SlideShare une entreprise Scribd logo
1  sur  25
61T01411 – Project Execution Plan for Valeo Foshan New Facility Project
Valeo
Tebodin
Jul 22, 2014
Agenda
page 2
Agenda:
•PEP project Execution Plan
•Procurement Plan
•Master Schedule
•Engineering Status
page 3
Index
Project Execution Plan
 Project Organization
 Project Schedule (milestone)
 Communication and Interface Management
 Engineering Management
 Construction Management
 HSSE
 Quality Management
 Project Control
page 4
Project Team Organization Chart (Sample)
Project Schedule (milestones) Vs Progress
▪ Time Schedule
▪ Engineering Phase: 23 weeks
▪ Conceptual Design: 7 weeks; (4.29~6.20)
▪ Conceptual Design Review/Approval/optimizing: 2 weeks; (6.10~7.3)
▪ Detail Design Phase 1: (for exiting building refurbishment) 7 weeks; (6.19~7.24)
▪ Detail Design Phase 2: 5 weeks; (7.24~8.28)
▪ Detail Design Review/Approval/Audit: 2 weeks; (8.28 ~9.18)
▪ Procurement Phase:
▪ Phase 1: (for exiting building refurbishment) 4 weeks; (7.3~7.23)
▪ Phase 2: (for new buildings and utilities) 4 weeks; (9.1~9.25)
▪ Construction Phase: 5 months. (7.31~12.31)
page 5
page 6
Key Activities- Interface Management
• Interface with Authorities and third parts
• Interface with GC Contractor/suppliers
• Interface with operation Team
• Interface with Project Management Team
• Interface with Land Lord
Communication Management
page 7
2 Project Management for EPC phase
Communication Management
Tools - Interface Management :
▪ Role and Responsibility Matrix
▪ Action List
▪ Master Schedule
▪ Permitting matrix
▪ Technical Interface Schedule
▪ Turnaround Plan
page 8
Meeting and Reporting
1. Tebodin to Borouge
• Weekly Report
• Weekly Contract and Manning report
• Monthly Status report
2. GC Contractor to PM team
• Project Kick off Meetings
• Weekly Coordination Meeting and Report
• Monthly Progress Report –
Communication Management
page 9
Data Transfer Systems
 Implement Borouge Document System
1. Numbering/Naming of Documents
2. Filling of Documents
3. Distribution of Documents
4. Documents templates
Audit Document System of GC
Review JianLi Technical Document System
Communication Management
page 10
1. The design manager and team will transfer the Conceptual phase design and
requirements to the detailed design through gate review of EPC’s design.
2. Supervise the detail design at progress of 30%, 60% & 90% and final. Including activities:
• Review of Vendor Design
• Review of Documents and Records
• Safety Engineering
• Local Laws and Regulations
• Design Continuity Management
• Technical Interface Management
3. All information and data shall be documented amount interface boundaries through
design, procurement, construction and commissioning phase of project
Engineering Management
page 11
1. Construction Planning
• Temporary facilities plan
• Site logistic and access control plan
• Shut down and turnaround plan
• Staff personnel and security force
• Construction Schedule
• Construction Execution Plan
2. Construction Execution
• Implement quality control program
• Interface with Jian Li
• Implement design change and variation order approval procedure
• Co-ordinate daily construction activities
• Site quality inspection and testing
• Organize meetings and report a regular basis
• Ensure good housekeeping
• Conduct Health, Safety and Environmental Protection inspections and audits on site
