 inches while the finishing
coat will be around 3/16 inches thick. The surface of the rendering
preferably wetted before application of plastering. Rough surface
plastering is usually used outdoor to resist harsh weathering. Smooth
surface plastering with pores and easily defected characteristic is
preferably used indoor.
44 | P a g e
Activity 2: Ground Floor Tiling (Grid 10-13)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s
square (1)
Skilled Worker: General worker (2)
Technical Information: Tiles are precisely measured according to the
application area of the building. This can help to save number of tiles
and as well able to maximize the applying area. The tile will be cut
into varies sizes and shapes to fit those with smaller surface area.
45 | P a g e
Week 45
Activity 1: Second floor plastering (Grid 4b-6)
Duration: 14-21 days (interior and exterior)
Materials: cement plaster, skim coat
Equipment: buckets, cement spatula trowels, groovers, edgers,
planks, sponges, scaffolding, plaster spray
Skilled Workers: general workers (2), plasterers(3)
Technical information: The plaster layer is not more than half inches,
and left for drying about 7 days before the finishing is applied. The
first coating thickness is around 1/2 to 3/4 inches while the finishing
coat will be around 3/16 inches thick. The surface of the rendering
preferably wetted before application of plastering. Rough surface
plastering is usually used outdoor to resist harsh weathering. Smooth
surface plastering with pores and easily defected characteristic is
preferably used indoor.
46 | P a g e
Activity 2: Ground Floor Tiling (Grid 8- Grid 10)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s
square (1)
Skilled Worker: General worker (2)
Technical Information: Tiles are precisely measured according to the
application area of the building. This can help to save number of tiles
and as well able to maximize the applying area. The tile will be cut
into varies sizes and shapes to fit those with smaller surface area.
47 | P a g e
Activity 3: First Floor Tiling (Grid 14-17)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s
square (1)
Skilled Worker: General worker (2)
Technical Information: Tiles are precisely measured according to the
application area of the building. This can help to save number of tiles
and as well able to maximize the applying area. The tile will be cut
into varies sizes and shapes to fit those with smaller surface area.
48 | P a g e
Week 46
Activity 1: First Floor Tiling (Grid 10-14)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s
square (1)
Skilled Worker: General worker (2)
Technical Information: Tiles are precisely measured according to the
application area of the building. This can help to save number of tiles
and as well able to maximize the applying area. The tile will be cut
into varies sizes and shapes to fit those with smaller surface area.
49 | P a g e
Week 47
Activity 1: First Floor Tiling (Grid 8-10)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s
square (1)
Skilled Worker: General worker (2)
Technical Information: Tiles are precisely measured according to the
application area of the building. This can help to save number of tiles
and as well able to maximize the applying area. The tile will be cut
into varies sizes and shapes to fit those with smaller surface area.
50 | P a g e
Activity 2 : Second Floor Tiling (Grid 10 – Grid 13)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s
square (1)
Skilled Worker: General worker (2)
Technical Information: Tiles are precisely measured according to the
application area of the building. This can help to save number of tiles
and as well able to maximize the applying area. The tile will be cut
into varies sizes and shapes to fit those with smaller surface area.
51 | P a g e
Week 48
Activity 1: Second Floor Tiling (Grid 8- Grid 10)
Duration: 14-21 days
Materials: Ceramic tiles, Cement mortar, Silicone sealant
Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s
square (1)
Skilled Worker: General worker (2)
Technical Information: Tiles are precisely measured according to the
application area of the building. This can help to save number of tiles
and as well able to maximize the applying area. The tile will be cut
into varies sizes and shapes to fit those with smaller surface area.
52 | P a g e
Week 49
Activity 1: Finishing – undercoat (Ground floor)
Duration: 21 days
Materials: Wall Sealer
Equipment: Edgers, groovers, screed plank, Paint brushes, Point
rollers
Skilled Worker: Painter (5)
Technical Information: Sealer is required to seal the holes, hairline
cracks of the walls. The walls are needed to seal to prevent the
drywall from absorbing the moisture and the paint. By applying a
layer of sealer, it gives the wall an adhesive base for the paint to stick
on firmly without having bubbling and waterborne stain.
Week 50:
Activity 1: Finishing – Undercoat (First floor)
Duration: 21 days
Materials: Wall Sealer
Equipment: Edgers, groovers,plank, Paint brushes, Point rollers
Skilled Worker: Painter (5)
Technical Information: Sealer is required to seal the holes, hairline
cracks of the walls. The walls are needed to seal to prevent the
drywall from absorbing the moisture and the paint. By applying a
layer of sealer, it gives the wall an adhesive base for the paint to stick
on firmly without having bubbling and waterborne stain.
Activity 2: Painting – Uppercoat (Ground floor)
Duration: 14 days
Materials: Paint
Equipment: Paint brush (3), Point roller (3)
Skilled Worker: Painter (5)
Technical Information: Painting for finishing should be done after the
plastering and undercoating are completely dried up to prevent
bubbling of the wall due to the moisture. Painting requires few layers
for better surface finishes.
53 | P a g e
Week 51
Activity 1: Finishing – Undercoat (Second floor)
Duration: 21 days
Materials: Wall Sealer
Equipment: Edgers, groovers,plank, Paint brushes, Point rollers
Skilled Worker: Painter (5)
Technical Information: Sealer is required to seal the holes, hairline
cracks of the walls. The walls are needed to seal to prevent the
drywall from absorbing the moisture and the paint. By applying a
layer of sealer, it gives the wall an adhesive base for the paint to stick
on firmly without having bubbling and waterborne stain.
Activity 2: Painting – First coat (First Floor)
Duration: 14 days
Materials: Paint
Equipment: Paint brush (3), Point roller (3)
Skilled Worker: Painter (5)
Technical Information: Painting for finishing should be done after the
plastering and undercoating are completely dried up to prevent
bubbling of the wall due to the moisture. Painting requires few layers
for better surface finishes.
54 | P a g e
Week 52
Activity 1: Painting – First coat (Second Floor)
Duration: 14 days
Materials: Paint
Equipment: Paint brush (3), Point roller (3)
Skilled Worker: Painter (5)
Technical Information: Painting for finishing should be done after the
plastering and undercoating are completely dried up to prevent
bubbling of the wall due to the moisture. Painting requires few layers
for better surface finishes.
55 | P a g e
Week 53
Activity 1: Doors, Windows and Screens installation
Durations: 10-14 days
Materials: precast aluminum window frames, doors, glass windows
panels, door frames, pre-manufactured wooden,wooden crossed
screen , screws, sealer
Equipment: Bolts and Nuts, Screwdriver and related toolkit.
Skilled worker: General worker (4)
Technical information: The doors and windows are then installed to
the walls, replacing the temporary frames and secured with screws
and sealer.
56 | P a g e
Week 54
Activity 1: Doors, Windows and Screens installation
Durations: 10-14 days (continued)
Materials: precast aluminum window frames, doors, glass windows
panels, door frames, pre-manufactured wooden,wooden crossed
screen , screws, sealer
Equipment: Bolts and Nuts, Screwdriver and related toolkit.
Skilled worker: General worker (4)
Technical information: The doors and windows are then installed to
the walls, replacing the temporary frames and secured with screws
and sealer. Prefabricated screen is secured with fixtures and nut onto
the walls.
Activity 2: Electrical & Sanitary fittings
Durations: 14 days
Materials: Wall sockets, Wall plugs and bathroom porcelain
appliances
Equipment: Bolts and Nuts, Screwdriver and related toolkit.
Skilled worker: General worker (4)
Technical information: Standard electrical appliances are then fixed
during the last phase.
57 | P a g e
Week 55
Activity 1: Pavings
Duration: 10-15 days
Materials: paving stones, bricks, Concrete Grade 30, reinforcements,
timber formworks,plank
Equipment: wheel barrow, Concrete Mixer(1), (1), table saw
Skilled Workers: general workers (4)
Technical information: Paving stones to be laid on the soil as
pavement of walkway, parking, and garden.
Week 56
Activity 1: Pavings
Duration: 10-15 days (continued)
Materials: paving stones, bricks, Concrete Grade 30, reinforcements,
timber formworks,plank
Equipment: wheel barrow, Concrete Mixer(1), (1), table saw
Skilled Workers: general workers (4)
Technical information: Paving stones to be laid on the soil as
pavement of walkway, parking, and garden.
Week 57
Activity 1: Grass turfing – External work
Duration: 7 days
Materials: lawn turf rolls (depends on the size of garden), bricks
Equipment: wheel barrow, gardening tool kits, water pipes
Skilled Workers: lawn turf layers(2), general workers (2)
Technical information: Soil preparation is done before laying the rolls
of grass turf on the soil surfaces. Excavated soil can be reused as the
base of the courtyard. Loose stones and building rubble will prevent
the turves roots from making contact with the soil and could make
the turf die in patches. The top soil should then be thoroughly
rotivated down to about the first 6 inches to aerate it properly. It is
then raked level and gently treaded down.

Contenu connexe

Tendances

Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction TechniquesDavid H Moloney
 
Shotcrete technology ppt.
Shotcrete technology ppt.Shotcrete technology ppt.
Shotcrete technology ppt.shivamsingh1111
 
Reinforced earth structures notes.pdf
Reinforced earth structures notes.pdfReinforced earth structures notes.pdf
Reinforced earth structures notes.pdfRamyaNarasimhan5
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGJAPJEETSINGH13
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential buildingShariful Haque Robin
 
Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building Self-employed
 
Equipments for erection and compaction
Equipments for erection and compactionEquipments for erection and compaction
Equipments for erection and compactionPrasanthi Nelloor
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering fieldswetha110
 
BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1Cryslyn Tan
 
Earth work equipment
Earth work equipmentEarth work equipment
Earth work equipmentswetha110
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTShankar Ramasamy
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction Mereia Kali
 
CONSTRUCTION EQUIPMENTS
CONSTRUCTION EQUIPMENTSCONSTRUCTION EQUIPMENTS
CONSTRUCTION EQUIPMENTSshalz_singh
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFShankar Ramasamy
 
BASICS OF CIVIL ENGINEERING
BASICS OF CIVIL ENGINEERINGBASICS OF CIVIL ENGINEERING
BASICS OF CIVIL ENGINEERINGajal jose
 

Tendances (20)

Civil Engineering Construction Techniques
Civil Engineering  Construction TechniquesCivil Engineering  Construction Techniques
Civil Engineering Construction Techniques
 
Shotcrete technology ppt.
Shotcrete technology ppt.Shotcrete technology ppt.
Shotcrete technology ppt.
 