• Manage EPC contractors work to be acceptance by authority.
• Plan and execute Project handover
Construction Management
page 12
HSSE Management
HSSE Management
Manage and monitor EPC execution, including:
• Organize Health Security & Safety Policy
• Action and Resources
• Compliance with Laws and Regulations
• Training
• Control of HSSE Document
• HSSE audit and Management Review
Key Safety Risks – listed but not limited
• Material and warehousing is narrow on site
• Tie-in impact to the existing production
• Separation fence (for both external and internal work)
• Pipe-line protection
• Underground pipeline protection
• Crane Work
• Fire Protection on construction site
• Fall down Protection on construction site
• Edge Protection
• Rubbish and Pollution control
• Dust protection
• Site Security and Access control
• Plant fire Loop blocked and lost function
page 13
HSSE Management
page 14
Quality Management
The Quality Control Manager will implement quality procedures and will conduct regular inspect and
audit, including activities:
QA (Quality Assurance)
• Tebodin TQS as Guideline (Tebodin Quality System)
• Project Quality Plan
• Manage Jianli (Local Quality Supervision Company)
QC( Quality Control):
• Design quality control
• Procurement quality control
• Construction quality control
• Document quality control
page 15
Project Progress Control
Progress Control
 Milestone Summary Schedule (Level 1)
 EPC Level Schedule (Level 2)
• Permitting schedule
• Procurement Schedule
• Construction Schedule
• Long Lead items
• T&C schedules
• Start-up schedules
 Detailed Construction Schedule (Level 3)
 Weekly Working Plan
page 16
Project Cost Control
Cost Control
 EPC Cost Baseline
 Log changes
 Change Order Control
 Monitor Deviation
 Action and Forecast
Area of Concerns
1. Permitting
2. Interface of Landlord
page 17
Questions
▪ Any questions?
page 18
always close
page 20
2.3 Information and Document Content
Meeting Management
Meeting Schedule
frequency for each meeting is described as below:
 Project and program control meeting – once a week
 Design coordination meeting – once a week
 Site construction meeting – once a week
 Site safety meeting – once a week
 Procurement meeting – once a month
 Change control meeting - once bi-week
page 21
2.1 Information and Document Content
Meeting Management
General
o Agenda
o Request
o Meeting schedule
o Meeting minutes
o Distribution matrix
Pre-construction Meetings
Construction stage meetings
page 22
2.1 Information and Document Content
Technical Report
 Internal review
 Client for approval
Project Weekly Report
 EHS,
 Engineering
 Quality,
 Procurement
 Cost control
 Schedule and Progress
 Risk
 Site photos
Note:
Submission date on each Monday for last week
page 23
2.1 Information and Document Content
Project Monthly Report
 EHS,
 Engineering
 Quality,
 Procurement
 Cost control
 Schedule and Progress
 Risk
 Site photos
Note:
Submission date within 1st week of next month.
Cut date is end of current.
page 24
3. Procurement Management
Bidder Long List Preparation
Pre-qualification
Bidder short list
Preparation of inquiry
Bidding
Bid Clarifications
Evaluation Team Set Up
Bid Evaluation
Authorization to Order
Expediting
Critical Equipment / Critical Delivery Time
Vendor Documents
Inspection
Project Procurement Report
Payment Control
1.Bidding
page 25