Reinforced earth structures notes.pdf
Reinforced earth structures notes.pdfReinforced earth structures notes.pdf
Reinforced earth structures notes.pdf
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERING
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
 
Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building
 
Equipments for erection and compaction
Equipments for erection and compactionEquipments for erection and compaction
Equipments for erection and compaction
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering field
 
BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1BUILDING CONSTRUCTION PROJECT 1
BUILDING CONSTRUCTION PROJECT 1
 
Concrete equipment
Concrete equipmentConcrete equipment
Concrete equipment
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Earth work equipment
Earth work equipmentEarth work equipment
Earth work equipment
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Material approval procedure
Material approval procedureMaterial approval procedure
Material approval procedure
 
CONSTRUCTION EQUIPMENTS
CONSTRUCTION EQUIPMENTSCONSTRUCTION EQUIPMENTS
CONSTRUCTION EQUIPMENTS
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
 
BASICS OF CIVIL ENGINEERING
BASICS OF CIVIL ENGINEERINGBASICS OF CIVIL ENGINEERING
BASICS OF CIVIL ENGINEERING
 

Similaire à Construction Activities and Process

Bcon final report
Bcon final reportBcon final report
Bcon final reportQing Cheng
 
Building Construction 1 - Final Project
Building Construction 1 - Final ProjectBuilding Construction 1 - Final Project
Building Construction 1 - Final ProjectEvelyn Paul
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1Jing Chuang
 
Building Construction Project 2 Report
Building Construction Project 2 ReportBuilding Construction Project 2 Report
Building Construction Project 2 ReportappleManiac
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIPMkh Nantu
 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 finaldhanapal143
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel ProjectsKeith Kong
 
Building construction
Building constructionBuilding construction
Building constructionnhmurad
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingAnchit Agrawal
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement reportKailyn Lee
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and CostingGanesh Tatikonda
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdfDeepak37004
 
IRJET- Experimental Study of Concrete with Excavated Soil as a Fine Aggregate
IRJET- Experimental Study of Concrete with Excavated Soil as a Fine AggregateIRJET- Experimental Study of Concrete with Excavated Soil as a Fine Aggregate
IRJET- Experimental Study of Concrete with Excavated Soil as a Fine AggregateIRJET Journal
 
Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...Akshaya Selvam
 
Integrated site vite report
Integrated site vite reportIntegrated site vite report
Integrated site vite reportxennechau
 

Similaire à Construction Activities and Process (20)

Bcon final report
Bcon final reportBcon final report
Bcon final report
 
Building Construction 1 - Final Project
Building Construction 1 - Final ProjectBuilding Construction 1 - Final Project
Building Construction 1 - Final Project
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1
 
Building Construction Project 2 Report
Building Construction Project 2 ReportBuilding Construction Project 2 Report
Building Construction Project 2 Report
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 
Geotechnical Investigation
Geotechnical InvestigationGeotechnical Investigation
Geotechnical Investigation
 
Major Project ppt
Major Project ppt Major Project ppt
Major Project ppt
 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 final
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel Projects
 
Site report 1
Site report 1Site report 1
Site report 1
 
Building construction
Building constructionBuilding construction
Building construction
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and Costing
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdf
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
IRJET- Experimental Study of Concrete with Excavated Soil as a Fine Aggregate
IRJET- Experimental Study of Concrete with Excavated Soil as a Fine AggregateIRJET- Experimental Study of Concrete with Excavated Soil as a Fine Aggregate
IRJET- Experimental Study of Concrete with Excavated Soil as a Fine Aggregate
 
Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...
 
Integrated site vite report
Integrated site vite reportIntegrated site vite report
Integrated site vite report
 
Ece part 1
Ece part 1Ece part 1
Ece part 1
 

Plus de J.j. Hayashi

Building service project1
Building service project1Building service project1
Building service project1J.j. Hayashi
 
Aa Presentation slides
Aa Presentation slides Aa Presentation slides
Aa Presentation slides J.j. Hayashi
 
Vernacular as a model for contemporary design
Vernacular as a model for contemporary designVernacular as a model for contemporary design
Vernacular as a model for contemporary designJ.j. Hayashi
 
Jj bstructure individual
Jj bstructure individual Jj bstructure individual
Jj bstructure individual J.j. Hayashi
 
bstructureproject2-150706142716-lva1-app6892.pdf
bstructureproject2-150706142716-lva1-app6892.pdfbstructureproject2-150706142716-lva1-app6892.pdf
bstructureproject2-150706142716-lva1-app6892.pdfJ.j. Hayashi
 
Bstructure project2
Bstructure project2 Bstructure project2
Bstructure project2 J.j. Hayashi
 
Building structuresproject1 fettuccinnefinalm
Building structuresproject1 fettuccinnefinalmBuilding structuresproject1 fettuccinnefinalm
Building structuresproject1 fettuccinnefinalmJ.j. Hayashi
 
Hypatia - Invisible Cities
Hypatia - Invisible CitiesHypatia - Invisible Cities
Hypatia - Invisible CitiesJ.j. Hayashi
 
Site analysis at Kuala Selangor-Lake
Site analysis at Kuala Selangor-LakeSite analysis at Kuala Selangor-Lake
Site analysis at Kuala Selangor-LakeJ.j. Hayashi
 
Final history report
Final history reportFinal history report
Final history reportJ.j. Hayashi
 

Plus de J.j. Hayashi (13)