Contenu connexe

Tendances

Johnson controls case study consultancy
Johnson controls case study   consultancyJohnson controls case study   consultancy
Johnson controls case study consultancygrahamelanders
 
Johnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project ManagementJohnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project Managementgrahamelanders
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projectsmtingle
 
Summer Student Presentation 2016 Charlie Morgan
Summer Student Presentation 2016 Charlie MorganSummer Student Presentation 2016 Charlie Morgan
Summer Student Presentation 2016 Charlie MorganCharlie Morgan
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2Jerry Bauers
 
Project Management Class ( based on PMBOK) - Day 5
Project Management Class ( based on PMBOK) - Day 5Project Management Class ( based on PMBOK) - Day 5
Project Management Class ( based on PMBOK) - Day 5Highmark Health
 
Basement remodel rev eh
Basement remodel rev ehBasement remodel rev eh
Basement remodel rev ehesands2437
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendationsubk1411
 
BEXEL Manager - Estudo de caso
BEXEL Manager - Estudo de casoBEXEL Manager - Estudo de caso
BEXEL Manager - Estudo de casoN.A. Tecnologia
 
Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Lee Maserian R.D.I.
 
Lou Fanglin's Document Control Procedure and DOC Experience Summary
Lou Fanglin's Document Control Procedure and DOC Experience SummaryLou Fanglin's Document Control Procedure and DOC Experience Summary
Lou Fanglin's Document Control Procedure and DOC Experience SummaryLou Fanglin
 
The management of construction
The management of constructionThe management of construction
The management of constructionThomas Britto
 

Tendances (20)

Johnson controls case study consultancy
Johnson controls case study   consultancyJohnson controls case study   consultancy
Johnson controls case study consultancy
 
Johnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project ManagementJohnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project Management
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projects
 
Summer Student Presentation 2016 Charlie Morgan
Summer Student Presentation 2016 Charlie MorganSummer Student Presentation 2016 Charlie Morgan
Summer Student Presentation 2016 Charlie Morgan
 
GOEFF STEBBINS RESUME
GOEFF STEBBINS RESUMEGOEFF STEBBINS RESUME
GOEFF STEBBINS RESUME
 
The Commercial Energy Codes Support Program
The Commercial Energy Codes Support ProgramThe Commercial Energy Codes Support Program
The Commercial Energy Codes Support Program
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2
 
MMC
MMCMMC
MMC
 
Project Management Class ( based on PMBOK) - Day 5
Project Management Class ( based on PMBOK) - Day 5Project Management Class ( based on PMBOK) - Day 5
Project Management Class ( based on PMBOK) - Day 5
 
Kumlachew Mechanical QC Eng.
Kumlachew Mechanical QC Eng.Kumlachew Mechanical QC Eng.
Kumlachew Mechanical QC Eng.
 
Basement remodel rev eh
Basement remodel rev ehBasement remodel rev eh
Basement remodel rev eh
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
 
BEXEL Manager - Estudo de caso
BEXEL Manager - Estudo de casoBEXEL Manager - Estudo de caso
BEXEL Manager - Estudo de caso
 
Ddg architecture
Ddg architectureDdg architecture
Ddg architecture
 
Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)Construction Phase Mgmt Srvcs (2)
Construction Phase Mgmt Srvcs (2)
 
Lou Fanglin's Document Control Procedure and DOC Experience Summary
Lou Fanglin's Document Control Procedure and DOC Experience SummaryLou Fanglin's Document Control Procedure and DOC Experience Summary
Lou Fanglin's Document Control Procedure and DOC Experience Summary
 
GWP Monitoring and Reporting
GWP Monitoring and ReportingGWP Monitoring and Reporting
GWP Monitoring and Reporting
 
Rich Gesimondo
Rich GesimondoRich Gesimondo
Rich Gesimondo
 
The management of construction
The management of constructionThe management of construction
The management of construction
 
2015_Resume 2
2015_Resume 22015_Resume 2
2015_Resume 2
 

Similaire à 61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draft

FMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxFMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxArJayTambaoan
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)Nur Azwin
 
madhu updated cv
madhu updated cvmadhu updated cv
madhu updated cvMadhu Civil
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTRiyaVerma238431
 
CV_ Azhar. (Civil_ Engr)...
CV_ Azhar. (Civil_ Engr)...CV_ Azhar. (Civil_ Engr)...
CV_ Azhar. (Civil_ Engr)...Azhar Niazi
 
Bilal updated cv
Bilal updated cvBilal updated cv
Bilal updated cvBilal Nisar
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionGalala University
 
WEC CV_2016 09 06
WEC CV_2016 09 06WEC CV_2016 09 06
WEC CV_2016 09 06Wauren Cruz
 
Introduction to construction project.pptx
Introduction to construction project.pptxIntroduction to construction project.pptx
Introduction to construction project.pptxJignesh patel
 
Vignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI CoordinatorVignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI CoordinatorVignesh Kumar C
 
engr ijaz 1 qc civil engineer I did civil engineering from University peshawar
engr ijaz 1 qc  civil engineer I did civil engineering from University peshawarengr ijaz 1 qc  civil engineer I did civil engineering from University peshawar
engr ijaz 1 qc civil engineer I did civil engineering from University peshawarengrijaz727
 
Nihal Kamal Othman Final CV
Nihal Kamal Othman Final CVNihal Kamal Othman Final CV
Nihal Kamal Othman Final CVNihal kamal
 

Similaire à 61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draft (20)

CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05
 
FMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptxFMA - 2_CM651_Group.pptx
FMA - 2_CM651_Group.pptx
 
Lecture 8 monitoring & controlling (1)
Lecture 8  monitoring & controlling (1)Lecture 8  monitoring & controlling (1)
Lecture 8 monitoring & controlling (1)
 
Santhan CV-2016
Santhan CV-2016Santhan CV-2016
Santhan CV-2016
 
madhu updated cv
madhu updated cvmadhu updated cv
madhu updated cv
 
Varun Garg_CV
Varun Garg_CVVarun Garg_CV
Varun Garg_CV
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENT
 
CV_ Azhar. (Civil_ Engr)...
CV_ Azhar. (Civil_ Engr)...CV_ Azhar. (Civil_ Engr)...
CV_ Azhar. (Civil_ Engr)...
 