Building service project1
Building service project1Building service project1
Building service project1
 
Aa Presentation slides
Aa Presentation slides Aa Presentation slides
Aa Presentation slides
 
Vernacular as a model for contemporary design
Vernacular as a model for contemporary designVernacular as a model for contemporary design
Vernacular as a model for contemporary design
 
Jj bstructure individual
Jj bstructure individual Jj bstructure individual
Jj bstructure individual
 
bstructureproject2-150706142716-lva1-app6892.pdf
bstructureproject2-150706142716-lva1-app6892.pdfbstructureproject2-150706142716-lva1-app6892.pdf
bstructureproject2-150706142716-lva1-app6892.pdf
 
Bstructure project2
Bstructure project2 Bstructure project2
Bstructure project2
 
Building structuresproject1 fettuccinnefinalm
Building structuresproject1 fettuccinnefinalmBuilding structuresproject1 fettuccinnefinalm
Building structuresproject1 fettuccinnefinalm
 
Hypatia - Invisible Cities
Hypatia - Invisible CitiesHypatia - Invisible Cities
Hypatia - Invisible Cities
 
ESD
ESD ESD
ESD
 
Reflective essay
Reflective essayReflective essay
Reflective essay
 
ESD Report
ESD ReportESD Report
ESD Report
 
Site analysis at Kuala Selangor-Lake
Site analysis at Kuala Selangor-LakeSite analysis at Kuala Selangor-Lake
Site analysis at Kuala Selangor-Lake
 
Final history report
Final history reportFinal history report
Final history report
 

Dernier

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 

Dernier (20)

Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 

Construction Activities and Process

  • 1. BUILDING CONSTRUCTION 1 CONSTRUCTION ACTIVITIES AND PROCESS TUTORS: MR. LEE XIA SHENG AR. CHIN TUCK HING, MS. SUJA LIM JIAN JUN 0316867
  • 2. 1 | P a g e Site preparation Survey work 1 week setting out 1 week Earthwork 1-2 weeks Foundation Pile 3 weeks pile cap 2 weeks Stump 2 weeks Ground Beam 2 weeks Ground Floor Slab 2 weeks Column 2 weeks Beam 2 weeks Staircase 2 weeks wall 2 weeks plastering 2 weeks First Floor Slab 2 weeks Column 2 weeks Beam 2 weeks Staircase 2 weeks wall 2 weeks plastering 2 weeks Second Floor Slab 2 weeks Column 2 weeks Beam 2 weeks Staircase 2 weeks wall 2 weeks plastering 2 weeks Roof Slab Utility Electrical Supply 1 week Water Supply 1 week Door and Windows Total: 2 week Finishes 1st floor Kitchen Plumbing 1 week Plastering interiors 1st floor 2 week Plastering Interiors 2nd floor 1 week Skidding floors Painting - first coat 2 week Painting - second coat 2 week Sanitary fitting of bathroom and kitchen 1 week Electrical fitting 1 week Total 57 week
  • 3. 2 | P a g e WEEK 1 Activity 1: Site survey Duration: 7 days Materials: - Equipment:- Skilled Workers: Backhoe Loader Operator(1), General workers(4), Lorry driver(1) Technical Information: Analysis is done to the construction site by surveyor and further planning and advices to the site for construction preparation and development. Activity 2: Mobilization Duration: 2-3 days Materials: Machineries Equipment: Lorries(2), mobile crane(1), backhoe loaders(1), Hydraulic Piling Hammer(1), excavator(1), compactor (1), boring machine(1) Skilled Workers: lorry drivers(2), excavator operator(1), backhoe loader operator(1), Hydraulic Piling Hammer operator(1), compactor operators (1), boring machine operator(1) Technical Information: Machineries required is delivered to the site and wait for job to be executed. Activity 3: Site Clearing Duration: 7 days Materials: - Equipment: Backhoe Loader, chainsaw, lorry truck (carry earth & plants away) Skilled Workers: Backhoe Loader Operator(1), General workers(4), Lorry driver(1) Technical Information: Excavation of unfavorable soil and substances such as stones and tree barks. Initial leveling is done for the preparation of earthwork.
  • 4. 3 | P a g e WEEK 2 Activity 1: Hoarding (setting out), staking (plan boundary) Duration: 5 days Materials: blue metal decks, nails, wooden pegs, planks, stakes, Builder’s line Equipment: hammer, measuring tape, theodolite, Dummy level, construction sign board Skilled Workers: quantity surveyor (2), general workers (4) Technical Information: Boundary of the construction site is precisely measured and borders the site where the construction takes place. The site is marked with gridlines with a setback of 20 feet from the road and 10 feet for the porch according to UBBL and the location of the pile is marked. Activity 2: Earthwork Duration: 7 days Materials: - Equipment: excavator, compactor Skilled Workers: Excavator Operator (1), Compactor Operator (1) Technical Information: Removal of top soil and land leveling. The land is excavated to around 300mm of the top soil. Keep away or stored well for reuse due to its high water retentive characteristic.
  • 5. 4 | P a g e WEEK 3 Activity 1: Earthwork (continued) Duration: 7 days (continued from last week) Materials: - Equipment: excavator, compactor Skilled Workers: Excavator Operator (1), Compactor Operator (1) Technical information: Removal of top soil and land leveling. The land is excavated to around 300mm of the top soil. Keep away or stored well for reuse due to its high water retentive characteristic Activity 2: Piling (Grid 13- Grid 15) Duration: 10-14 days Materials: Reinforced concrete piles, Concrete Grade 30, Reinforcement, wooden formworks Equipment: Hydraulic Piling Hammer(1), Rebar Bending machine(1), Boring Machine(1), cement concrete mixer (1), hacker (1) Skilled Workers: Hydraulic Piling Hammer Operator (1), Boring Machine Operator (1), Rebar Bender (1), General construction workers (6) Technical Information: The depth/length of the piles is depending on the soil condition based on the soil test, after that the engineers will decide the pile length to fit the soil condition of the site, based on the result of the test. Difference in height of the piles will be cut below cap using hacker. The rebar connected to the piles are then removed and left for the joining of capping reinforcement. Soil specimen is taken for soil test experiment to determine the length of the pile. The pile integrity test (Load test) is done to determine the strength to support the load.
  • 6. 5 | P a g e Week 4 Activity 1: Piling (Grid 8 - Grid 12) Duration: 10-14 days Materials: Reinforced concrete piles, Concrete Grade 30, Reinforcement, wooden formworks Equipment: Hydraulic Piling Hammer(1), Rebar Bending machine(1), Boring Machine(1), cement concrete mixer (1) Skilled Workers: Hydraulic Piling Hammer Operator (1), Boring Machine Operator (1), Rebar Bender (1), General construction workers (6) Technical Information: The depth/length of the piles is depending on the soil condition based on the soil test, after that the engineers will decide the pile length to fit the soil condition of the site, based on the result of the test. Difference in height of the piles will be cut below cap using hacker. The rebar connected to the piles are then removed and left for the joining of capping reinforcement. Soil specimen is taken for soil test experiment to determine the length of the pile. The pile integrity test (Load test) is done to determine the strength to support the load.
  • 7. 6 | P a g e Week 5 Activity 1: Leveling of Piles before capping Duration: 3 days Materials: Reinforced concrete piles, Concrete Grade 30, Reinforcement, wooden formworks Equipment: Hydraulic Piling Hammer(1), Rebar Bending machine(1), Boring Machine(1), cement concrete mixer (1) Skilled Workers: Hydraulic Piling Hammer Operator (1), Boring Machine Operator (1), Rebar Bender (1), General construction workers (6) Technical Information: When the piling is penetrated into the soil, the piles are in different height. The piles need to be cut before cap by using hacker. The rebar are removed and then the capping reinforcement are applied. Activity 2: Pile capping Duration: 7 -14 days Materials: Reinforced concrete piles, Concrete Grade 30, Reinforcement, wooden formworks Equipment: Hydraulic Piling Hammer(1), Rebar Bending machine(1), Boring Machine(1), cement concrete mixer (1) Skilled Workers: Hydraulic Piling Hammer Operator (1), Boring Machine Operator (1), Rebar Bender (1), General construction workers (6) Technical Information: pile caps takes around 2 weeks to reach its maximum strength, but usually it can be done after it is left curing for about a week. Stumping can be constructed around that time.
  • 8. 7 | P a g e Week 6 Activity 1: Stump from Pile caps Duration:7 days-14 days Materials: Concrete Grade 30, reinforcements, timber formworks. Equipment: Concrete Vibrator(1), Rebar bending machine(1), tablesaw(1) Skilled Workers: Land Surveyor (1), Carpenter(2), Bar Bender (1), General worker (2) Technical Information: After pilings , the land surveyor will identity of the height required of the stumps and thereafter construct the stumps based on the data. Steel rebar are bent into cage form, with starter bar protruding upward to connect for latter construction of columns. Constructed the same way as the pile capping, the stumps are left for curing in order to achieve its required structural strength before the construction of the beams. It is left to cure for a week.
  • 9. 8 | P a g e WEEK 7 Activity 1: Ground Beam (Grid 13-Grid 17) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical information: Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting form and left for curing around a week time.
  • 10. 9 | P a g e WEEK 8 Activity 1: Ground Beam (Grid 8-Grid 13) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical information: Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting form and left for curing around a week time.
  • 11. 10 | P a g e Week 9 Activity 1: Ground floor slab (grid 12- grid 17) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beam, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting form and left for curing around a week time. DPM is laid on the concrete and screeded with long even plank.
  • 12. 11 | P a g e Week 10 Activity 1: Ground floor slab (grid 8 - 12 ,continued from the first ) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beam, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting form and left for curing around a week time. DPM is laid on the concrete and screeded with long even plank.
  • 13. 12 | P a g e Week 11 Activity 1: Ground Floor Columns (Grid 12 – Grid 15) Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: Same as the construction of beams, the formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time.
  • 14. 13 | P a g e Week 12 Activity 1: Ground Floor Columns (Grid 8-Grid 11) Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: Same as the construction of beams, the formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. Activity 2: First Floor Beam (Grid 12- Grid 17) , first half Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: The formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time.
  • 15. 14 | P a g e Week 13 Activity 2: First Floor Beam (Grid 8 - Grid 12) , second half Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: The formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time.
  • 16. 15 | P a g e Week 14 Activity 1: First Floor Slab (Grid 13-grid 17) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beams, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting, screeded with plank and then left for curing around a week time. A layer of protection is laid on top of the concrete during curing.
  • 17. 16 | P a g e Week 15 Activity 1: First Floor Slab ( second half floor) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beams, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting, screeded with plank and then left for curing around a week time. A layer of protection is laid on top of the concrete during curing.
  • 18. 17 | P a g e Week 16 Activity 1: first floor column (grid 12-grid 17), first half Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: Same as the construction of beams, the formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. Activity 2: Ground Floor Staircase (to level 1) Duration: 8-14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), spirit level. Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3) Technical Information: The formworks of the stairs is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. A concrete test is taken to check the strength of the casting after it was left to cure for a week.
  • 19. 18 | P a g e Week 17 Activity 1: first floor column (grid 8-grid 12), second half Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: Same as the construction of beams, the formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. Activity 2: Second Floor Beam (Grid 12- Grid 17) , first half Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: The formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. Activity 3: Ground Floor Staircase (to level 1, continued) Duration: 8-14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), spirit level. Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3) Technical Information: The formworks of the stairs is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. A concrete test is taken to check the strength of the casting after it was left to cure for a week.
  • 20. 19 | P a g e Week 18 Activity 1: Second Floor Beam (Grid 8- Grid 12) , second half Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: The formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time.
  • 21. 20 | P a g e Week 19 Activity 1: Second Floor Slab (first half) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beams, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting, screeded with plank and then left for curing around a week time. A layer of protection is laid on top of the concrete during curing.
  • 22. 21 | P a g e Week 20 Activity 1: Second Floor Slab (second half) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beams, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting, screeded with plank and then left for curing around a week time. A layer of protection is laid on top of the concrete during curing.
  • 23. 22 | P a g e Week 21 Activity 1: Second floor column (grid 8-grid 13) Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: Same as the construction of beams, the formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. Activity 2: First Floor Staircase (to level 2) Duration: 8-14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), spirit level. Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3) Technical Information: The formworks of the stairs is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time. A concrete test is taken to check the strength of the casting after it was left to cure for a week.
  • 24. 23 | P a g e Week 22 Activity 1: Roof floor Beams (Grid 8- Grid 13) , All floor Duration: 14 Days Materials: Concrete Grade 30, reinforcement, timber formwork Equipment: Concrete Mixer(1), Concrete vibrator (1) , bar bending machine (1), table saw Skilled worker: Carpenter (2) , bar bender (2), general worker (4) Technical information: The formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pouring into the casting form and left for curing around a week time.
  • 25. 24 | P a g e Week 23 Activity 1: third floor Slab (all floor) Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beams, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting, screeded with plank and then left for curing around a week time. A layer of protection is laid on top of the concrete during curing.
  • 26. 25 | P a g e WEEK 24 Activity 1: brickwalls Ground Level (Grid 3- 4) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.
  • 27. 26 | P a g e WEEK 25 Activity 1: brickwalls Ground Level (Grid 4-5) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.
  • 28. 27 | P a g e Week 26 Activity 1: brickwalls Ground Level (Grid 5-6) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.
  • 29. 28 | P a g e Week 27 Activity 1: Brickwall First Level (Grid 3-4) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.
  • 30. 29 | P a g e Week 28 Activity 1: Brickwall First Level (Grid 4-5) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.
  • 31. 30 | P a g e Week 29 Activity 1: Brickwall First Level (Grid 4-5) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.
  • 32. 31 | P a g e Week 30 Activity 1: Brickwall Second Level (Grid 3-4a) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.
  • 33. 32 | P a g e Week 31 Activity 1: Brickwall Second Level (Grid 4a-5) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls.