CV of KP Tomy
CV of KP TomyCV of KP Tomy
CV of KP Tomy
 
Bilal updated cv
Bilal updated cvBilal updated cv
Bilal updated cv
 
Quality management
Quality managementQuality management
Quality management
 
Prashant Wani1
Prashant Wani1Prashant Wani1
Prashant Wani1
 
Civil Engineer 2
Civil Engineer 2Civil Engineer 2
Civil Engineer 2
 
Time & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and InspectionTime & Schedule, Submittals, Site visits, Testing and Inspection
Time & Schedule, Submittals, Site visits, Testing and Inspection
 
WEC CV_2016 09 06
WEC CV_2016 09 06WEC CV_2016 09 06
WEC CV_2016 09 06
 
Introduction to construction project.pptx
Introduction to construction project.pptxIntroduction to construction project.pptx
Introduction to construction project.pptx
 
Vignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI CoordinatorVignesh Kumar C- TPI Coordinator
Vignesh Kumar C- TPI Coordinator
 
engr ijaz 1 qc civil engineer I did civil engineering from University peshawar
engr ijaz 1 qc  civil engineer I did civil engineering from University peshawarengr ijaz 1 qc  civil engineer I did civil engineering from University peshawar
engr ijaz 1 qc civil engineer I did civil engineering from University peshawar
 
COE
COECOE
COE
 
Nihal Kamal Othman Final CV
Nihal Kamal Othman Final CVNihal Kamal Othman Final CV
Nihal Kamal Othman Final CV
 