  • 34. 33 | P a g e Week 32 Activity 1: Brickwall Second Level (Grid 13 -17) Duration: 15-20 days Materials: 100mmx 215mmx 75mm Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5) Skilled Workers: General Workers (6) Technical Information: Builder’s line is used to alight the walls during stacking of bricks and construction of the wall. The clay bricks are bonded with mortar and stack together with specific bonding pattern. Wire mesh is laid on the bricks in certain layer interval as reinforcement and stiffer will be constructed between walls to strengthen the walls. Activitity 2: Façade roof slab Duration: 14 days Materials: Concrete Grade 30, reinforcements, timber formworks, Damp Proof Membrane (DPM), Rigid Floor Insulation, screed plank Equipment: Concrete Vibrator(1), Rebar bending machine(1), table saw(1), concrete mixer(1), Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (3) Technical Information: The Ground slab is cast after beam, the workers can proceed to next construction during curing time. Formworks is constructed with steel rebar reinforcement and starter bar. Thereafter a mixture of concrete with aggregates and cement is then pour into the casting form and left for curing around a week time. DPM is laid on the concrete and screeded with long even plank.
  • 35. 34 | P a g e Week 33 Activity 1: Framing (ground floor) Durations: 7 days Materials: Openings wooden frame (for door and windows) Equipment: Spirit level, Measuring tape Skilled Workers: General Workers (4) Technical Information: The opening frames are constructed in position and align after the brick wall is done. Architrave is added after the door/window frame is added. Activity 2: Incoming Electrical Circuit Supply Installation Duration: 10-14 days Materials: Copper Cables (different sizes), Kilowatt hour meter Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Skilled Workers: Electric Technician (2), Plumbers (2) Technical Information: Incoming electricity cables are brought into the house and connected to a circuit box in the house to facilitate the plumbing works later on. Week 34 Activity 1: Framing (First floor) Durations: 7 days Materials: Openings wooden frame (for door and windows) Equipment: Spirit level, Measuring tape Skilled Workers: General Workers (4) Technical Information: The opening frames are constructed in position and align after the brick wall is done. Architrave is added after the door/window frame is added. Activity 2: Incoming Electrical Circuit Supply Installation Duration: 10-14 days (continued) Materials: Copper Cables (different sizes), Kilowatt hour meter Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Skilled Workers: Electric Technician (2), Plumbers (2) Technical Information: Incoming electricity cables are brought into the house and connected to a circuit box in the house to facilitate the plumbing works later on.
  • 36. 35 | P a g e Week 35 Activity 1: Framing (Second floor) Durations: 7 days Materials: Openings wooden frame (for door and windows) Equipment: Spirit level, Measuring tape Skilled Workers: General Workers (4) Technical Information: The opening frames are constructed in position and align after the brick wall is done. Architrave is added after the door/window frame is added. Activity 2: Ground Floor Plumbing (First Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electricians(2), Plumbers (2) Technical Information: Technicians will determine the location of the sockets according to the engineering blue print. The brick wall is hacked to accommodate the wiring pipe from the top to the ground according UBBL requirements. The wall sockets will be installed after the wiring is done.
  • 37. 36 | P a g e Week 36 Activity 1: First Floor Plumbing (First Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electricians(2), Plumbers (2) Technical Information: Technicians will determine the location of the sockets according to the engineering blue print. The brick wall is hacked to accommodate the wiring pipe from the top to the ground according UBBL requirements. The wall sockets will be installed after the wiring is done. Week 37 Activity 1: First Floor Plumbing (First Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electricians(2), Plumbers (2) Technical Information: Technicians will determine the location of the sockets according to the engineering blue print. The brick wall is hacked to accommodate the wiring pipe from the top to the ground according UBBL requirements. The wall sockets will be installed after the wiring is done. Activity 2: Second Floor Plumbing (First Fix) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electricians(2), Plumbers (2) Technical Information: Technicians will determine the location of the sockets according to the engineering blue print. The brick wall is hacked to accommodate the wiring pipe from the top to the ground according UBBL requirements. The wall sockets will be installed after the wiring is done. Activity 3: Plumbing (Sanitary and Kitchen) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electricians(2), Plumbers (2) Technical Information: Technicians will determine the location of the sockets according to the engineering blue print. The brick wall is hacked to accommodate the wiring pipe from the top to the ground according UBBL requirements. The wall sockets will be installed after the wiring is done.
  • 38. 37 | P a g e Week 38 Activity 1: Plumbing (Sanitary and Kitchen) Duration: 14 days Materials: Copper Cables (different sizes), PVC pipes, socket box Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine Skilled Workers: Electricians(2), Plumbers (2) Technical Information: Technicians will determine the location of the sockets according to the engineering blue print. The brick wall is hacked to accommodate the wiring pipe from the top to the ground according UBBL requirements. The wall sockets will be installed after the wiring is done. Week 39 Activity 1: Ground floor Wall Plastering (Grid 1-Grid 3) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The first coating thickness is around 1/2 to 3/4 inches while the finishing coat will be around 3/16 inches thick. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.
  • 39. 38 | P a g e Week 40 Activity 1: Ground floor wall plastering (Grid 4-4a) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The first coating thickness is around 1/2 to 3/4 inches while the finishing coat will be around 3/16 inches thick. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.
  • 40. 39 | P a g e Week 41 Activity 1: Ground floor plastering (Grid 4a-6) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The first coating thickness is around 1/2 to 3/4 inches while the finishing coat will be around 3/16 inches thick. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor. Activity 2: First floor plastering (Grid 1- Grid 4) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.
  • 41. 40 | P a g e Week 42 Activity 1: First floor plastering (Grid 4- Grid 4a) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The first coating thickness is around 1/2 to 3/4 inches while the finishing coat will be around 3/16 inches thick. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.
  • 42. 41 | P a g e Week 43 Activity 1: First floor plastering (Grid 4a-6) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor. Activity 2: Second floor plastering (Grid 1-Grid 4) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.
  • 43. 42 | P a g e Activity 3: Ground Floor Tiling (Grid 13- Grid 17) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.