61T01411 - PEP for Valeo Fosha New Facility - rev 0.0 -draft

  • 1. 61T01411 – Project Execution Plan for Valeo Foshan New Facility Project Valeo Tebodin Jul 22, 2014
  • 2. Agenda page 2 Agenda: •PEP project Execution Plan •Procurement Plan •Master Schedule •Engineering Status
  • 3. page 3 Index Project Execution Plan  Project Organization  Project Schedule (milestone)  Communication and Interface Management  Engineering Management  Construction Management  HSSE  Quality Management  Project Control
  • 4. page 4 Project Team Organization Chart (Sample)
  • 5. Project Schedule (milestones) Vs Progress ▪ Time Schedule ▪ Engineering Phase: 23 weeks ▪ Conceptual Design: 7 weeks; (4.29~6.20) ▪ Conceptual Design Review/Approval/optimizing: 2 weeks; (6.10~7.3) ▪ Detail Design Phase 1: (for exiting building refurbishment) 7 weeks; (6.19~7.24) ▪ Detail Design Phase 2: 5 weeks; (7.24~8.28) ▪ Detail Design Review/Approval/Audit: 2 weeks; (8.28 ~9.18) ▪ Procurement Phase: ▪ Phase 1: (for exiting building refurbishment) 4 weeks; (7.3~7.23) ▪ Phase 2: (for new buildings and utilities) 4 weeks; (9.1~9.25) ▪ Construction Phase: 5 months. (7.31~12.31) page 5
  • 6. page 6 Key Activities- Interface Management • Interface with Authorities and third parts • Interface with GC Contractor/suppliers • Interface with operation Team • Interface with Project Management Team • Interface with Land Lord Communication Management
  • 7. page 7 2 Project Management for EPC phase Communication Management Tools - Interface Management : ▪ Role and Responsibility Matrix ▪ Action List ▪ Master Schedule ▪ Permitting matrix ▪ Technical Interface Schedule ▪ Turnaround Plan
  • 8. page 8 Meeting and Reporting 1. Tebodin to Borouge • Weekly Report • Weekly Contract and Manning report • Monthly Status report 2. GC Contractor to PM team • Project Kick off Meetings • Weekly Coordination Meeting and Report • Monthly Progress Report – Communication Management
  • 9. page 9 Data Transfer Systems  Implement Borouge Document System 1. Numbering/Naming of Documents 2. Filling of Documents 3. Distribution of Documents 4. Documents templates Audit Document System of GC Review JianLi Technical Document System Communication Management
  • 10. page 10 1. The design manager and team will transfer the Conceptual phase design and requirements to the detailed design through gate review of EPC’s design. 2. Supervise the detail design at progress of 30%, 60% & 90% and final. Including activities: • Review of Vendor Design • Review of Documents and Records • Safety Engineering • Local Laws and Regulations • Design Continuity Management • Technical Interface Management 3. All information and data shall be documented amount interface boundaries through design, procurement, construction and commissioning phase of project Engineering Management
  • 11. page 11 1. Construction Planning • Temporary facilities plan • Site logistic and access control plan • Shut down and turnaround plan • Staff personnel and security force • Construction Schedule • Construction Execution Plan 2. Construction Execution • Implement quality control program • Interface with Jian Li • Implement design change and variation order approval procedure • Co-ordinate daily construction activities • Site quality inspection and testing • Organize meetings and report a regular basis • Ensure good housekeeping • Conduct Health, Safety and Environmental Protection inspections and audits on site • Manage EPC contractors work to be acceptance by authority. • Plan and execute Project handover Construction Management
  • 12. page 12 HSSE Management HSSE Management Manage and monitor EPC execution, including: • Organize Health Security & Safety Policy • Action and Resources • Compliance with Laws and Regulations • Training • Control of HSSE Document • HSSE audit and Management Review
  • 13. Key Safety Risks – listed but not limited • Material and warehousing is narrow on site • Tie-in impact to the existing production • Separation fence (for both external and internal work) • Pipe-line protection • Underground pipeline protection • Crane Work • Fire Protection on construction site • Fall down Protection on construction site • Edge Protection • Rubbish and Pollution control • Dust protection • Site Security and Access control • Plant fire Loop blocked and lost function page 13 HSSE Management
  • 14. page 14 Quality Management The Quality Control Manager will implement quality procedures and will conduct regular inspect and audit, including activities: QA (Quality Assurance) • Tebodin TQS as Guideline (Tebodin Quality System) • Project Quality Plan • Manage Jianli (Local Quality Supervision Company) QC( Quality Control): • Design quality control • Procurement quality control • Construction quality control • Document quality control
  • 15. page 15 Project Progress Control Progress Control  Milestone Summary Schedule (Level 1)  EPC Level Schedule (Level 2) • Permitting schedule • Procurement Schedule • Construction Schedule • Long Lead items • T&C schedules • Start-up schedules  Detailed Construction Schedule (Level 3)  Weekly Working Plan
  • 16. page 16 Project Cost Control Cost Control  EPC Cost Baseline  Log changes  Change Order Control  Monitor Deviation  Action and Forecast
  • 17. Area of Concerns 1. Permitting 2. Interface of Landlord page 17
  • 20. page 20 2.3 Information and Document Content Meeting Management Meeting Schedule frequency for each meeting is described as below:  Project and program control meeting – once a week  Design coordination meeting – once a week  Site construction meeting – once a week  Site safety meeting – once a week  Procurement meeting – once a month  Change control meeting - once bi-week
  • 21. page 21 2.1 Information and Document Content Meeting Management General o Agenda o Request o Meeting schedule o Meeting minutes o Distribution matrix Pre-construction Meetings Construction stage meetings
  • 22. page 22 2.1 Information and Document Content Technical Report  Internal review  Client for approval Project Weekly Report  EHS,  Engineering  Quality,  Procurement  Cost control  Schedule and Progress  Risk  Site photos Note: Submission date on each Monday for last week
  • 23. page 23 2.1 Information and Document Content Project Monthly Report  EHS,  Engineering  Quality,  Procurement  Cost control  Schedule and Progress  Risk  Site photos Note: Submission date within 1st week of next month. Cut date is end of current.
  • 24. page 24 3. Procurement Management Bidder Long List Preparation Pre-qualification Bidder short list Preparation of inquiry Bidding Bid Clarifications Evaluation Team Set Up Bid Evaluation Authorization to Order Expediting Critical Equipment / Critical Delivery Time Vendor Documents Inspection Project Procurement Report Payment Control 1.Bidding