  • 44. 43 | P a g e Week 44 Activity 1: second floor plastering (Grid 4-4b) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The first coating thickness is around 1/2 to 3/4 inches while the finishing coat will be around 3/16 inches thick. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.
  • 45. 44 | P a g e Activity 2: Ground Floor Tiling (Grid 10-13) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.
  • 46. 45 | P a g e Week 45 Activity 1: Second floor plastering (Grid 4b-6) Duration: 14-21 days (interior and exterior) Materials: cement plaster, skim coat Equipment: buckets, cement spatula trowels, groovers, edgers, planks, sponges, scaffolding, plaster spray Skilled Workers: general workers (2), plasterers(3) Technical information: The plaster layer is not more than half inches, and left for drying about 7 days before the finishing is applied. The first coating thickness is around 1/2 to 3/4 inches while the finishing coat will be around 3/16 inches thick. The surface of the rendering preferably wetted before application of plastering. Rough surface plastering is usually used outdoor to resist harsh weathering. Smooth surface plastering with pores and easily defected characteristic is preferably used indoor.
  • 47. 46 | P a g e Activity 2: Ground Floor Tiling (Grid 8- Grid 10) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.
  • 48. 47 | P a g e Activity 3: First Floor Tiling (Grid 14-17) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.
  • 49. 48 | P a g e Week 46 Activity 1: First Floor Tiling (Grid 10-14) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.
  • 50. 49 | P a g e Week 47 Activity 1: First Floor Tiling (Grid 8-10) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.
  • 51. 50 | P a g e Activity 2 : Second Floor Tiling (Grid 10 – Grid 13) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.
  • 52. 51 | P a g e Week 48 Activity 1: Second Floor Tiling (Grid 8- Grid 10) Duration: 14-21 days Materials: Ceramic tiles, Cement mortar, Silicone sealant Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1) Skilled Worker: General worker (2) Technical Information: Tiles are precisely measured according to the application area of the building. This can help to save number of tiles and as well able to maximize the applying area. The tile will be cut into varies sizes and shapes to fit those with smaller surface area.
  • 53. 52 | P a g e Week 49 Activity 1: Finishing – undercoat (Ground floor) Duration: 21 days Materials: Wall Sealer Equipment: Edgers, groovers, screed plank, Paint brushes, Point rollers Skilled Worker: Painter (5) Technical Information: Sealer is required to seal the holes, hairline cracks of the walls. The walls are needed to seal to prevent the drywall from absorbing the moisture and the paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain. Week 50: Activity 1: Finishing – Undercoat (First floor) Duration: 21 days Materials: Wall Sealer Equipment: Edgers, groovers,plank, Paint brushes, Point rollers Skilled Worker: Painter (5) Technical Information: Sealer is required to seal the holes, hairline cracks of the walls. The walls are needed to seal to prevent the drywall from absorbing the moisture and the paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain. Activity 2: Painting – Uppercoat (Ground floor) Duration: 14 days Materials: Paint Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Painting for finishing should be done after the plastering and undercoating are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few layers for better surface finishes.
  • 54. 53 | P a g e Week 51 Activity 1: Finishing – Undercoat (Second floor) Duration: 21 days Materials: Wall Sealer Equipment: Edgers, groovers,plank, Paint brushes, Point rollers Skilled Worker: Painter (5) Technical Information: Sealer is required to seal the holes, hairline cracks of the walls. The walls are needed to seal to prevent the drywall from absorbing the moisture and the paint. By applying a layer of sealer, it gives the wall an adhesive base for the paint to stick on firmly without having bubbling and waterborne stain. Activity 2: Painting – First coat (First Floor) Duration: 14 days Materials: Paint Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Painting for finishing should be done after the plastering and undercoating are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few layers for better surface finishes.
  • 55. 54 | P a g e Week 52 Activity 1: Painting – First coat (Second Floor) Duration: 14 days Materials: Paint Equipment: Paint brush (3), Point roller (3) Skilled Worker: Painter (5) Technical Information: Painting for finishing should be done after the plastering and undercoating are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few layers for better surface finishes.
  • 56. 55 | P a g e Week 53 Activity 1: Doors, Windows and Screens installation Durations: 10-14 days Materials: precast aluminum window frames, doors, glass windows panels, door frames, pre-manufactured wooden,wooden crossed screen , screws, sealer Equipment: Bolts and Nuts, Screwdriver and related toolkit. Skilled worker: General worker (4) Technical information: The doors and windows are then installed to the walls, replacing the temporary frames and secured with screws and sealer.
  • 57. 56 | P a g e Week 54 Activity 1: Doors, Windows and Screens installation Durations: 10-14 days (continued) Materials: precast aluminum window frames, doors, glass windows panels, door frames, pre-manufactured wooden,wooden crossed screen , screws, sealer Equipment: Bolts and Nuts, Screwdriver and related toolkit. Skilled worker: General worker (4) Technical information: The doors and windows are then installed to the walls, replacing the temporary frames and secured with screws and sealer. Prefabricated screen is secured with fixtures and nut onto the walls. Activity 2: Electrical & Sanitary fittings Durations: 14 days Materials: Wall sockets, Wall plugs and bathroom porcelain appliances Equipment: Bolts and Nuts, Screwdriver and related toolkit. Skilled worker: General worker (4) Technical information: Standard electrical appliances are then fixed during the last phase.
  • 58. 57 | P a g e Week 55 Activity 1: Pavings Duration: 10-15 days Materials: paving stones, bricks, Concrete Grade 30, reinforcements, timber formworks,plank Equipment: wheel barrow, Concrete Mixer(1), (1), table saw Skilled Workers: general workers (4) Technical information: Paving stones to be laid on the soil as pavement of walkway, parking, and garden. Week 56 Activity 1: Pavings Duration: 10-15 days (continued) Materials: paving stones, bricks, Concrete Grade 30, reinforcements, timber formworks,plank Equipment: wheel barrow, Concrete Mixer(1), (1), table saw Skilled Workers: general workers (4) Technical information: Paving stones to be laid on the soil as pavement of walkway, parking, and garden. Week 57 Activity 1: Grass turfing – External work Duration: 7 days Materials: lawn turf rolls (depends on the size of garden), bricks Equipment: wheel barrow, gardening tool kits, water pipes Skilled Workers: lawn turf layers(2), general workers (2) Technical information: Soil preparation is done before laying the rolls of grass turf on the soil surfaces. Excavated soil can be reused as the base of the courtyard. Loose stones and building rubble will prevent the turves roots from making contact with the soil and could make the turf die in patches. The top soil should then be thoroughly rotivated down to about the first 6 inches to aerate it properly. It is then raked level and gently treaded down.